2. About The Company
2
CONFIGURATION ( Pragati Power Station – 1)
Gas Turbines 2 x1 04 MW (open cycle) +
Steam Turbine of 1 x 122MW (combined cycle) = 330 MW
CONSTRUCTED ON ASH FILLED AREA OF 17 ACRES
SEWAGE TREATED WATER FROM STPs BEING USED – NO
WATER FROM RIVER YAMUNA IS USED.
ENVIRONMENT FRIENDLY DRY LOW NOx
BURNER TECHNOLOGY ADOPTED TO CONTROL
NOx LEVEL WITHIN ENVOIRNMENTAL LIMITS
OF LESS THAN 35 PPM.
3. 3
STATION
Rajghat
Power House
I.P. Gas
Turbine
Power Station
Pragati-I Combined
Cycle Gas Power
Station
Pragati-III Combined
Cycle Gas Power
Project, Bawana
Capacity (MW) 135 270 330 1500 (N)
Units (MW) 2x67.5
6 x 30 (GTs)
+
3 x 30 (STGs)
2 x 104 (GT*s)
+
1 x 122 (STG*)
4 x 250 (GTs)
+
2 x 250 (STGs)
Commissioning 1989-90
1985-86 (GTs)
+
1995-96
(STGs)
2002-03
Synchronized on –
GT-1: 11th Oct., 2010
GT-2: 09th Feb., 2011
STG-1: 03rd Oct.,
2011
Water
River
Yamuna
River Yamuna
Treated water
From Sen Nursing
Home & Delhi Gate
STPs
Treated water From
Rithala STP*
(GTs : Gas turbines ; STG : Steam Gas Turbine ; STP : Sewage Treatment Plant )
4. 4
KEY TERMS RELATED TO
POWER GENERATION
Gross Generation
Plant Load Factor
Availability Factor
Machine Availability Factor
Plant Heat Rate
Auxiliary Power Consumption
Special Gas Consumption
Back Down
Total Partial Loading
DM Makeup
6. 6
Comparison of O&M Performance up to : Jan ’
2014
Sr. No.
Performance
parameters
Units
Actual
Performance up
to Jan’2013
Actual
Performance up
to Jan’2014
Annual Gross Generation at Rated Capacity (330 MW) =2890.80 MU
1
Availability based on
DC
% 89.66 91.66
2 Gross Generation MU 2101.708 2032.153
3 Plant Load Factor % 86.72 83.85
4 Forced Outages % 0.52 2.24
5 Planned Outages % 2.58 0.66
6 Heat Rate (CC) Kcal / Kwh 1992.91 1988.68
7 Aux power cons. % 2.63 2.85
8 DM Consumption % 0.67 0.87
9 Back Down % 2.90 7.81
13. 13
BEST PERFORMANCE
FINANCIAL YEAR 2011- 2012
Gross Generation - 2560 MU
Actual PLF - 88.32%
Availability - 97.66%
Aux. Power Consumption -2.62%
Plant Position in Country
Pragati Power Station is 3rd Best Station in country during
Financial Year 2011-12
During Current FY 2013-14
At No 1- KARAIKAL CCPP* (PLF 90.98%) (*combined cycle power plant)
At No 2- AGARTALA GT (PLF 87.22%)
At No 3- PRAGATI CCPP (PLF 83.90 %)
14. 14
ENVIRONMENT FRIENDLY
INITIATIVES
Planted 3000 trees around the Power
Station to improve the Environment
No river/ ground water used for power
generation. Only Sewage treated water
is used
Dry Low NOx burners installed to
control Nox level.
*( NOx : Nitrogen oxides )
15. 15
LEARNING …..
Types Of Power Stations and techniques of generating
electricity.
Factors Affecting Power Generation.
Observing and maintaining large data sets on daily basis.
Growing Sector In India contributing in Country’s
Development.