Chapter 8
Resource Allocation
Allocating Resources to the Project
 Allocation of physical resources to one or multiple
projects.
 At any given time, the firm may have fixed level of
various resources like
- labor-hours of various types of professionals
- machine hours of various types of machinery
- hours of computing time
- specialized locations
 The project schedule should be adjusted to
smooth the use of the resources
Critical Path Method—Crashing a
Project
 Time and cost are interrelated
 The faster an activity is completed, the
more it costs
 Change the schedule and you change
the budget
 Thus many activities can be speeded up
by spending more money
What is Crashing / Crunching?
 To speed up, or expedite, a project
 Of course, the resources to do this must be
available
 Crunching a project changes the schedule for
all activities
 This will have an impact on schedules for all
the subcontractors
 Crunching a project often introduces
unanticipated problems
Direct Cost vs. Indirect Cost
 Direct cost increases if the activity
duration is to be reduced.
 The Indirect cost decreases if the activity
duration is to be reduced.
Activity Cost Slope
Time
Normal
-
Time
Crash
Cost
Normal
-
Cost
Crash

Slope
An Example of Two-Time CPM
Activity Slopes—Cost per Period for
Crashing
Negative slope: as the time required for a project or task is decreased,
the cost is increased.
Crashing the Project
When crashing a project, first task is to
develop a table or graph of the cost of a
project as a function of the project’s various
possible completion dates.
Crash selected activities, one at a time, to
decrease the project duration.
Crashing the Project
Two principles:
•Focus on the critical path(s) when trying to
shorten the duration of a project. (Crashing
a non-critical activity will not influence
project duration.)
•When shortening a project’s duration, select
the least expensive way to do it.
Crashing example
1
3
2
4 6
5
D [10,8]
10
•Direct Cost – Rs. 25,500
Indirect Cost – Rs. 200/day
Step 1
Path Normal Crashing A
by 2 day
ADG 21 19
AEH 37 35
BH 35 35
CFH 25 25
Step 2
Path Normal Crashing A
by 2 day
Crashing E, B
by 3 days
ADG 21 19 19
AEH 37 35 32
BH 35 35 32
CFH 25 25 25
Step 3
Path Normal Crashing
A by 2 day
Crashing
E, B by 3
days
Crashing H
by 2 days
ADG 21 19 19 19
AEH 37 35 32 30
BH 35 35 32 30
CFH 25 25 25 23
Crashing Table
2
5
3
6 7
1 4
A [9,6]
210
G [5,3]
180
H [2,1]
300
Question
•Direct Cost – Rs. 37,500
Indirect Cost – Rs. 250/day
Solution
Question 1:
Events Normal Crash
Activity Time
(days)
Cost
(Rs)
Time
(days)
Cost
(Rs)
1-2 3 360 2 400
2-3 6 1440 4 1620
2-4 9 2160 5 2380
2-5 7 1120 5 1600
3-4 8 400 4 800
4-5 5 1600 3 1770
5-6 3 480 2 760
Indirect cost: Rs100/day
Question 2:
Normal Crash
Activity Time
(days)
Cost
(Rs)
Time
(days)
Cost
(Rs)
Slope
1-2 8 100 6 200 50
1-3 4 150 2 350 100
2-4 2 50 1 90 40
2-5 10 100 5 400 60
3-4 5 100 1 200 25
4-5 3 80 1 100 10
Indirect cost: Rs. 70/day
Risks in Project Crashing
Various external and internal factors may lead project
manager to go for crashing, but it usually affects the
quality of work as the time taken (besides cost) is the
major issue on his mind:
 New resources aren't going to be familiar with the tasks
at hand, so they will probably be less productive than
current team members.
 Who will guide the new members up the learning curve?
Usually it will be the most productive members of the
team, who could themselves be working to get the task
finished more quickly.
 Being available does not equal being qualified. For
example, while outsourcing, one can't be sure that
workers are trained enough to deliver as per expected
standards.
Project Fast Tracking
 Fast tracking means that the activities that are
normally done in sequence are instead performed
partially in parallel. In other words, Fast tracking is
applied by re-scheduling various activities within the
project to be worked on simultaneously instead of
waiting for each piece to be completed separately.
 Fast-tracking always involves risk that could lead to
increased cost and some rework later.
 A good rule of thumb is that sequential activities can
sometimes be fast-tracked by up to 33%. In other
words, if you're fast-tracking, you can start the
second of two sequential activities when the first
activity is 66% complete.
The Resource Allocation
Problem
 As discussed, CPM/PERT ignore resource
utilization and availability
 Critical resources can’t be renewed or
inventoried.
 Schedules need to be evaluated in terms of
both time and resources (scarce ones)
 Time Limited vs. Resource Limited
Resource Loading
 Resource loading describes the amount
of resources an existing schedule
requires
 Gives an understanding of the demands
a project will make of a firm’s resources
Resource A
Resource B
Resource Leveling
 Approach to even out the peaks and
valleys of resource requirements so that
a fixed amount of resources can be
employed over time.
 Less hands-on management is required
 May be able to use just-in-time inventory
 Improves morale
 Fewer personnel problems
Resource Leveling Continued
 When an activity has slack, we can move that
activity to shift its resource usage
 May also be possible to alter the sequence of
activities to levelize resources
 Small projects can be levelized by hand
 Software can levelize resources for larger
projects
 Large projects with multiple resources are very
complex to levelize
Resource Leveling Steps
Create a project activity network diagram and
mention the duration of the activities
Calculate EOT( earliest occurrence time) for
all the events. This helps in calculation of float/
slack of activities
Develop a time-phased resource loading
diagram
Identify any resource conflicts and begin to
smooth the loading table using slacks
Resource Leveling Techniques
1. Shift the start date of an activity within its
slack time
2. Split the activity within its slack time
Resource Leveling Example:
Activity Duration Manpower Req.
1-2 6 8
1-3 10 4
1-4 6 9
2-3 10 7
2-4 4 6
3-5 6 17
4-5 6 6
Q: Reduce the peak manpower requirement and smoothen the period
to period resource requirement.
Solution
Question:
 A job requires the following resources:
Six crane operators have been recruited for the
job. How would you manage the job so as to
complete it at the earliest?
Constrained Resource Scheduling
Heuristic
Approach
An approach, such as a
rule of thumb, that yields
a good solution that may
or may not be optimal.
Optimization
Approach
An approach, such as
linear programming, that
yields the one best
solution.
Heuristic Methods
 The only feasible way on large projects
 While not optimal, the schedules are very
good
 Take the CPM/PERT schedule as a baseline
 They sequentially step through the schedule
trying to move resource requirements around
to levelize them
 Resources are moved around based on one or
more priority rules
Common Priority Rules
 As soon as possible
 As late as possible
 Shortest task first
 Most resources first
 Minimum slack first
 Most critical followers
 Most successors
 Arbitrary
Heuristic Methods Continued
 These are just the common ones
 There are many more
 The heuristic can either start at the
beginning and work forwards
 Or it can start at the end and work
backwards
Optimization Methods
 Finds the one best solution
 Uses either linear programming or
enumeration
 Not all projects can be optimized
 Approaches only work with small to
medium projects
Multi-Project Scheduling and
Resource Allocation
 Scheduling and resource allocation problems increase
with more than one project
 The greater the number of projects, the greater the
problems
 One way is to consider each project as part of a much
larger project
 However, different projects have different goals so
combining may not make sense
 Must also tell us if there are resources to tackle new
projects we are considering
Standards to Measure Schedule
Effectiveness
1. Schedule slippage
2. Resource utilization
3. In-process inventory
Schedule Slippage
 The time past a project’s due date when the
project is completed
 Slippage may cause penalties
 Different projects will have different penalties
 Expediting one project can cause others to slip
 Taking on a new project can cause existing
projects to slip
Resource Utilization
 The percentage of a resource that is
actually used
 We want a schedule that smoothes out
the dips and peaks of resource utilization
 This is especially true of labor, where
hiring and firing is expensive
In-Process Inventory
 This is the amount of work waiting to be
processed because there is a shortage
of some resource
 Similar to WIP in manufacturing
 The cost here is holding cost
Heuristic Techniques
 Multi-projects are too complex for
optimization approaches
 Many of the heuristics are extensions of
the ones used for one project
Additional Priority Rules
 Resource scheduling method
 Minimum late finish time
 Greatest resource demand
 Greatest resource utilization
 Most possible jobs

Contenu connexe

Tendances

Project controls
Project controlsProject controls
Project controlsAshok Kumar
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Schedulingsslovepk
 
Project Management and Process
Project Management and ProcessProject Management and Process
Project Management and ProcessMuhammad Rehman
 
7.4 Earned Value Analysis
7.4 Earned Value Analysis7.4 Earned Value Analysis
7.4 Earned Value AnalysisDavidMcLachlan1
 
Project Management
Project ManagementProject Management
Project ManagementMark Roman
 
Construction Project management
Construction Project management Construction Project management
Construction Project management Anupama holla
 
9.0 Project Resource Management Overview
9.0 Project Resource Management Overview9.0 Project Resource Management Overview
9.0 Project Resource Management OverviewDavidMcLachlan1
 
05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Control05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Controlakashpadole
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimatinghatim ahmed
 

Tendances (20)

Project controls
Project controlsProject controls
Project controls
 
Different project management methodologies
Different project management methodologiesDifferent project management methodologies
Different project management methodologies
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 
Project Planning & Management
Project Planning & ManagementProject Planning & Management
Project Planning & Management
 
crashing of project
crashing of project crashing of project
crashing of project
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
Project Resource Management
Project Resource ManagementProject Resource Management
Project Resource Management
 
Project Management and Process
Project Management and ProcessProject Management and Process
Project Management and Process
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
7.4 Earned Value Analysis
7.4 Earned Value Analysis7.4 Earned Value Analysis
7.4 Earned Value Analysis
 
Project Management
Project ManagementProject Management
Project Management
 
Project management
Project managementProject management
Project management
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
9.0 Project Resource Management Overview
9.0 Project Resource Management Overview9.0 Project Resource Management Overview
9.0 Project Resource Management Overview
 
Project Management
Project ManagementProject Management
Project Management
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Control05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Control
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
 
4 Phases of Project Management Cycle
4 Phases of Project Management Cycle4 Phases of Project Management Cycle
4 Phases of Project Management Cycle
 

Similaire à Resource-Allocation.ppt

Chapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptChapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptTecnicoItca
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxstilliegeorgiana
 
Estimating time and cost resoures
Estimating time and cost resouresEstimating time and cost resoures
Estimating time and cost resouresMayank Kothawade
 
MBA 6951, Managing Complex Projects 1 Course Learning.docx
 MBA 6951, Managing Complex Projects 1 Course Learning.docx MBA 6951, Managing Complex Projects 1 Course Learning.docx
MBA 6951, Managing Complex Projects 1 Course Learning.docxaryan532920
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
PM Session 6
PM Session 6PM Session 6
PM Session 6dmdk12
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1reddvise
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-seminiMaya
 
The Effective Management of Time
The Effective Management of TimeThe Effective Management of Time
The Effective Management of TimeInSync Conference
 
Project TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxProject TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxbriancrawford30935
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET Journal
 
Scheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.pptScheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.pptTecnicoItca
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksSHAZEBALIKHAN1
 

Similaire à Resource-Allocation.ppt (20)

ch09s.ppt
ch09s.pptch09s.ppt
ch09s.ppt
 
-PM-09-7.ppt
-PM-09-7.ppt-PM-09-7.ppt
-PM-09-7.ppt
 
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptChapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.ppt
 
Ch09 (1).pptx
Ch09 (1).pptxCh09 (1).pptx
Ch09 (1).pptx
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docx
 
Allocating resources
Allocating resourcesAllocating resources
Allocating resources
 
Estimating time and cost resoures
Estimating time and cost resouresEstimating time and cost resoures
Estimating time and cost resoures
 
MBA 6951, Managing Complex Projects 1 Course Learning.docx
 MBA 6951, Managing Complex Projects 1 Course Learning.docx MBA 6951, Managing Complex Projects 1 Course Learning.docx
MBA 6951, Managing Complex Projects 1 Course Learning.docx
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
PM Session 6
PM Session 6PM Session 6
PM Session 6
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-
 
CSRA Havranek Hostetter Palisade 2012
CSRA Havranek Hostetter Palisade 2012CSRA Havranek Hostetter Palisade 2012
CSRA Havranek Hostetter Palisade 2012
 
The Effective Management of Time
The Effective Management of TimeThe Effective Management of Time
The Effective Management of Time
 
Project TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxProject TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docx
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
 
4) PTM & PCM .pptx
4) PTM & PCM .pptx4) PTM & PCM .pptx
4) PTM & PCM .pptx
 
Scheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.pptScheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.ppt
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & Tricks
 

Plus de TecnicoItca

tipos-de-organizacion-empresarial.pdf
tipos-de-organizacion-empresarial.pdftipos-de-organizacion-empresarial.pdf
tipos-de-organizacion-empresarial.pdfTecnicoItca
 
-Interes-Simple.ppt
-Interes-Simple.ppt-Interes-Simple.ppt
-Interes-Simple.pptTecnicoItca
 
Tesis-de-gerencia-de-proyectos (1).pptx
Tesis-de-gerencia-de-proyectos (1).pptxTesis-de-gerencia-de-proyectos (1).pptx
Tesis-de-gerencia-de-proyectos (1).pptxTecnicoItca
 
Gestion-Financiera-Semestre-2016-0-ppt.ppt
Gestion-Financiera-Semestre-2016-0-ppt.pptGestion-Financiera-Semestre-2016-0-ppt.ppt
Gestion-Financiera-Semestre-2016-0-ppt.pptTecnicoItca
 
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt08-Project-Control-ppt.ppt
08-Project-Control-ppt.pptTecnicoItca
 
Project-Progress-Presentation.pptx
Project-Progress-Presentation.pptxProject-Progress-Presentation.pptx
Project-Progress-Presentation.pptxTecnicoItca
 
-Project-Management.ppt
-Project-Management.ppt-Project-Management.ppt
-Project-Management.pptTecnicoItca
 
Telsys-Case-International-Management.ppt
Telsys-Case-International-Management.pptTelsys-Case-International-Management.ppt
Telsys-Case-International-Management.pptTecnicoItca
 
Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptxTecnicoItca
 
Project-Management.ppt
Project-Management.pptProject-Management.ppt
Project-Management.pptTecnicoItca
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxTecnicoItca
 
Project-Management-Introduction.ppt
Project-Management-Introduction.pptProject-Management-Introduction.ppt
Project-Management-Introduction.pptTecnicoItca
 
Project-Manager.ppt
Project-Manager.pptProject-Manager.ppt
Project-Manager.pptTecnicoItca
 
Lecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptxLecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptxTecnicoItca
 
Chapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.pptChapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.pptTecnicoItca
 
PM-Chapter8-1.pptx
PM-Chapter8-1.pptxPM-Chapter8-1.pptx
PM-Chapter8-1.pptxTecnicoItca
 
Clases-de-Bonos-matematica.ppt
Clases-de-Bonos-matematica.pptClases-de-Bonos-matematica.ppt
Clases-de-Bonos-matematica.pptTecnicoItca
 
Valoracion-de-Bonos.pptx
Valoracion-de-Bonos.pptxValoracion-de-Bonos.pptx
Valoracion-de-Bonos.pptxTecnicoItca
 

Plus de TecnicoItca (20)

tipos-de-organizacion-empresarial.pdf
tipos-de-organizacion-empresarial.pdftipos-de-organizacion-empresarial.pdf
tipos-de-organizacion-empresarial.pdf
 
-Interes-Simple.ppt
-Interes-Simple.ppt-Interes-Simple.ppt
-Interes-Simple.ppt
 
Tesis-de-gerencia-de-proyectos (1).pptx
Tesis-de-gerencia-de-proyectos (1).pptxTesis-de-gerencia-de-proyectos (1).pptx
Tesis-de-gerencia-de-proyectos (1).pptx
 
Gestion-Financiera-Semestre-2016-0-ppt.ppt
Gestion-Financiera-Semestre-2016-0-ppt.pptGestion-Financiera-Semestre-2016-0-ppt.ppt
Gestion-Financiera-Semestre-2016-0-ppt.ppt
 
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt
 
Project-Progress-Presentation.pptx
Project-Progress-Presentation.pptxProject-Progress-Presentation.pptx
Project-Progress-Presentation.pptx
 
-Project-Management.ppt
-Project-Management.ppt-Project-Management.ppt
-Project-Management.ppt
 
Telsys-Case-International-Management.ppt
Telsys-Case-International-Management.pptTelsys-Case-International-Management.ppt
Telsys-Case-International-Management.ppt
 
Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptx
 
Project-Management.ppt
Project-Management.pptProject-Management.ppt
Project-Management.ppt
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 
Project-Management-Introduction.ppt
Project-Management-Introduction.pptProject-Management-Introduction.ppt
Project-Management-Introduction.ppt
 
Project-Manager.ppt
Project-Manager.pptProject-Manager.ppt
Project-Manager.ppt
 
ch10s.ppt
ch10s.pptch10s.ppt
ch10s.ppt
 
Lecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptxLecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptx
 
Chapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.pptChapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.ppt
 
PM-Chapter8-1.pptx
PM-Chapter8-1.pptxPM-Chapter8-1.pptx
PM-Chapter8-1.pptx
 
Clases-de-Bonos-matematica.ppt
Clases-de-Bonos-matematica.pptClases-de-Bonos-matematica.ppt
Clases-de-Bonos-matematica.ppt
 
Valoracion-de-Bonos.pptx
Valoracion-de-Bonos.pptxValoracion-de-Bonos.pptx
Valoracion-de-Bonos.pptx
 
Bonos-Clase.ppt
Bonos-Clase.pptBonos-Clase.ppt
Bonos-Clase.ppt
 

Dernier

(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 

Dernier (20)

(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 

Resource-Allocation.ppt

  • 2. Allocating Resources to the Project  Allocation of physical resources to one or multiple projects.  At any given time, the firm may have fixed level of various resources like - labor-hours of various types of professionals - machine hours of various types of machinery - hours of computing time - specialized locations  The project schedule should be adjusted to smooth the use of the resources
  • 3. Critical Path Method—Crashing a Project  Time and cost are interrelated  The faster an activity is completed, the more it costs  Change the schedule and you change the budget  Thus many activities can be speeded up by spending more money
  • 4. What is Crashing / Crunching?  To speed up, or expedite, a project  Of course, the resources to do this must be available  Crunching a project changes the schedule for all activities  This will have an impact on schedules for all the subcontractors  Crunching a project often introduces unanticipated problems
  • 5. Direct Cost vs. Indirect Cost  Direct cost increases if the activity duration is to be reduced.  The Indirect cost decreases if the activity duration is to be reduced.
  • 7. An Example of Two-Time CPM
  • 8. Activity Slopes—Cost per Period for Crashing Negative slope: as the time required for a project or task is decreased, the cost is increased.
  • 9. Crashing the Project When crashing a project, first task is to develop a table or graph of the cost of a project as a function of the project’s various possible completion dates. Crash selected activities, one at a time, to decrease the project duration.
  • 10. Crashing the Project Two principles: •Focus on the critical path(s) when trying to shorten the duration of a project. (Crashing a non-critical activity will not influence project duration.) •When shortening a project’s duration, select the least expensive way to do it.
  • 11. Crashing example 1 3 2 4 6 5 D [10,8] 10 •Direct Cost – Rs. 25,500 Indirect Cost – Rs. 200/day
  • 12. Step 1 Path Normal Crashing A by 2 day ADG 21 19 AEH 37 35 BH 35 35 CFH 25 25
  • 13. Step 2 Path Normal Crashing A by 2 day Crashing E, B by 3 days ADG 21 19 19 AEH 37 35 32 BH 35 35 32 CFH 25 25 25
  • 14. Step 3 Path Normal Crashing A by 2 day Crashing E, B by 3 days Crashing H by 2 days ADG 21 19 19 19 AEH 37 35 32 30 BH 35 35 32 30 CFH 25 25 25 23
  • 16. 2 5 3 6 7 1 4 A [9,6] 210 G [5,3] 180 H [2,1] 300 Question •Direct Cost – Rs. 37,500 Indirect Cost – Rs. 250/day
  • 18. Question 1: Events Normal Crash Activity Time (days) Cost (Rs) Time (days) Cost (Rs) 1-2 3 360 2 400 2-3 6 1440 4 1620 2-4 9 2160 5 2380 2-5 7 1120 5 1600 3-4 8 400 4 800 4-5 5 1600 3 1770 5-6 3 480 2 760 Indirect cost: Rs100/day
  • 19. Question 2: Normal Crash Activity Time (days) Cost (Rs) Time (days) Cost (Rs) Slope 1-2 8 100 6 200 50 1-3 4 150 2 350 100 2-4 2 50 1 90 40 2-5 10 100 5 400 60 3-4 5 100 1 200 25 4-5 3 80 1 100 10 Indirect cost: Rs. 70/day
  • 20. Risks in Project Crashing Various external and internal factors may lead project manager to go for crashing, but it usually affects the quality of work as the time taken (besides cost) is the major issue on his mind:  New resources aren't going to be familiar with the tasks at hand, so they will probably be less productive than current team members.  Who will guide the new members up the learning curve? Usually it will be the most productive members of the team, who could themselves be working to get the task finished more quickly.  Being available does not equal being qualified. For example, while outsourcing, one can't be sure that workers are trained enough to deliver as per expected standards.
  • 21. Project Fast Tracking  Fast tracking means that the activities that are normally done in sequence are instead performed partially in parallel. In other words, Fast tracking is applied by re-scheduling various activities within the project to be worked on simultaneously instead of waiting for each piece to be completed separately.  Fast-tracking always involves risk that could lead to increased cost and some rework later.  A good rule of thumb is that sequential activities can sometimes be fast-tracked by up to 33%. In other words, if you're fast-tracking, you can start the second of two sequential activities when the first activity is 66% complete.
  • 22. The Resource Allocation Problem  As discussed, CPM/PERT ignore resource utilization and availability  Critical resources can’t be renewed or inventoried.  Schedules need to be evaluated in terms of both time and resources (scarce ones)  Time Limited vs. Resource Limited
  • 23. Resource Loading  Resource loading describes the amount of resources an existing schedule requires  Gives an understanding of the demands a project will make of a firm’s resources
  • 26. Resource Leveling  Approach to even out the peaks and valleys of resource requirements so that a fixed amount of resources can be employed over time.  Less hands-on management is required  May be able to use just-in-time inventory  Improves morale  Fewer personnel problems
  • 27. Resource Leveling Continued  When an activity has slack, we can move that activity to shift its resource usage  May also be possible to alter the sequence of activities to levelize resources  Small projects can be levelized by hand  Software can levelize resources for larger projects  Large projects with multiple resources are very complex to levelize
  • 28. Resource Leveling Steps Create a project activity network diagram and mention the duration of the activities Calculate EOT( earliest occurrence time) for all the events. This helps in calculation of float/ slack of activities Develop a time-phased resource loading diagram Identify any resource conflicts and begin to smooth the loading table using slacks
  • 29. Resource Leveling Techniques 1. Shift the start date of an activity within its slack time 2. Split the activity within its slack time
  • 30. Resource Leveling Example: Activity Duration Manpower Req. 1-2 6 8 1-3 10 4 1-4 6 9 2-3 10 7 2-4 4 6 3-5 6 17 4-5 6 6 Q: Reduce the peak manpower requirement and smoothen the period to period resource requirement.
  • 32. Question:  A job requires the following resources: Six crane operators have been recruited for the job. How would you manage the job so as to complete it at the earliest?
  • 33. Constrained Resource Scheduling Heuristic Approach An approach, such as a rule of thumb, that yields a good solution that may or may not be optimal. Optimization Approach An approach, such as linear programming, that yields the one best solution.
  • 34. Heuristic Methods  The only feasible way on large projects  While not optimal, the schedules are very good  Take the CPM/PERT schedule as a baseline  They sequentially step through the schedule trying to move resource requirements around to levelize them  Resources are moved around based on one or more priority rules
  • 35. Common Priority Rules  As soon as possible  As late as possible  Shortest task first  Most resources first  Minimum slack first  Most critical followers  Most successors  Arbitrary
  • 36. Heuristic Methods Continued  These are just the common ones  There are many more  The heuristic can either start at the beginning and work forwards  Or it can start at the end and work backwards
  • 37. Optimization Methods  Finds the one best solution  Uses either linear programming or enumeration  Not all projects can be optimized  Approaches only work with small to medium projects
  • 38. Multi-Project Scheduling and Resource Allocation  Scheduling and resource allocation problems increase with more than one project  The greater the number of projects, the greater the problems  One way is to consider each project as part of a much larger project  However, different projects have different goals so combining may not make sense  Must also tell us if there are resources to tackle new projects we are considering
  • 39. Standards to Measure Schedule Effectiveness 1. Schedule slippage 2. Resource utilization 3. In-process inventory
  • 40. Schedule Slippage  The time past a project’s due date when the project is completed  Slippage may cause penalties  Different projects will have different penalties  Expediting one project can cause others to slip  Taking on a new project can cause existing projects to slip
  • 41. Resource Utilization  The percentage of a resource that is actually used  We want a schedule that smoothes out the dips and peaks of resource utilization  This is especially true of labor, where hiring and firing is expensive
  • 42. In-Process Inventory  This is the amount of work waiting to be processed because there is a shortage of some resource  Similar to WIP in manufacturing  The cost here is holding cost
  • 43. Heuristic Techniques  Multi-projects are too complex for optimization approaches  Many of the heuristics are extensions of the ones used for one project
  • 44. Additional Priority Rules  Resource scheduling method  Minimum late finish time  Greatest resource demand  Greatest resource utilization  Most possible jobs