SlideShare une entreprise Scribd logo
1  sur  25
By: Anand Bobade (nmbobade@gmail.com)
Chapter 11 –
Project Risk Management
PMP
Trainer: Anand BobadePMBOK 6th Edition, 2019, All rights reserved.
Identify Risk
SIXTH EDITION
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
11.2 Identify Risks
Identify Risks - Definition
Who is involved in Risk identification?
Identify Risks : ITTO
What is Delphi technique?
What is Risk register?
Review
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project Risk Management Processes
Plan Risk
management
Identify Risk
Perform Qualitative
Risk Analysis
Perform Quantitative
Risk Analysis
Plan Risk Response Implement Risk Monitor Risk
P
MC
P P P
P E
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Determine which risks may affect the project
& document their characteristics
Focuses on documentation of existing risks. It provides
Knowledge & ability to project team, to anticipate events.
Project
Risk1
Risk2
Risk3
Risk4Risk5
Risk6
Risk7
Identify Risk -> Definition
Determine Risks Documenting their characteristics
Document
Risk
Charaterstics1
Charaterstics2
Charaterstics3
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Risk Identification is an iterative process.
Consistent format should be used to ensure each risk is understood
clearly & unambiguously.
Ownership & Responsibility - Project team should be involved in the
process.
The more participants involved in the process will help to identify more
risks.
Identify Risk -> Introduction
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project
Manager /
Project team
Risk
Management
Experts
Customers &
end users
SME /
Consultants
Project
stakeholders
Industry
representatives
Quality/ HR
experts
Identify Risk -> Stakeholders involved
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Identify Risk ->ITTO
Expert Judgment
Data Gathering
Data analysis
Interpersonal and team skills
Prompt lists
Meetings
Project Management Plan
Project documents
Agreements
Procurement Documents
Enterprise environmental factors
Organizational process assets
Risk Register
Risk Report
Project document updates
Inputs Tools & Techniques Outputs
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project Management
Plan
Project documents Agreements
Procurement
Documents
Enterprise
environmental factors
Organizational process
assets
Identify Risk ->Inputs
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project
Management Plan
Requirements
Manag. Plan
Schedule
Manag. plan
Cost Manag.
Plan
Quality Manag.
Plan
Resource
Manag. Plan
Risk Manag.
Plan
Identify Risk ->Inputs -> PMP
Scope baseline
Schedule
baseline
Cost baseline
Baselines
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project documents Assumption log
Lessons learned
register
Requirements
documentation
Risk Register
Stakeholder
Register
Issue log
Cost estimates Duration Estimates
Identify Risk ->Inputs -> Project documents
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Expert Judgment Data Gathering Data Analysis Prompt lists
Meeting
Interpersonal &
team skills
Identify Risk ->Tools & Techniques
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Data Gathering Checklist Brainstorming Interviews
Identify Risk ->T&T-> Data Gathering
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Data Gathering Checklist
Identify Risk ->T&T-> Data Gathering
Risk identification checklists.
Lowest level of RBS can be used as checklist.
Best if Developed based on prior projects.
It is impossible to build exhaustive checklist.
Over reliance over checklist should be avoided.
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Data Analysis
Root cause
analysis
Assumptions &
Constraints
analysis
SWOT analysis
Document
analysis
Identify Risk ->T&T -> Data Analysis
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Data Analysis
SWOT analysis
• It is a framework for analyzing organization's strengths &
weaknesses, & the opportunities and threats that you face.
Identify Risk ->T&T -> Data Analysis
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Data Analysis
Assumptions & Constraints analysis
•It explores the validity of assumptions as they
applied to the project.
•All project assumptions should be verified.
•Changes to assumptions or new assumptions
should be identified.
•Focus on the assumptions that impacts
multiple project objectives.
Document analysis:
•Understand the content of all relevant
documents
•Focus on Scope, cost, time & quality
•Question Assumption, Constraints
•Quality of doc - completeness, consistency
Identify Risk ->T&T -> Data Analysis
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Expert Judgment
Expertize should be considered from groups or individuals with specialized
knowledge in the area of Risk management.
Senior Management Project Stakeholders
PM with similar
project experience
Subject Matter
expert
Consultants
Professional &
technical associates
Identify Risks->T&T->Expert Judgement
Help PM to do
SWOT analysis
Use Delphi
technique to
identify risks.
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Prompt lists
Prompt lists are predetermined list of categories.
The lowest level of RBS is used as prompt list.
strategic frameworks to identifying overall project risks - PESTLE, TECOP, VUCA
Identify Risks->T&T-> Prompt lists
Complexity
Multiple key decision
factors
Volatility
Rate of change
Ambiguity
Lack of clarity about
meaning of an event
Uncertainty
Unclear about the
present
VUCA
Howwellcanyoupredictthe
outcomeofyouractions?
How much do you know about the situation?
+
+- -
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Prompt lists
Identify Risks->T&T-> Prompt lists
PESTLE
Political Economic Social Technological Legal Environmental.
TECOP
Technical Economical Commercial Organizational Political.
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Risk Register Risk Report Project doc. updates
Identify Risks->Output->Risk Register
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Risk Register
The output is, initial entries into the risk register, which includes:
Identify Risks->Output->Risk Register
Risk Register:
List of risk
List of initial
POTENTIAL
responses
Potential risk
owners
Root causes of risks
Updated risk
categories
Impact
I
D
Risk Statement Probability Scope Quality Schedule Cost Potential Response
Potential
Owner
1
Project owner on the client
side is replaced.
Low Medium Orient new project owner.
Project
Manager
2
Senior programmer is taken
from the project.
Medium High High
Find replacement
programmer.
Project
Manager
3
External system A is not ready
in time to implement feature
B.
High Low Medium Low
Discuss with stakeholders and
make adjustments as agreed.
Project
Manager
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Risk
Register
Risk Statement:
Identify Risks->Output->Risk Register
Context Risk Statement
Source Condition Consequences
If (event) occurs due to (driver), the consequences
could result in (impact).
Significant delays in retrieving records due to
current tools for data storage and retrieval practices
may leave the department unable to adequately
respond to Access to Information requests.
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project doc. updates Assumption log Issue log
Lessons learned
register
Identify Risks->Output-> Project doc. updates
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Who is involved in Risk identification?
What is Delphi technique?
What is assumption analysis?
What is SWOT analysis.
What is Risk register?
What is risk statement.
Identify Risks -> Review
By: Anand Bobade (nmbobade@gmail.com)

Contenu connexe

Tendances

Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity ResourceAnand Bobade
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate CostAnand Bobade
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1Anand Bobade
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1Anand Bobade
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control CostAnand Bobade
 
PMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life CyclePMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life CycleAnand Bobade
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource ManagementAnand Bobade
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesAnand Bobade
 
PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2Anand Bobade
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop TeamAnand Bobade
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overviewAnand Bobade
 
Chap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkChap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkAnand Bobade
 
PMP Chap 10 - Project Communication Management Details
PMP  Chap 10 - Project Communication Management DetailsPMP  Chap 10 - Project Communication Management Details
PMP Chap 10 - Project Communication Management DetailsAnand Bobade
 
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2Anand Bobade
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2Anand Bobade
 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationAnand Bobade
 
Chap 4.0 Project integration management Overview
Chap 4.0 Project integration management OverviewChap 4.0 Project integration management Overview
Chap 4.0 Project integration management OverviewAnand Bobade
 
PMP Chap 8 - Project Quality Management
PMP Chap 8 - Project Quality ManagementPMP Chap 8 - Project Quality Management
PMP Chap 8 - Project Quality ManagementAnand Bobade
 
Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewAnand Bobade
 
Chap 8.3 Control Quality
Chap 8.3  Control QualityChap 8.3  Control Quality
Chap 8.3 Control QualityAnand Bobade
 

Tendances (20)

Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity Resource
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate Cost
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control Cost
 
PMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life CyclePMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life Cycle
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource Management
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management Processes
 
PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop Team
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overview
 
Chap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkChap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project Work
 
PMP Chap 10 - Project Communication Management Details
PMP  Chap 10 - Project Communication Management DetailsPMP  Chap 10 - Project Communication Management Details
PMP Chap 10 - Project Communication Management Details
 
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2
 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity Duration
 
Chap 4.0 Project integration management Overview
Chap 4.0 Project integration management OverviewChap 4.0 Project integration management Overview
Chap 4.0 Project integration management Overview
 
PMP Chap 8 - Project Quality Management
PMP Chap 8 - Project Quality ManagementPMP Chap 8 - Project Quality Management
PMP Chap 8 - Project Quality Management
 
Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management Overview
 
Chap 8.3 Control Quality
Chap 8.3  Control QualityChap 8.3  Control Quality
Chap 8.3 Control Quality
 

Similaire à PMP Project Risk Management Processes

Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor RisksAnand Bobade
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementAnand Bobade
 
Chap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterChap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterAnand Bobade
 
Chap 5.3 define scope
Chap 5.3 define scopeChap 5.3 define scope
Chap 5.3 define scopeAnand Bobade
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workAnand Bobade
 
Chap 5.2 Collect requirements
Chap 5.2 Collect requirementsChap 5.2 Collect requirements
Chap 5.2 Collect requirementsAnand Bobade
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage CommunicationAnand Bobade
 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define ActivityAnand Bobade
 
Chap 8.1 Plan quality management
Chap 8.1 Plan quality managementChap 8.1 Plan quality management
Chap 8.1 Plan quality managementAnand Bobade
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire ResourcesAnand Bobade
 
Chap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementChap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementAnand Bobade
 
Chap 13.1 Identify stakeholders
Chap 13.1 Identify stakeholdersChap 13.1 Identify stakeholders
Chap 13.1 Identify stakeholdersAnand Bobade
 
Chap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management planChap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management planAnand Bobade
 
Chap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseChap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseAnand Bobade
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationAnand Bobade
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication ManagementAnand Bobade
 
Get Ready to Crack PeopleCert PRINCE2 Foundation Certification Exam
Get Ready to Crack PeopleCert PRINCE2 Foundation Certification ExamGet Ready to Crack PeopleCert PRINCE2 Foundation Certification Exam
Get Ready to Crack PeopleCert PRINCE2 Foundation Certification ExamMeghna Arora
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control ResourcesAnand Bobade
 
Project risk analysis in Construction Industry
Project risk analysis in Construction IndustryProject risk analysis in Construction Industry
Project risk analysis in Construction IndustryIntaver Insititute
 
Prince2 resources e-book 1
Prince2 resources e-book 1Prince2 resources e-book 1
Prince2 resources e-book 1Knowledge Train
 

Similaire à PMP Project Risk Management Processes (20)

Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor Risks
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement Management
 
Chap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterChap 4.1- Develop Project Charter
Chap 4.1- Develop Project Charter
 
Chap 5.3 define scope
Chap 5.3 define scopeChap 5.3 define scope
Chap 5.3 define scope
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project work
 
Chap 5.2 Collect requirements
Chap 5.2 Collect requirementsChap 5.2 Collect requirements
Chap 5.2 Collect requirements
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage Communication
 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define Activity
 
Chap 8.1 Plan quality management
Chap 8.1 Plan quality managementChap 8.1 Plan quality management
Chap 8.1 Plan quality management
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire Resources
 
Chap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementChap 5.1 Plan Scope Management
Chap 5.1 Plan Scope Management
 
Chap 13.1 Identify stakeholders
Chap 13.1 Identify stakeholdersChap 13.1 Identify stakeholders
Chap 13.1 Identify stakeholders
 
Chap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management planChap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management plan
 
Chap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseChap 4.7 Project or Phase Close
Chap 4.7 Project or Phase Close
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor Communication
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication Management
 
Get Ready to Crack PeopleCert PRINCE2 Foundation Certification Exam
Get Ready to Crack PeopleCert PRINCE2 Foundation Certification ExamGet Ready to Crack PeopleCert PRINCE2 Foundation Certification Exam
Get Ready to Crack PeopleCert PRINCE2 Foundation Certification Exam
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control Resources
 
Project risk analysis in Construction Industry
Project risk analysis in Construction IndustryProject risk analysis in Construction Industry
Project risk analysis in Construction Industry
 
Prince2 resources e-book 1
Prince2 resources e-book 1Prince2 resources e-book 1
Prince2 resources e-book 1
 

Plus de Anand Bobade

Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control ProcurementAnand Bobade
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementAnand Bobade
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overviewAnand Bobade
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage TeamAnand Bobade
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost ManagementAnand Bobade
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control ScheduleAnand Bobade
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define ScheduleAnand Bobade
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityAnand Bobade
 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementAnand Bobade
 
Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control ScopeAnand Bobade
 
Chap 5.5 validate scope
Chap 5.5 validate scopeChap 5.5 validate scope
Chap 5.5 validate scopeAnand Bobade
 

Plus de Anand Bobade (11)

Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control Procurement
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct Procurement
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overview
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage Team
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost Management
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control Schedule
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define Schedule
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence Activity
 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule Management
 
Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control Scope
 
Chap 5.5 validate scope
Chap 5.5 validate scopeChap 5.5 validate scope
Chap 5.5 validate scope
 

Dernier

Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, MumbaiPooja Nehwal
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Hedda Bird
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607dollysharma2066
 
Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningCIToolkit
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxSaqib Mansoor Ahmed
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementTulsiDhidhi1
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxalinstan901
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptxAss.Prof. Dr. Mogeeb Mosleh
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 

Dernier (20)

Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdfImagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 
Disrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdfDisrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdf
 
Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for Learning
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptx
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing management
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 

PMP Project Risk Management Processes

  • 1. By: Anand Bobade (nmbobade@gmail.com) Chapter 11 – Project Risk Management PMP Trainer: Anand BobadePMBOK 6th Edition, 2019, All rights reserved. Identify Risk SIXTH EDITION
  • 2. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) 11.2 Identify Risks Identify Risks - Definition Who is involved in Risk identification? Identify Risks : ITTO What is Delphi technique? What is Risk register? Review
  • 3. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Project Risk Management Processes Plan Risk management Identify Risk Perform Qualitative Risk Analysis Perform Quantitative Risk Analysis Plan Risk Response Implement Risk Monitor Risk P MC P P P P E
  • 4. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Determine which risks may affect the project & document their characteristics Focuses on documentation of existing risks. It provides Knowledge & ability to project team, to anticipate events. Project Risk1 Risk2 Risk3 Risk4Risk5 Risk6 Risk7 Identify Risk -> Definition Determine Risks Documenting their characteristics Document Risk Charaterstics1 Charaterstics2 Charaterstics3
  • 5. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Risk Identification is an iterative process. Consistent format should be used to ensure each risk is understood clearly & unambiguously. Ownership & Responsibility - Project team should be involved in the process. The more participants involved in the process will help to identify more risks. Identify Risk -> Introduction
  • 6. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Project Manager / Project team Risk Management Experts Customers & end users SME / Consultants Project stakeholders Industry representatives Quality/ HR experts Identify Risk -> Stakeholders involved
  • 7. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Identify Risk ->ITTO Expert Judgment Data Gathering Data analysis Interpersonal and team skills Prompt lists Meetings Project Management Plan Project documents Agreements Procurement Documents Enterprise environmental factors Organizational process assets Risk Register Risk Report Project document updates Inputs Tools & Techniques Outputs
  • 8. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Project Management Plan Project documents Agreements Procurement Documents Enterprise environmental factors Organizational process assets Identify Risk ->Inputs
  • 9. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Project Management Plan Requirements Manag. Plan Schedule Manag. plan Cost Manag. Plan Quality Manag. Plan Resource Manag. Plan Risk Manag. Plan Identify Risk ->Inputs -> PMP Scope baseline Schedule baseline Cost baseline Baselines
  • 10. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Project documents Assumption log Lessons learned register Requirements documentation Risk Register Stakeholder Register Issue log Cost estimates Duration Estimates Identify Risk ->Inputs -> Project documents
  • 11. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Expert Judgment Data Gathering Data Analysis Prompt lists Meeting Interpersonal & team skills Identify Risk ->Tools & Techniques
  • 12. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Data Gathering Checklist Brainstorming Interviews Identify Risk ->T&T-> Data Gathering
  • 13. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Data Gathering Checklist Identify Risk ->T&T-> Data Gathering Risk identification checklists. Lowest level of RBS can be used as checklist. Best if Developed based on prior projects. It is impossible to build exhaustive checklist. Over reliance over checklist should be avoided.
  • 14. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Data Analysis Root cause analysis Assumptions & Constraints analysis SWOT analysis Document analysis Identify Risk ->T&T -> Data Analysis
  • 15. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Data Analysis SWOT analysis • It is a framework for analyzing organization's strengths & weaknesses, & the opportunities and threats that you face. Identify Risk ->T&T -> Data Analysis
  • 16. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Data Analysis Assumptions & Constraints analysis •It explores the validity of assumptions as they applied to the project. •All project assumptions should be verified. •Changes to assumptions or new assumptions should be identified. •Focus on the assumptions that impacts multiple project objectives. Document analysis: •Understand the content of all relevant documents •Focus on Scope, cost, time & quality •Question Assumption, Constraints •Quality of doc - completeness, consistency Identify Risk ->T&T -> Data Analysis
  • 17. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Expert Judgment Expertize should be considered from groups or individuals with specialized knowledge in the area of Risk management. Senior Management Project Stakeholders PM with similar project experience Subject Matter expert Consultants Professional & technical associates Identify Risks->T&T->Expert Judgement Help PM to do SWOT analysis Use Delphi technique to identify risks.
  • 18. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Prompt lists Prompt lists are predetermined list of categories. The lowest level of RBS is used as prompt list. strategic frameworks to identifying overall project risks - PESTLE, TECOP, VUCA Identify Risks->T&T-> Prompt lists Complexity Multiple key decision factors Volatility Rate of change Ambiguity Lack of clarity about meaning of an event Uncertainty Unclear about the present VUCA Howwellcanyoupredictthe outcomeofyouractions? How much do you know about the situation? + +- -
  • 19. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Prompt lists Identify Risks->T&T-> Prompt lists PESTLE Political Economic Social Technological Legal Environmental. TECOP Technical Economical Commercial Organizational Political.
  • 20. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Risk Register Risk Report Project doc. updates Identify Risks->Output->Risk Register
  • 21. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Risk Register The output is, initial entries into the risk register, which includes: Identify Risks->Output->Risk Register Risk Register: List of risk List of initial POTENTIAL responses Potential risk owners Root causes of risks Updated risk categories Impact I D Risk Statement Probability Scope Quality Schedule Cost Potential Response Potential Owner 1 Project owner on the client side is replaced. Low Medium Orient new project owner. Project Manager 2 Senior programmer is taken from the project. Medium High High Find replacement programmer. Project Manager 3 External system A is not ready in time to implement feature B. High Low Medium Low Discuss with stakeholders and make adjustments as agreed. Project Manager
  • 22. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Risk Register Risk Statement: Identify Risks->Output->Risk Register Context Risk Statement Source Condition Consequences If (event) occurs due to (driver), the consequences could result in (impact). Significant delays in retrieving records due to current tools for data storage and retrieval practices may leave the department unable to adequately respond to Access to Information requests.
  • 23. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Project doc. updates Assumption log Issue log Lessons learned register Identify Risks->Output-> Project doc. updates
  • 24. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Who is involved in Risk identification? What is Delphi technique? What is assumption analysis? What is SWOT analysis. What is Risk register? What is risk statement. Identify Risks -> Review
  • 25. By: Anand Bobade (nmbobade@gmail.com)