CABLE STAY BRIDGE CONSTRUCTION
By-
BALKRISHAN KUSHWAH
CABLE-STAYED BRIDGE construction
It is a bridge in which the weight of the deck is supported by a number of cables running
directly to one or more towers. These bridges are very economical for long spans (over 100
meters), especially when access to the construction site is restricted.
 Water work and coffer dam:-
Construction in water generally takes place in between 1st
July to 31st October because
during the period fewer organisms are present around the river. Water work includes
construction of foundation that is constructing piles and pile cap at the position where pylon
of tower is to be constructed. For this, focus is made on installation of piles for temporary
work bridge and also on getting sheet piles for forming coffer dams and scour protection
around them.
Sheet piles are installed with the help of pile driving hammers and coffer dam is formed, that
is an island in the river with no fishes and is isolated from render of the flowing water and so
that work can be done in any season.
Shows cofferdam
 Foundation construction: -
After the construction of coffer dam, drilling is done to 150` to 170` and temporary casing or
drilled shafts of 10` diameter are installed with help of oscillator placed over temporary
platform. Now, in these casing cage made of rebar (about 60 tones of steel) is inserted with
the help of two big cranes. Rebar stands for reinforcing bars of steel which acts as back bone
of concrete and makes structure sound. Finally concrete is poured into the casing with the
help of pipe and pump trucks to have piles. Over the piles so constructed pile cap is formed
above which tower/pylon can be constructed.
Shows cage of rebar with couplers at ends (about 14 pounds per foot)
Six piles/drilled shafts and pile cap construction
 Pile cap and pylon/tower construction:-
After the foundation is constructed, the piles are connected by pile cap in which large amount
of concrete is required. Above this pile cap, pylons or towers are constructed with the help of
prefabricated steel bars as shown below. These are green because of the oxy coating over
them which protect them from corrosion. These towers are constructed to about 80ft and over
these pylons deck is than constructed. The total height of pylons here shown is 200ft.
Prefabricated bars for pylon construction
The green cages are placed and concrete is poured with proper scaffoldings/ form work. For
the construction of pylon above deck tower crane is required. In the construction of pylons
above deck, there are precast units called saddles, are inserted in the cage which will act as a
way for cable to pass through pylon as shown.
Precast units inserted in pylon cage
 Pier table and Deck construction:-
After the construction of pylon up to deck level, pier table is constructed. A pier table is the
first portion of deck, through which cast units are placed and span is constructed. It is a
launching zone for the rest of bridge. Here pier table is of about 65` and requires about 1000
cubic yard of concrete. After the construction of pier table, remaining portion of the deck is
constructed with the help of segments either precast or cast in place. For placing segments
temporary cables are required which are distressed after stressing permanent cables. Stressing
or tensioning is done with hydraulic jacks and cables are anchored by wedges. With the help
of temporary cables, hanged by hydraulic jack from temporary precast platform over the
tower, the precast segments were held in level of pier table. The segments are connected to
the pier table with the help of projecting bars & pipes as shown.
Shows Construction of pier table
Fig shows projecting bars and pipes and precast segment.
The segments used in construction of bridge shown above are 75 feet wide and 16 feet long
and total 78 segments are used. In the construction of deck form work (anchor block) is
provided to pass cable below the deck for stressing.
Fig shows hydraulics for stressing of temporary cables and insertion of wedges.
 Installation of permanent cable and its components:-
A cable consists of six strands twisted together with resin in between them and coated with
black plastic. A group of these cables holds the deck. This group of cable is covered by
HDME pipe.
Now installation process is carried out, in which HDME pipes are held in air and with the
help of machine cable is forced through HDME pipe to reach saddle of pylon. There are 30 to
110 strands in each saddle from one to other side of tower. After the cables reached the other
side they individually are stressed with the help of hydraulic jack and computers on both
sides of tower.
Above fig shows stressing while bottom one shows hydraulic jack.
After stressing the bridge is surveyed for stability. If it is not so stable than more stressing is
done. If bridge settles after some years the cables can again be stressed. These cables below
the bridge are protected by galvanized cap and whole anchor is injected with wax. Finally
construction completes and temporary cables are removed.

Contenu connexe

Tendances

Calculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeCalculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridge
Mohammed Abdelkawy
 

Tendances (20)

Cable stay bridges, summary of a lecture delivered at Uni of Surrey, UK
Cable stay bridges, summary of a lecture delivered at Uni of Surrey, UKCable stay bridges, summary of a lecture delivered at Uni of Surrey, UK
Cable stay bridges, summary of a lecture delivered at Uni of Surrey, UK
 
Bearings in Bridges
Bearings in BridgesBearings in Bridges
Bearings in Bridges
 
Types of bridge(concept)
Types of bridge(concept)Types of bridge(concept)
Types of bridge(concept)
 
Signature bridge ppt2
Signature bridge ppt2Signature bridge ppt2
Signature bridge ppt2
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
Calculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeCalculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridge
 
Erection of steel Structure
Erection of steel StructureErection of steel Structure
Erection of steel Structure
 
Bridge,types of bridges
Bridge,types of bridgesBridge,types of bridges
Bridge,types of bridges
 
Spine and wing method for box girders
Spine and wing method for box girdersSpine and wing method for box girders
Spine and wing method for box girders
 
Prestressed construction
Prestressed constructionPrestressed construction
Prestressed construction
 
Suspension bridge
Suspension bridgeSuspension bridge
Suspension bridge
 
Suspension bridge
Suspension bridge Suspension bridge
Suspension bridge
 
cfst columns
cfst columnscfst columns
cfst columns
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
 
Extradosed Bridges: Exploring the Boundaries
Extradosed Bridges: Exploring the BoundariesExtradosed Bridges: Exploring the Boundaries
Extradosed Bridges: Exploring the Boundaries
 
Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road construction
 
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
 
Fundamentals of-psc-bridge
Fundamentals of-psc-bridgeFundamentals of-psc-bridge
Fundamentals of-psc-bridge
 
Bridge
BridgeBridge
Bridge
 
Introduction of bridges
Introduction of bridgesIntroduction of bridges
Introduction of bridges
 

Similaire à Cable stay bridge construction

Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
toddr4
 
Calculation Note Final
Calculation Note FinalCalculation Note Final
Calculation Note Final
Mohamed Elfike
 

Similaire à Cable stay bridge construction (20)

Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea link
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptx
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
 
Rail and Road Over Rail Bridge
Rail and Road Over Rail BridgeRail and Road Over Rail Bridge
Rail and Road Over Rail Bridge
 
Calculation Note Final
Calculation Note FinalCalculation Note Final
Calculation Note Final
 
Bridge-SIT-01.pptx
Bridge-SIT-01.pptxBridge-SIT-01.pptx
Bridge-SIT-01.pptx
 
Gaurav-Jhalani-Seminar-ppt.pptx
Gaurav-Jhalani-Seminar-ppt.pptxGaurav-Jhalani-Seminar-ppt.pptx
Gaurav-Jhalani-Seminar-ppt.pptx
 
suspension bridge ppt
suspension bridge pptsuspension bridge ppt
suspension bridge ppt
 
Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)
 
Millau viaduct
Millau viaductMillau viaduct
Millau viaduct
 
Susppension bridges
Susppension bridges Susppension bridges
Susppension bridges
 
Tony
TonyTony
Tony
 
THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTI...
THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTI...THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTI...
THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTI...
 
Bridge-SGI-01_Pranoti.pdf
Bridge-SGI-01_Pranoti.pdfBridge-SGI-01_Pranoti.pdf
Bridge-SGI-01_Pranoti.pdf
 
Transmission tower
Transmission towerTransmission tower
Transmission tower
 
STRESS RIBBON BRIDGE
STRESS RIBBON BRIDGESTRESS RIBBON BRIDGE
STRESS RIBBON BRIDGE
 
Presentation on Suspension Bridge
Presentation on Suspension BridgePresentation on Suspension Bridge
Presentation on Suspension Bridge
 
Suspension-Bridge-dfsdfsfdsfsdppt sos.pptx
Suspension-Bridge-dfsdfsfdsfsdppt sos.pptxSuspension-Bridge-dfsdfsfdsfsdppt sos.pptx
Suspension-Bridge-dfsdfsfdsfsdppt sos.pptx
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
 

Dernier

Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.
MateoGardella
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 
An Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdfAn Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdf
SanaAli374401
 

Dernier (20)

Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
An Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdfAn Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdf
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 

Cable stay bridge construction

  • 1. CABLE STAY BRIDGE CONSTRUCTION By- BALKRISHAN KUSHWAH
  • 2. CABLE-STAYED BRIDGE construction It is a bridge in which the weight of the deck is supported by a number of cables running directly to one or more towers. These bridges are very economical for long spans (over 100 meters), especially when access to the construction site is restricted.  Water work and coffer dam:- Construction in water generally takes place in between 1st July to 31st October because during the period fewer organisms are present around the river. Water work includes construction of foundation that is constructing piles and pile cap at the position where pylon of tower is to be constructed. For this, focus is made on installation of piles for temporary work bridge and also on getting sheet piles for forming coffer dams and scour protection around them. Sheet piles are installed with the help of pile driving hammers and coffer dam is formed, that is an island in the river with no fishes and is isolated from render of the flowing water and so that work can be done in any season. Shows cofferdam  Foundation construction: - After the construction of coffer dam, drilling is done to 150` to 170` and temporary casing or drilled shafts of 10` diameter are installed with help of oscillator placed over temporary platform. Now, in these casing cage made of rebar (about 60 tones of steel) is inserted with the help of two big cranes. Rebar stands for reinforcing bars of steel which acts as back bone of concrete and makes structure sound. Finally concrete is poured into the casing with the help of pipe and pump trucks to have piles. Over the piles so constructed pile cap is formed above which tower/pylon can be constructed.
  • 3. Shows cage of rebar with couplers at ends (about 14 pounds per foot) Six piles/drilled shafts and pile cap construction
  • 4.  Pile cap and pylon/tower construction:- After the foundation is constructed, the piles are connected by pile cap in which large amount of concrete is required. Above this pile cap, pylons or towers are constructed with the help of prefabricated steel bars as shown below. These are green because of the oxy coating over them which protect them from corrosion. These towers are constructed to about 80ft and over these pylons deck is than constructed. The total height of pylons here shown is 200ft. Prefabricated bars for pylon construction The green cages are placed and concrete is poured with proper scaffoldings/ form work. For the construction of pylon above deck tower crane is required. In the construction of pylons above deck, there are precast units called saddles, are inserted in the cage which will act as a way for cable to pass through pylon as shown. Precast units inserted in pylon cage  Pier table and Deck construction:- After the construction of pylon up to deck level, pier table is constructed. A pier table is the first portion of deck, through which cast units are placed and span is constructed. It is a launching zone for the rest of bridge. Here pier table is of about 65` and requires about 1000 cubic yard of concrete. After the construction of pier table, remaining portion of the deck is constructed with the help of segments either precast or cast in place. For placing segments temporary cables are required which are distressed after stressing permanent cables. Stressing or tensioning is done with hydraulic jacks and cables are anchored by wedges. With the help of temporary cables, hanged by hydraulic jack from temporary precast platform over the tower, the precast segments were held in level of pier table. The segments are connected to the pier table with the help of projecting bars & pipes as shown.
  • 5. Shows Construction of pier table Fig shows projecting bars and pipes and precast segment. The segments used in construction of bridge shown above are 75 feet wide and 16 feet long and total 78 segments are used. In the construction of deck form work (anchor block) is provided to pass cable below the deck for stressing. Fig shows hydraulics for stressing of temporary cables and insertion of wedges.
  • 6.  Installation of permanent cable and its components:- A cable consists of six strands twisted together with resin in between them and coated with black plastic. A group of these cables holds the deck. This group of cable is covered by HDME pipe. Now installation process is carried out, in which HDME pipes are held in air and with the help of machine cable is forced through HDME pipe to reach saddle of pylon. There are 30 to 110 strands in each saddle from one to other side of tower. After the cables reached the other side they individually are stressed with the help of hydraulic jack and computers on both sides of tower. Above fig shows stressing while bottom one shows hydraulic jack. After stressing the bridge is surveyed for stability. If it is not so stable than more stressing is done. If bridge settles after some years the cables can again be stressed. These cables below the bridge are protected by galvanized cap and whole anchor is injected with wax. Finally construction completes and temporary cables are removed.