Individual Assignment II

           PGDM (III Semester), Project Management and Analysis
Note: To be submitted on or before 5th Dec 2012



   Q 1.          A restaurant chain is considering automating the billing process. Following is the list
       and duration analysis of activities that has to be carried out in order to automate the
       process:
                                                                                  Time (Days)
                                                       Immediate
        Activity               Description                                Most       Most         Most
                                                      Predecessor
                                                                       Optimistic Likely Pessimistic
           A        Select the Hardware                     --              4           6           8
           B        Design Input/output system              A               5           7          15
           C        Design Monitoring System                A               4           8          12
           D        Assemble computer hardware              B              15          20          25
           E        Develop the main programs               B              10          18          26
           F        Develop input/output routines           C               8           9          16
           G        Create data base                        E               4           8          12
           H        Install the system                     D,F              1           2           3
           I        Test and Implement                    G,H               6           7           8

             a)   Construct an arrow diagram for this problem
             b)   Determine the critical path and compute the expected project completion time
             c)   Determine ES, EF, LS and LF time for all activities on the basis of expected time (Te)
             d)   Determine the probability of completing the project in 55 days

   Q 2.           Data for a project is:
                                                  Time (in weeks)                   Cost (in Rs)
          Activity     Preceding Activity
                                                Normal        Crash            Normal          Crash
             A               None                  3            2              18000           19000
             B               None                  8            6               600             1000
             C                  B                  6            4              10000           12000
             D                  B                  5            2               4000           10000
             E                  A                 13           10               3000            9000
             F                  A                  4            4              15000           15000
             G                  F                  2            1               1200            1400
             H               C, E, G               6            4               3500            4500
             I                  F                  2            1               7000            8000


             a) Draw a project network diagram and find the critical path
             b) If a deadline of 20 weeks is imposed for completing the project, what all activities
                will be reduced in terms of time duration and what will be cost of completing the
                project in 20 weeks
             c) What is the minimum time in which above project can be completed and what the
                cost at which project will be completed in that minimum time

Contenu connexe

Tendances

การเขียนคำสั่งควบคุมแบบซ้ำ
การเขียนคำสั่งควบคุมแบบซ้ำการเขียนคำสั่งควบคุมแบบซ้ำ
การเขียนคำสั่งควบคุมแบบซ้ำ
Siwakorn Riw
 
ฟหกกกกกกก
ฟหกกกกกกกฟหกกกกกกก
ฟหกกกกกกก
Edz Chatchawan
 
การเขียนแบบวนซ้ำ
การเขียนแบบวนซ้ำการเขียนแบบวนซ้ำ
การเขียนแบบวนซ้ำ
Edz Chatchawan
 
แผนการจัดการเรียนรู้ที่ ๓
แผนการจัดการเรียนรู้ที่  ๓แผนการจัดการเรียนรู้ที่  ๓
แผนการจัดการเรียนรู้ที่ ๓
mathawee wattana
 

Tendances (8)

Ripple look-ahead-header
Ripple look-ahead-headerRipple look-ahead-header
Ripple look-ahead-header
 
การเขียนคำสั่งควบคุมแบบซ้ำ
การเขียนคำสั่งควบคุมแบบซ้ำการเขียนคำสั่งควบคุมแบบซ้ำ
การเขียนคำสั่งควบคุมแบบซ้ำ
 
ฟหกกกกกกก
ฟหกกกกกกกฟหกกกกกกก
ฟหกกกกกกก
 
การเขียนแบบวนซ้ำ
การเขียนแบบวนซ้ำการเขียนแบบวนซ้ำ
การเขียนแบบวนซ้ำ
 
แผนการจัดการเรียนรู้ที่ ๓
แผนการจัดการเรียนรู้ที่  ๓แผนการจัดการเรียนรู้ที่  ๓
แผนการจัดการเรียนรู้ที่ ๓
 
C++ Corehard Autumn 2018. Обучаем на Python, применяем на C++ - Павел Филонов
C++ Corehard Autumn 2018. Обучаем на Python, применяем на C++ - Павел ФилоновC++ Corehard Autumn 2018. Обучаем на Python, применяем на C++ - Павел Филонов
C++ Corehard Autumn 2018. Обучаем на Python, применяем на C++ - Павел Филонов
 
Pic programms FOR 8TH SEM STUDENTS BY LOHITH KUMAR | 11GUEE6018
Pic programms FOR 8TH SEM STUDENTS BY LOHITH KUMAR | 11GUEE6018Pic programms FOR 8TH SEM STUDENTS BY LOHITH KUMAR | 11GUEE6018
Pic programms FOR 8TH SEM STUDENTS BY LOHITH KUMAR | 11GUEE6018
 
Yacf
YacfYacf
Yacf
 

Similaire à Pma individual assignment ii

Project management activity task
Project management activity taskProject management activity task
Project management activity task
Tadele Asmare
 
Scheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docxScheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docx
kenjordan97598
 
Vlsilab13
Vlsilab13Vlsilab13
Vlsilab13
Krish s
 
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
drennanmicah
 

Similaire à Pma individual assignment ii (20)

Project management project scheduling
Project management  project schedulingProject management  project scheduling
Project management project scheduling
 
Project management activity task
Project management activity taskProject management activity task
Project management activity task
 
CPM-PERT-Examples .pptx
CPM-PERT-Examples .pptxCPM-PERT-Examples .pptx
CPM-PERT-Examples .pptx
 
UNIT-2.pptx
UNIT-2.pptxUNIT-2.pptx
UNIT-2.pptx
 
Cm exercise 7
Cm exercise 7Cm exercise 7
Cm exercise 7
 
Executable Specifications in Action
Executable Specifications in ActionExecutable Specifications in Action
Executable Specifications in Action
 
Executable Specifications in Action
Executable Specifications in ActionExecutable Specifications in Action
Executable Specifications in Action
 
Network diagram problems
Network diagram problemsNetwork diagram problems
Network diagram problems
 
Cm exercise 4
Cm exercise 4Cm exercise 4
Cm exercise 4
 
Network analysis & cpm
Network analysis & cpmNetwork analysis & cpm
Network analysis & cpm
 
Scheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docxScheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docx
 
04 b50d01
04 b50d0104 b50d01
04 b50d01
 
Critical path analysis
Critical path analysisCritical path analysis
Critical path analysis
 
Cpm & network diagrams
Cpm & network diagramsCpm & network diagrams
Cpm & network diagrams
 
Vlsilab13
Vlsilab13Vlsilab13
Vlsilab13
 
Time cost-trade-off
Time cost-trade-offTime cost-trade-off
Time cost-trade-off
 
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
 
Home touch
Home touchHome touch
Home touch
 
Critical path method
Critical path methodCritical path method
Critical path method
 

Dernier

Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
Chris Hunter
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
PECB
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
QucHHunhnh
 

Dernier (20)

This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesEnergy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 

Pma individual assignment ii

  • 1. Individual Assignment II PGDM (III Semester), Project Management and Analysis Note: To be submitted on or before 5th Dec 2012 Q 1. A restaurant chain is considering automating the billing process. Following is the list and duration analysis of activities that has to be carried out in order to automate the process: Time (Days) Immediate Activity Description Most Most Most Predecessor Optimistic Likely Pessimistic A Select the Hardware -- 4 6 8 B Design Input/output system A 5 7 15 C Design Monitoring System A 4 8 12 D Assemble computer hardware B 15 20 25 E Develop the main programs B 10 18 26 F Develop input/output routines C 8 9 16 G Create data base E 4 8 12 H Install the system D,F 1 2 3 I Test and Implement G,H 6 7 8 a) Construct an arrow diagram for this problem b) Determine the critical path and compute the expected project completion time c) Determine ES, EF, LS and LF time for all activities on the basis of expected time (Te) d) Determine the probability of completing the project in 55 days Q 2. Data for a project is: Time (in weeks) Cost (in Rs) Activity Preceding Activity Normal Crash Normal Crash A None 3 2 18000 19000 B None 8 6 600 1000 C B 6 4 10000 12000 D B 5 2 4000 10000 E A 13 10 3000 9000 F A 4 4 15000 15000 G F 2 1 1200 1400 H C, E, G 6 4 3500 4500 I F 2 1 7000 8000 a) Draw a project network diagram and find the critical path b) If a deadline of 20 weeks is imposed for completing the project, what all activities will be reduced in terms of time duration and what will be cost of completing the project in 20 weeks c) What is the minimum time in which above project can be completed and what the cost at which project will be completed in that minimum time