AS RUN ENERGY EFFICIENCY
        ASSESSMENT OF HEAT RECOVERY
        STEAM GENERATORS &TURBINES
        OBJECTIVE:
    •   TO ASSESS THE AS RUN PERFORMANCE
        OF HEAT RECOVERY STEAM GENERATORS
        TOWARDS MAINT.PLG. AND UPKEEP

    AS RUN MEASUREMENTS INVOLVED:

•   G.T. AND S.T . OUTPUT MW
•   Flue Gas TEMP AT HPSH INLET& OUTLET
•   Flue Gas TEMP AT HP ECONOMISER INLET&
    OUTLET
•   Flue Gas TEMP AT LPSH INLET& OUTLET
•   Flue Gas TEMP AT LP ECONOMISER INLET&
    OUTLET
•   Flue Gas TEMP AT LP EVAPORATOR INLET &
    OUTLET
•   Flue Gas TEMP AT COND.PREHEATER INLET&
    OUTLET
•   FEED WATER FLOW AND TEMP.
•   PRESSURE & SUPER HEAT AT LP SUPER
HEAT RECOVERY STEAM GENERATORS
                 (Illustrative as run values)
     S.No. ITEM REFERENCE                         VALUE


.      G.T.OUTPUT MW                             89.62
.      S.T.OUTPUT MW                            104.71
.      H.P.STEAM FLOW TPH                       161.00
.      L.P. STEAM FLOW TPH                       37.62
.      H.P. STEAM PRESSURE BAR                            64.75
.      L.P. STEAM PRESSURE BAR                    5.11
.      H.P.SUPER HEATER TEMP.oC                          517.00
.      H.P.SUPER HEATER STEAM                   827.00
       ENTHALPY kCal/kg
.      H.P. SATURATED STEAM                     663.70
       ENTHALPY kCal/kg
0.     Flue Gas TEMP. HP SUPER HTR.             527.00
       INLET oC
1.     Flue Gas TEMP TO HPSH OUT                435/451
2.     HEAT PICK-UP IN HPSH                     26.291
       (MkCal/hr)
       Item 3*103(Item 8 - Item 9)
HRSG PERFORMANCE FEATURES
              (Illustrative as run values)

     S.No. ITEM REFERENCE                        VALUE


3.     Flue Gas TEMP. AT HP EVAP.                      435/451
       INLET oC
4.     Flue Gas TEMP. AT HP EVAP.                  290/291
       OUTLET oC
5.     ECONOMISER-2 OUT WATER                280.90
       ENTHALPY
6.     HEAT PICK-UP IN H.P.                   61.63
       EVAPORATOR(MkCal/hr)
       Item 3*103(Item 9 - Item 15)
7.     Flue Gas TEMP @ HP ECON.-2            290/291
        INLET oC
8.     FG TEMP @ HP ECON.-2                  225.00
        OUTLET oC
9.     WATER TEMP & ENTHALPY                  106.90
        @ HP ECON.1 INLET
0.     HEAT PICK-UP IN H.P.                   28.01
       ECONOMISERS-1 &2
       (MkCal/hr)
       Item 3*103(Item 15 - Item 19)
HRSG PERFORMANCE FEATURES
          ((Illustrative as run values))

S.No. ITEM REFERENCE                       VALUE

21.    FG TEMP. AT LP SUPER HTR.           225.00
       INLET O C

22.    FG TEMP. AT LP SUPER HTR.           224.00
       OUTLET o C

23.    LP SUPER HTR. TEMP.O C              197.20

24.    ENTHALPY OF LP SUPER                680.00
       HEATER STEAM (kCal/kg)

25.    ENTHALPY OF LP SATURATED            650.50
       HEATER STEAM (kCal/kg)

26.    HEAT PICKUP IN LP SUPER              0.889
       HEATER ( MkCal/hr)
       item-4 * 103 (Item-24-Item-25)
HRSG PERFORMANCE FEATURES
          (Illustrative as run values)
S.No. ITEM REFERENCE                VALUE

27.    Fl.Gas TEMP. AT LP EVAP.
224.00
       INLET oC

28.     Fl.Gas TEMP. AT LP EVAP.        169.00
        OUTLET oC

29.     F.WATER ENTHALPY AT             160.70
        EVAP. INLET kCal/kg

30.     H. PICK-UP IN L.P.              18.727
        EVAP (Mkcal/hr)
        Item 4*103(Item 25 - Item 29)
HRSG PERFORMANCE FEATURES
            (Illustrative as run values)

S.No. ITEM REFERENCE                            VALUE


 31.   FG TEMP. AT LP/HP1                  169/169
       ECONOMISER INLET oC

 32.   FG TEMP. AT LP/HP1                  120/133
       ECONOMISER OUTLET oC

 33.   FG TEMP. AT LP ECONOMISER                 104.60
       INLET oC

 34.   HEAT PICK-UP IN L.P.                          0.889
       ECONOMISER-1
       (Mill.kcal/hr)
       (Item 4*103(Item 29 - Item 33)
HRSG PERFORMANCE FEATURES
           (Illustrative as run values)

  S.No. ITEM REFERENCE                      VALUE


35.   FG TEMP. AT CONDENSATE              120/133
      PRE HEATER INLET oC
36.   FG TEMP. AT CONDENSATE               105.00
      PRE HEATER OUTLET oC
37.   FLOW THROUGH CONDENSATE              190.62
      PRE HEATER TPH (Item3-Item4)
38.   FW TEMP. AT CONDENSATE                        47.00
      PRE HEATER INLET OC
39.   FW TEMP. AT CONDENSATE                        94.10
      PRE HEATER OUTLET OC


40.   HEAT PICKUP IN                       9.355
      CONDENSATE PREHEATER
      (MkCal/hour)

41.   TOTAL HEAT PICKUP BY                 47.00
      HRSG BY WATER & STEAM
      CIRCUIT (MkCal/hr)
BREAK UP OF HEAT PICKUP IN VARIOUS
    HEAT TRANSFER SURFACES

 S.No. ITEM REFERENCE                         VALUE

 1.     PERCENTAGE BREAKUP OF
        HEAT PICKUP IN VARIOUS HEAT
        TRANSFER SURFACES:

 A.     HP SUPER HEATER                          17.89
 B.     HP EVAP.                                 41.95
 C.     HP ECON. 1&2                             19.06
 D.     LP SUPER HEATER                           8.55
 E.     LP EVAP.                                 12.74
 F.     LP ECON.                                   1.42
 G.     CONDENSATE PREHEATER                       6.36

 2.     AMBIENT AIR TEMP. OC                     29.00

 3.     THERMAL EFFY. OF HRSG                      84.43
        (Item10 - Item36/
        (Item10 - Item43)*100
 Comparing the above as run values with design data
 Would serve as an audit and diagnostics tool for
 Improvements.
COMB.CYCLE STEAM TURBINES

  OBJECTIVE
• TO ASSESS THE AS RUN PERFORMANCE
  AND EFFICIENCY OF STEAM TURBINE SYSTEMS
    AS RUN MEASUREMENTS INVOLVED:
•   HRSG HP SUPER HEATED STEAM FLOW TO
    TURBINE IN MT/HR
•   HRSG LP SUPER HEATED STEAM FLOW TO
    TURBINE IN MT/HR
•   HP STEAM PRESSURE IN BAR
•   LP STEAM PRESSURE IN BAR
•   HP SUPER HEATED STEAM TEMPERATURE IN OC
•   LP SUPERHEATED STEAM TEMPERATURE IN OC
•   CONDENSER VACUUM (MILLI BAR)
•   STEAM TURBINE GENERATOR ACTIVE POWER
    IN MW
•   DRYNESS FRACTION OF TURBINE EXHAUST :
    ESTIMATED AS WARRANTED
STEAM TURBINE PERFORMANCE
          ASSESSMENT ILLUSTRATIVE
               CALCULATION
1)   Trial Duration          :   (As run Sample Reference)
2)   HP Steam Flow           : 350.26 TPH




3)   HP Steam Pressure & : 65.44 bar, 518 oC
     Temperature
4)   HP Steam Enthalpy : 3459.50
     kJ/KG
5)   LP Steam Flow in TPH : 79.58 TPH
6)   LP Steam Pressure & : 4.35 bar, 194.2 oC
     Temperature
7)   LP   Steam    Enthalpy : 2842.40
     kJ/KG
8)   Condenser Vacuum m : 93.50
     bar
9)   Condenser    Saturated : 44.5 oC and 186
     Temperature & Enthalpy
10) Exhaust            Steam : 2144.20
    Enthalpy      for    0.82
    Dryness     Fraction in
    kJ/KG
11) Condensate Enthalpy : 186.0
    kJ/KG
12) Heat Input to Steam : [(Total HP Steam Flow in TPH)
    Turbine 1000 * kJ/Hr. * (HP Steam Enthalpy – LP
                          Exhaust Enthalpy) + (Total LP
                          Steam Enthalpy - LP Exhaust
                          Enthalpy)]
                            : [(Item 2)(Item 4 - Item 10) +
                              (Item 5) (Item 7 - Item 10)]
                            : (350.26)(3459.5 - 2144.2) +
                              (79.58)(2842.40 - 2144.2)
                            : 460696.97 + 55562.76
                           : 516259.73
13) Theoretical Heat Input : Heat Input to Turbine in KJ/HR
    to Turbine in MW                  1000 * 3600

                            : Item 12/3600
                            : 143.40
14) Actual      Generator : 112.43
    Output (MW)
15) Turbine + Generator : Generator          Output/Turbine
    Efficiency              Input
                            : Item 14 / Item 13
                            : 78.40%
16) Turbine Heat Input with : [(Total HP Steam Flow in TPH)
    Reference            to   * (Heat Steam Enthalpy -
    condensate Enthalpy       Condensate Enthalpy) + (total
    (1000 * kJ/Hr)            LP Steam Flow in TPH) * (LP
                              Steam Enthalpy - Condensate
                              Enthalpy)]
                               : [(Item 2)(Item 4 - Item 11) +
                                 (Item 5)(Item 7 - Item 11)]
                               : [(350.26)(3459.5 - 186)          +
                                 (79.58)(2842.4 - 186)]
                               : 1146576.10 + 211396.30
                               : 1357972.40
17) Feed Water and Steam : (Turbine Heat Input w.r.t.
    Turbine System Heat    condensate     Enthalpy  in
    Rate in Kcal/kWh       Kcal)/(TG Output in kWh)
                               : (Item 16) / 4.18 * 1/(Item 14)
                           : 2889.56 Kcal/ kWh
18) TG Output as % of 100% : (Item 14) * 100 = (112.43) * 100
    Base Load Rating             115.69           115.69
                           : 97.18%

Contenu connexe

Tendances

Pre commissioning steam turbines load trial
Pre commissioning steam turbines load trialPre commissioning steam turbines load trial
Pre commissioning steam turbines load trialNagesh H
 
Hp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesHp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesBoben Anto Chemmannoor
 
Unit shutdown procedure operation
Unit shutdown procedure operationUnit shutdown procedure operation
Unit shutdown procedure operationNitin Patel
 
Final Turbine rolling ppt Akshay.pptx
Final Turbine rolling ppt Akshay.pptxFinal Turbine rolling ppt Akshay.pptx
Final Turbine rolling ppt Akshay.pptxBhimarajuKanireddy
 
Air Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance IndicesAir Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance IndicesManohar Tatwawadi
 
Performance calculation for feed water heater
Performance calculation  for feed water heaterPerformance calculation  for feed water heater
Performance calculation for feed water heaterSHIVAJI CHOUDHURY
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownNitin Mahalle
 
STEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGSTEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGAshish Kumar Jain
 
Standard boiler 500 mwerection manual (boiler auxiliaries)
Standard boiler 500 mwerection manual (boiler auxiliaries)Standard boiler 500 mwerection manual (boiler auxiliaries)
Standard boiler 500 mwerection manual (boiler auxiliaries)Ashutosh Sachan
 
THERMAL POWER PLANT EFFICIENCY AND HEAT RATE
THERMAL POWER PLANT EFFICIENCY AND HEAT RATETHERMAL POWER PLANT EFFICIENCY AND HEAT RATE
THERMAL POWER PLANT EFFICIENCY AND HEAT RATEManohar Tatwawadi
 
Training material for air preheater
Training material for air preheaterTraining material for air preheater
Training material for air preheaterHOANG VAN DUC
 
Maintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINEMaintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINESAI SHARATH GAMPA
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownAshvani Shukla
 
Steam Turbines
Steam Turbines Steam Turbines
Steam Turbines Amir Ayad
 
Energy adudit methodology for boiler
Energy adudit methodology for boilerEnergy adudit methodology for boiler
Energy adudit methodology for boilerKongkiert Tankayura
 

Tendances (20)

Pre commissioning steam turbines load trial
Pre commissioning steam turbines load trialPre commissioning steam turbines load trial
Pre commissioning steam turbines load trial
 
Hp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesHp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbines
 
Boiler calculations
Boiler calculationsBoiler calculations
Boiler calculations
 
Unit shutdown procedure operation
Unit shutdown procedure operationUnit shutdown procedure operation
Unit shutdown procedure operation
 
Final Turbine rolling ppt Akshay.pptx
Final Turbine rolling ppt Akshay.pptxFinal Turbine rolling ppt Akshay.pptx
Final Turbine rolling ppt Akshay.pptx
 
Air Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance IndicesAir Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance Indices
 
Performance calculation for feed water heater
Performance calculation  for feed water heaterPerformance calculation  for feed water heater
Performance calculation for feed water heater
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdown
 
STEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGSTEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTING
 
Standard boiler 500 mwerection manual (boiler auxiliaries)
Standard boiler 500 mwerection manual (boiler auxiliaries)Standard boiler 500 mwerection manual (boiler auxiliaries)
Standard boiler 500 mwerection manual (boiler auxiliaries)
 
Heat balance diagram
Heat balance diagramHeat balance diagram
Heat balance diagram
 
Turbine safety protection
Turbine safety protectionTurbine safety protection
Turbine safety protection
 
THERMAL POWER PLANT EFFICIENCY AND HEAT RATE
THERMAL POWER PLANT EFFICIENCY AND HEAT RATETHERMAL POWER PLANT EFFICIENCY AND HEAT RATE
THERMAL POWER PLANT EFFICIENCY AND HEAT RATE
 
Training material for air preheater
Training material for air preheaterTraining material for air preheater
Training material for air preheater
 
Maintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINEMaintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINE
 
Thermax report (1)
Thermax report (1)Thermax report (1)
Thermax report (1)
 
Unit protection scheme
Unit protection schemeUnit protection scheme
Unit protection scheme
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdown
 
Steam Turbines
Steam Turbines Steam Turbines
Steam Turbines
 
Energy adudit methodology for boiler
Energy adudit methodology for boilerEnergy adudit methodology for boiler
Energy adudit methodology for boiler
 

Similaire à Hrsg & turbine as run energy efficiency assessment

Turbine cycle heat rate calculation
Turbine  cycle heat rate calculationTurbine  cycle heat rate calculation
Turbine cycle heat rate calculationSHIVAJI CHOUDHURY
 
Steam Turbine Performance in TPS
Steam Turbine Performance in TPSSteam Turbine Performance in TPS
Steam Turbine Performance in TPSManohar Tatwawadi
 
Refrigeration system 2
Refrigeration system 2Refrigeration system 2
Refrigeration system 2Yuri Melliza
 
Refrigeration system 2
Refrigeration system 2Refrigeration system 2
Refrigeration system 2Yuri Melliza
 
Steam Power Cycle and Basics of Boiler
Steam Power Cycle and Basics of BoilerSteam Power Cycle and Basics of Boiler
Steam Power Cycle and Basics of BoilerMulugeta Wotango
 
Design Project Presentation
Design Project PresentationDesign Project Presentation
Design Project PresentationRobert Cote
 
Haitao Hu - NORWEGIAN UNIVERSITY OF SCIENCE AND TECHNOLOGY - POMPE DI CALORE ...
Haitao Hu - NORWEGIAN UNIVERSITY OF SCIENCE AND TECHNOLOGY - POMPE DI CALORE ...Haitao Hu - NORWEGIAN UNIVERSITY OF SCIENCE AND TECHNOLOGY - POMPE DI CALORE ...
Haitao Hu - NORWEGIAN UNIVERSITY OF SCIENCE AND TECHNOLOGY - POMPE DI CALORE ...Centro Studi Galileo
 
Ae32626632
Ae32626632Ae32626632
Ae32626632IJMER
 
Lec 10-11 - Refrigeration cycle
Lec 10-11 - Refrigeration cycle Lec 10-11 - Refrigeration cycle
Lec 10-11 - Refrigeration cycle Sijal Ahmed
 
thermal project 1
thermal project 1thermal project 1
thermal project 1James Li
 
Modeling and Valuing Cogeneration with AURORAxmp
Modeling and Valuing Cogeneration with AURORAxmpModeling and Valuing Cogeneration with AURORAxmp
Modeling and Valuing Cogeneration with AURORAxmpEPIS Inc
 
Downdraft biomass gasification: experimental investigation and aspen plus sim...
Downdraft biomass gasification: experimental investigation and aspen plus sim...Downdraft biomass gasification: experimental investigation and aspen plus sim...
Downdraft biomass gasification: experimental investigation and aspen plus sim...Antonio Geraldo de Paula Oliveira
 
Thermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its AuxillariesThermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its AuxillariesVaibhav Paydelwar
 
HdhdPM3125_Lectures_16to17_Evaporation.ppt
HdhdPM3125_Lectures_16to17_Evaporation.pptHdhdPM3125_Lectures_16to17_Evaporation.ppt
HdhdPM3125_Lectures_16to17_Evaporation.pptJENILPATEL919230
 
Fossil Fuel Steam Generator (Thermal Power Plant)
Fossil Fuel Steam Generator (Thermal Power Plant)Fossil Fuel Steam Generator (Thermal Power Plant)
Fossil Fuel Steam Generator (Thermal Power Plant)Hashim Hasnain Hadi
 
Dynamic simulation of Steam and Power System.ppt
Dynamic simulation of Steam and Power System.pptDynamic simulation of Steam and Power System.ppt
Dynamic simulation of Steam and Power System.pptMurty Moguluru
 

Similaire à Hrsg & turbine as run energy efficiency assessment (20)

Turbine cycle heat rate calculation
Turbine  cycle heat rate calculationTurbine  cycle heat rate calculation
Turbine cycle heat rate calculation
 
Steam Turbine Performance in TPS
Steam Turbine Performance in TPSSteam Turbine Performance in TPS
Steam Turbine Performance in TPS
 
Refrigeration system 2
Refrigeration system 2Refrigeration system 2
Refrigeration system 2
 
Refrigeration system 2
Refrigeration system 2Refrigeration system 2
Refrigeration system 2
 
Steam Power Cycle and Basics of Boiler
Steam Power Cycle and Basics of BoilerSteam Power Cycle and Basics of Boiler
Steam Power Cycle and Basics of Boiler
 
Design Project Presentation
Design Project PresentationDesign Project Presentation
Design Project Presentation
 
Haitao Hu - NORWEGIAN UNIVERSITY OF SCIENCE AND TECHNOLOGY - POMPE DI CALORE ...
Haitao Hu - NORWEGIAN UNIVERSITY OF SCIENCE AND TECHNOLOGY - POMPE DI CALORE ...Haitao Hu - NORWEGIAN UNIVERSITY OF SCIENCE AND TECHNOLOGY - POMPE DI CALORE ...
Haitao Hu - NORWEGIAN UNIVERSITY OF SCIENCE AND TECHNOLOGY - POMPE DI CALORE ...
 
Power cycles 1
Power cycles 1Power cycles 1
Power cycles 1
 
Ae32626632
Ae32626632Ae32626632
Ae32626632
 
Lec 10-11 - Refrigeration cycle
Lec 10-11 - Refrigeration cycle Lec 10-11 - Refrigeration cycle
Lec 10-11 - Refrigeration cycle
 
thermal project 1
thermal project 1thermal project 1
thermal project 1
 
Modeling and Valuing Cogeneration with AURORAxmp
Modeling and Valuing Cogeneration with AURORAxmpModeling and Valuing Cogeneration with AURORAxmp
Modeling and Valuing Cogeneration with AURORAxmp
 
Turbin gas cal.
Turbin gas cal.Turbin gas cal.
Turbin gas cal.
 
Downdraft biomass gasification: experimental investigation and aspen plus sim...
Downdraft biomass gasification: experimental investigation and aspen plus sim...Downdraft biomass gasification: experimental investigation and aspen plus sim...
Downdraft biomass gasification: experimental investigation and aspen plus sim...
 
project 2
project 2project 2
project 2
 
Thermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its AuxillariesThermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its Auxillaries
 
HdhdPM3125_Lectures_16to17_Evaporation.ppt
HdhdPM3125_Lectures_16to17_Evaporation.pptHdhdPM3125_Lectures_16to17_Evaporation.ppt
HdhdPM3125_Lectures_16to17_Evaporation.ppt
 
Fossil Fuel Steam Generator (Thermal Power Plant)
Fossil Fuel Steam Generator (Thermal Power Plant)Fossil Fuel Steam Generator (Thermal Power Plant)
Fossil Fuel Steam Generator (Thermal Power Plant)
 
Gross turbine cycle_heat_rate_ch-8.2
Gross turbine cycle_heat_rate_ch-8.2Gross turbine cycle_heat_rate_ch-8.2
Gross turbine cycle_heat_rate_ch-8.2
 
Dynamic simulation of Steam and Power System.ppt
Dynamic simulation of Steam and Power System.pptDynamic simulation of Steam and Power System.ppt
Dynamic simulation of Steam and Power System.ppt
 

Plus de D.Pawan Kumar

Indian energy efficiency scene..a macro perspective.
Indian energy efficiency scene..a macro perspective.Indian energy efficiency scene..a macro perspective.
Indian energy efficiency scene..a macro perspective.D.Pawan Kumar
 
Roadmap for distribution loss reduction.. a step by step approach
Roadmap  for distribution loss reduction.. a step by step approachRoadmap  for distribution loss reduction.. a step by step approach
Roadmap for distribution loss reduction.. a step by step approachD.Pawan Kumar
 
Water conservation opportunities.
Water conservation opportunities.Water conservation opportunities.
Water conservation opportunities.D.Pawan Kumar
 
Turnkey implementation of distribution projects
Turnkey implementation of distribution projectsTurnkey implementation of distribution projects
Turnkey implementation of distribution projectsD.Pawan Kumar
 
Cogeneration: regional experiences
Cogeneration: regional experiencesCogeneration: regional experiences
Cogeneration: regional experiencesD.Pawan Kumar
 
Energy efficient technology procurement
Energy efficient technology  procurementEnergy efficient technology  procurement
Energy efficient technology procurementD.Pawan Kumar
 
Boiler ea case study 16 jan 2012 varanasi
Boiler ea case study  16 jan 2012 varanasiBoiler ea case study  16 jan 2012 varanasi
Boiler ea case study 16 jan 2012 varanasiD.Pawan Kumar
 
Ea of cw, ct & cond. system
Ea of cw, ct & cond. systemEa of cw, ct & cond. system
Ea of cw, ct & cond. systemD.Pawan Kumar
 
Training manual on energy efficiency for SMEs
Training manual on energy efficiency for SMEsTraining manual on energy efficiency for SMEs
Training manual on energy efficiency for SMEsD.Pawan Kumar
 
Electricity demand side management and end use efficiency
Electricity demand side management and end use efficiencyElectricity demand side management and end use efficiency
Electricity demand side management and end use efficiencyD.Pawan Kumar
 
As run energy efficiency of cooling towers
As run energy efficiency of cooling towersAs run energy efficiency of cooling towers
As run energy efficiency of cooling towersD.Pawan Kumar
 
Focus areas in economic operation of DG sets
Focus areas in economic operation of DG setsFocus areas in economic operation of DG sets
Focus areas in economic operation of DG setsD.Pawan Kumar
 
How to conduct energy audit
How to conduct energy auditHow to conduct energy audit
How to conduct energy auditD.Pawan Kumar
 
Desirable as run information system for energy efficiency of utility clas...
Desirable as run information system  for energy efficiency  of  utility  clas...Desirable as run information system  for energy efficiency  of  utility  clas...
Desirable as run information system for energy efficiency of utility clas...D.Pawan Kumar
 
As run boiler performance assessment for energy efficiency
As run boiler performance assessment for energy efficiencyAs run boiler performance assessment for energy efficiency
As run boiler performance assessment for energy efficiencyD.Pawan Kumar
 
Energy efficiency in pumps and fans ppt
Energy efficiency in pumps and fans pptEnergy efficiency in pumps and fans ppt
Energy efficiency in pumps and fans pptD.Pawan Kumar
 
Energy efficiency in buildings
Energy efficiency in buildingsEnergy efficiency in buildings
Energy efficiency in buildingsD.Pawan Kumar
 
Compressed air and refrigeration system
Compressed air and refrigeration systemCompressed air and refrigeration system
Compressed air and refrigeration systemD.Pawan Kumar
 

Plus de D.Pawan Kumar (19)

Indian energy efficiency scene..a macro perspective.
Indian energy efficiency scene..a macro perspective.Indian energy efficiency scene..a macro perspective.
Indian energy efficiency scene..a macro perspective.
 
Roadmap for distribution loss reduction.. a step by step approach
Roadmap  for distribution loss reduction.. a step by step approachRoadmap  for distribution loss reduction.. a step by step approach
Roadmap for distribution loss reduction.. a step by step approach
 
Water conservation opportunities.
Water conservation opportunities.Water conservation opportunities.
Water conservation opportunities.
 
Turnkey implementation of distribution projects
Turnkey implementation of distribution projectsTurnkey implementation of distribution projects
Turnkey implementation of distribution projects
 
Cogeneration: regional experiences
Cogeneration: regional experiencesCogeneration: regional experiences
Cogeneration: regional experiences
 
Energy efficient technology procurement
Energy efficient technology  procurementEnergy efficient technology  procurement
Energy efficient technology procurement
 
Boiler ea case study 16 jan 2012 varanasi
Boiler ea case study  16 jan 2012 varanasiBoiler ea case study  16 jan 2012 varanasi
Boiler ea case study 16 jan 2012 varanasi
 
Ea of cw, ct & cond. system
Ea of cw, ct & cond. systemEa of cw, ct & cond. system
Ea of cw, ct & cond. system
 
Ee opportunities
Ee opportunities Ee opportunities
Ee opportunities
 
Training manual on energy efficiency for SMEs
Training manual on energy efficiency for SMEsTraining manual on energy efficiency for SMEs
Training manual on energy efficiency for SMEs
 
Electricity demand side management and end use efficiency
Electricity demand side management and end use efficiencyElectricity demand side management and end use efficiency
Electricity demand side management and end use efficiency
 
As run energy efficiency of cooling towers
As run energy efficiency of cooling towersAs run energy efficiency of cooling towers
As run energy efficiency of cooling towers
 
Focus areas in economic operation of DG sets
Focus areas in economic operation of DG setsFocus areas in economic operation of DG sets
Focus areas in economic operation of DG sets
 
How to conduct energy audit
How to conduct energy auditHow to conduct energy audit
How to conduct energy audit
 
Desirable as run information system for energy efficiency of utility clas...
Desirable as run information system  for energy efficiency  of  utility  clas...Desirable as run information system  for energy efficiency  of  utility  clas...
Desirable as run information system for energy efficiency of utility clas...
 
As run boiler performance assessment for energy efficiency
As run boiler performance assessment for energy efficiencyAs run boiler performance assessment for energy efficiency
As run boiler performance assessment for energy efficiency
 
Energy efficiency in pumps and fans ppt
Energy efficiency in pumps and fans pptEnergy efficiency in pumps and fans ppt
Energy efficiency in pumps and fans ppt
 
Energy efficiency in buildings
Energy efficiency in buildingsEnergy efficiency in buildings
Energy efficiency in buildings
 
Compressed air and refrigeration system
Compressed air and refrigeration systemCompressed air and refrigeration system
Compressed air and refrigeration system
 

Dernier

Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...rajveerescorts2022
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...lizamodels9
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756dollysharma2066
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 

Dernier (20)

Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 

Hrsg & turbine as run energy efficiency assessment

  • 1. AS RUN ENERGY EFFICIENCY ASSESSMENT OF HEAT RECOVERY STEAM GENERATORS &TURBINES OBJECTIVE: • TO ASSESS THE AS RUN PERFORMANCE OF HEAT RECOVERY STEAM GENERATORS TOWARDS MAINT.PLG. AND UPKEEP AS RUN MEASUREMENTS INVOLVED: • G.T. AND S.T . OUTPUT MW • Flue Gas TEMP AT HPSH INLET& OUTLET • Flue Gas TEMP AT HP ECONOMISER INLET& OUTLET • Flue Gas TEMP AT LPSH INLET& OUTLET • Flue Gas TEMP AT LP ECONOMISER INLET& OUTLET • Flue Gas TEMP AT LP EVAPORATOR INLET & OUTLET • Flue Gas TEMP AT COND.PREHEATER INLET& OUTLET • FEED WATER FLOW AND TEMP. • PRESSURE & SUPER HEAT AT LP SUPER
  • 2. HEAT RECOVERY STEAM GENERATORS (Illustrative as run values) S.No. ITEM REFERENCE VALUE . G.T.OUTPUT MW 89.62 . S.T.OUTPUT MW 104.71 . H.P.STEAM FLOW TPH 161.00 . L.P. STEAM FLOW TPH 37.62 . H.P. STEAM PRESSURE BAR 64.75 . L.P. STEAM PRESSURE BAR 5.11 . H.P.SUPER HEATER TEMP.oC 517.00 . H.P.SUPER HEATER STEAM 827.00 ENTHALPY kCal/kg . H.P. SATURATED STEAM 663.70 ENTHALPY kCal/kg 0. Flue Gas TEMP. HP SUPER HTR. 527.00 INLET oC 1. Flue Gas TEMP TO HPSH OUT 435/451 2. HEAT PICK-UP IN HPSH 26.291 (MkCal/hr) Item 3*103(Item 8 - Item 9)
  • 3. HRSG PERFORMANCE FEATURES (Illustrative as run values) S.No. ITEM REFERENCE VALUE 3. Flue Gas TEMP. AT HP EVAP. 435/451 INLET oC 4. Flue Gas TEMP. AT HP EVAP. 290/291 OUTLET oC 5. ECONOMISER-2 OUT WATER 280.90 ENTHALPY 6. HEAT PICK-UP IN H.P. 61.63 EVAPORATOR(MkCal/hr) Item 3*103(Item 9 - Item 15) 7. Flue Gas TEMP @ HP ECON.-2 290/291 INLET oC 8. FG TEMP @ HP ECON.-2 225.00 OUTLET oC 9. WATER TEMP & ENTHALPY 106.90 @ HP ECON.1 INLET 0. HEAT PICK-UP IN H.P. 28.01 ECONOMISERS-1 &2 (MkCal/hr) Item 3*103(Item 15 - Item 19)
  • 4. HRSG PERFORMANCE FEATURES ((Illustrative as run values)) S.No. ITEM REFERENCE VALUE 21. FG TEMP. AT LP SUPER HTR. 225.00 INLET O C 22. FG TEMP. AT LP SUPER HTR. 224.00 OUTLET o C 23. LP SUPER HTR. TEMP.O C 197.20 24. ENTHALPY OF LP SUPER 680.00 HEATER STEAM (kCal/kg) 25. ENTHALPY OF LP SATURATED 650.50 HEATER STEAM (kCal/kg) 26. HEAT PICKUP IN LP SUPER 0.889 HEATER ( MkCal/hr) item-4 * 103 (Item-24-Item-25)
  • 5. HRSG PERFORMANCE FEATURES (Illustrative as run values) S.No. ITEM REFERENCE VALUE 27. Fl.Gas TEMP. AT LP EVAP. 224.00 INLET oC 28. Fl.Gas TEMP. AT LP EVAP. 169.00 OUTLET oC 29. F.WATER ENTHALPY AT 160.70 EVAP. INLET kCal/kg 30. H. PICK-UP IN L.P. 18.727 EVAP (Mkcal/hr) Item 4*103(Item 25 - Item 29)
  • 6. HRSG PERFORMANCE FEATURES (Illustrative as run values) S.No. ITEM REFERENCE VALUE 31. FG TEMP. AT LP/HP1 169/169 ECONOMISER INLET oC 32. FG TEMP. AT LP/HP1 120/133 ECONOMISER OUTLET oC 33. FG TEMP. AT LP ECONOMISER 104.60 INLET oC 34. HEAT PICK-UP IN L.P. 0.889 ECONOMISER-1 (Mill.kcal/hr) (Item 4*103(Item 29 - Item 33)
  • 7. HRSG PERFORMANCE FEATURES (Illustrative as run values) S.No. ITEM REFERENCE VALUE 35. FG TEMP. AT CONDENSATE 120/133 PRE HEATER INLET oC 36. FG TEMP. AT CONDENSATE 105.00 PRE HEATER OUTLET oC 37. FLOW THROUGH CONDENSATE 190.62 PRE HEATER TPH (Item3-Item4) 38. FW TEMP. AT CONDENSATE 47.00 PRE HEATER INLET OC 39. FW TEMP. AT CONDENSATE 94.10 PRE HEATER OUTLET OC 40. HEAT PICKUP IN 9.355 CONDENSATE PREHEATER (MkCal/hour) 41. TOTAL HEAT PICKUP BY 47.00 HRSG BY WATER & STEAM CIRCUIT (MkCal/hr)
  • 8. BREAK UP OF HEAT PICKUP IN VARIOUS HEAT TRANSFER SURFACES S.No. ITEM REFERENCE VALUE 1. PERCENTAGE BREAKUP OF HEAT PICKUP IN VARIOUS HEAT TRANSFER SURFACES: A. HP SUPER HEATER 17.89 B. HP EVAP. 41.95 C. HP ECON. 1&2 19.06 D. LP SUPER HEATER 8.55 E. LP EVAP. 12.74 F. LP ECON. 1.42 G. CONDENSATE PREHEATER 6.36 2. AMBIENT AIR TEMP. OC 29.00 3. THERMAL EFFY. OF HRSG 84.43 (Item10 - Item36/ (Item10 - Item43)*100 Comparing the above as run values with design data Would serve as an audit and diagnostics tool for Improvements.
  • 9. COMB.CYCLE STEAM TURBINES OBJECTIVE • TO ASSESS THE AS RUN PERFORMANCE AND EFFICIENCY OF STEAM TURBINE SYSTEMS AS RUN MEASUREMENTS INVOLVED: • HRSG HP SUPER HEATED STEAM FLOW TO TURBINE IN MT/HR • HRSG LP SUPER HEATED STEAM FLOW TO TURBINE IN MT/HR • HP STEAM PRESSURE IN BAR • LP STEAM PRESSURE IN BAR • HP SUPER HEATED STEAM TEMPERATURE IN OC • LP SUPERHEATED STEAM TEMPERATURE IN OC • CONDENSER VACUUM (MILLI BAR) • STEAM TURBINE GENERATOR ACTIVE POWER IN MW • DRYNESS FRACTION OF TURBINE EXHAUST : ESTIMATED AS WARRANTED
  • 10. STEAM TURBINE PERFORMANCE ASSESSMENT ILLUSTRATIVE CALCULATION 1) Trial Duration : (As run Sample Reference) 2) HP Steam Flow : 350.26 TPH 3) HP Steam Pressure & : 65.44 bar, 518 oC Temperature 4) HP Steam Enthalpy : 3459.50 kJ/KG 5) LP Steam Flow in TPH : 79.58 TPH 6) LP Steam Pressure & : 4.35 bar, 194.2 oC Temperature 7) LP Steam Enthalpy : 2842.40 kJ/KG 8) Condenser Vacuum m : 93.50 bar 9) Condenser Saturated : 44.5 oC and 186 Temperature & Enthalpy 10) Exhaust Steam : 2144.20 Enthalpy for 0.82 Dryness Fraction in kJ/KG
  • 11. 11) Condensate Enthalpy : 186.0 kJ/KG 12) Heat Input to Steam : [(Total HP Steam Flow in TPH) Turbine 1000 * kJ/Hr. * (HP Steam Enthalpy – LP Exhaust Enthalpy) + (Total LP Steam Enthalpy - LP Exhaust Enthalpy)] : [(Item 2)(Item 4 - Item 10) + (Item 5) (Item 7 - Item 10)] : (350.26)(3459.5 - 2144.2) + (79.58)(2842.40 - 2144.2) : 460696.97 + 55562.76 : 516259.73 13) Theoretical Heat Input : Heat Input to Turbine in KJ/HR to Turbine in MW 1000 * 3600 : Item 12/3600 : 143.40 14) Actual Generator : 112.43 Output (MW) 15) Turbine + Generator : Generator Output/Turbine Efficiency Input : Item 14 / Item 13 : 78.40%
  • 12. 16) Turbine Heat Input with : [(Total HP Steam Flow in TPH) Reference to * (Heat Steam Enthalpy - condensate Enthalpy Condensate Enthalpy) + (total (1000 * kJ/Hr) LP Steam Flow in TPH) * (LP Steam Enthalpy - Condensate Enthalpy)] : [(Item 2)(Item 4 - Item 11) + (Item 5)(Item 7 - Item 11)] : [(350.26)(3459.5 - 186) + (79.58)(2842.4 - 186)] : 1146576.10 + 211396.30 : 1357972.40 17) Feed Water and Steam : (Turbine Heat Input w.r.t. Turbine System Heat condensate Enthalpy in Rate in Kcal/kWh Kcal)/(TG Output in kWh) : (Item 16) / 4.18 * 1/(Item 14) : 2889.56 Kcal/ kWh 18) TG Output as % of 100% : (Item 14) * 100 = (112.43) * 100 Base Load Rating 115.69 115.69 : 97.18%