SlideShare une entreprise Scribd logo
1  sur  116
Slide 1
8-1
Capital Budgeting
• Analysis of potential projects
• Long-term decisions
• Large expenditures
• Difficult/impossible to reverse
• Determines firm’s strategic direction
When a company is deciding whether to invest in a new project,
large sums of money can be at stake. For
example, the Artic LNG project would build a pipeline from
Alaska’s North Slope to allow natural gas to
be sent from the area. The cost of the pipeline and plant to clean
the gas of impurities was expected to be
$45 to $65 billion. Decisions such as these long-term
investments, with price tags in the billions, are
obviously major undertakings, and the risks and rewards must
be carefully weighed. We called this the
capital budgeting decision. This module introduces you to the
practice of capital budgeting. We will
consider a variety of techniques financial analysts and corporate
executives routinely use for the capital
budgeting decisions.
1. Net Present Value (NPV)
2. Payback Period
3. Average Accounting Rate (AAR)
4. Internal Rate of Return (IRR) or Modified Internal Rate of
Return (MIRR)
5. Profitability Index (PI)
Slide 2
8-2
• All cash flows considered?
• TVM considered?
• Risk-adjusted?
• Ability to rank projects?
• Indicates added value to the firm?
Good Decision Criteria
All things here are related to maximize the stock price. We need
to ask ourselves the following
questions when evaluating capital budgeting decision rules:
creating value for the firm?
Slide 3
8-3
Net Present Value
• The difference between the market value of a
project and its cost
• How much value is created from undertaking
an investment?
Step 1: Estimate the expected future cash flows.
Step 2: Estimate the required return for projects of
this risk level.
Step 3: Find the present value of the cash flows and
subtract the initial investment to arrive at the Net
Present Value.
Net present value—the difference between the market value of
an investment and its cost.
The NPV measures the increase in firm value, which is also the
increase in the value of what the
shareholders own. Thus, making decisions with the NPV rule
facilitates the achievement of our
goal – making decisions that will maximize shareholder wealth.
Slide 4
8-4
Net Present Value
Sum of the PVs of all cash flows
Initial cost often is CF0 and is an outflow.
NPV =∑
n
t = 0
CFt
(1 + R)t
NPV =∑
n
t = 1
CFt
(1 + R)t
- CF0
NOTE: t=0
Up to now, we’ve avoided cash flows at time t = 0, the
summation begins with cash flow zero—
not one.
The PV of future cash flows is not NPV; rather, NPV is the
amount remaining after offsetting the
PV of future cash flows with the initial cost. Thus, the NPV
amount determines the incremental
value created by undertaking the investment.
Slide 5
8-5
NPV – Decision Rule
• If NPV is positive, accept the project
• NPV > 0 means:
– Project is expected to add value to the firm
– Will increase the wealth of the owners
• NPV is a direct measure of how well this
project will meet the goal of increasing
shareholder wealth.
Slide 6
8-6
Rationale for the NPV Method
• NPV = PV inflows – Cost
NPV=0 → Project’s inflows are “exactly
sufficient to repay the invested capital and
provide the required rate of return”
Conceptually, a zero-NPV project earns exactly its required
return. Assuming that risk has been
adequately accounted for, investing in a zero-NPV project is
equivalent to purchasing a financial
asset in an efficient market. In this sense, one would be
indifferent between the capital expenditure
project and the financial asset investment. Further, since firm
value is completely unaffected by
the investment, there is no reason for shareholders to prefer
either one.
In practice, financial managers are rarely presented with zero
NPV projects for at least two reasons.
First, in an abstract sense, zero is just another of the infinite
number of values the NPV can take;
as such, the likelihood of obtaining any particular number is
small. Second, and more pragmatically,
in most large firms, capital investment proposals are submitted
to the finance group from other
areas for analysis. Those submitting proposals recognize the
ambivalence associated with zero
NPVs and are less likely to send them to the finance group in
the first place.
Slide 7
8-7
Sample Project Data
• You are looking at a new project and have estimated
the following cash flows, net income and book value
data:
– Year 0: CF = -165,000
– Year 1: CF = 63,120 NI = 13,620
– Year 2: CF = 70,800 NI = 3,300
– Year 3: CF = 91,080 NI = 29,100
– Average book value = $72,000
• Your required return for assets of this risk is 12%.
• This project will be the example for all problem
exhibits in this module.
This example will be used for each of the decision rules so that
we can compare the different rules
and see that conflicts can arise. This illustrates the importance
of recognizing which decision rules
provide the best information for making decisions that will
increase owner wealth.
Slide 8
8-8
Display You Enter
CF, 2nd,CLR WORK
CF0 -165000 Enter, Down
C01 63120 Enter, Down
F01 1 Enter, Down
C02 70800 Enter, Down
F02 1 Enter, Down
C03 91080 Enter, Down
F03 1 Enter, NPV
I 12 Enter, Down
NPV CPT
12,627.41
Cash Flows:
CF0 = -165000
CF1 = 63120
CF2 = 70800
CF3 = 91080
Computing NPV for the Project
Using the TI BAII+
Do we accept or reject the project? Accept
Again, the calculator used for the illustration is the TI BA-II
plus. The basic procedure is the same;
you start with the year 0 cash flow and then enter the cash flows
in order. F01, F02, etc. are used
to set the frequency of a cash flow occurrence. Many calculators
only require you to use this
function if the frequency is something other than 1.
Using the formulas:
NPV = -165,000 + 63,120/(1.12) + 70,800/(1.12)2 +
91,080/(1.12)3 = 12,627.41
Using the calculator (details):
Press the following keys: 2nd, CF, 2nd, Clear.
Calculator displays CF0, 165,000 +|– key, press the Enter key.
Press down arrow, enter 63,120, and press Enter.
Press down arrow, enter 1, and press Enter.
Press down arrow, enter 70,800, and press Enter.
Press down arrow, enter 1, and press Enter.
Press down arrow, enter 91,080, and press Enter.
Press down arrow, enter 1, and press Enter.
Press NPV; calculator shows I = 0; enter 12 and press Enter.
Press down arrow; calculator shows NPV = 0.00.
Press CPT; calculator shows NPV = 12,627.41.
Slide 9
8-9
• Does the NPV rule account for the time
value of money?
• Does the NPV rule account for the risk of
the cash flows?
• Does the NPV rule provide an indication
about the increase in value?
• Should we consider the NPV rule for our
primary decision rule?
Decision Criteria Test – NPV
The answer to all of these questions is yes. The risk of the cash
flows is accounted for through
the choice of the discount rate.
NPV meets all desirable criteria
TVM
Mutually exclusive investment decisions – taking one project
means another cannot be taken. An
excellent example of mutually exclusive projects is the choice
of which college or university to
attend. Many students apply and are accepted to more than one
college, yet they cannot attend
more than one at a time. Consequently, they have to decide
between mutually exclusive projects.
Slide 10
8-10
Payback Period
• How long does it take to recover the initial
cost of a project?
• Computation
– Estimate the cash flows
– Subtract the future cash flows from the initial cost
until initial investment is recovered
– A “break-even” type measure
• Decision Rule – Accept if the payback period
is less than some preset limit
Payback period—length of time until the accumulated cash
flows equal or exceed the original
investment, i.e., how fast you recover your initial investment.
Payback period rule – investment is acceptable if its calculated
payback is less than some
prespecified number of years.
Slide 11
8-11
Computing Payback for the
Project
• Do we accept or reject the project?
Capital Budgeting Project
Year CF Cum. CFs
0 (165,000)$ (165,000)$
1 63,120$ (101,880)$
2 70,800$ (31,080)$
3 91,080$ 60,000$
Payback = year 2 +
+ (31080/91080)
Payback = 2.34 years
Assume we will accept the project if it pays back within two
years.
Year 1: 165,000 – 63,120 = 101,880 still to recoup
Year 2: 101,880 – 70,800 = 31,080 still to recoup
Year 3: 31,080 – 91,080 = -60,000
If we assume that the cash flows occur evenly throughout the
year, which is typical for this method,
then the project pays back in 2.34 years. The payback rule
would say to reject the project.
Slide 12
8-12
• Does the payback rule account for the time value
of money?
• Does the payback rule account for the risk of the
cash flows?
• Does the payback rule provide an indication
about the increase in value?
• Should we consider the payback rule for our
primary decision rule?
Decision Criteria Test – Payback
The answer to all of these questions is no.
Decision Criteria Test – Payback
• -No discounting involved
• -Doesn’t consider risk differences
• -How do we determine the cutoff point
• -Biased toward short-term investments
Real-World Tip: Interestingly, the payback period technique is
used quite heavily in determining
the viability of certain investment projects in the health care
industry. Why? Consider the nature
of the health care industry: the technology is rapidly changing,
some of the equipment tends to be
extremely expensive, and the industry itself is increasingly
competitive. What this means is that, in
many cases, an equipment purchase is complicated by the fact
that, while the machine may be able
to perform its function for, say, 6 years or more, new and
improved equipment is likely to be
developed that will supersede the “old” equipment long before
its useful life is over. Demand from
patients and physicians for “cutting-edge technology” can drive
a push for new investment. In the
face of such a situation, many hospital administrators then focus
on how long it will take to recoup
the initial outlay, in addition to the NPV and IRR of the
equipment.
Slide 13
8-13
Advantages and Disadvantages of
Payback
• Advantages
– Easy to understand
– Adjusts for uncertainty
of later cash flows
– Biased towards liquidity
• Disadvantages
– Ignores the time value of
money
– Requires an arbitrary
cutoff point
– Ignores cash flows
beyond the cutoff date
– Biased against long-term
projects, such as
research and
development, and new
projects
Slide 14
8-14
Average Accounting Return
• Many different definitions for average accounting
return (AAR)
• In this module, we will use the following specific
definition:
– Note: Average book value depends on how the asset is
depreciated.
• Requires a target cutoff rate
• Decision Rule: Accept the project if the AAR is
greater than target rate.
Value Book Average
IncomeNet Average
Average accounting return = measure of accounting profit /
measure of average accounting
value. In other words, it is a benefit/cost ratio that produces a
pseudo rate of return. However,
due to the accounting conventions involved, the lack of risk
adjustment and the use of profits
rather than cash flows, it isn’t clear what is being measured.
Slide 15
8-15
• Assume we require an average accounting return
of 25%.
• Average Net Income:
• AAR = 15,340 / 72,000 = .213 = 21.3%
• Do we accept or reject the project?
Computing AAR
Sample Project Data:
Year 0: CF = -165,000
Year 1: CF = 63,120 NI = 13,620
Year 2: CF = 70,800 NI = 3,300
Year 3: CF = 91,080 NI = 29,100
Average book value = $72,000
You may ask where you came up with the 25%. Note that this is
one of the drawbacks of this
rule. There is no good theory for determining what the return
should be. We generally just use
some rule of thumb. This rule would indicate that we reject the
project.
- Another example
You are deciding whether to open a store in a new shopping
mall. The required investment in
improvements is $500,000. The store would have a five-year
life because everything reverts to the
mall owners after that time. The required investment would be
100 percent depreciated (straight-
line) over five years, so the depreciation would be $500,000 / 5
= $100,000 per year. Net income
is $100,000 in the first year, $150,000 in the second year,
$50,000 in the third year, $0 in Year 4,
and -$50,000 in Year 5. AAR?
To calculate the average book value for this investment, we note
that we started out with a book
value of $500,000 (the initial cost) and ended up at $0 (i.e., we
need to consider six book values).
The average book value during the life of the investment is thus
($500,000 + 0) / 2 = $250,000. As
long as we use straight-line depreciation, the average
investment will always be one-half of the
initial investment. We could, of course, calculate the average of
the six book values directly. In
thousands, we would have ($500 + 400 + 300 + 200 + 100 + 0) /
6 = $250. The average net income
is [$100,000 + 150,000 + 50,000 + 0 + (-50,000)] / 5 = $50,000.
Thus, AAR = $50,000 / $250,000
= 20%
Slide 16
8-16
Decision Criteria Test - AAR
• Does the AAR rule account for the time
value of money?
• Does the AAR rule account for the risk of
the cash flows?
• Does the AAR rule provide an indication
about the increase in value?
• Should we consider the AAR rule for our
primary decision criteria?
The answer to all of these questions is NO. In fact, this rule is
even worse than the payback rule in
that it doesn’t even use cash flows for the analysis. It uses net
income and book value. It isn’t clear
what is being measured. Thus, it is not surprising that most
surveys indicate that few large firms
employ the payback and/or AAR methods exclusively.
Slide 17
8-17
Advantages and Disadvantages of
AAR
• Advantages
– Easy to calculate
– Needed information
usually available
• Disadvantages
– Not a true rate of return
– Time value of money
ignored
– Uses an arbitrary
benchmark cutoff rate
– Based on accounting net
income and book values,
not cash flows and market
values
-Since it involves accounting figures rather than cash flows, it
is not comparable to returns in
capital markets
-It treats money in all periods as having the same value
-There is no objective way to find the cutoff rate
Slide 18
8-18
• This is the most important alternative to
NPV.
• It is often used in practice and is intuitively
appealing.
• It is based entirely on the estimated cash
flows and is independent of interest rates
found elsewhere.
Internal Rate of Return
Internal rate of return (IRR)—the rate that makes the present
value of the future cash flows equal
to the initial cost or investment. In other words, the discount
rate that gives a project a $0 NPV.
The IRR rule is very important. Management, and individuals in
general, often have a much better
feel for percentage returns, and the value that is created, than
they do for dollar increases. A dollar
increase doesn’t appear to provide as much information if we
don’t know what the initial
expenditure was. Whether or not the additional information is
relevant is another issue.
Slide 19
8-19
IRR
Definition and Decision Rule
• Definition:
• Decision Rule:
the required return
The goal of IRR is not to find zero NPV projects, but rather to
find a range of discount rates for
which the project is acceptable.
Slide 20
8-20
NPV vs. IRR
NPV
)R1(
CFn
0t
t
IRR: Enter NPV = 0, solve for IRR.
NPV: Enter r, solve for NPV
Slide 21
8-21
Display You Enter
CF, 2nd, CLR WORK
CF0 -165000 Enter, Down
C01 63120 Enter, Down
F01 1 Enter, Down
C02 70800 Enter, Down
F02 1 Enter, Down
C03 91080 Enter, Down
F03 1 Enter, IRR
IRR CPT
16.1322
Cash Flows:
CF0 = -165000
CF1 = 63120
CF2 = 70800
CF3 = 91080
Computing IRR for the Project
Using the TI BAII
IRR = 16.13% > 12% required return
Do we accept or reject the project?
Internal rate of return (IRR) – the rate that makes the present
value of the future cash flows equal
to the initial cost or investment. In other words, the discount
rate that gives a project a $0 NPV.
IRR decision rule – the investment is acceptable if its IRR
exceeds the required return
If you do not have a financial calculator, then this becomes a
trial and error process.
Enter the cash flows as you did with NPV.
Using the calculator (details):
Press the following keys: 2nd, CF, 2nd, Clear.
Calculator displays CF0, 165,000 +|– key, press the Enter key.
Press down arrow, enter 63,120, and press Enter.
Press down arrow, enter 1, and press Enter.
Press down arrow, enter 70,800, and press Enter.
Press down arrow, enter 1, and press Enter.
Press down arrow, enter 91,080, and press Enter.
Press down arrow, enter 1, and press Enter.
Press IRR; calculator shows IRR = 0.00
Press CPT; calculator shows IRR = 16.132.
Slide 22
8-22
NPV Profile For The Project
-20,000
-10,000
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
0 0.02 0.04 0.06 0.08 0.1 0.12 0.14 0.16 0.18 0.2 0.22
Discount Rate
N
P
V IRR = 16.13%
Note that the NPV profile is also a form of sensitivity
analysis—the slope of the NPV profile
indicates how much a project’s estimated NPV is affected by a
change in the discount rate used
to compute it.
Slide 23
8-23
• Does the IRR rule account for the time value of
money?
• Does the IRR rule account for the risk of the cash
flows?
• Does the IRR rule provide an indication about the
increase in value?
• Should we consider the IRR rule for our primary
decision criteria?
Decision Criteria Test - IRR
The answer to all of these questions is yes, although it is not
always as obvious.
The IRR rule accounts for time value because it is finding the
rate of return that equates all of the
cash flows on a time value basis. The IRR rule accounts for the
risk of the cash flows because you
compare it to the required return, which is determined by the
risk of the project. The IRR rule
provides an indication of value because we will always increase
value if we can earn a return
greater than our required return. We could consider the IRR rule
as our primary decision criteria,
but as we will see, it has some problems that the NPV does not
have. That is why we end up
choosing the NPV as our ultimate decision rule.
Slide 24
8-24
• Knowing a return is intuitively appealing
• It is a simple way to communicate the value of a
project to someone who doesn’t know all the
estimation details.
• If the IRR is high enough, you may not need to
estimate a required return, which is often a
difficult task.
Advantages of IRR
• Considers all cash flows
• Considers time value of money
• Provides indication of risk
However, if you get a very large IRR then you should go back
and look at your cash flow estimates
again. In competitive markets, extremely high IRRs should be
rare. Also, since the IRR calculation
assumes that you can reinvest future cash flows at the IRR, a
high IRR may be unrealistic.
Slide 25
8-25
NPV vs. IRR
• NPV and IRR will generally give the same
decision
• Exceptions
– Non-conventional cash flows
• Cash flow sign changes more than once
– Mutually exclusive projects
• Initial investments are substantially different
• Timing of cash flows is substantially different
NPV and IRR comparison: If a project’s cash flows are
conventional (costs are paid early and
benefits are received over the life), and if the project is
independent, then NPV and IRR will give
the same accept or reject decision.
There are situations where NPV and IRR will give conflicting
answers. Non-conventional cash
flows – the sign of the cash flows changes more than once or
the cash inflow comes first and
outflows come later.
Slide 26
8-26
• When the cash flows change sign more than
once, there is more than one IRR.
• When you solve for IRR you are solving for the
root of an equation, and when you cross the x-
axis more than once, there will be more than one
return that solves the equation.
• If you have more than one IRR, which one do you
use to make your decision?
IRR and Nonconventional
Cash Flows
Nonconventional cash flows means the sign of the cash flows
changes more than once or the cash
inflow comes first and outflows come later. If this occurs, you
will have multiple internal rates of
return. This is problematic for the IRR rule; however, the NPV
rule still works correctly.
Nonconventional cash flows and multiple IRRs occur when
there is a net cost to shutting down a
project. The most common examples deal with collecting
natural resources. After the resource has
been harvested, there is generally a cost associated with
restoring the environment.
Mutually exclusive investment decisions – taking one project
means another cannot be taken. An
excellent example of mutually exclusive projects is the choice
of which college or university to
attend. Many students apply and are accepted to more than one
college, yet they cannot attend
more than one at a time. Consequently, they have to decide
between mutually exclusive projects.
Slide 27
8-27
Non-Conventional Cash Flows
• Suppose an investment will cost $90,000
initially and will generate the following cash
flows:
-150,000
• The required return is 15%.
• Should we accept or reject the project?
NPV = – 90,000 + 132,000 / 1.15 + 100,000 / (1.15)2 – 150,000
/ (1.15)3 = 1,769.54
Calculator: CF0 = -90,000; C01 = 132,000; F01 = 1; C02 =
100,000; F02 = 1; C03 = -150,000;
F03 = 1; I = 15; CPT NPV = 1769.54
If you compute the IRR on the calculator, you get 10.11%
because it is the first one that you come
to. So, if you just blindly use the calculator without recognizing
the uneven cash flows, NPV would
say to accept and IRR would say to reject.
Another type of nonconventional cash flow involves a
“financing” project, where there is a positive
cash flow followed by a series of negative cash flows. This is
the opposite of an “investing” project.
In this case, our decision rule reverses, and we accept a project
if the IRR is less than the cost of
capital, since we are borrowing at a lower rate.
Slide 28
8-28
NPV Profile
($10,000.00)
($8,000.00)
($6,000.00)
($4,000.00)
($2,000.00)
$0.00
$2,000.00
$4,000.00
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45 0.5 0.55
Discount Rate
N
P
V
IRR = 10.11% and 42.66%
When you cross the x-axis more than once, there will
be more than one return that solves the equation
You should accept the project if the required return is between
10.11% and 42.66%.
This provides a good visual of the 2 IRRs.
Slide 29
8-29
• Mutually exclusive projects
either Harvard or Stanford, but not both.
• Intuitively, you would use the following decision
rules:
– choose the project with the higher NPV
– choose the project with the higher IRR
IRR and Mutually Exclusive Projects
Mutually exclusive investment decisions – taking one project
means another cannot be taken. An
excellent example of mutually exclusive projects is the choice
of which college or university to
attend. Many students apply and are accepted to more than one
college, yet they cannot attend
more than one at a time. Consequently, they have to decide
between mutually exclusive projects.
Slide 30
8-30
Example of Mutually Exclusive
Projects
Period Project A Project B
0 -500 -400
1 325 325
2 325 200
IRR 19.43% 22.17%
NPV 64.05 60.74
The required
return for both
projects is 10%.
Which project
should you accept
and why?
This is a simple example of two mutually exclusive projects that
result in conflicting signals
from NPV and IRR.
The important point is that we DO NOT use IRR to choose
between projects.
Slide 31
8-31
Conflicts Between NPV and IRR
• NPV directly measures the increase in value to
the firm
• Whenever there is a conflict between NPV and
another decision rule, always use NPV
• IRR is unreliable in the following situations:
– Non-conventional cash flows
– Mutually exclusive projects
Slide 32
8-32
Modified Internal Rate of Return
(MIRR)
• Controls for some problems with IRR
• Three Methods:
1.Discounting Approach = Discount future outflows
(negative CF) to present and add to CF0
2. Reinvestment Approach = Compound all CFs except
CF0 forward to end
3. Combination Approach – Discount outflows to
present; compound inflows to end
– MIRR will be unique number for each method
FR = Finance rate (discount)
RR = Reinvestment rate (compound)
let’s go back to the cash flows in Figure 8.5: −$60, +$155, and
−$100. As we saw, there are two
IRRs, 25 percent and 33⅓ percent. We next illustrate three
different MIRRs, all of which have the
property that only one answer will result, thereby eliminating
the multiple IRR problem.
1. With the discounting approach, the idea is to discount all
negative cash flows back to the present
at the required return and add them to the initial cost. Then,
calculate the IRR. Because only the
first modified cash flow is negative, there will be only one IRR.
2. We compound all cash flows (positive and negative) except
the first out to the end of the
project’s life and then calculate the IRR. In a sense, we are
“reinvesting” the cash flows and not
taking them out of the project until the very end.
3. As the name suggests, the combination approach blends our
first two methods. Negative cash
flows are discounted back to the present, and positive cash
flows are compounded to the end of
the project.
Slide 33
8-33
MIRR Method 1
Discounting Approach
Method 1: Discounting Approach
R = 20%
Yr CF ADJ MCF
0 -60 -69.444 -129.44444
1 155 155
2 -100 0
IRR= 19.74%
Step 1: Discount future outflows (negative
cash flows) to present and add to CF0
Step 2: Zero out negative cash flows which
have been added to CF0.
Step 3: Compute IRR normally
1. With the discounting approach, the idea is to discount all
negative cash flows back to the present
at the required return and add them to the initial cost. Then,
calculate the IRR. Because only the
first modified cash flow is negative, there will be only one IRR.
Slide 34
8-34
MIRR Method 2
Reinvestment Approach
Step 1: Compound ALL cash flows (except CF0)
to end of project’s life
Step 2: Zero out all cash flows which have been
added to the last year of the project’s life.
Step 3: Compute IRR normally
Method 2: Reinvestment Approach
R = 20%
Yr CF ADJ MCF
0 -60 -60
1 155 0
2 -100 186 86
IRR= 19.72%
We compound all cash flows (positive and negative) except the
first out to the end of the project’s
life and then calculate the IRR. In a sense, we are “reinvesting”
the cash flows and not taking them
out of the project until the very end.
The MIRR on this set of cash flows is 19.72 percent, or a little
lower than we got using the
discounting approach.
Slide 35
8-35
MIRR Method 3
Combination Approach
Step 1: Discount all outflows (except CF0) to
present and add to CF0.
Step 2: Compound all cash inflows to end of
project’s life
Step 3: Compute IRR normally
Method 3: Combination Approach
R = 20%
Yr CF ADJ MCF
0 -60 -69.444 -129.44444
1 155 0
2 -100 186 186
IRR= 19.87%
The combination approach blends our first two methods.
Negative cash flows are discounted back
to the present, and positive cash flows are compounded to the
end of the project.
Slide 36
8-36
MIRR versus IRR
• MIRR correctly assumes reinvestment at
opportunity cost = WACC
• MIRR avoids the multiple IRR problem
• Managers like rate of return comparisons,
and MIRR is better for this than IRR
As our example makes clear, one problem with MIRRs is that
there are different ways of
calculating them, and there is no clear reason to say one of our
three methods is better than any
other. The differences are small with our simple cash flows, but
they could be much larger for a
more complex project.
Slide 37
8-37
Profitability Index
• Measures the benefit per unit cost, based
on the time value of money
• If a project costs $200 and the present value of
its future cash flows is $220. (PI: 220/200=1.1)
– A profitability index of 1.1 implies that for
every $1 of investment, we create an
additional $0.10 in value
• Can be very useful in situations of capital
rationing
Another method used to evaluate projects involves the
profitability index (PI), or benefit-cost ratio.
This index is defined as the present value of the future cash
flows divided by the initial investment.
Slide 38
8-38
Profitability Index
• For conventional CF Projects:
PV(Cash Inflows)
Absolute Value of Initial
Investment0
n
1t
t
t
CF
)r1(
CF
PI
This index is defined as the present value of the future cash
flows divided by the initial investment.
If a project has a positive NPV, then the PI will be greater than
1.
Slide 39
8-39
Advantages and Disadvantages of
Profitability Index
• Advantages
– Closely related to NPV,
generally leading to
identical decisions
• Considers all CFs
• Considers TVM
– Easy to understand and
communicate
– Useful in capital
rationing
• Disadvantages
– May lead to incorrect
decisions in comparisons
of mutually exclusive
investments (can conflict
with NPV)
– Eg. Project A vs B
A: Cost: 5, PV of CF: 10
B: Cost: 100, PV of CF: 150
A: NPV 5, PI 2
B: NPV 50, PI 1.5
The PI is obviously very similar to the NPV. If a project has a
positive NPV, then the present value
of the future cash flows must be bigger than the initial
investment. The profitability index would
thus be bigger than 1.00
Slide 40
8-40
Capital Budgeting In Practice
• Consider all investment criteria when
making decisions
• NPV and IRR are the most commonly used
primary investment criteria
• Payback is a commonly used secondary
investment criteria
Even though payback and AAR should not be used to make the
final decision, we should consider
the project very carefully if they suggest rejection. There may
be more risk than we have
considered or we may want to pay additional attention to our
cash flow estimations. The fact that
payback is commonly used as a secondary criterion may be
because short paybacks allow firms to
have funds sooner to invest in other projects without going to
the capital markets.
It is common among large firms to employ a discounted cash
flow technique such as IRR or NPV
along with payback period or average accounting return. It is
suggested that this is one way to
resolve the considerable uncertainty over future events that
surrounds the estimation of NPV.
Why are smaller firms more likely to use payback as a primary
decision criterion?
• Small firms don’t have direct access to the capital markets and
therefore find it more difficult
to estimate discount rates based on funds cost; the AAR is the
project-level equivalent to the
ROA measure used for analyzing firm profitability; and some
small firm decision-makers
may be less aware of DCF approaches than their large firm
counterparts.
When managers are judged and rewarded primarily on the basis
of periodic accounting figures,
there is an incentive to evaluate projects with methods such as
payback or average accounting
return. On the other hand, when compensation is tied to firm
value, it makes more sense to use
NPV as the primary decision tool.
Slide 41
8-41
Capital Budgeting In Practice
There have been a number of surveys conducted asking firms
what types of investment criteria
they actually use
Slide 42
8-42
• Net present value
criterion
• Internal rate of return
mutually exclusive
projects.
• Profitability Index
-cost ratio
rationing
Summary – DCF Criteria
For IRR, we assume a conventional investment project. For a
financing project, we accept if the
IRR is less than the “required” rate.
Slide 43
8-43
• Payback period
within some specified period.
arbitrary cutoff period
• Discounted payback period
discounted basis
ck in some specified period.
Summary – Payback Criteria
Slide 44
8-44
• Average Accounting Return
e investment if the AAR exceeds some
specified return level.
Summary – Accounting Criterion
Slide 45
8-45
• An investment project has the following cash
flows: CF0 = -1,000,000; C01 – C08 = 200,000
each
• If the required rate of return is 12%, what
decision should be made using NPV?
• How would the IRR decision rule be used for this
project, and what decision would be reached?
• How are the above two decisions related?
Comprehensive Problem
NPV
Press the following keys: 2nd, CF, 2nd, Clear.
Calculator displays CF0, 1000,000 +|– key, press the Enter key.
Press down arrow, enter 200,000, and press Enter.
Press down arrow, enter 8, and press Enter.
Press NPV; calculator shows I = 0; enter 12 and press Enter.
Press down arrow; calculator shows NPV = 0.00.
Press CPT; calculator shows NPV = -6,472.
-$6,472; reject the project since it would lower the
value of the firm.
IRR (Don’t need to repeat above since the data is already in the
calculator, but just hit IRR after
computing NPV)
Press IRR; calculator shows IRR = 0.00
Press CPT; calculator shows IRR = 16.132.
investable funds in a project that will
provide insufficient return.
The NPV and IRR decision rules will provide the same decision
for all independent projects with
conventional/normal cash flow patterns. If a project adds value
to the firm (i.e., has a positive NPV), then
it must be expected to provide a return above that which is
required. Both of those justifications are good
for shareholders.
Slide 1
11-1
Return, Risk, and The Security Market Line
We have to define risk and then discuss how to measure it. We
then must quantify the relationship
between an asset’s risk and its required return.
There are two types of risk: systematic and unsystematic. This
distinction is crucial because, as we
will see, systematic risk affects almost all assets in the
economy, at least to some degree, while
unsystematic risk affects at most a small number of assets. We
then develop the principle of
diversification, which shows that highly diversified portfolios
will tend to have almost no
unsystematic risk.
Slide 2
11-2
• Expected returns are based on the probabilities of
possible outcomes.
• In this context, “expected” means average if the
process is repeated many times.
• The “expected” return does not even have to be a
possible return.
Where:
pi = the probability of state “i” occurring
Ri = the expected return on an asset in state i
Expected Returns
=
=
n
i
ii RpRE
1
)(
Slide 3
11-3
Example: Expected Returns
Stock C Stock T
State (i) Probability (Pi) (Ri) (Ri) ___
Boom 0.3 0.15 0.25
Normal 0.5 0.10 0.20
Recession ??? 0.02 0.01
1.00
• E(RC) = .3(.15) + .5(.1) + .2(.02) = 0.099
• E(RT) = .3(.25) + .5(.2) + .2(.01) = 0.177
13-3
• Suppose you have predicted the following
returns for stocks C and T in three possible
states of the economy. What are the
expected returns?
What is the probability of a recession? 1- 0.3 - 0.5 = 0.2
Or work in the percentage terms.
E(RC) = .3(15%) + .5(10%) + .2(2%) = 9.9%
E(RT) = .3(25%) + .5(20%) + .2(1%) = 17.7%
Slide 4
11-4
Variance and Standard Deviation
the volatility of returns
• Variance = Weighted average of squared
deviations
• Standard Deviation = Square root of variance
=
−=
n
i
ii RERp
1
22 ))((σ
Variance measures the dispersion of points around the mean of a
distribution. In this context, we
are attempting to characterize the variability of possible future
security returns around the expected
return. In other words, we are trying to quantify risk and return.
Variance measures the total risk
of the possible returns.
Slide 5
11-5
Variance and Standard Deviation
• Consider the previous example. What are the variance
and standard deviation for each stock?
Stock C Stock T
State (i) Probability (Pi) (Ri) (Ri) ___
Boom 0.3 0.15 0.25
Normal 0.5 0.10 0.20
Recession 0.2 0.02 0.01
E(RC) = 0.099 E(RT) = 0.177
• Stock C
-0.099)2 + .5(0.10-0.099)2 + .2(0.02-0.099)2 =
0.002029
• Stock T
-0.177)2 + .5(0.20-0.177)2 + .2(0.01-0.177)2 =
0.007441
13-5
Slide 6
11-6
Another Example
• Consider the following information:
State(i) Probability (Pi) ABC, Inc. Return
Boom .25 0.15
Normal .50 0.08
Slowdown .15 0.04
Recession .10 -0.03
• What is the expected return?
• E(R) = .25(0.15) + .5(0.08) + .15(0.04) + .1(-0.03) = 8.05%
• What is the variance?
• Variance = .25(.15-0.0805)2 + .5(0.08-0.0805)2 + .15(0.04-
0.0805)2 +
• .1(-0.03-0.0805)2 = 0.00267475
• What is the standard deviation?
• Standard Deviation = 5.17%
13-6
⚫ E(R) = .25(0.15) + .5(0.08) + .15(0.04) + .1(-0.03) = 0.0805
(=8.05%)
⚫ Variance = .25(.15-0.0805)2 + .5(0.08-0.0805)2 + .15(0.04-
0.0805)2 + .1(-0.03-0.0805)2 =
0.00267475
⚫ Standard Deviation = 0.0517 (=5.17%)
You may experience confusion in understanding the
mathematics of the variance calculation. You may
have the feeling that you should divide the variance of an
expected return by (n−1). Note that the
probabilities account for this division. We divide by n−1 in the
historical variance because we are looking
at a sample. If we looked at the entire population (which is what
we are doing with expected values), then
we would divide by n (or multiply by 1 ⁄ n) to get our historical
variance. This is the same as saying that the
“probability” of occurrence is the same for all observations and
is equal to 1 ⁄ n.
Slide 7
11-7
Portfolios
• Portfolio = collection of assets
• An asset’s risk and return impact how the
stock affects the risk and return of the
portfolio
• The risk-return trade-off for a portfolio is
measured by the portfolio expected return
and standard deviation, just as with
individual assets
Each individual has their own level of risk tolerance. Some
people are just naturally more inclined
to take risk, and they will not require the same level of
compensation as others for doing so. Our
risk preferences also change through time. We may be willing to
take more risk when we are young
and without a spouse or kids. But, once we start a family, our
risk tolerance may drop.
Slide 8
11-8
Portfolio Expected Returns
• Expected return for an asset:
• The expected return of a portfolio is the
weighted average of the expected returns
for each asset in the portfolio
• Weights (wj) = % of portfolio invested in
each asset
=
=
m
1j
jjP )R(Ew)R(E
=
=
n
1i
iiRp)R(E
The expected return on a portfolio is the sum of the product of
the expected returns on the
individual securities and their portfolio weights. Let wj be the
portfolio weight for asset j and m
be the total number of assets in the portfolio.
You can also find the expected return by finding the portfolio
return in each possible state and
computing the expected value as we did with individual
securities.
Slide 9
11-9
Example: Portfolio Weights
• Suppose you have $15,000 to invest and you have
purchased securities in the following amounts. What
are your portfolio weights in each security?
▪ $2000 of C
▪ $3000 of KO
▪ $4000 of INTC
▪ $6000 of BP
▪ C: 2000/15000 = .133
▪ KO: 3000/15000 = .2
▪ INTC: 4000/15000 = .267
▪ BP: 6000/15000 = .4
13-9
Weights (wj) ?
C – Citigroup
KO – Coca-Cola
INTC – Intel
BP – BP
Note that the sum of the weights = 1 (=100%).
A portfolio is a collection of assets, such as stocks and bonds,
held by an investor. Portfolios can
be described by the percentage investment in each asset. These
percentages are called portfolio
weights.
Example: If two securities in a portfolio have a combined value
of $10,000 with $6000 invested
in IBM and $4000 invested in GM, then the weight on IBM =
6000 ⁄ 10000 = .6 (=60%) and the
weight on GM = 4000 ⁄ 100000 = .4 (=40%) or we can simply
calculate the weight on GM by 1 –
0.6 = 0.4 (=40%) since the sum of the weights equals 1
(=100%).
Slide 10
11-10
Expected Portfolio Returns
• Consider the portfolio weights computed
previously. If the individual stocks have the
following expected returns, what is the
expected return for the portfolio?
•
▪ C: 19.69%
▪ KO: 5.25%
▪ INTC: 16.65%
▪ BP: 18.24%
• E(RP) = .133(0.1969) + .2(0.0525)
+ .267(0.1665) + .4(0.1824) = 0.1541
13-10
▪ C: 2000/15000 = .133
▪ KO: 3000/15000 = .2
▪ INTC: 4000/15000 = .267
▪ BP: 6000/15000 = .4
Weights (wj) Expected Return E(Rj)
Slide 11
11-11
Portfolio Variance
• Compute portfolio return for each state:
RP,i = w1R1,i + w2R2,i + … + wmRm,i
• Compute the overall expected portfolio
return using the same formula as for an
individual asset
• Compute the portfolio variance and standard
deviation using the same formulas as for an
individual asset
The calculation of portfolio variance requires three steps:
1. Compute the portfolio return for each state of the economy.
2. Compute the overall expected return of the portfolio.
3. Compute portfolio variance and standard deviation using the
same formulas as for an
individual asset.
Unlike expected return, the variance of a portfolio is NOT the
weighted sum of the individual
security variances. Combining securities into portfolios can
reduce the total variability of returns.
Slide 12
11-12
Example: Portfolio Variance
• Consider the following information on returns and
probabilities:
▪ Invest 50% of your money in Asset A
State Probability A B
Boom .4 30% -5%
Bust .6 -10% 25%
• What are the expected return and standard
deviation for each asset?
• What are the expected return and standard
deviation for the portfolio?
13-12
Slide 13
11-13
Example: Portfolio Variance
• Invest 50% of your money in Asset A
State Probability A B
Boom .4 30% -5%
Bust .6 -10% 25%
• What are the expected return and standard
deviation for each asset?
Asset A: E(RA) = .4(0.3) + .6(-0.1) = 0.06 (=6%)
Variance(A) = .4(0.3-0.06)2 + .6(-0.1-0.06)2 = 0.0384
Std. Dev.(A) = 0.196 (=19.6%)
Asset B: E(RB) = .4(-0.05) + .6(0.25) = 0.13 (=13%)
Variance(B) = .4(-0.05-0.13)2 + .6(0.25-0.13)2 = 0.0216
Std. Dev.(B) = 0.147 (=14.7%)
• What are the expected return for the portfolio?
E(Rp) = .5(0.06) + .5(0.13) = 0.095 (=9.5%)
13-13
Expected return and standard deviation for each asset
Or work in the percentage terms.
Asset A: E(RA) = .4(30%) + .6(-10%) = 6%
Variance(A) = .4(30%-6%)2 + .6(-10%-6%)2 = 384
Std. Dev.(A) = √384 =19.6%
Asset B: E(RB) = .4(-5%) + .6(25%) = 13%
Variance(B) = .4(-5%-13%)2 + .6(25%-13%)2 = 216
Std. Dev.(B) = √216 =14.7%
Expected return for the portfolio (1)
The expected return on a portfolio is the sum of the product of
the expected returns on the
individual securities and their portfolio weights. Weights (wj) =
% of portfolio invested in each
asset. There are two stocks in your portfolio and you invest 50%
of your money in Asset A.
What percent are you investing in Asset B? 50% (= (100% -
50%)). Thus, WA = 0.5, and WB = 0.5
Or work in the percentage terms.
E(Rp) = .5(6%) + .5(13%) = 9.5%
Slide 14
11-12
Example: Portfolio Variance
• Consider the following information on returns and
probabilities:
▪ Invest 50% of your money in Asset A
State Probability A B Portfolio
Boom .4 30% -5% 12.5% = RP,Boom
Bust .6 -10% 25% 7.5% = RP,Bust
E(RA) = 6% E(RB) = 13% E(Rp)
• What are the expected return and standard
deviation for the portfolio?
13-12
(1)
(2)
To compute the standard deviation for the portfolio, we need to
follow three steps (See Slide 11)
1. Compute the portfolio return for each state of the economy.
There are two stocks in your portfolio and you invest 50% of
your money in Asset A. What
percent are you investing in Asset B? 50% (= (100% - 50%)).
Thus, WA = 0.5, and WB = 0.5
Portfolio return in boom: RP,Boom = 0.5(0.3) + 0.5(-0.05) =
0.125 (=12.5%)
Portfolio return in bust: RP,Bust = 0.5(-0.1) + 0.5(0.25) = 0.075
(=7.5%)
Or work in the percentage terms.
RP,Boom = 0.5(30%) + 0.5(-5%) = 12.5%
RP,Bust = 0.5(-10%) + 0.5(25%) =7.5%
2. Compute the overall expected return of the portfolio.
In Slide 13, we computed E(Rp) = .5(6%) + .5(13%) = 9.5%
- (1)
You can also find the expected return for the portfolio by
finding the portfolio return in each
possible state and computing the expected value as we did with
individual securities.
E(Rp) = .4(12.5%) + .6(7.5%) = 9.5% - (2)
Slide 15
11-14
Example: Portfolio Variance
▪ Invest 50% of your money in Asset A
State Probability A B Portfolio
Boom .4 30% -5% 12.5%
Bust .6 -10% 25% 7.5%
• What are the expected return and standard
deviation for the portfolio?
Portfolio return in boom (RP,Boom) = .5(.3) + .5(-.05) = .125
Portfolio return in bust (RP,Bust) = .5(-.1) + .5(.25) = .075
Expected return for portfolio E(RP) = .5(.06) + .5(.13) = .095 or
.4(.125) + .6(.075) = .095
Variance of portfolio = .4(.125-.095)2 + .6(.075-.095)2 = .06
Standard deviation = .0245
13-14
3. Compute portfolio variance and standard deviation using the
same formulas as for an individual
asset.
Expected return = .5(6%) + .5(13%) = 9.5% or
Expected return = .4(12.5%) + .6(7.5%) = 9.5%
Variance of portfolio = .4(12.5%-9.5%)2 + .6(7.5%-9.5%)2 =
6%
Standard deviation = 2.45%
Unlike expected return, the variance of a portfolio is NOT the
weighted sum of the individual
security variances. Combining securities into portfolios can
reduce the total variability of returns.
• Note that the variance is NOT equal to .5(384) + .5(216) = 300
and
• Standard deviation is NOT equal to .5(19.6) + .5(14.7) =
17.17%
To compute variance of portfolio, follow the direction of (2) in
the previous slide.
Slide 16
11-15
• Realized returns are generally not equal to
expected returns.
• There is the expected component and the
unexpected component.
▪ At any point in time, the unexpected return can be
either positive or negative.
▪ Over time, the average of the unexpected component is
zero.
Expected vs. Unexpected Returns
Expected vs. Unexpected Returns
Total return = Expected return + Unexpected return
Total return differs from expected return because of surprises,
or “news.” This is one of the
reasons that realized returns differ from expected returns.
Slide 17
11-16
Announcements and News
• Announcements and news contain both an expected
component and a surprise component
• It is the surprise component that affects a stock’s
price and therefore its return
• This is very obvious when we watch how stock prices
move when an unexpected announcement is made
or earnings are different than anticipated
13-16
Announcement—the release of information not previously
available. Announcements have two
parts: the expected part and the surprise part. The expected part
is “discounted” information used
by the market to estimate the expected return, while the surprise
is news that influences the
unexpected return.
Slide 18
11-17
Announcements and News
• On November 17, 2004 it was announced that K-
Mart would acquire Sears in an $11 billion deal.
Sears’ stock price jumped from a closing price of
$45.20 on November 16 to a closing price of $52.99
(a 7.79% increase) and K-Mart’s stock price jumped
from $101.22 on November 16 to a closing price of
$109.00 on November 17 (a 7.69% increase). Both
stocks traded even higher during the day.
• Why the jump in price?
13-17
It is easy to see the effect of unexpected news on stock prices
and returns. Consider the following
two cases:
(1) On November 17, 2004 it was announced that K-Mart would
acquire Sears in an $11 billion
deal. Sears’ stock price jumped from a closing price of $45.20
on November 16 to a closing price
of $52.99 (a 7.79% increase) and K-Mart’s stock price jumped
from $101.22 on November 16 to
a closing price of $109.00 on November 17 (a 7.69% increase).
Both stocks traded even higher
during the day. Why the jump in price? Unexpected news, of
course.
(2) On November 18, 2004, Williams-Sonoma cut its sales and
earnings estimates for the fourth
quarter of 2004 and its share price dropped by 6%. There are
plenty of other examples where
unexpected news causes a change in price and expected returns.
Slide 19
11-18
Efficient Markets
• Efficient markets are a result of investors
trading on the unexpected portion of
announcements
• The easier it is to trade on surprises, the more
efficient markets should be
• Efficient markets involve random price
changes because we cannot predict surprises
13-18
Slide 20
11-19
Systematic Risk
• Risk factors that affect a large number of assets
• Also known as non-diversifiable risk or market risk.
• Examples: changes in GDP, inflation, interest rates,
etc.
Risk consists of surprises. There are two kinds of surprises:
Systematic Risk & Unsystematic
Risk
• Systematic risk is a surprise that affects a large number of
assets, although at varying
degrees. It is sometimes called market risk.
• Example: Changes in GDP, interest rates, and inflation are
examples of systematic risk.
Slide 21
11-20
Unsystematic Risk
• = Diversifiable risk
• Risk factors that affect a limited number of assets
• Also known as unique risk or asset-specific risk.
• Risk that can be eliminated by combining assets
into portfolios
• Examples: labor strikes, part shortages, etc.
• Unsystematic risk is a surprise that affects a small number of
assets (or one). It is
sometimes called unique or asset-specific risk.
• Example: Strikes, accidents, and takeovers are examples of
unsystematic risk.
Slide 22
11-21
Diversification
• Portfolio diversification is the investment in
several different asset classes or sectors
• Diversification is not just holding a lot of assets
• For example, if you own 50 Internet stocks, you
are not diversified
• However, if you own 50 stocks that span 20
different industries, then you are diversified
13-21
Portfolio diversification can substantially reduce risk without
an equivalent reduction in expected
returns
• Reduces the variability of returns
Minimum level of risk that cannot be diversified away =
systematic portion
Slide 23
11-22
• Diversification can substantially reduce the
variability of returns without an equivalent
reduction in expected returns.
• This reduction in risk arises because worse than
expected returns from one asset are offset by
better than expected returns from another.
• However, there is a minimum level of risk that
cannot be diversified away and that is the
systematic portion.
The Principle of Diversification
Principle of Diversification – States that combining imperfectly
correlated assets can produce a
portfolio with less variability than the typical individual asset.
The portion of variability present in a single security that is not
present in a portfolio of securities
is called diversifiable risk. The level of variance that is present
in portfolios of assets is non-
diversifiable risk.
Slide 24
11-23
Standard Deviations of Annual Portfolio Returns
Table 13.7
A typical single stock on the NYSE has a standard deviation of
annual returns around 49%, while
the typical large portfolio of NYSE stocks has a standard
deviation of around 20%.
Slide 25
11-24
• The risk that can be eliminated by combining
assets into a portfolio.
• Often considered the same as unsystematic,
unique or asset-specific risk
• If we hold only one asset, or assets in the same
industry, then we are exposing ourselves to risk
that we could diversify away.
Diversifiable Risk
When securities are combined into portfolios, their unique or
unsystematic risks tend to cancel out,
leaving only the variability that affects all securities to some
degree. Thus, diversifiable risk is
synonymous with unsystematic risk. Large portfolios have little
or no unsystematic risk.
Slide 26
11-25
Total Risk = Stand-alone Risk
• Total risk = Systematic risk + Unsystematic risk
– The standard deviation of returns is a measure of
total risk
• For well-diversified portfolios, unsystematic risk
is very small
– Total risk for a diversified portfolio is essentially
equivalent to the systematic risk
– The expected return (market required return) on an
asset depends only on that asset’s systematic or
market risk.
Systematic risk cannot be eliminated by diversification since it
represents the variability due to
influences that affect all securities to some degree. Therefore,
systematic risk and non-
diversifiable risk are the same.
Total risk = Non-diversifiable risk + Diversifiable risk
= Systematic risk + Unsystematic risk
Slide 27
11-26
Market Risk for Individual Securities
• Measures the stock’s volatility relative to the
market
While the standard deviation of returns is a measure of total
risk, the beta coefficient measures
how much systematic risk an asset has relative to an asset of
average risk.
Beta measures the volatility of an individual asset or portfolio
relative to the market as a whole.
Slide 28
11-27
Measuring Systematic Risk
• How do we measure systematic risk?
▪ We use the beta coefficient
• What does beta tell us?
▪ A beta = 1 implies the asset has the same systematic
risk as the overall market
▪ A beta < 1 implies the asset has less systematic risk
than the overall market
▪ A beta > 1 implies the asset has more systematic risk
than the overall market
▪ Most stocks have betas in the range of 0.5 to 1.5
▪ Beta of a T-Bill = 0
13-27
Robert Hamada derived the following equation to reflect the
relationship between levered and
unlevered betas (excluding tax effects):
where:
D/E = debt-to-equity ratio
Slide 29
11-28
Beta Coefficients for Selected Companies
Table 13.8
Slide 30
11-29
• Consider the following information:
Standard Deviation Beta
Security C 20% 1.25
Security K 30% 0.95
• Which security has more total risk?
• Which security has more systematic risk?
• Which security should have the higher expected return?
Total vs. Systematic Risk
Security K has the higher total risk.
Security C has the higher systematic risk.
Security C should have the higher expected return.
• When securities are combined into portfolios, their unique or
unsystematic risks tend to
cancel out, leaving only the variability that affects all securities
to some degree. Thus,
Total risk for a diversified portfolio is essentially equivalent to
the systematic risk. The
expected return (market required return) on an asset depends
only on that asset’s
systematic or market risk.
Slide 31
11-30
Portfolio Beta
βp = Weighted average of the Betas of the
assets in the portfolio
Weights (wj)= % of portfolio invested in asset j
=
=
n
j
jjp w
1
The beta of the portfolio is simply a weighted average of the
betas of the securities in the
portfolio.
Slide 32
11-31
• Consider the previous example with the
following four securities.
Security Weight Beta
C .133 1.685
KO .2 0.195
INTC .267 1.161
BP .4 1.434
• What is the portfolio beta?
• .133(1.685) + .2(.195) + .267(1.161) + .4(1.434) = 1.147
Example: Portfolio Betas
Which security has the highest systematic risk?
C
Which security has the lowest systematic risk?
KO
Is the systematic risk of the portfolio more or less than the
market?
more
Slide 33
11-32
Example: Portfolio Expected Returns
and Betas
0%
5%
10%
15%
20%
25%
30%
0 0.5 1 1.5 2 2.5 3
E
x
p
ec
te
d
R
et
u
rn
Beta
Rf
E(RA)
There is a linear relationship between beta and expected return.
combined with a riskless asset, the
resulting expected return is the weighted sum of the expected
returns, and the portfolio beta is the
weighted sum of the betas. By varying the amount invested in
each asset, we can get an idea of the
relation between portfolio expected returns and betas. This
relationship is illustrated in this figure.
As can be seen, all of the risk-return combinations lie on a
straight line. The equation for a line is:
Y = mx + b
where: y = expected return
x = beta
m = slope = risk-premium per unit of beta
b = y-intercept = risk-free rate
E(R) = slope (Beta) + y-intercept
The y-intercept is = the risk-free rate, so all we need is the
slope
Slide 34
11-33
Reward-to-Risk Ratio: Definition and
Example
• The reward-to-risk ratio is the slope of the line
illustrated in the previous example
▪ Slope = (E(RA) – – 0)
▪ Reward-to-risk ratio for previous example =
(20 – 8) / (1.6 – 0) = 7.5
• What if an asset has a reward-to-risk ratio of 8
(implying that the asset plots above the line)?
• investors will want to buy the asset.
• What if an asset has a reward-to-risk ratio of 7
(implying that the asset plots below the line)?
• investors will want to sell the asset
13-33
The Reward-to-Risk Ratio is the expected return per unit of
systematic risk. In other words, it is
the ratio of risk premium to systematic risk.
If the reward-to-risk ratio = 8, then investors will want to buy
the asset. This will drive the price
up and the expected return down (remember time value of
money and valuation). When will the
flurry of trading stop? When the reward-to-risk ratio reaches
7.5.
If the reward-to-risk ratio = 7, then investors will want to sell
the asset. This will drive the price
down and the expected return up. When will the flurry of
trading stop? When the reward-to-risk
ratio reaches 7.5.
Slide 35
11-34
Beta and the Risk Premium
• Risk premium = E(R ) – Rf
• The higher the beta, the greater the risk
premium should be
• Can we define the relationship between the
risk premium and beta so that we can
estimate the expected return?
– YES!
The risk premium—the excess return of an asset above the risk-
free rate.
Slide 36
11-35
Security Market Line
• The security market line (SML) is the
representation of market equilibrium
• The slope of the SML = reward-to-risk ratio
= (E(RM) –
• But since the beta for the market is always
equal to one, the slope can be rewritten
• Slope = E(RM) – Rf = market risk premium
The line that gives the expected return/systematic risk
combinations of assets in a well-functioning,
active financial market is called the security market line.
Market Portfolios: Consider a portfolio of all the assets in the
market and call it the market portfolio.
This portfolio, by definition, has “average” systematic risk with
a beta of 1. Since all assets must
lie on the SML when appropriately priced, the market portfolio
must also lie on the SML. Let the
expected return on the market portfolio = E(RM). Then, the
slope of the SML = reward-to-risk ratio
Slide 37
11-36
Market Equilibrium
• In equilibrium, all assets and portfolios must
have the same reward-to-risk ratio
• Each ratio must equal the reward-to-risk
ratio for the market
M
fM
A
fA )RR(ER)R(E
−
=
−
The basic argument is that since systematic risk is all that
matters in determining expected return,
the reward-to-risk ratio must be the same for all assets. If it
were not, people would buy the asset
with the higher reward-to-risk ratio (driving the price up and
the return down).
The fundamental result is that in a competitive market where
only systematic risk affects E(R),
the reward-to-risk ratio must be the same for all assets in the
market. Consequently, the expected
returns and betas of all assets must plot on the same straight
line.
E.g., Amazon (Asset j =A)
We can solve for � ��
E RA Rf
βA
E RM Rf
βM
[E RA Rf] x βM = βA x [E RM Rf ]
Since the market beta, βM = 1 (Wee Slide 28),
E RA Rf = βA [E RM Rf ]
E RA = Rf + βA [E RM Rf ]
Since E(Rf) = Rf,
E RA = Rf + βA [E RM Rf]
This is called the capital asset pricing model (CAPM)
Slide 38
11-37
SML and Equilibrium
The Capital Asset Pricing Model (CAPM):
We can get an idea of the relationship between portfolio
expected returns and betas.
Slide 39
11-38
The SML and Required Return
• The Security Market Line (SML) is part of the
Capital Asset Pricing Model (CAPM)
Rf = Risk-free rate (T-Bill or T-Bond)
RM = Market return ≈ S&P 500
RPM = Market risk premium = E(RM) – Rf
E(Rj) = “Required Return of Asset j”
( )
( ) jMfj
jfMfj
RPRRE
RRERRE
+=
−+=
)(
)()(
Slide 40
11-39
Capital Asset Pricing Model
• The capital asset pricing model (CAPM)
defines the relationship between risk and
return
E(Rj) = Rf + βj(E(RM) – Rf)
• If an asset’s systematic r
CAPM can be used to determine its expected
return
Slide 41
11-40
Factors Affecting Required Return
• Rf measures the pure time value of money
• E(RM)-Rf measures the reward for bearing
systematic risk
amount of systematic risk
The CAPM states that the expected return for an asset depends
on:
-The time value of money, as measured by Rf
-The reward per unit risk, as measured by E(RM) − Rf
-The asset’s systematic risk,
Slide 42
11-41
Quick Quiz
Consider an asset with a beta of 1.2, a risk-free rate of
5%, and a market return of 13%.
– What is the reward-to-risk ratio in equilibrium?
– What is the expected return on the asset?
• E(R) = 5% + (13% - 5%)* 1.2 = 14.6%
Reward-to-risk ratio = 13 – 5 = 8%
Expected return = 5 + 1.2(8) = 14.6%

Contenu connexe

Similaire à Slide 1 8-1Capital Budgeting• Analysis of potent.docx

Similaire à Slide 1 8-1Capital Budgeting• Analysis of potent.docx (20)

NPV is net present value of document.ppt
NPV is net present value of document.pptNPV is net present value of document.ppt
NPV is net present value of document.ppt
 
Cap budget [autosaved]
Cap budget [autosaved]Cap budget [autosaved]
Cap budget [autosaved]
 
2. capital budgeting review
2. capital budgeting review2. capital budgeting review
2. capital budgeting review
 
Capital budgeting unit_2
Capital budgeting unit_2Capital budgeting unit_2
Capital budgeting unit_2
 
Project management
Project managementProject management
Project management
 
Iii. principles of_capital_budgeting
Iii. principles of_capital_budgetingIii. principles of_capital_budgeting
Iii. principles of_capital_budgeting
 
Cfd ppt
Cfd pptCfd ppt
Cfd ppt
 
Investment decision
Investment decisionInvestment decision
Investment decision
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
 
Npv n other invest cri lec 4
Npv n other invest cri lec 4Npv n other invest cri lec 4
Npv n other invest cri lec 4
 
Chapter iii capital budget
Chapter iii capital budgetChapter iii capital budget
Chapter iii capital budget
 
02_lecture 8.ppt
02_lecture 8.ppt02_lecture 8.ppt
02_lecture 8.ppt
 
02_lecture 8.ppt
02_lecture 8.ppt02_lecture 8.ppt
02_lecture 8.ppt
 
02_lecture 8.ppt
02_lecture 8.ppt02_lecture 8.ppt
02_lecture 8.ppt
 
Bsics of Capital Budgeting.pptx
Bsics of Capital Budgeting.pptxBsics of Capital Budgeting.pptx
Bsics of Capital Budgeting.pptx
 
Unit III.pptx
Unit III.pptxUnit III.pptx
Unit III.pptx
 
FN6033-CORP FIN-LECTURE 5A.ppt
FN6033-CORP FIN-LECTURE 5A.pptFN6033-CORP FIN-LECTURE 5A.ppt
FN6033-CORP FIN-LECTURE 5A.ppt
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
133CHAPTER122002.ppt
133CHAPTER122002.ppt133CHAPTER122002.ppt
133CHAPTER122002.ppt
 

Plus de edgar6wallace88877

Write a page to a page and half for each topic and read each topic a.docx
Write a page to a page and half for each topic and read each topic a.docxWrite a page to a page and half for each topic and read each topic a.docx
Write a page to a page and half for each topic and read each topic a.docxedgar6wallace88877
 
Write a page discussing why you believe PMI is focusing BA as the fi.docx
Write a page discussing why you believe PMI is focusing BA as the fi.docxWrite a page discussing why you believe PMI is focusing BA as the fi.docx
Write a page discussing why you believe PMI is focusing BA as the fi.docxedgar6wallace88877
 
Write a page of personal reflection of your present leadership compe.docx
Write a page of personal reflection of your present leadership compe.docxWrite a page of personal reflection of your present leadership compe.docx
Write a page of personal reflection of your present leadership compe.docxedgar6wallace88877
 
Write a page of compare and contrast for the Big Five Personalit.docx
Write a page of compare and contrast for the Big Five Personalit.docxWrite a page of compare and contrast for the Big Five Personalit.docx
Write a page of compare and contrast for the Big Five Personalit.docxedgar6wallace88877
 
Write a page of research and discuss an innovation that includes mul.docx
Write a page of research and discuss an innovation that includes mul.docxWrite a page of research and discuss an innovation that includes mul.docx
Write a page of research and discuss an innovation that includes mul.docxedgar6wallace88877
 
Write a page answering the questions below.Sometimes projects .docx
Write a page answering the questions below.Sometimes projects .docxWrite a page answering the questions below.Sometimes projects .docx
Write a page answering the questions below.Sometimes projects .docxedgar6wallace88877
 
Write a one-paragraph summary of one of the reading assignments from.docx
Write a one-paragraph summary of one of the reading assignments from.docxWrite a one-paragraph summary of one of the reading assignments from.docx
Write a one-paragraph summary of one of the reading assignments from.docxedgar6wallace88877
 
Write a one-paragraph summary of this article.Riordan, B. C..docx
Write a one-paragraph summary of this article.Riordan, B. C..docxWrite a one-paragraph summary of this article.Riordan, B. C..docx
Write a one-paragraph summary of this article.Riordan, B. C..docxedgar6wallace88877
 
Write a one-paragraph response to the following topic. Use the MLA f.docx
Write a one-paragraph response to the following topic. Use the MLA f.docxWrite a one-paragraph response to the following topic. Use the MLA f.docx
Write a one-paragraph response to the following topic. Use the MLA f.docxedgar6wallace88877
 
Write a one-page rhetorical analysis in which you analyze the argume.docx
Write a one-page rhetorical analysis in which you analyze the argume.docxWrite a one-page rhetorical analysis in which you analyze the argume.docx
Write a one-page rhetorical analysis in which you analyze the argume.docxedgar6wallace88877
 
Write a one pageliterature review of your figure( FIGURE A.docx
Write a one pageliterature review of your figure( FIGURE A.docxWrite a one pageliterature review of your figure( FIGURE A.docx
Write a one pageliterature review of your figure( FIGURE A.docxedgar6wallace88877
 
Write a one page-paper documenting the problemneed you wish to .docx
Write a one page-paper documenting the problemneed you wish to .docxWrite a one page-paper documenting the problemneed you wish to .docx
Write a one page-paper documenting the problemneed you wish to .docxedgar6wallace88877
 
Write a one page report on Chapter 1 and 2 with the same style of mo.docx
Write a one page report on Chapter 1 and 2 with the same style of mo.docxWrite a one page report on Chapter 1 and 2 with the same style of mo.docx
Write a one page report on Chapter 1 and 2 with the same style of mo.docxedgar6wallace88877
 
Write a one page reflection about the following1) Identify .docx
Write a one page reflection about the following1) Identify .docxWrite a one page reflection about the following1) Identify .docx
Write a one page reflection about the following1) Identify .docxedgar6wallace88877
 
Write a one page paper on the question belowSome of the current.docx
Write a one page paper on the question belowSome of the current.docxWrite a one page paper on the question belowSome of the current.docx
Write a one page paper on the question belowSome of the current.docxedgar6wallace88877
 
Write a one page paper (double spaced) describing and discussing the.docx
Write a one page paper (double spaced) describing and discussing the.docxWrite a one page paper (double spaced) describing and discussing the.docx
Write a one page paper (double spaced) describing and discussing the.docxedgar6wallace88877
 
write a one page about this topic and provide a reference.Will.docx
write a one page about this topic and provide a reference.Will.docxwrite a one page about this topic and provide a reference.Will.docx
write a one page about this topic and provide a reference.Will.docxedgar6wallace88877
 
Write a one or more paragraph on the following question below.docx
Write a one or more paragraph on the following question below.docxWrite a one or more paragraph on the following question below.docx
Write a one or more paragraph on the following question below.docxedgar6wallace88877
 
Write a one or more page paper on the following belowWhy are .docx
Write a one or more page paper on the following belowWhy are .docxWrite a one or more page paper on the following belowWhy are .docx
Write a one or more page paper on the following belowWhy are .docxedgar6wallace88877
 
Write a one page dialogue in which two characters are arguing but .docx
Write a one page dialogue in which two characters are arguing but .docxWrite a one page dialogue in which two characters are arguing but .docx
Write a one page dialogue in which two characters are arguing but .docxedgar6wallace88877
 

Plus de edgar6wallace88877 (20)

Write a page to a page and half for each topic and read each topic a.docx
Write a page to a page and half for each topic and read each topic a.docxWrite a page to a page and half for each topic and read each topic a.docx
Write a page to a page and half for each topic and read each topic a.docx
 
Write a page discussing why you believe PMI is focusing BA as the fi.docx
Write a page discussing why you believe PMI is focusing BA as the fi.docxWrite a page discussing why you believe PMI is focusing BA as the fi.docx
Write a page discussing why you believe PMI is focusing BA as the fi.docx
 
Write a page of personal reflection of your present leadership compe.docx
Write a page of personal reflection of your present leadership compe.docxWrite a page of personal reflection of your present leadership compe.docx
Write a page of personal reflection of your present leadership compe.docx
 
Write a page of compare and contrast for the Big Five Personalit.docx
Write a page of compare and contrast for the Big Five Personalit.docxWrite a page of compare and contrast for the Big Five Personalit.docx
Write a page of compare and contrast for the Big Five Personalit.docx
 
Write a page of research and discuss an innovation that includes mul.docx
Write a page of research and discuss an innovation that includes mul.docxWrite a page of research and discuss an innovation that includes mul.docx
Write a page of research and discuss an innovation that includes mul.docx
 
Write a page answering the questions below.Sometimes projects .docx
Write a page answering the questions below.Sometimes projects .docxWrite a page answering the questions below.Sometimes projects .docx
Write a page answering the questions below.Sometimes projects .docx
 
Write a one-paragraph summary of one of the reading assignments from.docx
Write a one-paragraph summary of one of the reading assignments from.docxWrite a one-paragraph summary of one of the reading assignments from.docx
Write a one-paragraph summary of one of the reading assignments from.docx
 
Write a one-paragraph summary of this article.Riordan, B. C..docx
Write a one-paragraph summary of this article.Riordan, B. C..docxWrite a one-paragraph summary of this article.Riordan, B. C..docx
Write a one-paragraph summary of this article.Riordan, B. C..docx
 
Write a one-paragraph response to the following topic. Use the MLA f.docx
Write a one-paragraph response to the following topic. Use the MLA f.docxWrite a one-paragraph response to the following topic. Use the MLA f.docx
Write a one-paragraph response to the following topic. Use the MLA f.docx
 
Write a one-page rhetorical analysis in which you analyze the argume.docx
Write a one-page rhetorical analysis in which you analyze the argume.docxWrite a one-page rhetorical analysis in which you analyze the argume.docx
Write a one-page rhetorical analysis in which you analyze the argume.docx
 
Write a one pageliterature review of your figure( FIGURE A.docx
Write a one pageliterature review of your figure( FIGURE A.docxWrite a one pageliterature review of your figure( FIGURE A.docx
Write a one pageliterature review of your figure( FIGURE A.docx
 
Write a one page-paper documenting the problemneed you wish to .docx
Write a one page-paper documenting the problemneed you wish to .docxWrite a one page-paper documenting the problemneed you wish to .docx
Write a one page-paper documenting the problemneed you wish to .docx
 
Write a one page report on Chapter 1 and 2 with the same style of mo.docx
Write a one page report on Chapter 1 and 2 with the same style of mo.docxWrite a one page report on Chapter 1 and 2 with the same style of mo.docx
Write a one page report on Chapter 1 and 2 with the same style of mo.docx
 
Write a one page reflection about the following1) Identify .docx
Write a one page reflection about the following1) Identify .docxWrite a one page reflection about the following1) Identify .docx
Write a one page reflection about the following1) Identify .docx
 
Write a one page paper on the question belowSome of the current.docx
Write a one page paper on the question belowSome of the current.docxWrite a one page paper on the question belowSome of the current.docx
Write a one page paper on the question belowSome of the current.docx
 
Write a one page paper (double spaced) describing and discussing the.docx
Write a one page paper (double spaced) describing and discussing the.docxWrite a one page paper (double spaced) describing and discussing the.docx
Write a one page paper (double spaced) describing and discussing the.docx
 
write a one page about this topic and provide a reference.Will.docx
write a one page about this topic and provide a reference.Will.docxwrite a one page about this topic and provide a reference.Will.docx
write a one page about this topic and provide a reference.Will.docx
 
Write a one or more paragraph on the following question below.docx
Write a one or more paragraph on the following question below.docxWrite a one or more paragraph on the following question below.docx
Write a one or more paragraph on the following question below.docx
 
Write a one or more page paper on the following belowWhy are .docx
Write a one or more page paper on the following belowWhy are .docxWrite a one or more page paper on the following belowWhy are .docx
Write a one or more page paper on the following belowWhy are .docx
 
Write a one page dialogue in which two characters are arguing but .docx
Write a one page dialogue in which two characters are arguing but .docxWrite a one page dialogue in which two characters are arguing but .docx
Write a one page dialogue in which two characters are arguing but .docx
 

Dernier

Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024Janet Corral
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Disha Kariya
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingTeacherCyreneCayanan
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...christianmathematics
 

Dernier (20)

Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 

Slide 1 8-1Capital Budgeting• Analysis of potent.docx

  • 1. Slide 1 8-1 Capital Budgeting • Analysis of potential projects • Long-term decisions • Large expenditures • Difficult/impossible to reverse • Determines firm’s strategic direction When a company is deciding whether to invest in a new project, large sums of money can be at stake. For example, the Artic LNG project would build a pipeline from Alaska’s North Slope to allow natural gas to be sent from the area. The cost of the pipeline and plant to clean the gas of impurities was expected to be $45 to $65 billion. Decisions such as these long-term investments, with price tags in the billions, are obviously major undertakings, and the risks and rewards must be carefully weighed. We called this the
  • 2. capital budgeting decision. This module introduces you to the practice of capital budgeting. We will consider a variety of techniques financial analysts and corporate executives routinely use for the capital budgeting decisions. 1. Net Present Value (NPV) 2. Payback Period 3. Average Accounting Rate (AAR) 4. Internal Rate of Return (IRR) or Modified Internal Rate of Return (MIRR) 5. Profitability Index (PI) Slide 2 8-2 • All cash flows considered? • TVM considered? • Risk-adjusted? • Ability to rank projects? • Indicates added value to the firm?
  • 3. Good Decision Criteria All things here are related to maximize the stock price. We need to ask ourselves the following questions when evaluating capital budgeting decision rules: creating value for the firm? Slide 3 8-3 Net Present Value • The difference between the market value of a project and its cost • How much value is created from undertaking
  • 4. an investment? Step 1: Estimate the expected future cash flows. Step 2: Estimate the required return for projects of this risk level. Step 3: Find the present value of the cash flows and subtract the initial investment to arrive at the Net Present Value. Net present value—the difference between the market value of an investment and its cost. The NPV measures the increase in firm value, which is also the increase in the value of what the shareholders own. Thus, making decisions with the NPV rule facilitates the achievement of our goal – making decisions that will maximize shareholder wealth.
  • 5. Slide 4 8-4 Net Present Value Sum of the PVs of all cash flows Initial cost often is CF0 and is an outflow. NPV =∑ n t = 0 CFt (1 + R)t NPV =∑ n t = 1 CFt (1 + R)t - CF0 NOTE: t=0 Up to now, we’ve avoided cash flows at time t = 0, the
  • 6. summation begins with cash flow zero— not one. The PV of future cash flows is not NPV; rather, NPV is the amount remaining after offsetting the PV of future cash flows with the initial cost. Thus, the NPV amount determines the incremental value created by undertaking the investment. Slide 5 8-5 NPV – Decision Rule • If NPV is positive, accept the project • NPV > 0 means: – Project is expected to add value to the firm – Will increase the wealth of the owners
  • 7. • NPV is a direct measure of how well this project will meet the goal of increasing shareholder wealth. Slide 6 8-6 Rationale for the NPV Method • NPV = PV inflows – Cost NPV=0 → Project’s inflows are “exactly sufficient to repay the invested capital and provide the required rate of return” Conceptually, a zero-NPV project earns exactly its required return. Assuming that risk has been adequately accounted for, investing in a zero-NPV project is equivalent to purchasing a financial asset in an efficient market. In this sense, one would be indifferent between the capital expenditure
  • 8. project and the financial asset investment. Further, since firm value is completely unaffected by the investment, there is no reason for shareholders to prefer either one. In practice, financial managers are rarely presented with zero NPV projects for at least two reasons. First, in an abstract sense, zero is just another of the infinite number of values the NPV can take; as such, the likelihood of obtaining any particular number is small. Second, and more pragmatically, in most large firms, capital investment proposals are submitted to the finance group from other areas for analysis. Those submitting proposals recognize the ambivalence associated with zero NPVs and are less likely to send them to the finance group in the first place. Slide 7
  • 9. 8-7 Sample Project Data • You are looking at a new project and have estimated the following cash flows, net income and book value data: – Year 0: CF = -165,000 – Year 1: CF = 63,120 NI = 13,620 – Year 2: CF = 70,800 NI = 3,300 – Year 3: CF = 91,080 NI = 29,100 – Average book value = $72,000 • Your required return for assets of this risk is 12%. • This project will be the example for all problem exhibits in this module. This example will be used for each of the decision rules so that we can compare the different rules and see that conflicts can arise. This illustrates the importance of recognizing which decision rules provide the best information for making decisions that will increase owner wealth.
  • 10. Slide 8 8-8 Display You Enter CF, 2nd,CLR WORK CF0 -165000 Enter, Down C01 63120 Enter, Down F01 1 Enter, Down C02 70800 Enter, Down F02 1 Enter, Down C03 91080 Enter, Down F03 1 Enter, NPV I 12 Enter, Down NPV CPT 12,627.41 Cash Flows: CF0 = -165000 CF1 = 63120 CF2 = 70800 CF3 = 91080 Computing NPV for the Project
  • 11. Using the TI BAII+ Do we accept or reject the project? Accept Again, the calculator used for the illustration is the TI BA-II plus. The basic procedure is the same; you start with the year 0 cash flow and then enter the cash flows in order. F01, F02, etc. are used to set the frequency of a cash flow occurrence. Many calculators only require you to use this function if the frequency is something other than 1. Using the formulas: NPV = -165,000 + 63,120/(1.12) + 70,800/(1.12)2 + 91,080/(1.12)3 = 12,627.41 Using the calculator (details): Press the following keys: 2nd, CF, 2nd, Clear. Calculator displays CF0, 165,000 +|– key, press the Enter key. Press down arrow, enter 63,120, and press Enter. Press down arrow, enter 1, and press Enter. Press down arrow, enter 70,800, and press Enter. Press down arrow, enter 1, and press Enter.
  • 12. Press down arrow, enter 91,080, and press Enter. Press down arrow, enter 1, and press Enter. Press NPV; calculator shows I = 0; enter 12 and press Enter. Press down arrow; calculator shows NPV = 0.00. Press CPT; calculator shows NPV = 12,627.41. Slide 9 8-9 • Does the NPV rule account for the time value of money? • Does the NPV rule account for the risk of the cash flows? • Does the NPV rule provide an indication about the increase in value? • Should we consider the NPV rule for our primary decision rule? Decision Criteria Test – NPV
  • 13. The answer to all of these questions is yes. The risk of the cash flows is accounted for through the choice of the discount rate. NPV meets all desirable criteria TVM Mutually exclusive investment decisions – taking one project means another cannot be taken. An excellent example of mutually exclusive projects is the choice of which college or university to attend. Many students apply and are accepted to more than one college, yet they cannot attend more than one at a time. Consequently, they have to decide between mutually exclusive projects.
  • 14. Slide 10 8-10 Payback Period • How long does it take to recover the initial cost of a project? • Computation – Estimate the cash flows – Subtract the future cash flows from the initial cost until initial investment is recovered – A “break-even” type measure • Decision Rule – Accept if the payback period is less than some preset limit Payback period—length of time until the accumulated cash flows equal or exceed the original investment, i.e., how fast you recover your initial investment. Payback period rule – investment is acceptable if its calculated payback is less than some prespecified number of years.
  • 15. Slide 11 8-11 Computing Payback for the Project • Do we accept or reject the project? Capital Budgeting Project Year CF Cum. CFs 0 (165,000)$ (165,000)$ 1 63,120$ (101,880)$ 2 70,800$ (31,080)$ 3 91,080$ 60,000$ Payback = year 2 + + (31080/91080) Payback = 2.34 years
  • 16. Assume we will accept the project if it pays back within two years. Year 1: 165,000 – 63,120 = 101,880 still to recoup Year 2: 101,880 – 70,800 = 31,080 still to recoup Year 3: 31,080 – 91,080 = -60,000 If we assume that the cash flows occur evenly throughout the year, which is typical for this method, then the project pays back in 2.34 years. The payback rule would say to reject the project. Slide 12 8-12 • Does the payback rule account for the time value of money? • Does the payback rule account for the risk of the cash flows?
  • 17. • Does the payback rule provide an indication about the increase in value? • Should we consider the payback rule for our primary decision rule? Decision Criteria Test – Payback The answer to all of these questions is no. Decision Criteria Test – Payback • -No discounting involved • -Doesn’t consider risk differences • -How do we determine the cutoff point • -Biased toward short-term investments Real-World Tip: Interestingly, the payback period technique is used quite heavily in determining the viability of certain investment projects in the health care industry. Why? Consider the nature of the health care industry: the technology is rapidly changing, some of the equipment tends to be extremely expensive, and the industry itself is increasingly competitive. What this means is that, in many cases, an equipment purchase is complicated by the fact that, while the machine may be able
  • 18. to perform its function for, say, 6 years or more, new and improved equipment is likely to be developed that will supersede the “old” equipment long before its useful life is over. Demand from patients and physicians for “cutting-edge technology” can drive a push for new investment. In the face of such a situation, many hospital administrators then focus on how long it will take to recoup the initial outlay, in addition to the NPV and IRR of the equipment. Slide 13 8-13 Advantages and Disadvantages of Payback • Advantages – Easy to understand – Adjusts for uncertainty of later cash flows
  • 19. – Biased towards liquidity • Disadvantages – Ignores the time value of money – Requires an arbitrary cutoff point – Ignores cash flows beyond the cutoff date – Biased against long-term projects, such as research and development, and new projects Slide 14 8-14 Average Accounting Return • Many different definitions for average accounting return (AAR)
  • 20. • In this module, we will use the following specific definition: – Note: Average book value depends on how the asset is depreciated. • Requires a target cutoff rate • Decision Rule: Accept the project if the AAR is greater than target rate. Value Book Average IncomeNet Average Average accounting return = measure of accounting profit / measure of average accounting value. In other words, it is a benefit/cost ratio that produces a pseudo rate of return. However, due to the accounting conventions involved, the lack of risk adjustment and the use of profits rather than cash flows, it isn’t clear what is being measured.
  • 21. Slide 15 8-15 • Assume we require an average accounting return of 25%. • Average Net Income: • AAR = 15,340 / 72,000 = .213 = 21.3% • Do we accept or reject the project? Computing AAR Sample Project Data: Year 0: CF = -165,000 Year 1: CF = 63,120 NI = 13,620 Year 2: CF = 70,800 NI = 3,300 Year 3: CF = 91,080 NI = 29,100 Average book value = $72,000 You may ask where you came up with the 25%. Note that this is one of the drawbacks of this rule. There is no good theory for determining what the return
  • 22. should be. We generally just use some rule of thumb. This rule would indicate that we reject the project. - Another example You are deciding whether to open a store in a new shopping mall. The required investment in improvements is $500,000. The store would have a five-year life because everything reverts to the mall owners after that time. The required investment would be 100 percent depreciated (straight- line) over five years, so the depreciation would be $500,000 / 5 = $100,000 per year. Net income is $100,000 in the first year, $150,000 in the second year, $50,000 in the third year, $0 in Year 4, and -$50,000 in Year 5. AAR? To calculate the average book value for this investment, we note that we started out with a book value of $500,000 (the initial cost) and ended up at $0 (i.e., we need to consider six book values). The average book value during the life of the investment is thus ($500,000 + 0) / 2 = $250,000. As long as we use straight-line depreciation, the average investment will always be one-half of the
  • 23. initial investment. We could, of course, calculate the average of the six book values directly. In thousands, we would have ($500 + 400 + 300 + 200 + 100 + 0) / 6 = $250. The average net income is [$100,000 + 150,000 + 50,000 + 0 + (-50,000)] / 5 = $50,000. Thus, AAR = $50,000 / $250,000 = 20% Slide 16 8-16 Decision Criteria Test - AAR • Does the AAR rule account for the time value of money? • Does the AAR rule account for the risk of the cash flows? • Does the AAR rule provide an indication about the increase in value? • Should we consider the AAR rule for our primary decision criteria? The answer to all of these questions is NO. In fact, this rule is
  • 24. even worse than the payback rule in that it doesn’t even use cash flows for the analysis. It uses net income and book value. It isn’t clear what is being measured. Thus, it is not surprising that most surveys indicate that few large firms employ the payback and/or AAR methods exclusively. Slide 17 8-17 Advantages and Disadvantages of AAR • Advantages – Easy to calculate – Needed information usually available • Disadvantages – Not a true rate of return
  • 25. – Time value of money ignored – Uses an arbitrary benchmark cutoff rate – Based on accounting net income and book values, not cash flows and market values -Since it involves accounting figures rather than cash flows, it is not comparable to returns in capital markets -It treats money in all periods as having the same value -There is no objective way to find the cutoff rate Slide 18 8-18 • This is the most important alternative to
  • 26. NPV. • It is often used in practice and is intuitively appealing. • It is based entirely on the estimated cash flows and is independent of interest rates found elsewhere. Internal Rate of Return Internal rate of return (IRR)—the rate that makes the present value of the future cash flows equal to the initial cost or investment. In other words, the discount rate that gives a project a $0 NPV. The IRR rule is very important. Management, and individuals in general, often have a much better feel for percentage returns, and the value that is created, than they do for dollar increases. A dollar increase doesn’t appear to provide as much information if we don’t know what the initial expenditure was. Whether or not the additional information is relevant is another issue.
  • 27. Slide 19 8-19 IRR Definition and Decision Rule • Definition: • Decision Rule: the required return The goal of IRR is not to find zero NPV projects, but rather to find a range of discount rates for which the project is acceptable. Slide 20
  • 28. 8-20 NPV vs. IRR NPV )R1( CFn 0t t IRR: Enter NPV = 0, solve for IRR. NPV: Enter r, solve for NPV Slide 21
  • 29. 8-21 Display You Enter CF, 2nd, CLR WORK CF0 -165000 Enter, Down C01 63120 Enter, Down F01 1 Enter, Down C02 70800 Enter, Down F02 1 Enter, Down C03 91080 Enter, Down F03 1 Enter, IRR IRR CPT 16.1322 Cash Flows: CF0 = -165000 CF1 = 63120 CF2 = 70800 CF3 = 91080 Computing IRR for the Project Using the TI BAII IRR = 16.13% > 12% required return Do we accept or reject the project?
  • 30. Internal rate of return (IRR) – the rate that makes the present value of the future cash flows equal to the initial cost or investment. In other words, the discount rate that gives a project a $0 NPV. IRR decision rule – the investment is acceptable if its IRR exceeds the required return If you do not have a financial calculator, then this becomes a trial and error process. Enter the cash flows as you did with NPV. Using the calculator (details): Press the following keys: 2nd, CF, 2nd, Clear. Calculator displays CF0, 165,000 +|– key, press the Enter key. Press down arrow, enter 63,120, and press Enter. Press down arrow, enter 1, and press Enter. Press down arrow, enter 70,800, and press Enter. Press down arrow, enter 1, and press Enter. Press down arrow, enter 91,080, and press Enter. Press down arrow, enter 1, and press Enter.
  • 31. Press IRR; calculator shows IRR = 0.00 Press CPT; calculator shows IRR = 16.132. Slide 22 8-22 NPV Profile For The Project -20,000 -10,000 0 10,000 20,000 30,000 40,000 50,000 60,000 70,000
  • 32. 0 0.02 0.04 0.06 0.08 0.1 0.12 0.14 0.16 0.18 0.2 0.22 Discount Rate N P V IRR = 16.13% Note that the NPV profile is also a form of sensitivity analysis—the slope of the NPV profile indicates how much a project’s estimated NPV is affected by a change in the discount rate used to compute it. Slide 23 8-23 • Does the IRR rule account for the time value of money? • Does the IRR rule account for the risk of the cash
  • 33. flows? • Does the IRR rule provide an indication about the increase in value? • Should we consider the IRR rule for our primary decision criteria? Decision Criteria Test - IRR The answer to all of these questions is yes, although it is not always as obvious. The IRR rule accounts for time value because it is finding the rate of return that equates all of the cash flows on a time value basis. The IRR rule accounts for the risk of the cash flows because you compare it to the required return, which is determined by the risk of the project. The IRR rule provides an indication of value because we will always increase value if we can earn a return greater than our required return. We could consider the IRR rule as our primary decision criteria, but as we will see, it has some problems that the NPV does not have. That is why we end up choosing the NPV as our ultimate decision rule.
  • 34. Slide 24 8-24 • Knowing a return is intuitively appealing • It is a simple way to communicate the value of a project to someone who doesn’t know all the estimation details. • If the IRR is high enough, you may not need to estimate a required return, which is often a difficult task. Advantages of IRR • Considers all cash flows • Considers time value of money • Provides indication of risk However, if you get a very large IRR then you should go back and look at your cash flow estimates again. In competitive markets, extremely high IRRs should be rare. Also, since the IRR calculation
  • 35. assumes that you can reinvest future cash flows at the IRR, a high IRR may be unrealistic. Slide 25 8-25 NPV vs. IRR • NPV and IRR will generally give the same decision • Exceptions – Non-conventional cash flows • Cash flow sign changes more than once – Mutually exclusive projects • Initial investments are substantially different • Timing of cash flows is substantially different NPV and IRR comparison: If a project’s cash flows are conventional (costs are paid early and
  • 36. benefits are received over the life), and if the project is independent, then NPV and IRR will give the same accept or reject decision. There are situations where NPV and IRR will give conflicting answers. Non-conventional cash flows – the sign of the cash flows changes more than once or the cash inflow comes first and outflows come later. Slide 26 8-26 • When the cash flows change sign more than once, there is more than one IRR. • When you solve for IRR you are solving for the root of an equation, and when you cross the x- axis more than once, there will be more than one return that solves the equation. • If you have more than one IRR, which one do you use to make your decision?
  • 37. IRR and Nonconventional Cash Flows Nonconventional cash flows means the sign of the cash flows changes more than once or the cash inflow comes first and outflows come later. If this occurs, you will have multiple internal rates of return. This is problematic for the IRR rule; however, the NPV rule still works correctly. Nonconventional cash flows and multiple IRRs occur when there is a net cost to shutting down a project. The most common examples deal with collecting natural resources. After the resource has been harvested, there is generally a cost associated with restoring the environment. Mutually exclusive investment decisions – taking one project means another cannot be taken. An excellent example of mutually exclusive projects is the choice of which college or university to attend. Many students apply and are accepted to more than one college, yet they cannot attend more than one at a time. Consequently, they have to decide
  • 38. between mutually exclusive projects. Slide 27 8-27 Non-Conventional Cash Flows • Suppose an investment will cost $90,000 initially and will generate the following cash flows: -150,000 • The required return is 15%. • Should we accept or reject the project? NPV = – 90,000 + 132,000 / 1.15 + 100,000 / (1.15)2 – 150,000 / (1.15)3 = 1,769.54
  • 39. Calculator: CF0 = -90,000; C01 = 132,000; F01 = 1; C02 = 100,000; F02 = 1; C03 = -150,000; F03 = 1; I = 15; CPT NPV = 1769.54 If you compute the IRR on the calculator, you get 10.11% because it is the first one that you come to. So, if you just blindly use the calculator without recognizing the uneven cash flows, NPV would say to accept and IRR would say to reject. Another type of nonconventional cash flow involves a “financing” project, where there is a positive cash flow followed by a series of negative cash flows. This is the opposite of an “investing” project. In this case, our decision rule reverses, and we accept a project if the IRR is less than the cost of capital, since we are borrowing at a lower rate. Slide 28
  • 40. 8-28 NPV Profile ($10,000.00) ($8,000.00) ($6,000.00) ($4,000.00) ($2,000.00) $0.00 $2,000.00 $4,000.00 0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45 0.5 0.55 Discount Rate N P V IRR = 10.11% and 42.66% When you cross the x-axis more than once, there will be more than one return that solves the equation
  • 41. You should accept the project if the required return is between 10.11% and 42.66%. This provides a good visual of the 2 IRRs. Slide 29 8-29 • Mutually exclusive projects either Harvard or Stanford, but not both. • Intuitively, you would use the following decision rules: – choose the project with the higher NPV – choose the project with the higher IRR IRR and Mutually Exclusive Projects
  • 42. Mutually exclusive investment decisions – taking one project means another cannot be taken. An excellent example of mutually exclusive projects is the choice of which college or university to attend. Many students apply and are accepted to more than one college, yet they cannot attend more than one at a time. Consequently, they have to decide between mutually exclusive projects. Slide 30 8-30 Example of Mutually Exclusive Projects Period Project A Project B 0 -500 -400 1 325 325 2 325 200
  • 43. IRR 19.43% 22.17% NPV 64.05 60.74 The required return for both projects is 10%. Which project should you accept and why? This is a simple example of two mutually exclusive projects that result in conflicting signals from NPV and IRR. The important point is that we DO NOT use IRR to choose between projects. Slide 31
  • 44. 8-31 Conflicts Between NPV and IRR • NPV directly measures the increase in value to the firm • Whenever there is a conflict between NPV and another decision rule, always use NPV • IRR is unreliable in the following situations: – Non-conventional cash flows – Mutually exclusive projects Slide 32 8-32 Modified Internal Rate of Return (MIRR) • Controls for some problems with IRR • Three Methods:
  • 45. 1.Discounting Approach = Discount future outflows (negative CF) to present and add to CF0 2. Reinvestment Approach = Compound all CFs except CF0 forward to end 3. Combination Approach – Discount outflows to present; compound inflows to end – MIRR will be unique number for each method FR = Finance rate (discount) RR = Reinvestment rate (compound) let’s go back to the cash flows in Figure 8.5: −$60, +$155, and −$100. As we saw, there are two IRRs, 25 percent and 33⅓ percent. We next illustrate three different MIRRs, all of which have the property that only one answer will result, thereby eliminating the multiple IRR problem. 1. With the discounting approach, the idea is to discount all negative cash flows back to the present at the required return and add them to the initial cost. Then, calculate the IRR. Because only the first modified cash flow is negative, there will be only one IRR.
  • 46. 2. We compound all cash flows (positive and negative) except the first out to the end of the project’s life and then calculate the IRR. In a sense, we are “reinvesting” the cash flows and not taking them out of the project until the very end. 3. As the name suggests, the combination approach blends our first two methods. Negative cash flows are discounted back to the present, and positive cash flows are compounded to the end of the project. Slide 33 8-33 MIRR Method 1 Discounting Approach Method 1: Discounting Approach R = 20%
  • 47. Yr CF ADJ MCF 0 -60 -69.444 -129.44444 1 155 155 2 -100 0 IRR= 19.74% Step 1: Discount future outflows (negative cash flows) to present and add to CF0 Step 2: Zero out negative cash flows which have been added to CF0. Step 3: Compute IRR normally 1. With the discounting approach, the idea is to discount all negative cash flows back to the present at the required return and add them to the initial cost. Then, calculate the IRR. Because only the first modified cash flow is negative, there will be only one IRR.
  • 48. Slide 34 8-34 MIRR Method 2 Reinvestment Approach Step 1: Compound ALL cash flows (except CF0) to end of project’s life Step 2: Zero out all cash flows which have been added to the last year of the project’s life. Step 3: Compute IRR normally Method 2: Reinvestment Approach R = 20% Yr CF ADJ MCF 0 -60 -60 1 155 0 2 -100 186 86 IRR= 19.72% We compound all cash flows (positive and negative) except the first out to the end of the project’s
  • 49. life and then calculate the IRR. In a sense, we are “reinvesting” the cash flows and not taking them out of the project until the very end. The MIRR on this set of cash flows is 19.72 percent, or a little lower than we got using the discounting approach. Slide 35 8-35 MIRR Method 3 Combination Approach Step 1: Discount all outflows (except CF0) to present and add to CF0. Step 2: Compound all cash inflows to end of project’s life Step 3: Compute IRR normally
  • 50. Method 3: Combination Approach R = 20% Yr CF ADJ MCF 0 -60 -69.444 -129.44444 1 155 0 2 -100 186 186 IRR= 19.87% The combination approach blends our first two methods. Negative cash flows are discounted back to the present, and positive cash flows are compounded to the end of the project. Slide 36 8-36 MIRR versus IRR • MIRR correctly assumes reinvestment at
  • 51. opportunity cost = WACC • MIRR avoids the multiple IRR problem • Managers like rate of return comparisons, and MIRR is better for this than IRR As our example makes clear, one problem with MIRRs is that there are different ways of calculating them, and there is no clear reason to say one of our three methods is better than any other. The differences are small with our simple cash flows, but they could be much larger for a more complex project. Slide 37 8-37 Profitability Index • Measures the benefit per unit cost, based on the time value of money
  • 52. • If a project costs $200 and the present value of its future cash flows is $220. (PI: 220/200=1.1) – A profitability index of 1.1 implies that for every $1 of investment, we create an additional $0.10 in value • Can be very useful in situations of capital rationing Another method used to evaluate projects involves the profitability index (PI), or benefit-cost ratio. This index is defined as the present value of the future cash flows divided by the initial investment. Slide 38 8-38 Profitability Index • For conventional CF Projects: PV(Cash Inflows)
  • 53. Absolute Value of Initial Investment0 n 1t t t CF )r1( CF PI This index is defined as the present value of the future cash flows divided by the initial investment. If a project has a positive NPV, then the PI will be greater than 1.
  • 54. Slide 39 8-39 Advantages and Disadvantages of Profitability Index • Advantages – Closely related to NPV, generally leading to identical decisions • Considers all CFs • Considers TVM – Easy to understand and communicate – Useful in capital rationing • Disadvantages – May lead to incorrect decisions in comparisons of mutually exclusive investments (can conflict with NPV) – Eg. Project A vs B A: Cost: 5, PV of CF: 10 B: Cost: 100, PV of CF: 150
  • 55. A: NPV 5, PI 2 B: NPV 50, PI 1.5 The PI is obviously very similar to the NPV. If a project has a positive NPV, then the present value of the future cash flows must be bigger than the initial investment. The profitability index would thus be bigger than 1.00 Slide 40 8-40 Capital Budgeting In Practice • Consider all investment criteria when making decisions • NPV and IRR are the most commonly used primary investment criteria • Payback is a commonly used secondary
  • 56. investment criteria Even though payback and AAR should not be used to make the final decision, we should consider the project very carefully if they suggest rejection. There may be more risk than we have considered or we may want to pay additional attention to our cash flow estimations. The fact that payback is commonly used as a secondary criterion may be because short paybacks allow firms to have funds sooner to invest in other projects without going to the capital markets. It is common among large firms to employ a discounted cash flow technique such as IRR or NPV along with payback period or average accounting return. It is suggested that this is one way to resolve the considerable uncertainty over future events that surrounds the estimation of NPV. Why are smaller firms more likely to use payback as a primary decision criterion? • Small firms don’t have direct access to the capital markets and therefore find it more difficult to estimate discount rates based on funds cost; the AAR is the project-level equivalent to the
  • 57. ROA measure used for analyzing firm profitability; and some small firm decision-makers may be less aware of DCF approaches than their large firm counterparts. When managers are judged and rewarded primarily on the basis of periodic accounting figures, there is an incentive to evaluate projects with methods such as payback or average accounting return. On the other hand, when compensation is tied to firm value, it makes more sense to use NPV as the primary decision tool. Slide 41 8-41 Capital Budgeting In Practice There have been a number of surveys conducted asking firms what types of investment criteria
  • 58. they actually use Slide 42 8-42 • Net present value criterion • Internal rate of return mutually exclusive projects. • Profitability Index -cost ratio rationing
  • 59. Summary – DCF Criteria For IRR, we assume a conventional investment project. For a financing project, we accept if the IRR is less than the “required” rate. Slide 43 8-43 • Payback period within some specified period. arbitrary cutoff period • Discounted payback period discounted basis ck in some specified period.
  • 60. Summary – Payback Criteria Slide 44 8-44 • Average Accounting Return e investment if the AAR exceeds some specified return level. Summary – Accounting Criterion
  • 61. Slide 45 8-45 • An investment project has the following cash flows: CF0 = -1,000,000; C01 – C08 = 200,000 each • If the required rate of return is 12%, what decision should be made using NPV? • How would the IRR decision rule be used for this project, and what decision would be reached? • How are the above two decisions related? Comprehensive Problem NPV Press the following keys: 2nd, CF, 2nd, Clear. Calculator displays CF0, 1000,000 +|– key, press the Enter key. Press down arrow, enter 200,000, and press Enter. Press down arrow, enter 8, and press Enter. Press NPV; calculator shows I = 0; enter 12 and press Enter. Press down arrow; calculator shows NPV = 0.00.
  • 62. Press CPT; calculator shows NPV = -6,472. -$6,472; reject the project since it would lower the value of the firm. IRR (Don’t need to repeat above since the data is already in the calculator, but just hit IRR after computing NPV) Press IRR; calculator shows IRR = 0.00 Press CPT; calculator shows IRR = 16.132. investable funds in a project that will provide insufficient return. The NPV and IRR decision rules will provide the same decision for all independent projects with conventional/normal cash flow patterns. If a project adds value to the firm (i.e., has a positive NPV), then it must be expected to provide a return above that which is required. Both of those justifications are good for shareholders.
  • 63. Slide 1 11-1 Return, Risk, and The Security Market Line We have to define risk and then discuss how to measure it. We then must quantify the relationship between an asset’s risk and its required return. There are two types of risk: systematic and unsystematic. This distinction is crucial because, as we will see, systematic risk affects almost all assets in the economy, at least to some degree, while unsystematic risk affects at most a small number of assets. We then develop the principle of diversification, which shows that highly diversified portfolios will tend to have almost no unsystematic risk.
  • 64. Slide 2 11-2 • Expected returns are based on the probabilities of possible outcomes. • In this context, “expected” means average if the process is repeated many times. • The “expected” return does not even have to be a possible return. Where: pi = the probability of state “i” occurring Ri = the expected return on an asset in state i Expected Returns = = n i ii RpRE 1
  • 65. )( Slide 3 11-3 Example: Expected Returns Stock C Stock T State (i) Probability (Pi) (Ri) (Ri) ___ Boom 0.3 0.15 0.25 Normal 0.5 0.10 0.20 Recession ??? 0.02 0.01 1.00 • E(RC) = .3(.15) + .5(.1) + .2(.02) = 0.099 • E(RT) = .3(.25) + .5(.2) + .2(.01) = 0.177 13-3 • Suppose you have predicted the following returns for stocks C and T in three possible
  • 66. states of the economy. What are the expected returns? What is the probability of a recession? 1- 0.3 - 0.5 = 0.2 Or work in the percentage terms. E(RC) = .3(15%) + .5(10%) + .2(2%) = 9.9% E(RT) = .3(25%) + .5(20%) + .2(1%) = 17.7% Slide 4 11-4 Variance and Standard Deviation the volatility of returns • Variance = Weighted average of squared deviations • Standard Deviation = Square root of variance
  • 67. = −= n i ii RERp 1 22 ))((σ Variance measures the dispersion of points around the mean of a distribution. In this context, we are attempting to characterize the variability of possible future security returns around the expected return. In other words, we are trying to quantify risk and return. Variance measures the total risk of the possible returns. Slide 5 11-5
  • 68. Variance and Standard Deviation • Consider the previous example. What are the variance and standard deviation for each stock? Stock C Stock T State (i) Probability (Pi) (Ri) (Ri) ___ Boom 0.3 0.15 0.25 Normal 0.5 0.10 0.20 Recession 0.2 0.02 0.01 E(RC) = 0.099 E(RT) = 0.177 • Stock C -0.099)2 + .5(0.10-0.099)2 + .2(0.02-0.099)2 = 0.002029 • Stock T -0.177)2 + .5(0.20-0.177)2 + .2(0.01-0.177)2 = 0.007441 13-5
  • 69. Slide 6 11-6 Another Example • Consider the following information: State(i) Probability (Pi) ABC, Inc. Return Boom .25 0.15 Normal .50 0.08 Slowdown .15 0.04 Recession .10 -0.03 • What is the expected return? • E(R) = .25(0.15) + .5(0.08) + .15(0.04) + .1(-0.03) = 8.05% • What is the variance? • Variance = .25(.15-0.0805)2 + .5(0.08-0.0805)2 + .15(0.04- 0.0805)2 + • .1(-0.03-0.0805)2 = 0.00267475 • What is the standard deviation? • Standard Deviation = 5.17% 13-6
  • 70. ⚫ E(R) = .25(0.15) + .5(0.08) + .15(0.04) + .1(-0.03) = 0.0805 (=8.05%) ⚫ Variance = .25(.15-0.0805)2 + .5(0.08-0.0805)2 + .15(0.04- 0.0805)2 + .1(-0.03-0.0805)2 = 0.00267475 ⚫ Standard Deviation = 0.0517 (=5.17%) You may experience confusion in understanding the mathematics of the variance calculation. You may have the feeling that you should divide the variance of an expected return by (n−1). Note that the probabilities account for this division. We divide by n−1 in the historical variance because we are looking at a sample. If we looked at the entire population (which is what we are doing with expected values), then we would divide by n (or multiply by 1 ⁄ n) to get our historical variance. This is the same as saying that the “probability” of occurrence is the same for all observations and is equal to 1 ⁄ n. Slide 7
  • 71. 11-7 Portfolios • Portfolio = collection of assets • An asset’s risk and return impact how the stock affects the risk and return of the portfolio • The risk-return trade-off for a portfolio is measured by the portfolio expected return and standard deviation, just as with individual assets Each individual has their own level of risk tolerance. Some people are just naturally more inclined to take risk, and they will not require the same level of compensation as others for doing so. Our risk preferences also change through time. We may be willing to take more risk when we are young and without a spouse or kids. But, once we start a family, our risk tolerance may drop.
  • 72. Slide 8 11-8 Portfolio Expected Returns • Expected return for an asset: • The expected return of a portfolio is the weighted average of the expected returns for each asset in the portfolio • Weights (wj) = % of portfolio invested in each asset = = m 1j jjP )R(Ew)R(E = = n 1i iiRp)R(E
  • 73. The expected return on a portfolio is the sum of the product of the expected returns on the individual securities and their portfolio weights. Let wj be the portfolio weight for asset j and m be the total number of assets in the portfolio. You can also find the expected return by finding the portfolio return in each possible state and computing the expected value as we did with individual securities. Slide 9 11-9 Example: Portfolio Weights • Suppose you have $15,000 to invest and you have purchased securities in the following amounts. What are your portfolio weights in each security?
  • 74. ▪ $2000 of C ▪ $3000 of KO ▪ $4000 of INTC ▪ $6000 of BP ▪ C: 2000/15000 = .133 ▪ KO: 3000/15000 = .2 ▪ INTC: 4000/15000 = .267 ▪ BP: 6000/15000 = .4 13-9 Weights (wj) ? C – Citigroup KO – Coca-Cola INTC – Intel BP – BP Note that the sum of the weights = 1 (=100%). A portfolio is a collection of assets, such as stocks and bonds, held by an investor. Portfolios can
  • 75. be described by the percentage investment in each asset. These percentages are called portfolio weights. Example: If two securities in a portfolio have a combined value of $10,000 with $6000 invested in IBM and $4000 invested in GM, then the weight on IBM = 6000 ⁄ 10000 = .6 (=60%) and the weight on GM = 4000 ⁄ 100000 = .4 (=40%) or we can simply calculate the weight on GM by 1 – 0.6 = 0.4 (=40%) since the sum of the weights equals 1 (=100%). Slide 10 11-10 Expected Portfolio Returns • Consider the portfolio weights computed previously. If the individual stocks have the following expected returns, what is the
  • 76. expected return for the portfolio? • ▪ C: 19.69% ▪ KO: 5.25% ▪ INTC: 16.65% ▪ BP: 18.24% • E(RP) = .133(0.1969) + .2(0.0525) + .267(0.1665) + .4(0.1824) = 0.1541 13-10 ▪ C: 2000/15000 = .133 ▪ KO: 3000/15000 = .2 ▪ INTC: 4000/15000 = .267 ▪ BP: 6000/15000 = .4 Weights (wj) Expected Return E(Rj) Slide 11
  • 77. 11-11 Portfolio Variance • Compute portfolio return for each state: RP,i = w1R1,i + w2R2,i + … + wmRm,i • Compute the overall expected portfolio return using the same formula as for an individual asset • Compute the portfolio variance and standard deviation using the same formulas as for an individual asset The calculation of portfolio variance requires three steps: 1. Compute the portfolio return for each state of the economy. 2. Compute the overall expected return of the portfolio. 3. Compute portfolio variance and standard deviation using the same formulas as for an individual asset. Unlike expected return, the variance of a portfolio is NOT the weighted sum of the individual
  • 78. security variances. Combining securities into portfolios can reduce the total variability of returns. Slide 12 11-12 Example: Portfolio Variance • Consider the following information on returns and probabilities: ▪ Invest 50% of your money in Asset A State Probability A B Boom .4 30% -5% Bust .6 -10% 25% • What are the expected return and standard deviation for each asset? • What are the expected return and standard deviation for the portfolio? 13-12
  • 79. Slide 13 11-13 Example: Portfolio Variance • Invest 50% of your money in Asset A State Probability A B Boom .4 30% -5% Bust .6 -10% 25% • What are the expected return and standard deviation for each asset? Asset A: E(RA) = .4(0.3) + .6(-0.1) = 0.06 (=6%) Variance(A) = .4(0.3-0.06)2 + .6(-0.1-0.06)2 = 0.0384 Std. Dev.(A) = 0.196 (=19.6%)
  • 80. Asset B: E(RB) = .4(-0.05) + .6(0.25) = 0.13 (=13%) Variance(B) = .4(-0.05-0.13)2 + .6(0.25-0.13)2 = 0.0216 Std. Dev.(B) = 0.147 (=14.7%) • What are the expected return for the portfolio? E(Rp) = .5(0.06) + .5(0.13) = 0.095 (=9.5%) 13-13 Expected return and standard deviation for each asset Or work in the percentage terms. Asset A: E(RA) = .4(30%) + .6(-10%) = 6% Variance(A) = .4(30%-6%)2 + .6(-10%-6%)2 = 384 Std. Dev.(A) = √384 =19.6% Asset B: E(RB) = .4(-5%) + .6(25%) = 13% Variance(B) = .4(-5%-13%)2 + .6(25%-13%)2 = 216
  • 81. Std. Dev.(B) = √216 =14.7% Expected return for the portfolio (1) The expected return on a portfolio is the sum of the product of the expected returns on the individual securities and their portfolio weights. Weights (wj) = % of portfolio invested in each asset. There are two stocks in your portfolio and you invest 50% of your money in Asset A. What percent are you investing in Asset B? 50% (= (100% - 50%)). Thus, WA = 0.5, and WB = 0.5 Or work in the percentage terms. E(Rp) = .5(6%) + .5(13%) = 9.5% Slide 14 11-12 Example: Portfolio Variance • Consider the following information on returns and probabilities: ▪ Invest 50% of your money in Asset A State Probability A B Portfolio
  • 82. Boom .4 30% -5% 12.5% = RP,Boom Bust .6 -10% 25% 7.5% = RP,Bust E(RA) = 6% E(RB) = 13% E(Rp) • What are the expected return and standard deviation for the portfolio? 13-12 (1) (2) To compute the standard deviation for the portfolio, we need to follow three steps (See Slide 11) 1. Compute the portfolio return for each state of the economy. There are two stocks in your portfolio and you invest 50% of your money in Asset A. What percent are you investing in Asset B? 50% (= (100% - 50%)). Thus, WA = 0.5, and WB = 0.5 Portfolio return in boom: RP,Boom = 0.5(0.3) + 0.5(-0.05) = 0.125 (=12.5%) Portfolio return in bust: RP,Bust = 0.5(-0.1) + 0.5(0.25) = 0.075 (=7.5%)
  • 83. Or work in the percentage terms. RP,Boom = 0.5(30%) + 0.5(-5%) = 12.5% RP,Bust = 0.5(-10%) + 0.5(25%) =7.5% 2. Compute the overall expected return of the portfolio. In Slide 13, we computed E(Rp) = .5(6%) + .5(13%) = 9.5% - (1) You can also find the expected return for the portfolio by finding the portfolio return in each possible state and computing the expected value as we did with individual securities. E(Rp) = .4(12.5%) + .6(7.5%) = 9.5% - (2) Slide 15 11-14 Example: Portfolio Variance ▪ Invest 50% of your money in Asset A State Probability A B Portfolio
  • 84. Boom .4 30% -5% 12.5% Bust .6 -10% 25% 7.5% • What are the expected return and standard deviation for the portfolio? Portfolio return in boom (RP,Boom) = .5(.3) + .5(-.05) = .125 Portfolio return in bust (RP,Bust) = .5(-.1) + .5(.25) = .075 Expected return for portfolio E(RP) = .5(.06) + .5(.13) = .095 or .4(.125) + .6(.075) = .095 Variance of portfolio = .4(.125-.095)2 + .6(.075-.095)2 = .06 Standard deviation = .0245 13-14 3. Compute portfolio variance and standard deviation using the same formulas as for an individual asset. Expected return = .5(6%) + .5(13%) = 9.5% or Expected return = .4(12.5%) + .6(7.5%) = 9.5% Variance of portfolio = .4(12.5%-9.5%)2 + .6(7.5%-9.5%)2 = 6%
  • 85. Standard deviation = 2.45% Unlike expected return, the variance of a portfolio is NOT the weighted sum of the individual security variances. Combining securities into portfolios can reduce the total variability of returns. • Note that the variance is NOT equal to .5(384) + .5(216) = 300 and • Standard deviation is NOT equal to .5(19.6) + .5(14.7) = 17.17% To compute variance of portfolio, follow the direction of (2) in the previous slide. Slide 16 11-15 • Realized returns are generally not equal to expected returns. • There is the expected component and the unexpected component. ▪ At any point in time, the unexpected return can be
  • 86. either positive or negative. ▪ Over time, the average of the unexpected component is zero. Expected vs. Unexpected Returns Expected vs. Unexpected Returns Total return = Expected return + Unexpected return Total return differs from expected return because of surprises, or “news.” This is one of the reasons that realized returns differ from expected returns. Slide 17 11-16 Announcements and News • Announcements and news contain both an expected component and a surprise component
  • 87. • It is the surprise component that affects a stock’s price and therefore its return • This is very obvious when we watch how stock prices move when an unexpected announcement is made or earnings are different than anticipated 13-16 Announcement—the release of information not previously available. Announcements have two parts: the expected part and the surprise part. The expected part is “discounted” information used by the market to estimate the expected return, while the surprise is news that influences the unexpected return. Slide 18 11-17 Announcements and News
  • 88. • On November 17, 2004 it was announced that K- Mart would acquire Sears in an $11 billion deal. Sears’ stock price jumped from a closing price of $45.20 on November 16 to a closing price of $52.99 (a 7.79% increase) and K-Mart’s stock price jumped from $101.22 on November 16 to a closing price of $109.00 on November 17 (a 7.69% increase). Both stocks traded even higher during the day. • Why the jump in price? 13-17 It is easy to see the effect of unexpected news on stock prices and returns. Consider the following two cases: (1) On November 17, 2004 it was announced that K-Mart would acquire Sears in an $11 billion deal. Sears’ stock price jumped from a closing price of $45.20 on November 16 to a closing price of $52.99 (a 7.79% increase) and K-Mart’s stock price jumped from $101.22 on November 16 to a closing price of $109.00 on November 17 (a 7.69% increase). Both stocks traded even higher during the day. Why the jump in price? Unexpected news, of course.
  • 89. (2) On November 18, 2004, Williams-Sonoma cut its sales and earnings estimates for the fourth quarter of 2004 and its share price dropped by 6%. There are plenty of other examples where unexpected news causes a change in price and expected returns. Slide 19 11-18 Efficient Markets • Efficient markets are a result of investors trading on the unexpected portion of announcements • The easier it is to trade on surprises, the more efficient markets should be • Efficient markets involve random price changes because we cannot predict surprises 13-18
  • 90. Slide 20 11-19 Systematic Risk • Risk factors that affect a large number of assets • Also known as non-diversifiable risk or market risk. • Examples: changes in GDP, inflation, interest rates, etc. Risk consists of surprises. There are two kinds of surprises: Systematic Risk & Unsystematic Risk • Systematic risk is a surprise that affects a large number of assets, although at varying degrees. It is sometimes called market risk. • Example: Changes in GDP, interest rates, and inflation are examples of systematic risk.
  • 91. Slide 21 11-20 Unsystematic Risk • = Diversifiable risk • Risk factors that affect a limited number of assets • Also known as unique risk or asset-specific risk. • Risk that can be eliminated by combining assets into portfolios • Examples: labor strikes, part shortages, etc. • Unsystematic risk is a surprise that affects a small number of assets (or one). It is sometimes called unique or asset-specific risk. • Example: Strikes, accidents, and takeovers are examples of unsystematic risk.
  • 92. Slide 22 11-21 Diversification • Portfolio diversification is the investment in several different asset classes or sectors • Diversification is not just holding a lot of assets • For example, if you own 50 Internet stocks, you are not diversified • However, if you own 50 stocks that span 20 different industries, then you are diversified 13-21 Portfolio diversification can substantially reduce risk without an equivalent reduction in expected returns • Reduces the variability of returns
  • 93. Minimum level of risk that cannot be diversified away = systematic portion Slide 23 11-22 • Diversification can substantially reduce the variability of returns without an equivalent reduction in expected returns. • This reduction in risk arises because worse than expected returns from one asset are offset by better than expected returns from another. • However, there is a minimum level of risk that cannot be diversified away and that is the systematic portion. The Principle of Diversification Principle of Diversification – States that combining imperfectly correlated assets can produce a portfolio with less variability than the typical individual asset.
  • 94. The portion of variability present in a single security that is not present in a portfolio of securities is called diversifiable risk. The level of variance that is present in portfolios of assets is non- diversifiable risk. Slide 24 11-23 Standard Deviations of Annual Portfolio Returns Table 13.7 A typical single stock on the NYSE has a standard deviation of annual returns around 49%, while the typical large portfolio of NYSE stocks has a standard deviation of around 20%.
  • 95. Slide 25 11-24 • The risk that can be eliminated by combining assets into a portfolio. • Often considered the same as unsystematic, unique or asset-specific risk • If we hold only one asset, or assets in the same industry, then we are exposing ourselves to risk that we could diversify away. Diversifiable Risk When securities are combined into portfolios, their unique or unsystematic risks tend to cancel out, leaving only the variability that affects all securities to some degree. Thus, diversifiable risk is synonymous with unsystematic risk. Large portfolios have little or no unsystematic risk.
  • 96. Slide 26 11-25 Total Risk = Stand-alone Risk • Total risk = Systematic risk + Unsystematic risk – The standard deviation of returns is a measure of total risk • For well-diversified portfolios, unsystematic risk is very small – Total risk for a diversified portfolio is essentially equivalent to the systematic risk – The expected return (market required return) on an asset depends only on that asset’s systematic or market risk. Systematic risk cannot be eliminated by diversification since it represents the variability due to influences that affect all securities to some degree. Therefore, systematic risk and non- diversifiable risk are the same.
  • 97. Total risk = Non-diversifiable risk + Diversifiable risk = Systematic risk + Unsystematic risk Slide 27 11-26 Market Risk for Individual Securities • Measures the stock’s volatility relative to the market While the standard deviation of returns is a measure of total risk, the beta coefficient measures how much systematic risk an asset has relative to an asset of average risk. Beta measures the volatility of an individual asset or portfolio relative to the market as a whole.
  • 98. Slide 28 11-27 Measuring Systematic Risk • How do we measure systematic risk? ▪ We use the beta coefficient • What does beta tell us? ▪ A beta = 1 implies the asset has the same systematic risk as the overall market ▪ A beta < 1 implies the asset has less systematic risk than the overall market ▪ A beta > 1 implies the asset has more systematic risk than the overall market ▪ Most stocks have betas in the range of 0.5 to 1.5 ▪ Beta of a T-Bill = 0 13-27 Robert Hamada derived the following equation to reflect the
  • 99. relationship between levered and unlevered betas (excluding tax effects): where: D/E = debt-to-equity ratio Slide 29 11-28 Beta Coefficients for Selected Companies Table 13.8
  • 100. Slide 30 11-29 • Consider the following information: Standard Deviation Beta Security C 20% 1.25 Security K 30% 0.95 • Which security has more total risk? • Which security has more systematic risk? • Which security should have the higher expected return? Total vs. Systematic Risk Security K has the higher total risk. Security C has the higher systematic risk. Security C should have the higher expected return. • When securities are combined into portfolios, their unique or unsystematic risks tend to cancel out, leaving only the variability that affects all securities to some degree. Thus,
  • 101. Total risk for a diversified portfolio is essentially equivalent to the systematic risk. The expected return (market required return) on an asset depends only on that asset’s systematic or market risk. Slide 31 11-30 Portfolio Beta βp = Weighted average of the Betas of the assets in the portfolio Weights (wj)= % of portfolio invested in asset j = = n j jjp w 1
  • 102. The beta of the portfolio is simply a weighted average of the betas of the securities in the portfolio. Slide 32 11-31 • Consider the previous example with the following four securities. Security Weight Beta C .133 1.685 KO .2 0.195 INTC .267 1.161 BP .4 1.434 • What is the portfolio beta? • .133(1.685) + .2(.195) + .267(1.161) + .4(1.434) = 1.147 Example: Portfolio Betas
  • 103. Which security has the highest systematic risk? C Which security has the lowest systematic risk? KO Is the systematic risk of the portfolio more or less than the market? more Slide 33 11-32 Example: Portfolio Expected Returns and Betas 0% 5% 10% 15%
  • 104. 20% 25% 30% 0 0.5 1 1.5 2 2.5 3 E x p ec te d R et u rn Beta Rf E(RA) There is a linear relationship between beta and expected return.
  • 105. combined with a riskless asset, the resulting expected return is the weighted sum of the expected returns, and the portfolio beta is the weighted sum of the betas. By varying the amount invested in each asset, we can get an idea of the relation between portfolio expected returns and betas. This relationship is illustrated in this figure. As can be seen, all of the risk-return combinations lie on a straight line. The equation for a line is: Y = mx + b where: y = expected return x = beta m = slope = risk-premium per unit of beta b = y-intercept = risk-free rate E(R) = slope (Beta) + y-intercept The y-intercept is = the risk-free rate, so all we need is the slope
  • 106. Slide 34 11-33 Reward-to-Risk Ratio: Definition and Example • The reward-to-risk ratio is the slope of the line illustrated in the previous example ▪ Slope = (E(RA) – – 0) ▪ Reward-to-risk ratio for previous example = (20 – 8) / (1.6 – 0) = 7.5 • What if an asset has a reward-to-risk ratio of 8 (implying that the asset plots above the line)? • investors will want to buy the asset. • What if an asset has a reward-to-risk ratio of 7 (implying that the asset plots below the line)? • investors will want to sell the asset 13-33 The Reward-to-Risk Ratio is the expected return per unit of
  • 107. systematic risk. In other words, it is the ratio of risk premium to systematic risk. If the reward-to-risk ratio = 8, then investors will want to buy the asset. This will drive the price up and the expected return down (remember time value of money and valuation). When will the flurry of trading stop? When the reward-to-risk ratio reaches 7.5. If the reward-to-risk ratio = 7, then investors will want to sell the asset. This will drive the price down and the expected return up. When will the flurry of trading stop? When the reward-to-risk ratio reaches 7.5. Slide 35 11-34 Beta and the Risk Premium
  • 108. • Risk premium = E(R ) – Rf • The higher the beta, the greater the risk premium should be • Can we define the relationship between the risk premium and beta so that we can estimate the expected return? – YES! The risk premium—the excess return of an asset above the risk- free rate. Slide 36 11-35 Security Market Line • The security market line (SML) is the representation of market equilibrium • The slope of the SML = reward-to-risk ratio = (E(RM) –
  • 109. • But since the beta for the market is always equal to one, the slope can be rewritten • Slope = E(RM) – Rf = market risk premium The line that gives the expected return/systematic risk combinations of assets in a well-functioning, active financial market is called the security market line. Market Portfolios: Consider a portfolio of all the assets in the market and call it the market portfolio. This portfolio, by definition, has “average” systematic risk with a beta of 1. Since all assets must lie on the SML when appropriately priced, the market portfolio must also lie on the SML. Let the expected return on the market portfolio = E(RM). Then, the slope of the SML = reward-to-risk ratio
  • 110. Slide 37 11-36 Market Equilibrium • In equilibrium, all assets and portfolios must have the same reward-to-risk ratio • Each ratio must equal the reward-to-risk ratio for the market M fM A fA )RR(ER)R(E − = − The basic argument is that since systematic risk is all that matters in determining expected return, the reward-to-risk ratio must be the same for all assets. If it were not, people would buy the asset with the higher reward-to-risk ratio (driving the price up and
  • 111. the return down). The fundamental result is that in a competitive market where only systematic risk affects E(R), the reward-to-risk ratio must be the same for all assets in the market. Consequently, the expected returns and betas of all assets must plot on the same straight line. E.g., Amazon (Asset j =A) We can solve for � �� E RA Rf βA E RM Rf βM [E RA Rf] x βM = βA x [E RM Rf ] Since the market beta, βM = 1 (Wee Slide 28), E RA Rf = βA [E RM Rf ] E RA = Rf + βA [E RM Rf ]
  • 112. Since E(Rf) = Rf, E RA = Rf + βA [E RM Rf] This is called the capital asset pricing model (CAPM) Slide 38 11-37 SML and Equilibrium The Capital Asset Pricing Model (CAPM): We can get an idea of the relationship between portfolio expected returns and betas.
  • 113. Slide 39 11-38 The SML and Required Return • The Security Market Line (SML) is part of the Capital Asset Pricing Model (CAPM) Rf = Risk-free rate (T-Bill or T-Bond) RM = Market return ≈ S&P 500 RPM = Market risk premium = E(RM) – Rf E(Rj) = “Required Return of Asset j” ( ) ( ) jMfj jfMfj RPRRE RRERRE += −+=
  • 114. )( )()( Slide 40 11-39 Capital Asset Pricing Model • The capital asset pricing model (CAPM) defines the relationship between risk and return E(Rj) = Rf + βj(E(RM) – Rf) • If an asset’s systematic r CAPM can be used to determine its expected return Slide 41
  • 115. 11-40 Factors Affecting Required Return • Rf measures the pure time value of money • E(RM)-Rf measures the reward for bearing systematic risk amount of systematic risk The CAPM states that the expected return for an asset depends on: -The time value of money, as measured by Rf -The reward per unit risk, as measured by E(RM) − Rf -The asset’s systematic risk, Slide 42
  • 116. 11-41 Quick Quiz Consider an asset with a beta of 1.2, a risk-free rate of 5%, and a market return of 13%. – What is the reward-to-risk ratio in equilibrium? – What is the expected return on the asset? • E(R) = 5% + (13% - 5%)* 1.2 = 14.6% Reward-to-risk ratio = 13 – 5 = 8% Expected return = 5 + 1.2(8) = 14.6%