SlideShare une entreprise Scribd logo
1  sur  35
COSTS AND BENEFITS OF
ELECTRICITY INVESTMENTS




        Copyright©2007 CRI South-America   1
Economic Valuation of Additional
            Electricity Supply


• Willingness to pay for new connections
• Willingness to pay for more reliable service
• Resource cost savings from replacement of
  more expensive generation plants
• Marginal cost pricing



                  Copyright©2007 CRI South-America   2
ECONOMIC VALUE OF ELECTRICITY
              FOR NEW CONNECTIONS OR FOR REDUCTION OF
                   WITH ROTATING POWER SHORTAGES

      $
                          S0
PMAX=P’ D                                                         Shaded area = economic
                                                                  value of shortage power
                        B
                                                                  (Q’-Q0) = Power
                                                                  shortage, evenly rotated
                                        C                         to all customers
     P0   m
                    F
                                               D0
      0              Q0                Q’             Quantity

Assuming willingness to pay (WTP) of all customers are also evenly distributed
from highest 0P’ to lowest P0m:

  Economic Value of Additional Power Supply = ((PMAX+ P0m)/2) * (Q’-Q0)
                               Copyright©2007 CRI South-America                          3
ECONOMIC VALUE OF ELECTRICITY
                      COMPUTATION FORMULA
                D
          P’                    S0

                                B


          Pt                                            C
                            F
                                                               D0

            0                   Q0                    Q’            Quantity

P’ = Maximum willingness to pay per unit of shortage power
   = 2 (capital costs of own generation/KWh) + Fuel Costs/KWh
Need one generation to produce electricity and
the second generation to provide reliability

                            Copyright©2007 CRI South-America                   4
WILLINGNESS TO PAY (WTP) FOR
                SHORTAGE POWER IN INDIA
Customer Class                          Highest WTP*
                                        1996 Rs/kwh

COMMERCIAL                              4.00
(Diesel autogeneration)

INDUSTRIAL                               3.22
(Diesel autogeneration)

FARMER                                   3.77
(Diesel pump replacement)

RESIDENTIAL                             10.00
(Kerosene replacement)

•    Based on the financial costs of autogeneration or fuel replacement, World
    Bank Report, 14298-IN, 1996, for Orissa state of India. Actual WTP should be higher
     because of the inconveniences of operating diesel generators, diesel pumps,
     kerosene lamps and burners.Copyright©2007 CRI South-America                    5
OWN-GENERATION COST AND WILLINGNESS
          TO PAY IN MEXICO



Total Own-generation Cost ($/kWh)                         0.169

Average Power Price (Gross of Tax, $/kWh)                 0.037

Maximum Willingness To Pay ($/kWh)                        0.212

Average Willingness To Pay ($/kWh)                        0.125




                       Copyright©2007 CRI South-America           6
Estimated Cost of Power Failure

1. Based on willingness to pay
   • Based on customers survey

2. Based on actual costs to users

3. Based on linear relationship between GDP and
   electricity consumption of industrial/commercial
   users



                    Copyright©2007 CRI South-America   7
Estimated Cost of Power Failure*
1. Based on Willingness to Pay
     • Based on customers survey (Contingent valuation)
                  Ontario Hydro Estimates of Outage Costs (1981 US$/kwh)
    Duration      Large             Small           Commercial     Residential
               Manufacturers       Manufacturers
    1 min         58.76             83.25              1.96             0.17
    20 min         8.81             13.56              1.66             0.15
    1 hr          4.35              7.16               1.68             0.05
    2 hr          3.75              7.35               2.52             0.03
    4 hr          1.87              8.13               2.10             0.03
    8 hr          1.80              6.42               1.89             0.02
    16 hr          1.45             4.96               1.75             0.02
    Average**     2.15               6.38              1.98             0.12
    All groups average***:          1.96
    Average power price:            0.025
Average willingness for power during outage = 78.4 times average power price.
English Estimate (1996): 4 $/kwh
* C.W. Gellings and J.H. Chamberlin, Demand-Side Management: Concepts and Methods,
  Liburn, Georgia, The Fairmont Press, Inc., 1988.
** Based on system simulation model
                                   Copyright©2007 CRI South-America                  8
*** Based on shares: 13.5/13.5/39/34 %.
Estimated Cost of Power Failure (continued)
    2. Based on actual costs to users (Loss in contribution to
        profits)
              COST OF POWER FAILURE IN NEPAL*
                                                (Multiples of electric tariff)

   Year                            1              2              3        4       5

   Firm 1                      5.56             2.73 5.01 1.50                   3.43
   Firm 2                      3.31             2.86 1.71 3.24                   3.76
   Firm 3                     15.25            11.77 14.37 12.16                 5.26
   Average each year           8.04             5.79 7.03 5.63                   4.15
   Average all years           6.13
* Source: Table 7-10, Roop Jyoti, Investment Appraisal of Management Strategies for
Addressing Uncertainties in Power Supply in the Context of Nepalese Manufacturing
Enterprises, PhD Thesis, The Kennedy School of Government, Harvard
University,December, 1998.
                              Copyright©2007 CRI South-America                          9
Estimated Cost of Power Failure (continued)
             San Diego (sudden outage of a few hours)*
                                             (1981 US $/kwh)
                                      Industrial Commercial
Direct User                           2.79         2.40
Employees of Direct User              0.21         0.09
Indirect User                         0.12         0.13
Total                                 3.12         2.62
Multiples of Av Tariff**              62.4         52.4

        Key West, Florida (rotating blackout for 26 days)*
                                      % of                  Cost             Multiples
                                      Time                                   of Price
Nonresidential Users                  4.8                        $2.30/kwh    46.0

* Electric Power Research Institute study EPRI EA-1215, 1981, Vol. 2.
** Average price in 1981 is 0.05 $/kwh.
                              Copyright©2007 CRI South-America                       10
Estimated Cost of Power Failure (continued)

3. Based on linear relationship between GDP and electricity
   consumption of industrial/commercial users*

    Outage cost = 1.35   (1981$/kwh)
     Or:
                  = 27 (multiples of the average power price)


*    M. L. Telson, “The Economics of Alternative Levels of Reliability for Electric
     Power Generation Systems,” Bell Journal of Economics, Autumn, 1975.




                                Copyright©2007 CRI South-America                      11
Summary:
 Average power outage cost
 ranges from 6 to 80 times of
 the average power price.


          Copyright©2007 CRI South-America   12
Investment in New Generation
     to obtain Cost Savings




          Copyright©2007 CRI South-America   13
Load Curve hours for Year                     Load Duration Curve hours for
                                                              Year

Capacity                                        Capacity
  MW                                              MW




                                                                                            8760 hrs
                         8760 hrs                             Peak hours   Off-Peak hours




                           Copyright©2007 CRI South-America                                  14
Calculation of Marginal Cost of Electricity Supply

• During the off-peak hours when the capacity is not fully
  utilized, the marginal cost in any given hour is the marginal
  running cost (fuel and operating cost per Kwh) of the most
  expensive plant operating during that hour.
• During the peak hours, when generation capacity is fully
  utilized, the marginal cost of electricity per Kwh is equal to
  the marginal running cost of the most expensive plant
  running at the time plus the capital costs of adding more
  generation capacity, expressed as a cost per Kwh of peak
  energy supplied.



                      Copyright©2007 CRI South-America        15
Optimal Stacking of Thermal
Capacity                                                                            Plant   Capital    Fuel
KwH        1              MC4=0.08+ 400(0.15)/1000=0.14/KWH
                                                                                             Cost      Cost

               2                     MC3=0.05/KWH                                    4      1000      0.03 $

                                                MC2=0.04/KWH                         3       700      0.04 $
               3

               4                                           MC1=0.03/KWH              2       600      0.05 $

                    H2      H3       H4
                   1000     1500     4500                                            1       400      0.08 $



                            H4 solve for the minimum number of hours to run a plant 4 or
                                          the maximum number to run plant 3.
                                                         v = r+ d =0.15
                                                    v(K4)+f4(H4)=v(K3)+f3(H4)
                                            0.15(1000)+0.03(H4)=0.15(700)+0.04(H4)
                                                  (150-105)=0.4(H4)-0.03(H4)
                                                           45=0.01H4
                                                             H4=4500
                                                 Copyright©2007 CRI South-America                        16
Contribution to                                    Annualized Cost of Generation
             Generation Investments                                        Investments
        Hours Price MC         Amount $/yr.
                                                                                Capital           Annual
Plant 1: 1000 * (0.14 – 0.08) = 60                                              Cost         v   Cost
Plant 2: 1000 * (0.14 – 0.05) = 90
                                                                  Plant 1: 400            * 0.15 =    60
Plant 3: 1000 * (0.14 – 0.04) = 100
Plant 4: 1000 * (0.14 – 0.03) = 110                               Plant 2: 600            * 0.15 =    90
Plant 3: 500 * (0.05 – 0.04) = 5                                  Plant 3: 700            * 0.15 =   105
Plant 4: 500 * (0.05 – 0.03) = 10
                                                                  Plant 4: 1000           * 0.15 =   150
Plant 4: 3000 * (0.04 – 0.03) = 30
Total contribution per year = $405                                Total capital cost of system $405 per
                                                                        year.

            Plant 1 60                                                          60

            Plant 2      90                                                     90

                                                                               105
            Plant 3      100         5

            Plant 4      110      10          30                               150
                                            Copyright©2007 CRI South-America                          17
                           1000      1500        4500                   Total: $ 405
Stacking Problem: when do we replace a
                     thermal plant?
                                        KW
                                                      Output of plant #5 that
Plant No.       Marginal Running                      substitutes for plant #1 = Q1
                 Cost per Kwh              Hydro                      Output of plant #5 that
    1                 0.08                storage                     substitutes for plant #2 = Q2
                                             1 (2)   H1                     Output of plant #5 that
    2                 0.05
                                             2 (3)    H2                    substitutes for plant #3 = Q3
    3                 0.04                                                     Output of plant #5 that
                                             3 (4)    H3                       substitutes for plant #4 = Q4
    4                 0.03
                                             4 (5)    H4
    5                 0.02
                                                                            Load curve for plants 2,3,4
                                                                            after 5 is introduced

The question is whether or not we should build plant #5. We use the most efficient plant
first and then use the next most efficient and so on until the least efficient we need to
meet demand.
• Assume plant #5 has equal capacity to each of the other plants we would then have
  to shift all of the plants up one stage in production, thus there is no need to use plant
  number one now.
Benefits to Plant #5: It is going to be producing most of the time. Part of the time 5 is
  effectively substituting for 4, part for 3, part South-America part for 1.
                                      Copyright©2007 CRI for 2, and                       18
Two approaches to calculating benefits
A. The new plant is used to substitute for part of the other plants that now do not
   produce as much as previously:
   Benefits        Q4 x (0.03 – 0.02)
                   Q3 x (0.04 – 0.02)
                   Q2 x (0.05 – 0.02)
                   Q1 x (0.08 – 0.02)
                   Total A
B. Alternative approach
• Let H1, H2, H3, H4, be amount of electricity previously produced by plants 1 to 4.

    Original Total Cost                                  New Total Cost
    H4 x 0.03                                            H4 x 0.02
    H3 x 0.04                                            H3 x 0.03
    H2 x 0.05                                            H2 x 0.04
    H1 x 0.08                                            H1 x 0.05
    Total B                                              Total C

    Total A = Total B -Total C.
•   We now compare total A with the annual capital cost of plant 5.
                                Copyright©2007 CRI South-America                       19
The Situation where variations in the efficiency of
      thermal plants are taken into account
The optimum price to charge at any hour is the marginal running cost
of the oldest (least efficient) thermal plant that is in operation during that
hour.

 In this case, the benefits attributable to an investment in new capacity
  turn out to be the savings in system costs that the investment makes
  possible; and the present value of expected benefits is
                   j 1                                          j t
                         H (k , t ) C (k ) C ( j ) (1 r )
             t j 1k 1


 C(k) - the marginal running cost of a plant built in year k
 H(k,t) - the number of kilowatt-hours in the production of which a new
         plant would substitute for plants built in year k
  C(j) – running cost of plant j


                             Copyright©2007 CRI South-America                    20
When the plant is new, it is generating benefits all the time, but as it ages, and is
supplanted at the base of the system by more efficient plants, it generates benefits
                                only part of the time.

  Given this, the key investment criterion can be represented quite simply if we
                             assume that the function

                         j 1
           B( j, t )           H(k, t ) C(k) C( j)
                         k 1

 Declines exponentially through time at annual rate of y.

                                          2
      BJ 1 (1 y)       BJ 1 (1 y)                BJ 1 (1 y)3
                                                             .....,
         1 r            (1 r) 2                    (1 r ) 3




                               Copyright©2007 CRI South-America                    21
Marginal Cost Pricing
              of Electricity

• Efficient pricing of electricity.
  The basic assumption that we make is that the
  demand for electricity is increasing over time, 5-
  10% each year. Therefore with existing capacity
  economic rents will increase over time.




                   Copyright©2007 CRI South-America    22
Growth of Economic Rent Over Time
 Price of
electricity                                                 •     If choice is to either stay at A
                                                                  capacity forever, or to stay at
                                                                  B forever, then we add up
                                                                  the consumer surpluses
                                                                  between A and B to see if B
                                            Dt2                   plant is worthwhile to install.

                                        Dt1
                                    Dt0
              0          A    B
 Price of                                               Q
electricity
                                                            •      If we expand capacity from A
                                                                   to B to C in subsequent time
                                                                   period.

                                            Dt2
                                                                        Benefits of A
                                                                        Benefits of B
                                        Dt1
                                    Dt0                                 Benefits of C
              0         A                             Q
                               Copyright©2007 CRI South-America
                             B C                                                             23
Load Curve for Hours of Day
• We start with the assumption that all we have are
  homogeneous thermal plants.

   Capacity in
      K.W.



          K0




                                                         Qt1
                                                         Qt0
                 0
                                                 Hours of day

• If demand increases to Qt1 we either ration the available electricity or we
  build more capacity.      Copyright©2007 CRI South-America                  24
Load Curve for Hours of Day
• by varying the price of electricity through time we can spread out demand
  so that it does not exceed capacity.
                                                                     Surcharge
   Capacity in                                                         cents
      K.W.



          K0
                                                                           4
                            Si = Surcharge
                                                                           3
                                                                           2
                                                              Qt0          1
                 0                                                         0
                                                      Hours of day

• It is possible to keep quantity demanded constant by varying the price
  with the use of a surcharge.
• Let Ki be the length of time each surcharge is operative. Si is the difference
  between MC and the price charged, then:
                                             m
                      Total economic rent        Si K i
                                             i                                   25
• It is the economic rent accruing to the existing capacity.
Example
•   A kilowatt is the measure of capacity.
•   1 K.W. of capacity can produce 8760 Kilowatt hour (KWH) per year.
•   Assume it costs $400 /kw of capital cost, and the social opportunity cost of
    capital plus depreciation = 12%. Therefore we need $48 of rent per year
    before we install another additional k.w. of capacity.
•   As demand increases through time we require a higher surcharge in order to
    contain capacity. Price used to ration capacity.
•   This will generate more economic rent, and if this rent is big enough it would
    warrant an expansion of capacity.
•   The objective of pricing in this way is to have it reflect social opportunity cost
    or supply price.
•   In practical cases the price does not vary continuously with time but we have
    surcharges that go on and off at certain time periods.


                                Copyright©2007 CRI South-America                    26
Example (Cont’d)
• The “Load Factor” = KWH generated/8760 kwh
• Capital costs of per KW of capacity = 400/KW
• 10% interest + 2% depr = $48/yr
• Marginal running costs = 3 cents per KWH
• Peak hours are 2400 out of the year
• Off peak optimal charge is 3 cents per KWH
• On peak optimal charge is 5 cents per KWH
• Implicit rent of any new capacity = 2400 x 2 cents = $48/year




                        Copyright©2007 CRI South-America          27
Choice of different types of Electricity Generation
  Technologies to make Electricity Generation
                      System

  • Thermal Generation:
     –   Nuclear
     –   Large fossil fuel plants
     –   Combined cycle plants
     –   Gas turbines
  • Hydro Power
     – Run of the Stream
     – Daily Reservoir
     – Pump Storage

                       Copyright©2007 CRI South-America   28
Thermal vs. Hydro Generation

• The thermal capacity is relatively homogeneous if
  capacity costs are higher generally fuel costs are
  lower. e.g. Coal plant versus combined cycle plant.

• With hydro storage or use of the stream every
  particular site is different.

• Costs may range over a 5 fold difference.


                     Copyright©2007 CRI South-America   29
Run of the Stream
• No choice of when the water will come.
• Water comes at a zero marginal cost, therefore should use it
  when it comes.
• Suppose river runs for 8760 hrs. at full generation capacity.
• We will assume that the highest potential output during the
  year of the run of the stream is always less than total demand.
  Some thermal is being used.
• Peak hours = 2400
• Off peak hours = 6360
• Savings as compared to thermal plant (from previous example)
• 2400 x 5¢           120.00 Peak rationed price = 5 ¢
• 6360 x 3¢           190.80 off peak MRC of thermal = 3 ¢
                      310.80 per year
Question: Is US$ 310.80 per year enough to pay for run of stream
  capital plus running costs?
                        Copyright©2007 CRI South-America      30
Daily Reservoir
• Constructed to meet the peak day hours.
• To store water during the off peak for use during the peak
  hours.
• We don't generate any more electricity but we use the same
  amount of water and use it to produce peak priced electricity
  i.e. (5¢) instead of off peak (3¢) electricity.
• Instead of          2400 x 5 ¢                 = $120.00
                      6360 x 3 ¢                 = $190.80
                                                 = $310.80
• We get 8760 x 5 ¢ = $438.00.                   Net benefits = $127.20
• The costs are that of building the reservoir and the additional
  hydro generating capacity so as to generate more electricity in
  the peak hours.
                        Copyright©2007 CRI South-America                  31
Daily Reservoir (Cont’d)
• If previous run of stream generated 100 KW for 24 hours, now
  we will generate 300 KW for 8 hours.
• The gain from this switch in water is what we compare with
  the extra cost.
• If we now produce off peak electricity with thermal instead of
  run-of-the stream then this opportunity cost is calculated
  when calculating the opportunity costs of the daily reservoir.
• The additional marginal running costs of the thermal plants
  needed to meet the off peak demand are deducted from the
  benefits of switching off-peak run-of-stream water to peak
  time water.
                        Copyright©2007 CRI South-America      32
Pump Storage
•   We use off peak electricity to pump water up to a high area so that it can be
    released to produce electricity during peak demand periods.
Example:
•   It takes 1.4 KWH off peak to produce 1KWH on peak
•   Off peak value = 3 ¢ KWH                 Peak = 5 ¢ KWH
•   There is a profit here of [(5¢ - 3¢*1.4) = (5¢ - 4.2 ¢)] = 0.8 ¢/KWH of peak hour
    generated
•   Pump storage is becoming feasible because of the existence of nuclear and very
    large fossil fuel plants.
•   These plants are very costly to shut off and on.
•   Therefore, their surplus in off peak hours is very cheap electricity.
•   With large storage at top and bottom of till, a very small stream is all that is
    needed to produce a very large power station and use nuclear power to pump
    water back up on off peak hours.

                               Copyright©2007 CRI South-America                   33
Multipurpose Dams
• Multipurpose dams are used for irrigation, power and flood control.
• However, with multipurpose dams it is possible to have conflicting
  objectives.
• For example, it may be the case that irrigation water is needed in
  summer, but electrical power is at its lowest demand in summer.
• We may have to adjust prices of electricity to shift some of the demand to
  times when irrigation water is required.
• The different objectives have to be weighted.
• A useful solution is to provide the water during the peak time hours for
  electricity and then build a small regulatory dam to provide water for
  irrigation.
• The conflicting objectives may cause us to not have any optimal strategy
  over the year, but we still may be able to maximize during the day.
• In this case we still will have to have a larger thermal capacity than in the
  case of no irrigation objective.
                             Copyright©2007 CRI South-America                34
How do we price for the peak if the
             alternative is thermal generation?
  Capacity
             Hydro                        • Assume quantity of water
                                            available is fixed.
Thermal 2     Hydro                       • With an increase in peak demand
                                            we have to increase the thermal
Thermal 1                                   capacity and it is based on this
                                            cost that we have to calculate the
                                            peak time surcharge.
               2400     4000   8760 hrs

  Suppose system peak = 2,400 hours                     Thermal peak = 4,000 hours
• It is over the 4,000 hours that we spread the capital costs of new thermal plants.
  If $48/kw needed per year to cover the capital costs then we only require a
  surcharge of 1.2 ¢/Kwh (4800¢/4000hrs. = 1.2¢/Kwh)
• To find the price that should be charged for electricity during the peak hours, we
  add the capacity charge of 1.2 ¢ to the costs marginal running cost of the least
  efficient thermal plant operating during these hours.
• As long as we peak with hydro storage then the benefit of increasing hydro is the
                                Copyright©2007 CRI South-America                   35
  thermal peak cost.

Contenu connexe

En vedette

서비스디자인4
서비스디자인4서비스디자인4
서비스디자인4
Ye Eun Park
 
The chicago blackhawks
The chicago blackhawksThe chicago blackhawks
The chicago blackhawks
VT10692
 

En vedette (12)

Blackhawks 365 Case Study (CMT-011)
Blackhawks 365 Case Study (CMT-011)Blackhawks 365 Case Study (CMT-011)
Blackhawks 365 Case Study (CMT-011)
 
Starbucks
StarbucksStarbucks
Starbucks
 
Willingness To Pay
Willingness To PayWillingness To Pay
Willingness To Pay
 
Blackhawks Marketing Case Study
Blackhawks Marketing Case Study Blackhawks Marketing Case Study
Blackhawks Marketing Case Study
 
서비스디자인4
서비스디자인4서비스디자인4
서비스디자인4
 
Ice hockey
Ice hockeyIce hockey
Ice hockey
 
The chicago blackhawks
The chicago blackhawksThe chicago blackhawks
The chicago blackhawks
 
Starbucks Coffee: Case Study
Starbucks Coffee: Case StudyStarbucks Coffee: Case Study
Starbucks Coffee: Case Study
 
Starbucks International Case Study
Starbucks International Case StudyStarbucks International Case Study
Starbucks International Case Study
 
Starbucks Product Line Extension
Starbucks Product Line ExtensionStarbucks Product Line Extension
Starbucks Product Line Extension
 
Starbucks
StarbucksStarbucks
Starbucks
 
What is Starbucks missing from its marketing strategy?
What is Starbucks missing from its marketing strategy?What is Starbucks missing from its marketing strategy?
What is Starbucks missing from its marketing strategy?
 

Similaire à Cost benefit analysis for electricity investments

MET 401 Chapter 10 -_economics_of_power_generation_-_a._rezk
MET 401 Chapter 10 -_economics_of_power_generation_-_a._rezkMET 401 Chapter 10 -_economics_of_power_generation_-_a._rezk
MET 401 Chapter 10 -_economics_of_power_generation_-_a._rezk
Ibrahim AboKhalil
 
2012 Reenergize the Americas 1A: Richard Gruber
2012 Reenergize the Americas 1A: Richard Gruber2012 Reenergize the Americas 1A: Richard Gruber
2012 Reenergize the Americas 1A: Richard Gruber
Reenergize
 
Highlights from the Evaluation of California\'s Statewide Base Interruptible ...
Highlights from the Evaluation of California\'s Statewide Base Interruptible ...Highlights from the Evaluation of California\'s Statewide Base Interruptible ...
Highlights from the Evaluation of California\'s Statewide Base Interruptible ...
joshschel
 
First Solar Inc., July 2009
First Solar Inc., July 2009First Solar Inc., July 2009
First Solar Inc., July 2009
raja_lkc
 
FCOG Final Deliverable amen
FCOG Final Deliverable amenFCOG Final Deliverable amen
FCOG Final Deliverable amen
Jacob Tolman
 
Solar Storage Analyses by Team NU for Argonne Energy Storage Conference
Solar Storage Analyses by Team NU for Argonne Energy Storage ConferenceSolar Storage Analyses by Team NU for Argonne Energy Storage Conference
Solar Storage Analyses by Team NU for Argonne Energy Storage Conference
Mark Johnson
 
Pv sales intro and session one
Pv sales intro and session one Pv sales intro and session one
Pv sales intro and session one
moeshahram
 
March9 2009-workshop-slides
March9 2009-workshop-slidesMarch9 2009-workshop-slides
March9 2009-workshop-slides
SWITCHOntario
 
EDFCC_Final Presentation.pptx
EDFCC_Final Presentation.pptxEDFCC_Final Presentation.pptx
EDFCC_Final Presentation.pptx
Milad Korde
 
xcel energy BofA_09/16/03
xcel energy  BofA_09/16/03xcel energy  BofA_09/16/03
xcel energy BofA_09/16/03
finance26
 

Similaire à Cost benefit analysis for electricity investments (20)

IRJET- Implementing Zero Energy Efficiency in Residential Building
IRJET-  	  Implementing Zero Energy Efficiency in Residential BuildingIRJET-  	  Implementing Zero Energy Efficiency in Residential Building
IRJET- Implementing Zero Energy Efficiency in Residential Building
 
MET 401 Chapter 10 -_economics_of_power_generation_-_a._rezk
MET 401 Chapter 10 -_economics_of_power_generation_-_a._rezkMET 401 Chapter 10 -_economics_of_power_generation_-_a._rezk
MET 401 Chapter 10 -_economics_of_power_generation_-_a._rezk
 
XEL_090506
XEL_090506XEL_090506
XEL_090506
 
XEL_090506
XEL_090506XEL_090506
XEL_090506
 
XEL_090506
XEL_090506XEL_090506
XEL_090506
 
2012 Reenergize the Americas 1A: Richard Gruber
2012 Reenergize the Americas 1A: Richard Gruber2012 Reenergize the Americas 1A: Richard Gruber
2012 Reenergize the Americas 1A: Richard Gruber
 
Wind Vs Conventional Electricity Economics
Wind Vs Conventional Electricity EconomicsWind Vs Conventional Electricity Economics
Wind Vs Conventional Electricity Economics
 
Highlights from the Evaluation of California\'s Statewide Base Interruptible ...
Highlights from the Evaluation of California\'s Statewide Base Interruptible ...Highlights from the Evaluation of California\'s Statewide Base Interruptible ...
Highlights from the Evaluation of California\'s Statewide Base Interruptible ...
 
Highlights from the Evaluation of California\'s Base Interruptible Program
Highlights from the Evaluation of California\'s Base Interruptible ProgramHighlights from the Evaluation of California\'s Base Interruptible Program
Highlights from the Evaluation of California\'s Base Interruptible Program
 
First Solar Inc., July 2009
First Solar Inc., July 2009First Solar Inc., July 2009
First Solar Inc., July 2009
 
FCOG Final Deliverable amen
FCOG Final Deliverable amenFCOG Final Deliverable amen
FCOG Final Deliverable amen
 
Solar Storage Analyses by Team NU for Argonne Energy Storage Conference
Solar Storage Analyses by Team NU for Argonne Energy Storage ConferenceSolar Storage Analyses by Team NU for Argonne Energy Storage Conference
Solar Storage Analyses by Team NU for Argonne Energy Storage Conference
 
Energy Use and Pricing for Carlsbad Seawater Desalination
Energy Use and Pricing for Carlsbad Seawater DesalinationEnergy Use and Pricing for Carlsbad Seawater Desalination
Energy Use and Pricing for Carlsbad Seawater Desalination
 
Pv sales intro and session one
Pv sales intro and session one Pv sales intro and session one
Pv sales intro and session one
 
March9 2009-workshop-slides
March9 2009-workshop-slidesMarch9 2009-workshop-slides
March9 2009-workshop-slides
 
EDFCC_Final Presentation.pptx
EDFCC_Final Presentation.pptxEDFCC_Final Presentation.pptx
EDFCC_Final Presentation.pptx
 
Session 6 - Presentation by Georgian Industrial Group
Session 6 - Presentation by Georgian Industrial GroupSession 6 - Presentation by Georgian Industrial Group
Session 6 - Presentation by Georgian Industrial Group
 
A NOVEL SYSTEM OPTIMIZATION OF A GRID INDEPENDENT HYBRID RENEWABLE ENERGY SYS...
A NOVEL SYSTEM OPTIMIZATION OF A GRID INDEPENDENT HYBRID RENEWABLE ENERGY SYS...A NOVEL SYSTEM OPTIMIZATION OF A GRID INDEPENDENT HYBRID RENEWABLE ENERGY SYS...
A NOVEL SYSTEM OPTIMIZATION OF A GRID INDEPENDENT HYBRID RENEWABLE ENERGY SYS...
 
Renewable Energy in Nordic Countries - Alf Bjorseth - SCATEC - April 2010
Renewable Energy in Nordic Countries - Alf Bjorseth - SCATEC - April 2010Renewable Energy in Nordic Countries - Alf Bjorseth - SCATEC - April 2010
Renewable Energy in Nordic Countries - Alf Bjorseth - SCATEC - April 2010
 
xcel energy BofA_09/16/03
xcel energy  BofA_09/16/03xcel energy  BofA_09/16/03
xcel energy BofA_09/16/03
 

Dernier

Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
amitlee9823
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
lizamodels9
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
dlhescort
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
Renandantas16
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
Matteo Carbone
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
amitlee9823
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
daisycvs
 

Dernier (20)

Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 

Cost benefit analysis for electricity investments

  • 1. COSTS AND BENEFITS OF ELECTRICITY INVESTMENTS Copyright©2007 CRI South-America 1
  • 2. Economic Valuation of Additional Electricity Supply • Willingness to pay for new connections • Willingness to pay for more reliable service • Resource cost savings from replacement of more expensive generation plants • Marginal cost pricing Copyright©2007 CRI South-America 2
  • 3. ECONOMIC VALUE OF ELECTRICITY FOR NEW CONNECTIONS OR FOR REDUCTION OF WITH ROTATING POWER SHORTAGES $ S0 PMAX=P’ D Shaded area = economic value of shortage power B (Q’-Q0) = Power shortage, evenly rotated C to all customers P0 m F D0 0 Q0 Q’ Quantity Assuming willingness to pay (WTP) of all customers are also evenly distributed from highest 0P’ to lowest P0m: Economic Value of Additional Power Supply = ((PMAX+ P0m)/2) * (Q’-Q0) Copyright©2007 CRI South-America 3
  • 4. ECONOMIC VALUE OF ELECTRICITY COMPUTATION FORMULA D P’ S0 B Pt C F D0 0 Q0 Q’ Quantity P’ = Maximum willingness to pay per unit of shortage power = 2 (capital costs of own generation/KWh) + Fuel Costs/KWh Need one generation to produce electricity and the second generation to provide reliability Copyright©2007 CRI South-America 4
  • 5. WILLINGNESS TO PAY (WTP) FOR SHORTAGE POWER IN INDIA Customer Class Highest WTP* 1996 Rs/kwh COMMERCIAL 4.00 (Diesel autogeneration) INDUSTRIAL 3.22 (Diesel autogeneration) FARMER 3.77 (Diesel pump replacement) RESIDENTIAL 10.00 (Kerosene replacement) • Based on the financial costs of autogeneration or fuel replacement, World Bank Report, 14298-IN, 1996, for Orissa state of India. Actual WTP should be higher because of the inconveniences of operating diesel generators, diesel pumps, kerosene lamps and burners.Copyright©2007 CRI South-America 5
  • 6. OWN-GENERATION COST AND WILLINGNESS TO PAY IN MEXICO Total Own-generation Cost ($/kWh) 0.169 Average Power Price (Gross of Tax, $/kWh) 0.037 Maximum Willingness To Pay ($/kWh) 0.212 Average Willingness To Pay ($/kWh) 0.125 Copyright©2007 CRI South-America 6
  • 7. Estimated Cost of Power Failure 1. Based on willingness to pay • Based on customers survey 2. Based on actual costs to users 3. Based on linear relationship between GDP and electricity consumption of industrial/commercial users Copyright©2007 CRI South-America 7
  • 8. Estimated Cost of Power Failure* 1. Based on Willingness to Pay • Based on customers survey (Contingent valuation) Ontario Hydro Estimates of Outage Costs (1981 US$/kwh) Duration Large Small Commercial Residential Manufacturers Manufacturers 1 min 58.76 83.25 1.96 0.17 20 min 8.81 13.56 1.66 0.15 1 hr 4.35 7.16 1.68 0.05 2 hr 3.75 7.35 2.52 0.03 4 hr 1.87 8.13 2.10 0.03 8 hr 1.80 6.42 1.89 0.02 16 hr 1.45 4.96 1.75 0.02 Average** 2.15 6.38 1.98 0.12 All groups average***: 1.96 Average power price: 0.025 Average willingness for power during outage = 78.4 times average power price. English Estimate (1996): 4 $/kwh * C.W. Gellings and J.H. Chamberlin, Demand-Side Management: Concepts and Methods, Liburn, Georgia, The Fairmont Press, Inc., 1988. ** Based on system simulation model Copyright©2007 CRI South-America 8 *** Based on shares: 13.5/13.5/39/34 %.
  • 9. Estimated Cost of Power Failure (continued) 2. Based on actual costs to users (Loss in contribution to profits) COST OF POWER FAILURE IN NEPAL* (Multiples of electric tariff) Year 1 2 3 4 5 Firm 1 5.56 2.73 5.01 1.50 3.43 Firm 2 3.31 2.86 1.71 3.24 3.76 Firm 3 15.25 11.77 14.37 12.16 5.26 Average each year 8.04 5.79 7.03 5.63 4.15 Average all years 6.13 * Source: Table 7-10, Roop Jyoti, Investment Appraisal of Management Strategies for Addressing Uncertainties in Power Supply in the Context of Nepalese Manufacturing Enterprises, PhD Thesis, The Kennedy School of Government, Harvard University,December, 1998. Copyright©2007 CRI South-America 9
  • 10. Estimated Cost of Power Failure (continued) San Diego (sudden outage of a few hours)* (1981 US $/kwh) Industrial Commercial Direct User 2.79 2.40 Employees of Direct User 0.21 0.09 Indirect User 0.12 0.13 Total 3.12 2.62 Multiples of Av Tariff** 62.4 52.4 Key West, Florida (rotating blackout for 26 days)* % of Cost Multiples Time of Price Nonresidential Users 4.8 $2.30/kwh 46.0 * Electric Power Research Institute study EPRI EA-1215, 1981, Vol. 2. ** Average price in 1981 is 0.05 $/kwh. Copyright©2007 CRI South-America 10
  • 11. Estimated Cost of Power Failure (continued) 3. Based on linear relationship between GDP and electricity consumption of industrial/commercial users* Outage cost = 1.35 (1981$/kwh) Or: = 27 (multiples of the average power price) * M. L. Telson, “The Economics of Alternative Levels of Reliability for Electric Power Generation Systems,” Bell Journal of Economics, Autumn, 1975. Copyright©2007 CRI South-America 11
  • 12. Summary: Average power outage cost ranges from 6 to 80 times of the average power price. Copyright©2007 CRI South-America 12
  • 13. Investment in New Generation to obtain Cost Savings Copyright©2007 CRI South-America 13
  • 14. Load Curve hours for Year Load Duration Curve hours for Year Capacity Capacity MW MW 8760 hrs 8760 hrs Peak hours Off-Peak hours Copyright©2007 CRI South-America 14
  • 15. Calculation of Marginal Cost of Electricity Supply • During the off-peak hours when the capacity is not fully utilized, the marginal cost in any given hour is the marginal running cost (fuel and operating cost per Kwh) of the most expensive plant operating during that hour. • During the peak hours, when generation capacity is fully utilized, the marginal cost of electricity per Kwh is equal to the marginal running cost of the most expensive plant running at the time plus the capital costs of adding more generation capacity, expressed as a cost per Kwh of peak energy supplied. Copyright©2007 CRI South-America 15
  • 16. Optimal Stacking of Thermal Capacity Plant Capital Fuel KwH 1 MC4=0.08+ 400(0.15)/1000=0.14/KWH Cost Cost 2 MC3=0.05/KWH 4 1000 0.03 $ MC2=0.04/KWH 3 700 0.04 $ 3 4 MC1=0.03/KWH 2 600 0.05 $ H2 H3 H4 1000 1500 4500 1 400 0.08 $ H4 solve for the minimum number of hours to run a plant 4 or the maximum number to run plant 3. v = r+ d =0.15 v(K4)+f4(H4)=v(K3)+f3(H4) 0.15(1000)+0.03(H4)=0.15(700)+0.04(H4) (150-105)=0.4(H4)-0.03(H4) 45=0.01H4 H4=4500 Copyright©2007 CRI South-America 16
  • 17. Contribution to Annualized Cost of Generation Generation Investments Investments Hours Price MC Amount $/yr. Capital Annual Plant 1: 1000 * (0.14 – 0.08) = 60 Cost v Cost Plant 2: 1000 * (0.14 – 0.05) = 90 Plant 1: 400 * 0.15 = 60 Plant 3: 1000 * (0.14 – 0.04) = 100 Plant 4: 1000 * (0.14 – 0.03) = 110 Plant 2: 600 * 0.15 = 90 Plant 3: 500 * (0.05 – 0.04) = 5 Plant 3: 700 * 0.15 = 105 Plant 4: 500 * (0.05 – 0.03) = 10 Plant 4: 1000 * 0.15 = 150 Plant 4: 3000 * (0.04 – 0.03) = 30 Total contribution per year = $405 Total capital cost of system $405 per year. Plant 1 60 60 Plant 2 90 90 105 Plant 3 100 5 Plant 4 110 10 30 150 Copyright©2007 CRI South-America 17 1000 1500 4500 Total: $ 405
  • 18. Stacking Problem: when do we replace a thermal plant? KW Output of plant #5 that Plant No. Marginal Running substitutes for plant #1 = Q1 Cost per Kwh Hydro Output of plant #5 that 1 0.08 storage substitutes for plant #2 = Q2 1 (2) H1 Output of plant #5 that 2 0.05 2 (3) H2 substitutes for plant #3 = Q3 3 0.04 Output of plant #5 that 3 (4) H3 substitutes for plant #4 = Q4 4 0.03 4 (5) H4 5 0.02 Load curve for plants 2,3,4 after 5 is introduced The question is whether or not we should build plant #5. We use the most efficient plant first and then use the next most efficient and so on until the least efficient we need to meet demand. • Assume plant #5 has equal capacity to each of the other plants we would then have to shift all of the plants up one stage in production, thus there is no need to use plant number one now. Benefits to Plant #5: It is going to be producing most of the time. Part of the time 5 is effectively substituting for 4, part for 3, part South-America part for 1. Copyright©2007 CRI for 2, and 18
  • 19. Two approaches to calculating benefits A. The new plant is used to substitute for part of the other plants that now do not produce as much as previously: Benefits Q4 x (0.03 – 0.02) Q3 x (0.04 – 0.02) Q2 x (0.05 – 0.02) Q1 x (0.08 – 0.02) Total A B. Alternative approach • Let H1, H2, H3, H4, be amount of electricity previously produced by plants 1 to 4. Original Total Cost New Total Cost H4 x 0.03 H4 x 0.02 H3 x 0.04 H3 x 0.03 H2 x 0.05 H2 x 0.04 H1 x 0.08 H1 x 0.05 Total B Total C Total A = Total B -Total C. • We now compare total A with the annual capital cost of plant 5. Copyright©2007 CRI South-America 19
  • 20. The Situation where variations in the efficiency of thermal plants are taken into account The optimum price to charge at any hour is the marginal running cost of the oldest (least efficient) thermal plant that is in operation during that hour. In this case, the benefits attributable to an investment in new capacity turn out to be the savings in system costs that the investment makes possible; and the present value of expected benefits is j 1 j t H (k , t ) C (k ) C ( j ) (1 r ) t j 1k 1 C(k) - the marginal running cost of a plant built in year k H(k,t) - the number of kilowatt-hours in the production of which a new plant would substitute for plants built in year k C(j) – running cost of plant j Copyright©2007 CRI South-America 20
  • 21. When the plant is new, it is generating benefits all the time, but as it ages, and is supplanted at the base of the system by more efficient plants, it generates benefits only part of the time. Given this, the key investment criterion can be represented quite simply if we assume that the function j 1 B( j, t ) H(k, t ) C(k) C( j) k 1 Declines exponentially through time at annual rate of y. 2 BJ 1 (1 y) BJ 1 (1 y) BJ 1 (1 y)3 ....., 1 r (1 r) 2 (1 r ) 3 Copyright©2007 CRI South-America 21
  • 22. Marginal Cost Pricing of Electricity • Efficient pricing of electricity. The basic assumption that we make is that the demand for electricity is increasing over time, 5- 10% each year. Therefore with existing capacity economic rents will increase over time. Copyright©2007 CRI South-America 22
  • 23. Growth of Economic Rent Over Time Price of electricity • If choice is to either stay at A capacity forever, or to stay at B forever, then we add up the consumer surpluses between A and B to see if B Dt2 plant is worthwhile to install. Dt1 Dt0 0 A B Price of Q electricity • If we expand capacity from A to B to C in subsequent time period. Dt2 Benefits of A Benefits of B Dt1 Dt0 Benefits of C 0 A Q Copyright©2007 CRI South-America B C 23
  • 24. Load Curve for Hours of Day • We start with the assumption that all we have are homogeneous thermal plants. Capacity in K.W. K0 Qt1 Qt0 0 Hours of day • If demand increases to Qt1 we either ration the available electricity or we build more capacity. Copyright©2007 CRI South-America 24
  • 25. Load Curve for Hours of Day • by varying the price of electricity through time we can spread out demand so that it does not exceed capacity. Surcharge Capacity in cents K.W. K0 4 Si = Surcharge 3 2 Qt0 1 0 0 Hours of day • It is possible to keep quantity demanded constant by varying the price with the use of a surcharge. • Let Ki be the length of time each surcharge is operative. Si is the difference between MC and the price charged, then: m Total economic rent Si K i i 25 • It is the economic rent accruing to the existing capacity.
  • 26. Example • A kilowatt is the measure of capacity. • 1 K.W. of capacity can produce 8760 Kilowatt hour (KWH) per year. • Assume it costs $400 /kw of capital cost, and the social opportunity cost of capital plus depreciation = 12%. Therefore we need $48 of rent per year before we install another additional k.w. of capacity. • As demand increases through time we require a higher surcharge in order to contain capacity. Price used to ration capacity. • This will generate more economic rent, and if this rent is big enough it would warrant an expansion of capacity. • The objective of pricing in this way is to have it reflect social opportunity cost or supply price. • In practical cases the price does not vary continuously with time but we have surcharges that go on and off at certain time periods. Copyright©2007 CRI South-America 26
  • 27. Example (Cont’d) • The “Load Factor” = KWH generated/8760 kwh • Capital costs of per KW of capacity = 400/KW • 10% interest + 2% depr = $48/yr • Marginal running costs = 3 cents per KWH • Peak hours are 2400 out of the year • Off peak optimal charge is 3 cents per KWH • On peak optimal charge is 5 cents per KWH • Implicit rent of any new capacity = 2400 x 2 cents = $48/year Copyright©2007 CRI South-America 27
  • 28. Choice of different types of Electricity Generation Technologies to make Electricity Generation System • Thermal Generation: – Nuclear – Large fossil fuel plants – Combined cycle plants – Gas turbines • Hydro Power – Run of the Stream – Daily Reservoir – Pump Storage Copyright©2007 CRI South-America 28
  • 29. Thermal vs. Hydro Generation • The thermal capacity is relatively homogeneous if capacity costs are higher generally fuel costs are lower. e.g. Coal plant versus combined cycle plant. • With hydro storage or use of the stream every particular site is different. • Costs may range over a 5 fold difference. Copyright©2007 CRI South-America 29
  • 30. Run of the Stream • No choice of when the water will come. • Water comes at a zero marginal cost, therefore should use it when it comes. • Suppose river runs for 8760 hrs. at full generation capacity. • We will assume that the highest potential output during the year of the run of the stream is always less than total demand. Some thermal is being used. • Peak hours = 2400 • Off peak hours = 6360 • Savings as compared to thermal plant (from previous example) • 2400 x 5¢ 120.00 Peak rationed price = 5 ¢ • 6360 x 3¢ 190.80 off peak MRC of thermal = 3 ¢ 310.80 per year Question: Is US$ 310.80 per year enough to pay for run of stream capital plus running costs? Copyright©2007 CRI South-America 30
  • 31. Daily Reservoir • Constructed to meet the peak day hours. • To store water during the off peak for use during the peak hours. • We don't generate any more electricity but we use the same amount of water and use it to produce peak priced electricity i.e. (5¢) instead of off peak (3¢) electricity. • Instead of 2400 x 5 ¢ = $120.00 6360 x 3 ¢ = $190.80 = $310.80 • We get 8760 x 5 ¢ = $438.00. Net benefits = $127.20 • The costs are that of building the reservoir and the additional hydro generating capacity so as to generate more electricity in the peak hours. Copyright©2007 CRI South-America 31
  • 32. Daily Reservoir (Cont’d) • If previous run of stream generated 100 KW for 24 hours, now we will generate 300 KW for 8 hours. • The gain from this switch in water is what we compare with the extra cost. • If we now produce off peak electricity with thermal instead of run-of-the stream then this opportunity cost is calculated when calculating the opportunity costs of the daily reservoir. • The additional marginal running costs of the thermal plants needed to meet the off peak demand are deducted from the benefits of switching off-peak run-of-stream water to peak time water. Copyright©2007 CRI South-America 32
  • 33. Pump Storage • We use off peak electricity to pump water up to a high area so that it can be released to produce electricity during peak demand periods. Example: • It takes 1.4 KWH off peak to produce 1KWH on peak • Off peak value = 3 ¢ KWH Peak = 5 ¢ KWH • There is a profit here of [(5¢ - 3¢*1.4) = (5¢ - 4.2 ¢)] = 0.8 ¢/KWH of peak hour generated • Pump storage is becoming feasible because of the existence of nuclear and very large fossil fuel plants. • These plants are very costly to shut off and on. • Therefore, their surplus in off peak hours is very cheap electricity. • With large storage at top and bottom of till, a very small stream is all that is needed to produce a very large power station and use nuclear power to pump water back up on off peak hours. Copyright©2007 CRI South-America 33
  • 34. Multipurpose Dams • Multipurpose dams are used for irrigation, power and flood control. • However, with multipurpose dams it is possible to have conflicting objectives. • For example, it may be the case that irrigation water is needed in summer, but electrical power is at its lowest demand in summer. • We may have to adjust prices of electricity to shift some of the demand to times when irrigation water is required. • The different objectives have to be weighted. • A useful solution is to provide the water during the peak time hours for electricity and then build a small regulatory dam to provide water for irrigation. • The conflicting objectives may cause us to not have any optimal strategy over the year, but we still may be able to maximize during the day. • In this case we still will have to have a larger thermal capacity than in the case of no irrigation objective. Copyright©2007 CRI South-America 34
  • 35. How do we price for the peak if the alternative is thermal generation? Capacity Hydro • Assume quantity of water available is fixed. Thermal 2 Hydro • With an increase in peak demand we have to increase the thermal Thermal 1 capacity and it is based on this cost that we have to calculate the peak time surcharge. 2400 4000 8760 hrs Suppose system peak = 2,400 hours Thermal peak = 4,000 hours • It is over the 4,000 hours that we spread the capital costs of new thermal plants. If $48/kw needed per year to cover the capital costs then we only require a surcharge of 1.2 ¢/Kwh (4800¢/4000hrs. = 1.2¢/Kwh) • To find the price that should be charged for electricity during the peak hours, we add the capacity charge of 1.2 ¢ to the costs marginal running cost of the least efficient thermal plant operating during these hours. • As long as we peak with hydro storage then the benefit of increasing hydro is the Copyright©2007 CRI South-America 35 thermal peak cost.