SlideShare une entreprise Scribd logo
1  sur  14
WATER-STEAM CIRCUIT
          in
SUPER CRITICAL BOILER


              Prepared By: Hareesh VS
              Jr.Manager
              IOTEP BARH
BOILER PARAMETERS
                            Once Through, Single Reheat, Coal Fired, Balanced draft,
Main Boiler Type
                            Side Fired, Tower type & Symmetrical to Both Axis
                            Furnace    :- 14.9 X 23.04 M
Boiler Area                 Second Pass :- 6.07 X 23.04 M X 2( Both side of Furnace)
                            Roof       :- 44.35 X 23.04 M
                            Guarantee Bituminous Coal
Design Fuel                 LCV :- 3026 kcal/kg
                            HCV :- 3300 kcal/kg
Material of Construction    12X1MФ and 15X1MФ

Main Steam Flow             2225 T/Hr
Main Steam Pressure         256 Kg/cm2
Main Steam Temp             540 OC
RH Steam Flow               1746 T/Hr
RH Steam Pressure           46.13 Kg/cm2
RH Steam Temp               568 OC
Feed Water Temp             290 OC
Boiler Feed pump
                         Collecting Header
   Economizer
                         3320C, 299kg/cm2
 Suspension Tube

 Tubes to furnace
   ww first run

Furnace ww 1st Run       Steam to steam
                         heat exchanger Hot
Furnace ww 2st Run       suspension

 Attemperator 1st
                                Suspension Tubes
Furnace ww   3rd   run
                            Economizer Upper Block
Horizontal gas duct
       ww                     FRH & HP
                              Heaters
  Hanger tube 1               2900C, 304kg/cm2


     Roof ww
                          Line From              Economizer Lower Block             Line From BFP
  Hanger tube 2           Deaerator
                                                                              Tubes to furnace
  Convection ww                                                               ww first run
  Steam to steam                      Boiler Feed Pump
                                                                           Intermediate Header
  heat exchanger

    Separator

Platen super heater                              Inlet Header of Furnace
  Stage 1,2,3 & 4                                WW First run

Final Super heater          Reheat system

    HP Turbine              IP & LP Turbine                                Distribution Header of
                                                                           Furnace WW First run
Recirculation pump

   Economizer

 Suspension Tube

 Tubes to furnace
   ww first run

Furnace ww 1st Run

Furnace ww 2st Run

 Attemperator 1st

Furnace ww 3rd run

Horizontal gas duct
       ww

  Hanger tube 1       Furnace WW First Run                        Collecting Header Furnace
                                                                  WW first run
                      Furnace Front & Rear Water Wall
     Roof ww
                       Lower panels And Extreme End
  Hanger tube 2                                                 First Run WW Outlet
                      panels of Side water Wall Lower           Headers (Intermediate
  Convection ww                                                 Headers)
                                    part
  Steam to steam
  heat exchanger                   Tubes to Furnace Side Hot   Furnace Front & Rear Hot
                                   suspension Lower part       suspension Lower part
    Separator
                                                                Furnace Side Hot
Platen super heater             Furnace WW first run panels     suspension Lower Part
  Stage 1,2,3 & 4

Final Super heater    Reheat system                            Furnace Hot suspension
                                                               Lower Part collecting
    HP Turbine        IP & LP Turbine                          Header (3770C, 301kg/cm2)
Recirculation pump             Side View of Boiler
   Economizer

 Suspension Tube

 Tubes to furnace
   ww first run

Furnace ww 1st Run

Furnace ww 2st Run

 Attemperator 1st

Furnace ww 3rd run

Horizontal gas duct
       ww
                                                                   Collecting Header Furnace
  Hanger tube 1
                                                                   WW first run
     Roof ww

  Hanger tube 2                 Extreme Panels of Side WW
  Convection ww

  Steam to steam
  heat exchanger                                                  Furnace Side Hot
                                                                  suspension Lower part
    Separator
                                        Inlet Header of Furnace   Furnace Front & Rear Hot
Platen super heater                     Second Run                suspension Lower Part
  Stage 1,2,3 & 4

Final Super heater    Reheat system                               Furnace Hot suspension
                                                                  Lower Part collecting
    HP Turbine        IP & LP Turbine                             Header
Recirculation pump             Side View of Boiler
   Economizer

 Suspension Tube

 Tubes to furnace
   ww first run         Furnace WW Second Run
Furnace ww 1st Run      Furnace Side Water walls Lower Part
Furnace ww 2st Run

 Attemperator 1st                                              Collecting Headers of Middle
                                                               Part of Hot Suspension
Furnace ww 3rd run
                                                               Furnace Hot Suspension
Horizontal gas duct                                            Middle Part
       ww                      HP Spraying Attemperator-1

  Hanger tube 1                                                Tubes to Furnace Hot
                               Distribution Header to          suspension Middle part
     Roof ww                   Furnace 3rd Run

  Hanger tube 2
                                                              Mixing Headers of Furnace
                              Outlet Headers of Furnace
  Convection ww                                               Second run WW panels
                              Second run WW panels
  Steam to steam              (4010C, 296kg/cm2)
  heat exchanger

    Separator

Platen super heater     Furnace WW second run panels
  Stage 1,2,3 & 4

Final Super heater    Reheat system

    HP Turbine        IP & LP Turbine
Recirculation pump              Side View of Boiler
   Economizer

 Suspension Tube        Furnace WW Third Run
 Tubes to furnace         All Upper Panels of Furnace Front,
   ww first run
                                Rear & Side Water walls
Furnace ww 1st Run

Furnace ww 2st Run

 Attemperator 1st           Outlet Headers of Furnace WW
                            3rd run panels at Horizontal Gas
Furnace ww 3rd run          duct Bottom Area (Arch Area)       Tubes to Intermediate
                            (4330C,   291kg/cm2)               Headers of 3rd Run WW
Horizontal gas duct
       ww
                                Furnace WW 3rd run panels      Distribution Header to
  Hanger tube 1
                                                               Furnace 3rd Run
     Roof ww
                                                               Tubes to Inlet Headers of
                                Inlet Headers Furnace WW 3rd
  Hanger tube 2                                                 3rd Run WW
                                run panels
  Convection ww

  Steam to steam
  heat exchanger

    Separator

Platen super heater
  Stage 1,2,3 & 4

Final Super heater    Reheat system

    HP Turbine        IP & LP Turbine
Recirculation pump

   Economizer
                      Hanger Tube 1
 Suspension Tube      (4410C, 288kg/cm2)

 Tubes to furnace     Collecting Header of
   ww first run       Furnace 3rd Run

Furnace ww 1st Run    Horizontal Gas Duct WW

Furnace ww 2st Run    Inlet Headers of Horizontal
 Attemperator 1st     Gas Duct WW




                                                                `
Furnace ww 3rd run    Intermediate Headers of 3rd
                                                                          Outlet headers of
                      Run WW
                                                                          3rd run panels
Horizontal gas duct
                                                                          (4430C, 291kg/cm2)
       ww
                                  Furnace WW 3rd run panels          Inlet Header of Hanger
  Hanger tube 1
                                                                    Tube 1
     Roof ww
                                                                    Tubes to Inlet Headers of
                                 Inlet Headers Furnace WW 3rd
  Hanger tube 2                                                      3rd Run WW
                                 run panels
  Convection ww

  Steam to steam
  heat exchanger

    Separator

Platen super heater
  Stage 1,2,3 & 4

Final Super heater      Reheat system

    HP Turbine          IP & LP Turbine
Recirculation pump
                      Roof WW Inlet Header
   Economizer
                      Roof Water Wall
 Suspension Tube

 Tubes to furnace     Roof Water Wall Collecting
   ww first run       Header (4480C, 284kg/cm2)

Furnace ww 1st Run    Distribution Header of
                      Hanger Tube 2
Furnace ww 2st Run

 Attemperator 1st     Hanger Tube 2




                                                   `
Furnace ww 3rd run

Horizontal gas duct
       ww
                                                       Inlet Header of
  Hanger tube 1                                        Hanger tube 2
     Roof ww

  Hanger tube 2

  Convection ww

  Steam to steam
  heat exchanger

    Separator

Platen super heater
  Stage 1,2,3 & 4

Final Super heater      Reheat system

    HP Turbine          IP & LP Turbine
Recirculation pump    Distribution Header Of
                      Upper Hot suspension
   Economizer         Convection Shaft &
                      Furnace Area
 Suspension Tube

 Tubes to furnace     Collecting Header Of
   ww first run       Hanger Tube-2
                      (4520C, 281kg/cm2)
Furnace ww 1st Run    Tubes to Furnace
                      Hot Suspension
Furnace ww 2st Run

 Attemperator 1st




                                                       `
                                                       `
                                                       `
                                               `
                                               `
                                               `
                      Hanger Tube-3




                                                   `
Furnace ww 3rd run                                                Convection Shaft
                      Convection Shaft                            Hot Suspension
Horizontal gas duct
       ww             Water Walls

  Hanger tube 1                                            Tubes to Convection Hot
                                                           Suspension
                      Distribution Header of
     Roof ww
                      Convection Shaft WW
                                                       Tubes to Hot Suspension
  Hanger tube 2
                                                       Collecting Header
  Convection ww

  Steam to steam
  heat exchanger

    Separator

Platen super heater
  Stage 1,2,3 & 4

Final Super heater       Reheat system

    HP Turbine           IP & LP Turbine
High Pressure Spray
Recirculation pump    Attemperator – 2
                      (4390C, 273kg/cm2)
   Economizer
                      Wet Steam
 Suspension Tube
                      Separator
 Tubes to furnace
   ww first run       High Pressure Tubes to
                      Collecting Header of SSHE
Furnace ww 1st Run    (4570C, 274kg/cm2)
Furnace ww 2st Run
                      Drain Header
 Attemperator 1st




                                                                      `
                                                                      `
                                                                      `
                                                              `
                                                              `
                                                              `


                                                                  `
Furnace ww 3rd run                                                           Moisture Content in
                                                                             Steam After Separation
                      Tubes to Steam To Steam Heat
Horizontal gas duct
                      Exchanger
       ww
                                                                          Collecting Header of
  Hanger tube 1                                                           Convection Shaft WWs &
                                            Steam To Steam Heat           Hanger Tube – 3
     Roof ww                                Exchanger                     (4650C, 278kg/cm2)
  Hanger tube 2

  Convection ww

  Steam to steam
  heat exchanger

    Separator

Platen super heater
  Stage 1,2,3 & 4

Final Super heater       Reheat system

    HP Turbine           IP & LP Turbine
Recirculation pump    Tubes to Platen Super
                      Heater
   Economizer         (4390C, 273kg/cm2)

 Suspension Tube      Spray Type
                      Attemperator -3
 Tubes to furnace     (5110C, 259kg/cm2)
   ww first run       Tubes to Final
                       Super Heater
Furnace ww 1st Run    (5000C, 258kg/cm2)

Furnace ww 2st Run
                      Convection Super Heater
 Attemperator 1st     (Final Super Heater)




                                                        `
                                                        `
                                                        `
                                                `
                                                `
                                                `


                                                    `
Furnace ww 3rd run                                                             Main Steam
                                                                               Out Let Header
Horizontal gas duct                                                            (5400C, 256kg/cm2)
       ww
                                                                       Platen Super Heaters
  Hanger tube 1                                                        Stage 1, 2, 3 & 4.

     Roof ww
                                                               Steam Flow in 4 Stages of
  Hanger tube 2                                                   Platen Super Heater

  Convection ww                                                         Rear

  Steam to steam                                                         I/L
  heat exchanger

    Separator




                                                        O/L




                                                                                         O/L
Platen super heater
  Stage 1,2,3 & 4




                                                        Left




                                                                                               Right
Final Super heater        Reheat system
                                                                         I/L
    HP Turbine           IP & LP Turbine
                                                                       Front
Recirculation pump

   Economizer                                      LP Spray




                                                                                                                                                                                                                            HRH Line
                                                   Atemperator
 Suspension Tube
                                                     LPR Stage – 2
 Tubes to furnace                                    (Final)                                                                                                                                                       Collecting Header
   ww first run                                                                                                                                                                                                    of LPR
                                                     Steam to Steam
                                                                                                                                                                                                                   (4840C, 47kg/cm2)
                                                     Heat Exchanger
Furnace ww 1st Run



                                                                      Main Steam Line to TG(5400C, 256kg/cm2)
                                                                                                                                                                                                                    CRH Line from
Furnace ww 2st Run                                                                                                                                                                                                  HP Turbine




                                                                                                                Hot Re Heat Line (5680C, 46kg/cm2)
 Attemperator 1st




                                                                                                                                                                                                      `
                                                                                                                                                                                                      `
                                                                                                                                                                                                      `
                                                                                                                                                                               `
                                                                                                                                                                               `
                                                                                                                                                                               `


                                                                                                                                                                                                  `
                      Cooled Re Heat Line (2970C, 48kg/cm2)




Furnace ww 3rd run                                                                                                                                   LPR Upper                                                   Suspension Tubes
                                                                                                                                                                                                                 of LPR
Horizontal gas duct                                                                                                                                  LPR Middle
       ww
                                                                                                                                                     LPR Lower
  Hanger tube 1
                                                                                                                                                                                                          Tube to Low Pressure
     Roof ww                                                                                                                                                                                              Reheater
                                                                                                                                                                                                          (4490C, 28kg/cm2)
  Hanger tube 2

  Convection ww

  Steam to steam                                                                                                                                                  Generator
                                                                           IP Turbine
                                                                                                                                                                  Coupling
                                                                HP Turbine
  heat exchanger                                                                    LP Turbine                                                                                  Generator
                                                                 Cooling Water
    Separator                                                                                                                                                                  Condenser

Platen super heater                                              Hot Water to Cooling Tower
                                                                                                                                                                               Deaerator
  Stage 1,2,3 & 4                                              LPR Stage - I

Final Super heater                                             LPR Stage - II
                                                                                                                                                                     Water Line To Boiler Feed Pump
    HP Turbine                                                IP & LP Turbine                                                                                     Make Up Water Line From
                                                                                                                                                                  DM Plant
Water steam Circuit in Supercritical Boiler for 660MW Power Plant

Contenu connexe

Tendances

Heat rate audit in thermal power plant
Heat rate audit in thermal power plantHeat rate audit in thermal power plant
Heat rate audit in thermal power plant
SHIVAJI CHOUDHURY
 
Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plants
SHIVAJI CHOUDHURY
 
Energy adudit methodology for boiler
Energy adudit methodology for boilerEnergy adudit methodology for boiler
Energy adudit methodology for boiler
Kongkiert Tankayura
 

Tendances (20)

Heat rate audit in thermal power plant
Heat rate audit in thermal power plantHeat rate audit in thermal power plant
Heat rate audit in thermal power plant
 
Boiler light up & loading
Boiler light up & loadingBoiler light up & loading
Boiler light up & loading
 
Hp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesHp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbines
 
Construction of 500 MW Steam Boiler
Construction of 500 MW Steam BoilerConstruction of 500 MW Steam Boiler
Construction of 500 MW Steam Boiler
 
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
 
Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plants
 
Performance calculation for feed water heater
Performance calculation  for feed water heaterPerformance calculation  for feed water heater
Performance calculation for feed water heater
 
Thermax IR CFBC BOILER U BEAM TYPE
Thermax IR CFBC BOILER                U BEAM TYPEThermax IR CFBC BOILER                U BEAM TYPE
Thermax IR CFBC BOILER U BEAM TYPE
 
super critical power plant
super critical power plantsuper critical power plant
super critical power plant
 
210 MW BHEL Turbine Cycle Heat Balance
210 MW BHEL Turbine Cycle Heat Balance210 MW BHEL Turbine Cycle Heat Balance
210 MW BHEL Turbine Cycle Heat Balance
 
Steam Turbine Performance in TPS
Steam Turbine Performance in TPSSteam Turbine Performance in TPS
Steam Turbine Performance in TPS
 
Thermal Power Plant - Emergency situations
Thermal Power Plant   -   Emergency situations Thermal Power Plant   -   Emergency situations
Thermal Power Plant - Emergency situations
 
Report on Boilers at NTPC Ramagunadam
Report on  Boilers at NTPC RamagunadamReport on  Boilers at NTPC Ramagunadam
Report on Boilers at NTPC Ramagunadam
 
A technical overview of thermal power plant
A technical overview of thermal power plantA technical overview of thermal power plant
A technical overview of thermal power plant
 
Energy adudit methodology for boiler
Energy adudit methodology for boilerEnergy adudit methodology for boiler
Energy adudit methodology for boiler
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rate
 
Thermal power plant efficiency
Thermal power plant efficiencyThermal power plant efficiency
Thermal power plant efficiency
 
SOOT BLOWERS - Copy.pptx
SOOT BLOWERS - Copy.pptxSOOT BLOWERS - Copy.pptx
SOOT BLOWERS - Copy.pptx
 
Boiler Drum And Its Internals
Boiler Drum And Its InternalsBoiler Drum And Its Internals
Boiler Drum And Its Internals
 
Boiler Loss of Flame Protection- MFT
Boiler Loss of Flame Protection- MFTBoiler Loss of Flame Protection- MFT
Boiler Loss of Flame Protection- MFT
 

Similaire à Water steam Circuit in Supercritical Boiler for 660MW Power Plant

Suratgarh thermal power station
Suratgarh  thermal  power  stationSuratgarh  thermal  power  station
Suratgarh thermal power station
Gaurav Gunjan
 
L2 stationary combustion-p1-090712
L2 stationary combustion-p1-090712L2 stationary combustion-p1-090712
L2 stationary combustion-p1-090712
zs4007
 
Improve Shale Oil Crude Heater Performance
Improve Shale Oil Crude Heater PerformanceImprove Shale Oil Crude Heater Performance
Improve Shale Oil Crude Heater Performance
Aditya Shah
 
Tpp summer pro rep
Tpp summer pro repTpp summer pro rep
Tpp summer pro rep
Rohit Anand
 
Steam_Boiler_Basics_tim_powell_hughes.pdf
Steam_Boiler_Basics_tim_powell_hughes.pdfSteam_Boiler_Basics_tim_powell_hughes.pdf
Steam_Boiler_Basics_tim_powell_hughes.pdf
GaluhAjeng26
 
Coalfiredelectricpowerplants23 131208122612-phpapp01
Coalfiredelectricpowerplants23 131208122612-phpapp01Coalfiredelectricpowerplants23 131208122612-phpapp01
Coalfiredelectricpowerplants23 131208122612-phpapp01
arvind singh rathore
 
MET 401 Chapter 4 boilers_and_steam_generators
MET 401 Chapter 4 boilers_and_steam_generatorsMET 401 Chapter 4 boilers_and_steam_generators
MET 401 Chapter 4 boilers_and_steam_generators
Ibrahim AboKhalil
 
Coal fired electric power plants23
Coal fired electric power plants23Coal fired electric power plants23
Coal fired electric power plants23
Munna Sagar
 

Similaire à Water steam Circuit in Supercritical Boiler for 660MW Power Plant (20)

Suratgarh thermal power station
Suratgarh  thermal  power  stationSuratgarh  thermal  power  station
Suratgarh thermal power station
 
Kudgi_SG_Water___Steam_Circuit.pptx
Kudgi_SG_Water___Steam_Circuit.pptxKudgi_SG_Water___Steam_Circuit.pptx
Kudgi_SG_Water___Steam_Circuit.pptx
 
training report
training reporttraining report
training report
 
L2 stationary combustion-p1-090712
L2 stationary combustion-p1-090712L2 stationary combustion-p1-090712
L2 stationary combustion-p1-090712
 
Improve shale oil crude heater performance summary slideshare
Improve shale oil crude heater performance summary slideshareImprove shale oil crude heater performance summary slideshare
Improve shale oil crude heater performance summary slideshare
 
Improve Shale Oil Crude Heater Performance
Improve Shale Oil Crude Heater PerformanceImprove Shale Oil Crude Heater Performance
Improve Shale Oil Crude Heater Performance
 
Tpp summer pro rep
Tpp summer pro repTpp summer pro rep
Tpp summer pro rep
 
02 Boiler Construction.ppt
02 Boiler Construction.ppt02 Boiler Construction.ppt
02 Boiler Construction.ppt
 
Steam_Boiler_Basics_tim_powell_hughes.pdf
Steam_Boiler_Basics_tim_powell_hughes.pdfSteam_Boiler_Basics_tim_powell_hughes.pdf
Steam_Boiler_Basics_tim_powell_hughes.pdf
 
Study of Boilers for Mechanical Engineering
Study of Boilers for Mechanical EngineeringStudy of Boilers for Mechanical Engineering
Study of Boilers for Mechanical Engineering
 
Coalfiredelectricpowerplants23 131208122612-phpapp01
Coalfiredelectricpowerplants23 131208122612-phpapp01Coalfiredelectricpowerplants23 131208122612-phpapp01
Coalfiredelectricpowerplants23 131208122612-phpapp01
 
Ipe301 e steam generation unit
Ipe301 e steam generation unitIpe301 e steam generation unit
Ipe301 e steam generation unit
 
All about boilers: Complete Basics, Classification of boilers,types
All about boilers: Complete Basics, Classification of boilers,typesAll about boilers: Complete Basics, Classification of boilers,types
All about boilers: Complete Basics, Classification of boilers,types
 
Boilers ps mrng sessn
Boilers ps mrng sessnBoilers ps mrng sessn
Boilers ps mrng sessn
 
Boilers ps mrng sessn
Boilers ps mrng sessnBoilers ps mrng sessn
Boilers ps mrng sessn
 
Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT
 
MET 401 Chapter 4 boilers_and_steam_generators
MET 401 Chapter 4 boilers_and_steam_generatorsMET 401 Chapter 4 boilers_and_steam_generators
MET 401 Chapter 4 boilers_and_steam_generators
 
Presentation on CFBC Boilers
Presentation on CFBC BoilersPresentation on CFBC Boilers
Presentation on CFBC Boilers
 
Coal fired electric power plants23
Coal fired electric power plants23Coal fired electric power plants23
Coal fired electric power plants23
 
Boiler turbe failores
Boiler turbe failoresBoiler turbe failores
Boiler turbe failores
 

Dernier

Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
Joaquim Jorge
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
Enterprise Knowledge
 

Dernier (20)

TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
Evaluating the top large language models.pdf
Evaluating the top large language models.pdfEvaluating the top large language models.pdf
Evaluating the top large language models.pdf
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 

Water steam Circuit in Supercritical Boiler for 660MW Power Plant

  • 1. WATER-STEAM CIRCUIT in SUPER CRITICAL BOILER Prepared By: Hareesh VS Jr.Manager IOTEP BARH
  • 2. BOILER PARAMETERS Once Through, Single Reheat, Coal Fired, Balanced draft, Main Boiler Type Side Fired, Tower type & Symmetrical to Both Axis Furnace :- 14.9 X 23.04 M Boiler Area Second Pass :- 6.07 X 23.04 M X 2( Both side of Furnace) Roof :- 44.35 X 23.04 M Guarantee Bituminous Coal Design Fuel LCV :- 3026 kcal/kg HCV :- 3300 kcal/kg Material of Construction 12X1MФ and 15X1MФ Main Steam Flow 2225 T/Hr Main Steam Pressure 256 Kg/cm2 Main Steam Temp 540 OC RH Steam Flow 1746 T/Hr RH Steam Pressure 46.13 Kg/cm2 RH Steam Temp 568 OC Feed Water Temp 290 OC
  • 3. Boiler Feed pump Collecting Header Economizer 3320C, 299kg/cm2 Suspension Tube Tubes to furnace ww first run Furnace ww 1st Run Steam to steam heat exchanger Hot Furnace ww 2st Run suspension Attemperator 1st Suspension Tubes Furnace ww 3rd run Economizer Upper Block Horizontal gas duct ww FRH & HP Heaters Hanger tube 1 2900C, 304kg/cm2 Roof ww Line From Economizer Lower Block Line From BFP Hanger tube 2 Deaerator Tubes to furnace Convection ww ww first run Steam to steam Boiler Feed Pump Intermediate Header heat exchanger Separator Platen super heater Inlet Header of Furnace Stage 1,2,3 & 4 WW First run Final Super heater Reheat system HP Turbine IP & LP Turbine Distribution Header of Furnace WW First run
  • 4. Recirculation pump Economizer Suspension Tube Tubes to furnace ww first run Furnace ww 1st Run Furnace ww 2st Run Attemperator 1st Furnace ww 3rd run Horizontal gas duct ww Hanger tube 1 Furnace WW First Run Collecting Header Furnace WW first run Furnace Front & Rear Water Wall Roof ww Lower panels And Extreme End Hanger tube 2 First Run WW Outlet panels of Side water Wall Lower Headers (Intermediate Convection ww Headers) part Steam to steam heat exchanger Tubes to Furnace Side Hot Furnace Front & Rear Hot suspension Lower part suspension Lower part Separator Furnace Side Hot Platen super heater Furnace WW first run panels suspension Lower Part Stage 1,2,3 & 4 Final Super heater Reheat system Furnace Hot suspension Lower Part collecting HP Turbine IP & LP Turbine Header (3770C, 301kg/cm2)
  • 5. Recirculation pump Side View of Boiler Economizer Suspension Tube Tubes to furnace ww first run Furnace ww 1st Run Furnace ww 2st Run Attemperator 1st Furnace ww 3rd run Horizontal gas duct ww Collecting Header Furnace Hanger tube 1 WW first run Roof ww Hanger tube 2 Extreme Panels of Side WW Convection ww Steam to steam heat exchanger Furnace Side Hot suspension Lower part Separator Inlet Header of Furnace Furnace Front & Rear Hot Platen super heater Second Run suspension Lower Part Stage 1,2,3 & 4 Final Super heater Reheat system Furnace Hot suspension Lower Part collecting HP Turbine IP & LP Turbine Header
  • 6. Recirculation pump Side View of Boiler Economizer Suspension Tube Tubes to furnace ww first run Furnace WW Second Run Furnace ww 1st Run Furnace Side Water walls Lower Part Furnace ww 2st Run Attemperator 1st Collecting Headers of Middle Part of Hot Suspension Furnace ww 3rd run Furnace Hot Suspension Horizontal gas duct Middle Part ww HP Spraying Attemperator-1 Hanger tube 1 Tubes to Furnace Hot Distribution Header to suspension Middle part Roof ww Furnace 3rd Run Hanger tube 2 Mixing Headers of Furnace Outlet Headers of Furnace Convection ww Second run WW panels Second run WW panels Steam to steam (4010C, 296kg/cm2) heat exchanger Separator Platen super heater Furnace WW second run panels Stage 1,2,3 & 4 Final Super heater Reheat system HP Turbine IP & LP Turbine
  • 7. Recirculation pump Side View of Boiler Economizer Suspension Tube Furnace WW Third Run Tubes to furnace All Upper Panels of Furnace Front, ww first run Rear & Side Water walls Furnace ww 1st Run Furnace ww 2st Run Attemperator 1st Outlet Headers of Furnace WW 3rd run panels at Horizontal Gas Furnace ww 3rd run duct Bottom Area (Arch Area) Tubes to Intermediate (4330C, 291kg/cm2) Headers of 3rd Run WW Horizontal gas duct ww Furnace WW 3rd run panels Distribution Header to Hanger tube 1 Furnace 3rd Run Roof ww Tubes to Inlet Headers of Inlet Headers Furnace WW 3rd Hanger tube 2 3rd Run WW run panels Convection ww Steam to steam heat exchanger Separator Platen super heater Stage 1,2,3 & 4 Final Super heater Reheat system HP Turbine IP & LP Turbine
  • 8. Recirculation pump Economizer Hanger Tube 1 Suspension Tube (4410C, 288kg/cm2) Tubes to furnace Collecting Header of ww first run Furnace 3rd Run Furnace ww 1st Run Horizontal Gas Duct WW Furnace ww 2st Run Inlet Headers of Horizontal Attemperator 1st Gas Duct WW ` Furnace ww 3rd run Intermediate Headers of 3rd Outlet headers of Run WW 3rd run panels Horizontal gas duct (4430C, 291kg/cm2) ww Furnace WW 3rd run panels Inlet Header of Hanger Hanger tube 1 Tube 1 Roof ww Tubes to Inlet Headers of Inlet Headers Furnace WW 3rd Hanger tube 2 3rd Run WW run panels Convection ww Steam to steam heat exchanger Separator Platen super heater Stage 1,2,3 & 4 Final Super heater Reheat system HP Turbine IP & LP Turbine
  • 9. Recirculation pump Roof WW Inlet Header Economizer Roof Water Wall Suspension Tube Tubes to furnace Roof Water Wall Collecting ww first run Header (4480C, 284kg/cm2) Furnace ww 1st Run Distribution Header of Hanger Tube 2 Furnace ww 2st Run Attemperator 1st Hanger Tube 2 ` Furnace ww 3rd run Horizontal gas duct ww Inlet Header of Hanger tube 1 Hanger tube 2 Roof ww Hanger tube 2 Convection ww Steam to steam heat exchanger Separator Platen super heater Stage 1,2,3 & 4 Final Super heater Reheat system HP Turbine IP & LP Turbine
  • 10. Recirculation pump Distribution Header Of Upper Hot suspension Economizer Convection Shaft & Furnace Area Suspension Tube Tubes to furnace Collecting Header Of ww first run Hanger Tube-2 (4520C, 281kg/cm2) Furnace ww 1st Run Tubes to Furnace Hot Suspension Furnace ww 2st Run Attemperator 1st ` ` ` ` ` ` Hanger Tube-3 ` Furnace ww 3rd run Convection Shaft Convection Shaft Hot Suspension Horizontal gas duct ww Water Walls Hanger tube 1 Tubes to Convection Hot Suspension Distribution Header of Roof ww Convection Shaft WW Tubes to Hot Suspension Hanger tube 2 Collecting Header Convection ww Steam to steam heat exchanger Separator Platen super heater Stage 1,2,3 & 4 Final Super heater Reheat system HP Turbine IP & LP Turbine
  • 11. High Pressure Spray Recirculation pump Attemperator – 2 (4390C, 273kg/cm2) Economizer Wet Steam Suspension Tube Separator Tubes to furnace ww first run High Pressure Tubes to Collecting Header of SSHE Furnace ww 1st Run (4570C, 274kg/cm2) Furnace ww 2st Run Drain Header Attemperator 1st ` ` ` ` ` ` ` Furnace ww 3rd run Moisture Content in Steam After Separation Tubes to Steam To Steam Heat Horizontal gas duct Exchanger ww Collecting Header of Hanger tube 1 Convection Shaft WWs & Steam To Steam Heat Hanger Tube – 3 Roof ww Exchanger (4650C, 278kg/cm2) Hanger tube 2 Convection ww Steam to steam heat exchanger Separator Platen super heater Stage 1,2,3 & 4 Final Super heater Reheat system HP Turbine IP & LP Turbine
  • 12. Recirculation pump Tubes to Platen Super Heater Economizer (4390C, 273kg/cm2) Suspension Tube Spray Type Attemperator -3 Tubes to furnace (5110C, 259kg/cm2) ww first run Tubes to Final Super Heater Furnace ww 1st Run (5000C, 258kg/cm2) Furnace ww 2st Run Convection Super Heater Attemperator 1st (Final Super Heater) ` ` ` ` ` ` ` Furnace ww 3rd run Main Steam Out Let Header Horizontal gas duct (5400C, 256kg/cm2) ww Platen Super Heaters Hanger tube 1 Stage 1, 2, 3 & 4. Roof ww Steam Flow in 4 Stages of Hanger tube 2 Platen Super Heater Convection ww Rear Steam to steam I/L heat exchanger Separator O/L O/L Platen super heater Stage 1,2,3 & 4 Left Right Final Super heater Reheat system I/L HP Turbine IP & LP Turbine Front
  • 13. Recirculation pump Economizer LP Spray HRH Line Atemperator Suspension Tube LPR Stage – 2 Tubes to furnace (Final) Collecting Header ww first run of LPR Steam to Steam (4840C, 47kg/cm2) Heat Exchanger Furnace ww 1st Run Main Steam Line to TG(5400C, 256kg/cm2) CRH Line from Furnace ww 2st Run HP Turbine Hot Re Heat Line (5680C, 46kg/cm2) Attemperator 1st ` ` ` ` ` ` ` Cooled Re Heat Line (2970C, 48kg/cm2) Furnace ww 3rd run LPR Upper Suspension Tubes of LPR Horizontal gas duct LPR Middle ww LPR Lower Hanger tube 1 Tube to Low Pressure Roof ww Reheater (4490C, 28kg/cm2) Hanger tube 2 Convection ww Steam to steam Generator IP Turbine Coupling HP Turbine heat exchanger LP Turbine Generator Cooling Water Separator Condenser Platen super heater Hot Water to Cooling Tower Deaerator Stage 1,2,3 & 4 LPR Stage - I Final Super heater LPR Stage - II Water Line To Boiler Feed Pump HP Turbine IP & LP Turbine Make Up Water Line From DM Plant