SlideShare une entreprise Scribd logo
1  sur  25
Project CostProject Cost
‫ممم‬‫م‬‫ممم‬‫م‬‫ممممم‬‫م‬‫ممممم‬
Prepared by : Hat im Mohammed
Ahmed
Pr oj ect Cost
COST ENGINEERING IS THE APPLICATION OF
SCIENTIFIC PRINCIPLES AND TECHNIQUES TO
PROBLEMS OF ESTIMATION, COST CONTROL,
BUSINESS PLANNING AND MANAGEMENT SCIENCE,
PROFITABILITY ANALYSIS, PROJECT
MANAGEMENT, AND PLANNING AND
SCHEDULING . WITH THE OBJECTIVE TO ACHIEVE
THE LOWEST COST.
INTRODUCTION
Pr oj ect Cost
ESTIMATE ACCURACY
 From an owner’s perspective, if the cost estimate is not accurate, the
financial return from the capital investment may not be realized; and
compounding this problem is the fact that other deserving projects
may not have been funded. It is obvious that estimating is critical for
the economic and optimal use of an owner’s limited capital budget.
 From a contractor’s perspective, accurate estimating is just as
important. In a lump-sum bidding situation, the profit margin of the
contractor is dependent on the accuracy of his estimate. If the project
I s exceptionally large, the loss from an inaccurate estimate on a
lump-sum bid can potentially put a contractor out of business. For
cost-plus projects, the contractor will face less direct economic risk
from an inaccurate estimate, but the damage to the contractor’s
reputation can be severe.
Pr oj ect Cost
ESTIMATE
CLASSIFICATIONS
Estimate classifications are
commonly used to indicate
the overall maturity and
quality for the various types
of estimates that may be
prepared; and most
organizations will use some
form of classification system
to identify and categorize
the various types of project
estimates that they may
prepare during the life cycle
of a project.
Pr oj ect Cost
COST
Section 1
Pr oj ect Cost
1- COST STRUCTURING
It is important to further structure the cost elements within
the material, labor, and other resource categories in order
to understand how they influence the total cost of the
activity or asset and to get a better understanding of how
they can be controlled. This structuring sorts the cost
elements into direct costs, indirect costs, fixed costs, and
variable costs. In practice, some costs may fall in more than
one of these groupings.
Pr oj ect Cost
1-1.Direct Costs
Direct costs are those resources that are expended solely to
complete the activity or asset. In other words, “Any cost that
is specifically identified with a particular final cost objective,
but not necessarily limited to items that are incorporated in
the end product as material or labor” . Thus, the direct cost
of a foundation for a house includes equipment for trenching
for the footings, the wooden forms (if not reusable), the
concrete, and the labor to place and finish the concrete.
Pr oj ect Cost
1-2. Indirect Costs
Indirect costs are those resources that need to be expended to
support the activity or asset but that are also associated with
other activities and assets.
Indirect costs also may be referred to as “overhead costs” or
“burden costs.” Indirect costs are general administrative
activities associated with operating the business, costs for
providing and maintaining field equipment or a
manufacturing facility, and expenses for utilities, taxes,
légal services, etc.
Pr oj ect Cost
1-3. Fixed Costs
Fixed costs are those cost elements that must be provided
independent of the volume of work activity or asset production
that they support.
Pr oj ect Cost
1-4. Variable Costs
Variable costs are those cost elements that must be provided
and are dependent on the volume of work activity or asset
production that they support. Again, these can be either director
indirect costs.
Examples of Cost
Structure
Components
 Direct
Material: drafting paper, concrete, nails, lumber, deck
screws, paint, turpentine
Labor: draw plans, get permit, get materials, construct
footings, erect deck, paint deck
Other: building permit fee
 Indirect
Material: pencil, brushes, drop cloth
Labor: wife’s support in making lunch
Other: use of house to draw plans, shovel, power saw,
power drill, electricity, pickup truck, gasoline
 Fixed
Direct: get permit
Indirect: use of house to draw plans, shovel, power saw,
power drill, pickup truck, pencil, brushes, drop
cloth
 Variable
Direct: drafting paper, building permit fee, concrete,
nails, lumber, deck screws, paint, turpentine,
draw plans, get materials, construct footings,
erect deck, paint deck
Indirect: wife’s support in making lunch, electricity, gasoline
Pr oj ect Cost
2- Cost Elements
Cost-Based Estimates contain six basic elements:
Time, Equipment, Labor, Material, Overhead and
Profit. Each item of work on a project can be broken
up into tasks that it takes to complete the item of work.
Each of these tasks contains the six basic elements
that result in the cost for the project.
Pr oj ect Cost
2-1.Materials
TYPES OF
MATERIALS AND
RELATED
INFORMATION
Materials, for purposes of
differentiation, can be segregated
into four basic categories:
1. raw materials,
2. bulk materials,
3. fabricated materials, and
4. engineered or designed materials.
These categories are differentiated
on the criteria of the amount of
processing required for the material
to be useful for its intended purpose.
Pr oj ect Cost
2-2.Labor
LABOR
CLASSIFICATIONS
The following definitions were taken or adapted from
AACE International’s Cost Engineer’s Notebook [1].
• Direct Labor—The labor involved in the work
activities
that directly produce the product or complete the
installation being built.
• Indirect Labor—The labor needed for activities that
do
not become part of the final installation, product, or
goods produced, but that are required to complete the
project.
• Overhead Labor—The labor portion of costs inherent
in
the performing of a task (such as engineering,
construction, operating, or manufacturing), which
cannot be charged to or identified with a part of the
work, and, therefore, must be allocated on some
arbitrary basis believed to be equitable, or handled as a
business expense independent of the volume of
production.
Pr oj ect Cost
2-3.Equipment,
Parts, and Tools
ESTABLISHING AN
EQUIPMENT
VALUATION
DATABASE
Equipment Value Categories:
Replacement Cost New :has the
following subcategories:
 Reproduction Cost .
 Replacement Cost .
 Fair Value .
 Market Value, also contains several
subcategories:
1.Fair Market Value-in-Place .
2.Fair Market Value-in-Exchange.
3.Forced Liquidation Value.
4.Salvage Value/Part-Out Value.
5.Scrap Value.
Pr oj ect Cost
2-4.Other Cost
Elements
Overhead cost : Overhead or
indirect expenses are outlays that are
incurred in achieving project
completion but that do not apply
directly to any specific work item.
Two kinds of overhead pertain to a
contractor’s operations , project
overhead and office overhead.
Economic cost : Elements of
economic costs are Taxation policies
and the respective rates ,
Depreciation, Currency variations
and Some aspects of inflation and
interest .
Engineering cost .
Pr oj ect Cost
Pricing
Section 2
Pr oj ect Cost
Price Cost
Pricing, is adjusting the costs that
have been applied for specific
project conditions, and commercial
terms. Pricing includes adjustments
to cost to allow for overhead
and profit, to improve cash flow, or
otherwise serve the business
interests of the party preparing the
estimate. Thus, the level and type of
pricing adjustments depends on the
particular party preparing the
estimate.
Costing is the process of applying
unit costs to the individual
quantities of items associated with
the estimate. For a detailed
estimate, this is usually in the form
of labor hours, wage rates,
material costs, and perhaps
subcontract costs. These costs may
come from a variety of sources such
as an estimating database
(either in-house or commercial),
vendor quotes, the procurement
department, estimating experience,
etc.
COST AND PRICING—IS THERE
A DIFFERENCE?
Pr oj ect Cost
1-Price Analysis Techniques
Adequate Price Competition.
Historical Prices.
Parametric Estimates.
Catalogs or Market Prices
Engineering Cost Estimate (ECE)
Similar Projects.
Pr oj ect Cost
Summary Sheets
The total quantities are transferred from the quantity sheets to summary
sheets for pricing purposes.
On lump-sum projects, it is standard practice to transfer all quantities of
work pertaining to a single construction classification to the same summary
sheet before pricing them. As an example, concrete quantities and prices
would appear on a concrete summary sheet. Similar summary sheets are
prepared for the other work classifications, such as excavation, concrete
forms, masonry, and carpentry. On a unit-price job like the highway bridge,
each summary sheet lists the work types necessary to accomplish the total
quantity of a single bid item and may include several different classifications
of work.
Pr oj ect Cost
Example of Summary Sheets
Summary Sheet
Job: Highway Bridge Bid Item No. 6: Concrete, abutments Estimator: GAS
Cost Code Work Type Quantity Unit Calculations Labor Cost Equipment
Cost
Material Cost Total Cost
Direct Indirect
03150.20 Abutment forms,
prefabricate
1,810 sf Labor
labor unit cost = $1.96 per sf 1,810 x $1.96 = $3,548
Material
Ply form: $1.05 per sf 10% waste 50% salvage 1,810 x $1.05 x 1.10
x 50% = $1,045
lumber: $0.85 per bf 50% salvage 1.44 bf/sf 2 uses 1,810
x $0.85 x 1.44 x 50% = $1,108
$3,548 $1,596
$1,045
$1,108
$5,144
$1,045
$1,108
Total this account $3,548 $1,596 $0 $2,153 $7,297
03157.20 Abutment forms, place 3,620 sf Labor
labor unit cost = $2.02 per sf 3,620 x $2.02 = $7,312
Equipment
3 days of 50 ton crane time
3 x 8 x $105 = $2,520
Materials
nails, form ties, coating $0.28 per sf 3,620 x $0.28 = $1,014
$7,312 $2,559 $2,520 $1,014
$9,872
$2,520
$1,014
Total this account $7,312 $2,559 $2,520 $1,014 $13,405
03159.20 Abutment forms, strip 3,620 sf Labor
labor unit cost = $0.97 per sf 3,620 x $0.97 = $3,511
Equipment
1 day of 50 ton crane time
1 x 8 x $105 = $840
$3,511 $878 $840
$4,389 $840
Total this account $3,511 $878 $840 $0 $5,229
Pr oj ect Cost
ON THE RECAP SHEET, THE DIRECT COST OF THE ENTIRE QUANTITY
OF EACH BID ITEM IS OBTAINED AS THE SUM OF ITS LABOR,
EQUIPMENT, MATERIAL, AND SUBCONTRACT EXPENSES. THE SUM OF
ALL SUCH BID-ITEM DIRECT COSTS GIVES THE ESTIMATED TOTAL
DIRECT COST TO THIS ADDED THE JOB OVERHEAD, SMALL TOOLS,
TAX, MARKUP, AND THE PREMIUM CHARGE FOR THE PERFORMANCE
AND PAYMENT SURETY BONDS, GIVING THE TOTAL PRICE HE ENTIRE
PROJECT
2-Recap Sheet
Pr oj ect Cost
Example of Recap Sheet
Recap Sheet
Bid Date: April 25, 20XX
Job: Highway Bridge Estimator: GAS
Item Estimated Labor Equipment Material Subcontract Direct Bid
No. Bid Item Unit Quantity Cost Cost Cost Cost Cost Total Unit
1 Excavation, unclassified cy 1,667 $3,569 $929 $0 $0 $4,497 $6,386 $3.83
2 Excavation, structural cy 120 $3,731 $555 $0 $0 $4,286 $6,086 $50.72
3 Backfill, compacted cy 340 $3,591 $663 $0 $0 $4,254 $6,041 $17.77
4 Piling, steel lf 2,240 $21,390 $11,176 $72,279 $0 $104,845 $148,872 $66.46
5 Concrete, footings cy 120 $3,661 $685 $12,186 $0 $16,532 $23,475 $195.62
6 Concrete, abutments cy 280 $37,459 $7,104 $30,542 $0 $75,105 $106,644 $380.87
7 Concrete, deck slab, 10 in sy 200 $11,745 $1,790 $8,020 $0 $21,555 $30,606 $153.03
8 Steel, reinforcing lb 90,000 $0 $0 $0 $66,240 $66,240 $94,056 $1.045
9 Steel, structural lb 65,500 $4,220 $1,680 $73,688 $0 $79,588 $113,009 $1.725
10 Bearing plates lb 3,200 $1,943 $420 $3,250 $0 $5,613 $7,970 $2.49
11 Guardrail lf 120 $1,664 $420 $5,826 $0 $7,910 $11,231 $93.59
12 Paint ls job $0 $0 $0 $8,550 $8,550 $12,140 $12,140.39
Totals $92,974 $25,422 $205,790 $74,790 $398,975 $566,516
Job overhead $69,868
$468,844
Small tools (5% of labor) $4,649
$473,492
Factor = $566,516 = 1.4199 Tax 3% $14,205
$487,697
$398,975 Markup 15% $73,155
$560,852
Bonds $5,665
Total Project Bid $566,516
Pr oj ect Cost
3- Unit Price Schedule
The unit prices just computed have been obtained on
the basis that each bid item includes its own direct
cost plus its pro rata share of the project overhead,
small tools, tax, markup, and bond. If these unit
prices are now entered without change onto the bid
form, this is called a balanced bid. For several
reasons, a contractor may raise the prices on certain
bid items and decrease the prices on others
proportionately so that the bid amount
for the total job remains unaffected. This is called an
unbalanced bid.
Pr oj ect Cost
Example of Unit Price
Schedule
Pr oj ect Cost
COST ENGINEERING IS OBVIOUSLY A VITAL COMPONENT TO
PROJECT SUCCESS.
THEY ARE USED NOT ONLY TO ESTABLISH PROJECT
BUDGETS, BUT ALSO TO PROVIDE ACCURATE INFORMATION
TO SUPPORT SCHEDULING , COST MONITORING, AND
PROGRESS MEASUREMENT OF A PROJECT DURING
EXECUTION.
THE INTEGRATION OF COST ENGINEERING AND COST
MANAGEMENT PRINCIPLES USED IN MANAGING THE TOTAL
LIFE CYCLE COST INVESTMENT IN STRATEGIC ASSETS.
Conclusion
Pr oj ect Cost

Contenu connexe

Tendances

Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management Rajat Nainwal
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project ManagementAravind Samala
 
PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction CostingManish Kandpal
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Managementjohnkirth1898
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionWaleed Liaqat
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Schedulingakashpadole
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor温 庄壁
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource SmoothingDavidMcLachlan1
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tenderingvvsasane
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & managementManit Agarwal
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and CostingSakshi Kirar
 
Specification writing-I
Specification writing-ISpecification writing-I
Specification writing-IKishor Ade
 
Estimating and costing
Estimating and costingEstimating and costing
Estimating and costingAyushHajare
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.NAVNEET KUMAR JHA
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contractssrinivas2036
 

Tendances (20)

Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Estimating & Costing - I
Estimating & Costing - IEstimating & Costing - I
Estimating & Costing - I
 
PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction Costing
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
 
Bills of quantities
Bills of quantitiesBills of quantities
Bills of quantities
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and Costing
 
Specification writing-I
Specification writing-ISpecification writing-I
Specification writing-I
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
 
Estimating and costing
Estimating and costingEstimating and costing
Estimating and costing
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 

En vedette

Change your board operator to a process control manager
Change your board operator to a process control managerChange your board operator to a process control manager
Change your board operator to a process control managerMary Claire Simoneaux
 
Micro Electro Mechanical Systems (MEMS) Class Materials - Lecture 03
Micro Electro Mechanical Systems (MEMS) Class Materials - Lecture 03Micro Electro Mechanical Systems (MEMS) Class Materials - Lecture 03
Micro Electro Mechanical Systems (MEMS) Class Materials - Lecture 03Manipal Institute of Technology
 
Control of Manufacturing Processes
Control of Manufacturing ProcessesControl of Manufacturing Processes
Control of Manufacturing Processeshumanist3
 
Types process control system
Types process control systemTypes process control system
Types process control systemJigar Nayak
 
Contro lsystem
Contro lsystemContro lsystem
Contro lsystemshan dj
 
Electronic Devices For Oil Gas Facilities.The System For Control Of Gas Conta...
Electronic Devices For Oil Gas Facilities.The System For Control Of Gas Conta...Electronic Devices For Oil Gas Facilities.The System For Control Of Gas Conta...
Electronic Devices For Oil Gas Facilities.The System For Control Of Gas Conta...ArtemTruff
 
Quality & process control in textile processing
Quality & process control in textile processingQuality & process control in textile processing
Quality & process control in textile processingMd. Mazadul Hasan Shishir
 
How to write an abstract
How to write an abstractHow to write an abstract
How to write an abstractdanix_cata
 
Project scheduling and control techniques
Project scheduling and control techniquesProject scheduling and control techniques
Project scheduling and control techniquesCjkayes CjKayes
 
block diagram representation of control systems
block diagram representation of  control systemsblock diagram representation of  control systems
block diagram representation of control systemsAhmed Elmorsy
 
Industrial process control
Industrial process controlIndustrial process control
Industrial process controlMohamed A Hakim
 

En vedette (14)

Change your board operator to a process control manager
Change your board operator to a process control managerChange your board operator to a process control manager
Change your board operator to a process control manager
 
Chapter 1
Chapter 1Chapter 1
Chapter 1
 
Testing
TestingTesting
Testing
 
Micro Electro Mechanical Systems (MEMS) Class Materials - Lecture 03
Micro Electro Mechanical Systems (MEMS) Class Materials - Lecture 03Micro Electro Mechanical Systems (MEMS) Class Materials - Lecture 03
Micro Electro Mechanical Systems (MEMS) Class Materials - Lecture 03
 
Control of Manufacturing Processes
Control of Manufacturing ProcessesControl of Manufacturing Processes
Control of Manufacturing Processes
 
Types process control system
Types process control systemTypes process control system
Types process control system
 
Contro lsystem
Contro lsystemContro lsystem
Contro lsystem
 
Electronic Devices For Oil Gas Facilities.The System For Control Of Gas Conta...
Electronic Devices For Oil Gas Facilities.The System For Control Of Gas Conta...Electronic Devices For Oil Gas Facilities.The System For Control Of Gas Conta...
Electronic Devices For Oil Gas Facilities.The System For Control Of Gas Conta...
 
Quality & process control in textile processing
Quality & process control in textile processingQuality & process control in textile processing
Quality & process control in textile processing
 
How to write an abstract
How to write an abstractHow to write an abstract
How to write an abstract
 
Control systems
Control systemsControl systems
Control systems
 
Project scheduling and control techniques
Project scheduling and control techniquesProject scheduling and control techniques
Project scheduling and control techniques
 
block diagram representation of control systems
block diagram representation of  control systemsblock diagram representation of  control systems
block diagram representation of control systems
 
Industrial process control
Industrial process controlIndustrial process control
Industrial process control
 

Similaire à Project cost stimating

Chapter11 economics
Chapter11 economicsChapter11 economics
Chapter11 economicsVin Voro
 
Preparation and approaches of cost estimates
Preparation and approaches of cost estimatesPreparation and approaches of cost estimates
Preparation and approaches of cost estimatesnagashree123
 
Module 1 - cost and management accounting.pptx
Module 1 - cost and management accounting.pptxModule 1 - cost and management accounting.pptx
Module 1 - cost and management accounting.pptxMahesh Bendigeri
 
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET Journal
 
Introduction to Cost Accounting - Dr.J.Mexon
Introduction to Cost Accounting - Dr.J.MexonIntroduction to Cost Accounting - Dr.J.Mexon
Introduction to Cost Accounting - Dr.J.MexonDr. J.Mexon Fernando
 
Bca i fma u 4.2 marginal costing
Bca i fma u 4.2 marginal costingBca i fma u 4.2 marginal costing
Bca i fma u 4.2 marginal costingRai University
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - BriefKai Yun Pang
 
Mca i fma u 4.2 marginal costing
Mca i fma u 4.2 marginal costingMca i fma u 4.2 marginal costing
Mca i fma u 4.2 marginal costingRai University
 
Preparing cost estimate for manufactured products.ppt by-aragaw gebremedhin
Preparing cost estimate for manufactured products.ppt by-aragaw gebremedhinPreparing cost estimate for manufactured products.ppt by-aragaw gebremedhin
Preparing cost estimate for manufactured products.ppt by-aragaw gebremedhinAragaw Gebremedhin
 
Introduction of civil engineering.pdf
Introduction of civil engineering.pdfIntroduction of civil engineering.pdf
Introduction of civil engineering.pdfbkbk37
 
5 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp015 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp01hlksd
 

Similaire à Project cost stimating (20)

CCP Material.pdf
CCP Material.pdfCCP Material.pdf
CCP Material.pdf
 
Chapter11 economics
Chapter11 economicsChapter11 economics
Chapter11 economics
 
Preparation and approaches of cost estimates
Preparation and approaches of cost estimatesPreparation and approaches of cost estimates
Preparation and approaches of cost estimates
 
Preparing Cost Estimate for Manufactured Products.ppt-Aragaw-edited.pdf
Preparing Cost Estimate for Manufactured Products.ppt-Aragaw-edited.pdfPreparing Cost Estimate for Manufactured Products.ppt-Aragaw-edited.pdf
Preparing Cost Estimate for Manufactured Products.ppt-Aragaw-edited.pdf
 
ESTIMATING.pdf
ESTIMATING.pdfESTIMATING.pdf
ESTIMATING.pdf
 
Module 1 - cost and management accounting.pptx
Module 1 - cost and management accounting.pptxModule 1 - cost and management accounting.pptx
Module 1 - cost and management accounting.pptx
 
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
 
Basics
BasicsBasics
Basics
 
CCP Material
CCP MaterialCCP Material
CCP Material
 
Bf icab chapter 2, Business and Finance, ICAB
Bf icab chapter 2, Business and Finance, ICABBf icab chapter 2, Business and Finance, ICAB
Bf icab chapter 2, Business and Finance, ICAB
 
Introduction to Cost Accounting - Dr.J.Mexon
Introduction to Cost Accounting - Dr.J.MexonIntroduction to Cost Accounting - Dr.J.Mexon
Introduction to Cost Accounting - Dr.J.Mexon
 
Bca i fma u 4.2 marginal costing
Bca i fma u 4.2 marginal costingBca i fma u 4.2 marginal costing
Bca i fma u 4.2 marginal costing
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - Brief
 
Mca i fma u 4.2 marginal costing
Mca i fma u 4.2 marginal costingMca i fma u 4.2 marginal costing
Mca i fma u 4.2 marginal costing
 
UNIT-3.pptx
UNIT-3.pptxUNIT-3.pptx
UNIT-3.pptx
 
Preparing cost estimate for manufactured products.ppt by-aragaw gebremedhin
Preparing cost estimate for manufactured products.ppt by-aragaw gebremedhinPreparing cost estimate for manufactured products.ppt by-aragaw gebremedhin
Preparing cost estimate for manufactured products.ppt by-aragaw gebremedhin
 
Project cost management
Project cost management Project cost management
Project cost management
 
Introduction of civil engineering.pdf
Introduction of civil engineering.pdfIntroduction of civil engineering.pdf
Introduction of civil engineering.pdf
 
Eca workshop
Eca workshopEca workshop
Eca workshop
 
5 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp015 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp01
 

Dernier

Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Dernier (20)

Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 

Project cost stimating

  • 2. COST ENGINEERING IS THE APPLICATION OF SCIENTIFIC PRINCIPLES AND TECHNIQUES TO PROBLEMS OF ESTIMATION, COST CONTROL, BUSINESS PLANNING AND MANAGEMENT SCIENCE, PROFITABILITY ANALYSIS, PROJECT MANAGEMENT, AND PLANNING AND SCHEDULING . WITH THE OBJECTIVE TO ACHIEVE THE LOWEST COST. INTRODUCTION Pr oj ect Cost
  • 3. ESTIMATE ACCURACY  From an owner’s perspective, if the cost estimate is not accurate, the financial return from the capital investment may not be realized; and compounding this problem is the fact that other deserving projects may not have been funded. It is obvious that estimating is critical for the economic and optimal use of an owner’s limited capital budget.  From a contractor’s perspective, accurate estimating is just as important. In a lump-sum bidding situation, the profit margin of the contractor is dependent on the accuracy of his estimate. If the project I s exceptionally large, the loss from an inaccurate estimate on a lump-sum bid can potentially put a contractor out of business. For cost-plus projects, the contractor will face less direct economic risk from an inaccurate estimate, but the damage to the contractor’s reputation can be severe. Pr oj ect Cost
  • 4. ESTIMATE CLASSIFICATIONS Estimate classifications are commonly used to indicate the overall maturity and quality for the various types of estimates that may be prepared; and most organizations will use some form of classification system to identify and categorize the various types of project estimates that they may prepare during the life cycle of a project. Pr oj ect Cost
  • 6. 1- COST STRUCTURING It is important to further structure the cost elements within the material, labor, and other resource categories in order to understand how they influence the total cost of the activity or asset and to get a better understanding of how they can be controlled. This structuring sorts the cost elements into direct costs, indirect costs, fixed costs, and variable costs. In practice, some costs may fall in more than one of these groupings. Pr oj ect Cost
  • 7. 1-1.Direct Costs Direct costs are those resources that are expended solely to complete the activity or asset. In other words, “Any cost that is specifically identified with a particular final cost objective, but not necessarily limited to items that are incorporated in the end product as material or labor” . Thus, the direct cost of a foundation for a house includes equipment for trenching for the footings, the wooden forms (if not reusable), the concrete, and the labor to place and finish the concrete. Pr oj ect Cost
  • 8. 1-2. Indirect Costs Indirect costs are those resources that need to be expended to support the activity or asset but that are also associated with other activities and assets. Indirect costs also may be referred to as “overhead costs” or “burden costs.” Indirect costs are general administrative activities associated with operating the business, costs for providing and maintaining field equipment or a manufacturing facility, and expenses for utilities, taxes, légal services, etc. Pr oj ect Cost
  • 9. 1-3. Fixed Costs Fixed costs are those cost elements that must be provided independent of the volume of work activity or asset production that they support. Pr oj ect Cost 1-4. Variable Costs Variable costs are those cost elements that must be provided and are dependent on the volume of work activity or asset production that they support. Again, these can be either director indirect costs.
  • 10. Examples of Cost Structure Components  Direct Material: drafting paper, concrete, nails, lumber, deck screws, paint, turpentine Labor: draw plans, get permit, get materials, construct footings, erect deck, paint deck Other: building permit fee  Indirect Material: pencil, brushes, drop cloth Labor: wife’s support in making lunch Other: use of house to draw plans, shovel, power saw, power drill, electricity, pickup truck, gasoline  Fixed Direct: get permit Indirect: use of house to draw plans, shovel, power saw, power drill, pickup truck, pencil, brushes, drop cloth  Variable Direct: drafting paper, building permit fee, concrete, nails, lumber, deck screws, paint, turpentine, draw plans, get materials, construct footings, erect deck, paint deck Indirect: wife’s support in making lunch, electricity, gasoline Pr oj ect Cost
  • 11. 2- Cost Elements Cost-Based Estimates contain six basic elements: Time, Equipment, Labor, Material, Overhead and Profit. Each item of work on a project can be broken up into tasks that it takes to complete the item of work. Each of these tasks contains the six basic elements that result in the cost for the project. Pr oj ect Cost
  • 12. 2-1.Materials TYPES OF MATERIALS AND RELATED INFORMATION Materials, for purposes of differentiation, can be segregated into four basic categories: 1. raw materials, 2. bulk materials, 3. fabricated materials, and 4. engineered or designed materials. These categories are differentiated on the criteria of the amount of processing required for the material to be useful for its intended purpose. Pr oj ect Cost
  • 13. 2-2.Labor LABOR CLASSIFICATIONS The following definitions were taken or adapted from AACE International’s Cost Engineer’s Notebook [1]. • Direct Labor—The labor involved in the work activities that directly produce the product or complete the installation being built. • Indirect Labor—The labor needed for activities that do not become part of the final installation, product, or goods produced, but that are required to complete the project. • Overhead Labor—The labor portion of costs inherent in the performing of a task (such as engineering, construction, operating, or manufacturing), which cannot be charged to or identified with a part of the work, and, therefore, must be allocated on some arbitrary basis believed to be equitable, or handled as a business expense independent of the volume of production. Pr oj ect Cost
  • 14. 2-3.Equipment, Parts, and Tools ESTABLISHING AN EQUIPMENT VALUATION DATABASE Equipment Value Categories: Replacement Cost New :has the following subcategories:  Reproduction Cost .  Replacement Cost .  Fair Value .  Market Value, also contains several subcategories: 1.Fair Market Value-in-Place . 2.Fair Market Value-in-Exchange. 3.Forced Liquidation Value. 4.Salvage Value/Part-Out Value. 5.Scrap Value. Pr oj ect Cost
  • 15. 2-4.Other Cost Elements Overhead cost : Overhead or indirect expenses are outlays that are incurred in achieving project completion but that do not apply directly to any specific work item. Two kinds of overhead pertain to a contractor’s operations , project overhead and office overhead. Economic cost : Elements of economic costs are Taxation policies and the respective rates , Depreciation, Currency variations and Some aspects of inflation and interest . Engineering cost . Pr oj ect Cost
  • 17. Price Cost Pricing, is adjusting the costs that have been applied for specific project conditions, and commercial terms. Pricing includes adjustments to cost to allow for overhead and profit, to improve cash flow, or otherwise serve the business interests of the party preparing the estimate. Thus, the level and type of pricing adjustments depends on the particular party preparing the estimate. Costing is the process of applying unit costs to the individual quantities of items associated with the estimate. For a detailed estimate, this is usually in the form of labor hours, wage rates, material costs, and perhaps subcontract costs. These costs may come from a variety of sources such as an estimating database (either in-house or commercial), vendor quotes, the procurement department, estimating experience, etc. COST AND PRICING—IS THERE A DIFFERENCE? Pr oj ect Cost
  • 18. 1-Price Analysis Techniques Adequate Price Competition. Historical Prices. Parametric Estimates. Catalogs or Market Prices Engineering Cost Estimate (ECE) Similar Projects. Pr oj ect Cost
  • 19. Summary Sheets The total quantities are transferred from the quantity sheets to summary sheets for pricing purposes. On lump-sum projects, it is standard practice to transfer all quantities of work pertaining to a single construction classification to the same summary sheet before pricing them. As an example, concrete quantities and prices would appear on a concrete summary sheet. Similar summary sheets are prepared for the other work classifications, such as excavation, concrete forms, masonry, and carpentry. On a unit-price job like the highway bridge, each summary sheet lists the work types necessary to accomplish the total quantity of a single bid item and may include several different classifications of work. Pr oj ect Cost
  • 20. Example of Summary Sheets Summary Sheet Job: Highway Bridge Bid Item No. 6: Concrete, abutments Estimator: GAS Cost Code Work Type Quantity Unit Calculations Labor Cost Equipment Cost Material Cost Total Cost Direct Indirect 03150.20 Abutment forms, prefabricate 1,810 sf Labor labor unit cost = $1.96 per sf 1,810 x $1.96 = $3,548 Material Ply form: $1.05 per sf 10% waste 50% salvage 1,810 x $1.05 x 1.10 x 50% = $1,045 lumber: $0.85 per bf 50% salvage 1.44 bf/sf 2 uses 1,810 x $0.85 x 1.44 x 50% = $1,108 $3,548 $1,596 $1,045 $1,108 $5,144 $1,045 $1,108 Total this account $3,548 $1,596 $0 $2,153 $7,297 03157.20 Abutment forms, place 3,620 sf Labor labor unit cost = $2.02 per sf 3,620 x $2.02 = $7,312 Equipment 3 days of 50 ton crane time 3 x 8 x $105 = $2,520 Materials nails, form ties, coating $0.28 per sf 3,620 x $0.28 = $1,014 $7,312 $2,559 $2,520 $1,014 $9,872 $2,520 $1,014 Total this account $7,312 $2,559 $2,520 $1,014 $13,405 03159.20 Abutment forms, strip 3,620 sf Labor labor unit cost = $0.97 per sf 3,620 x $0.97 = $3,511 Equipment 1 day of 50 ton crane time 1 x 8 x $105 = $840 $3,511 $878 $840 $4,389 $840 Total this account $3,511 $878 $840 $0 $5,229 Pr oj ect Cost
  • 21. ON THE RECAP SHEET, THE DIRECT COST OF THE ENTIRE QUANTITY OF EACH BID ITEM IS OBTAINED AS THE SUM OF ITS LABOR, EQUIPMENT, MATERIAL, AND SUBCONTRACT EXPENSES. THE SUM OF ALL SUCH BID-ITEM DIRECT COSTS GIVES THE ESTIMATED TOTAL DIRECT COST TO THIS ADDED THE JOB OVERHEAD, SMALL TOOLS, TAX, MARKUP, AND THE PREMIUM CHARGE FOR THE PERFORMANCE AND PAYMENT SURETY BONDS, GIVING THE TOTAL PRICE HE ENTIRE PROJECT 2-Recap Sheet Pr oj ect Cost
  • 22. Example of Recap Sheet Recap Sheet Bid Date: April 25, 20XX Job: Highway Bridge Estimator: GAS Item Estimated Labor Equipment Material Subcontract Direct Bid No. Bid Item Unit Quantity Cost Cost Cost Cost Cost Total Unit 1 Excavation, unclassified cy 1,667 $3,569 $929 $0 $0 $4,497 $6,386 $3.83 2 Excavation, structural cy 120 $3,731 $555 $0 $0 $4,286 $6,086 $50.72 3 Backfill, compacted cy 340 $3,591 $663 $0 $0 $4,254 $6,041 $17.77 4 Piling, steel lf 2,240 $21,390 $11,176 $72,279 $0 $104,845 $148,872 $66.46 5 Concrete, footings cy 120 $3,661 $685 $12,186 $0 $16,532 $23,475 $195.62 6 Concrete, abutments cy 280 $37,459 $7,104 $30,542 $0 $75,105 $106,644 $380.87 7 Concrete, deck slab, 10 in sy 200 $11,745 $1,790 $8,020 $0 $21,555 $30,606 $153.03 8 Steel, reinforcing lb 90,000 $0 $0 $0 $66,240 $66,240 $94,056 $1.045 9 Steel, structural lb 65,500 $4,220 $1,680 $73,688 $0 $79,588 $113,009 $1.725 10 Bearing plates lb 3,200 $1,943 $420 $3,250 $0 $5,613 $7,970 $2.49 11 Guardrail lf 120 $1,664 $420 $5,826 $0 $7,910 $11,231 $93.59 12 Paint ls job $0 $0 $0 $8,550 $8,550 $12,140 $12,140.39 Totals $92,974 $25,422 $205,790 $74,790 $398,975 $566,516 Job overhead $69,868 $468,844 Small tools (5% of labor) $4,649 $473,492 Factor = $566,516 = 1.4199 Tax 3% $14,205 $487,697 $398,975 Markup 15% $73,155 $560,852 Bonds $5,665 Total Project Bid $566,516 Pr oj ect Cost
  • 23. 3- Unit Price Schedule The unit prices just computed have been obtained on the basis that each bid item includes its own direct cost plus its pro rata share of the project overhead, small tools, tax, markup, and bond. If these unit prices are now entered without change onto the bid form, this is called a balanced bid. For several reasons, a contractor may raise the prices on certain bid items and decrease the prices on others proportionately so that the bid amount for the total job remains unaffected. This is called an unbalanced bid. Pr oj ect Cost
  • 24. Example of Unit Price Schedule Pr oj ect Cost
  • 25. COST ENGINEERING IS OBVIOUSLY A VITAL COMPONENT TO PROJECT SUCCESS. THEY ARE USED NOT ONLY TO ESTABLISH PROJECT BUDGETS, BUT ALSO TO PROVIDE ACCURATE INFORMATION TO SUPPORT SCHEDULING , COST MONITORING, AND PROGRESS MEASUREMENT OF A PROJECT DURING EXECUTION. THE INTEGRATION OF COST ENGINEERING AND COST MANAGEMENT PRINCIPLES USED IN MANAGING THE TOTAL LIFE CYCLE COST INVESTMENT IN STRATEGIC ASSETS. Conclusion Pr oj ect Cost

Notes de l'éditeur

  1. 1
  2. 2
  3. 3
  4. 4