International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 3523
A Review Paper on Quantifay the Different Constraints for Delays in
Infrastructure Construction Project Work and Recommending
Corrective Measures for Same
Avinash Adinath Chougule1, Dr. D.N. Mudgal2, Prof. S.B. Patil3
1PG Student, Civil Engineering Department, Ashokrao Mane Group of Institutions, Vathar, Maharashtra, India,
2Director of Ashokrao Mane Group of Institutions, Vathar, Maharashtra, India,
3PG Co-Ordinator, Civil Engineering Department, Ashokrao Mane Group of Institutions, Vathar,
Maharashtra, India.
---------------------------------------------------------------------***----------------------------------------------------------------------
Abstract - The aim and scope of this project is to identify the
constraints in infrastructure construction project working
environment. If constraints are better understood at the
outset, it is believed that better performance can be assured.
Identifying and removing constraints from bottleneck
activities help to reduce uncertainties in infrastructure
construction processes and increases the transparency of
project management. This study was carried out based on
literature review and a questionnaire survey. Thedataforthis
study will be gathering through a detailed questionnaire
survey. The questionnaire form is forwarded to various
construction industries through email and in personal. The
objectives of the study is to successfully reduce the constraints
which will help to decrease the unnecessary wastage and loss
of both money and time because of inadequate planning.
Key Words: Constraints,Bottleneck activities,Quantifay,
Workflow, Relative Important Index.
1. INTRODUCTION
Constraints becomes an important factors which focuses on
the weakest rings in the chain. Constraints are defined as
anything that limits a system from attaining higher
performance towards its goal. Identifying and removing
constraints from bottleneck activities help to reduce
uncertainties in construction processes and increases the
transparency of project management. Needsandconstraints
in a multi-party working situation bring complications in
project management. Needs arediversified whentheclientis
a large organization such as a public client or a corporate
client. However, constraints in construction projects limit
their achievement of high performance that we areunaware
of the existence of the constraints, or, we tend to put more
emphasis on the project goals. The construction working
environment involves multi-party participation. Needs and
constraints in a multi-party working situation bring
complications in project management. These can further
develop into conflicts and disputes, which bring cost
consequences, direct and indirect, to clientsandcontractors.
The project team members have to meet client’s needs on
one hand and to overcome constraints on the other hand.
With the limited literature for the constraints in the
construction working environment, it is important to
identify the potential constraints in theconstructionproject,
which will help to decrease the unnecessary wastage and
loss of both money and time becauseofinadequateplanning.
Controlling the constraints is thus a pre-condition for high
performance of the project. Constraints is based on the idea
that every system has at least one bottleneck which can be
defined as any kind of situation that impedes the system to
reach high performance level in terms of its purposes. A
constraint is defined as anything that limits an organization
or entity from moving toward or achieving its goal.
Constraints logic forms major portions of the organization's
philosophy of continuous improvement. It is applied to
identify what factors limit an organizationfromachieving its
goals, developing a solution to the problem, and getting the
individuals in the process to invent the requisite changesfor
themselves. It has been realized that reducing and
eliminating critical constraints through better meansoflook
ahead planning are the keys to achieving reliable workflow
and, consequently, increased productivity. Constraint
modeling is an indispensable step in construction planning.
Reliable planning depends on effective identification,
formulation, and satisfaction of key constraints in
production processes. Constraint management helps to
optimize production plans, resolve resource conflicts, and
increase the availability of resource and information
prerequisites. Reducing uncertainties in the workflow
requires new methodologies and tools that can deal with
other types of constraints rather than only the process
constraints. Infrastructure Constructionprojectsarefacinga
greater number of uncertainties and more severe risks,
which could cause much bigger losses than in the past.
Construction projects are subjecttonumerousconstraintsof
various types, including contractual due dates, resource
limitations, and safety, financial,andmanagerial constraints.
Construction projects are characterized by theircomplexity,
uniqueness, and the fact that there are various types of
constraints imposed by stakeholders. If constraints are
better understood at the outset, it is believed that better
performance can be assured.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 3524
2. LITERATURE REVIEW
Title - Key Constraints Analysis with Integrated
Production Scheduler. Author – Chua D. K. H.
Identifying and removing constraints from bottleneck
activities help to reduce uncertainties in construction
processes and increases the transparency of project
management. The present means of look-ahead planning do
poorly in resolving hidden constraints in the supply chain
and information flow. Accordingly, work plans are
vulnerable to the uncertainties that result in flow variation.
It has been realized that reducing and eliminating critical
constraints through bettermeansoflook-aheadplanningare
the keys to achieving reliable workflow and, consequently,
increased productivity. Constraint modeling is an
indispensable step in construction planning. Reliable
planning depends on effective identification, formulation,
and satisfaction of key constraints in production processes.
Constraint management helps to optimize productionplans,
resolve resource conflicts, and increase the availability of
resource and information prerequisites. Most existing
project planning tools are usually based on the critical path
method CPM, which, typically, only one type of constraints
i.e., the PROCESS constraints concerning precedence
relationships of activities, is modeled. The CPM does not
provide the means to deal with many hidden constraints
regarding resource supply and information acquisition.
Without identifying these hidden constraints explicitly, it is
hard to control and reduce the workflow uncertainties that
result in process variability. Making reliable work plans is
important in achieving high productivity and continuous
workflow. Existing CPM-based planningtoolslack theability
to manage the hidden constraints in the supply chain and
information flow with respect to resource and information
availabilities. As a result, the quality of production is
vulnerable to many uncertainties that are difficult to
eliminate or reduce. A new tool, Integrated Production
Scheduler, is introduced to ameliorate the reliability of
construction look-ahead plans bymodelingtheresource and
information constraints in addition to the process
constraints for construction processes.
Title - Quantification of Delay Factors Using the Relative
Importance Index Method for Construction Projects in
Turkey. Author – Gunduz M.
To identify delay factors on construction projects and
analyse these factors with the relative importance index
method. The relativeimportancesofthesedelayfactors were
quantified by the relative importance index method. The
ranking of the factors and groups were demonstrated
according to their importance level on delay. To identify the
delay factors in construction projects because delays are
considered to be a serious problem in the construction
industry. The common results of delays are late completion
of the project, increased cost, disruption of work, loss of
productivity, third-party claims,disputes,andabandonment
or terminationofcontracts.Therefore,delaysinconstruction
projects give rise to dissatisfaction to all parties involved.
Research aimed to (1) identify the delay factors in
construction projects, (2) categorize the delay factors in
construction projects, (3) quantifythe relativeimportanceof
delay factors and to demonstrate the ranking of the factors
and groups according to their importance with respect to
delays, (4) address the factors and groups contributingmost
to delays, and (5) make recommendations in order to
minimize or control delays in construction projects.
Title- Identification of Constraints in infrastructure
Construction Projects to Improve Performance.
Author – Lau E.
Needs and constraints in a multi-party working situation
bring complications in project management. Needs are
diversified when the client is a large organization such as a
public client or a corporate client. However, constraints in
construction projects limit their achievement of high
performance. To identify the constraints in construction
project working environment and apply the theory of
constraints (TOC), which providespractical stepsformaking
organizational decisions in situations in which constraints
exist. If constraints are better understood at the outset, it is
believed that better performance can be assured. Presently
clients’ needs in construction are well discussed, but
constraints have yet to be understood in context. The
constraints in five categories, they are:
(1) Economic constraints,
(2) Legal constraints,
(3) Environmental constraints,
(4) Technical constraints, and
(5) Social constraints.
The impacts of these constraints to the construction project
were studied. Developing awareness to managing and
controlling the constraints in construction working
environment for achieving high performance in the
construction working environment.
Title – Financial related causes contributing to project
delays. Author – Rahman H.
Delay in constructionprojectsisa commonphenomenon and
a costly problem. The issues of financial related delays in
construction projects. It identifies the root causes and
scrutinises the suitable mitigation actions of financial-
related project delays. Four main factors were identified in
the literature, namely late payment, poor cash flow
management, insufficient financial resources and financial
market instability. The result revealed that poor cash flow
management is the most significant factor that leads to a
project’s delay followed by late payment, insufficient
financial resources and financial market instability.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 3525
Contractors instable financial background, client’s poor
financial and business management, difficulties in obtaining
loan from financiers andinflationwereidentifiedasthemost
significant underlying causes. The clients play the most
important role in reducing the impact of financial problems
towards the extent of project’s delay. Several suitable
mitigation actions were suggested by the respondents. The
importance of having more intensive research that give
emphasis on clients achieving a well managed cash flow in
order to obtain a prompt payment practice in the
construction industry. The greater the delay in paymentdue
to a contractor, the greater the cash flow problems, the
greater the extent of delays. The poorer the cash flow
management, the greaterthe cashflowproblems,thegreater
the extent of delays. The greater the shortage of financial
resources, the greater the cash flow problems, the greater
the extent of delays. The greater the instability of financial
market, the greater the cash flow problems, the greater the
extent of delays.
3. SCOPE
Following are the objectives of the proposed dissertation
work.
a) To study and identify the constraints in construction
industry for Residential Building Scheme.
b) To identify the major root causes of financial related
problems that would lead to delays in project.
c) To investigate the opinions of the parties upon the
actions that they undertake to manage the financial
problems.
d) To analyse the causes by using quantitative
techniques.
e) To give suggestive recommendations in order to
reduce the delay problems by considering case study.
4. Methodology
For carrying out the proposed work, following methodology
will be adopted for data collecting and analysis.
a) Collection of preliminary information through
literature review.
b) Collection of data by surveying amongst the
practitioners of building construction. (Engineers,
Contractors, Architects, Builders)
c) Identifying constraints in delay of construction work.
d) Feaslibility study of constraints by using Relative
Importance Index Method.
e) To give results and conclusion from thedata analysed.
5. CONCLUSION
All the papers reviewed above are mainly focuses on to
identify the different constraints for delays in construction
projects. Identifying and removing constraints from
bottleneck activities help to reduce uncertainties in
construction processes and increases the transparency of
project management. Construction projects are subject to
numerous constraints ofvarioustypes,includingcontractual
due dates, resource limitations, and safety, financial, and
managerial constraints. But the previous study has not
covered the effectiveness for particular infra structure
construction project. And it is necessary to quantify the
different constraints for delays in infrastructure
construction project work and also for this, recommending
corrective measures for the same.
6. REFERENCES
[1]Jacob D.B and McClelland W.T.,(2001),“Theory of
Constraints Project Management” Manual of the Goldratt
Institute, pp - 1-12.
[2]Lorterapong P. and Ussavadilokrit M.,(2013),
“Construction Scheduling Using the Constraint Satisfaction
Problem Method”Journal of Construction Engineering and
Management, Vol 139, No. 4, pp - 414-422.
[3]Lau E. and Kong J. J., (2006), “Identification of Constraints
in Construction Projects to Improve Performance” The Joint
International Conference on Construction, Culture,
Innovation and Management, pp - 655-663.
[4]MirzaeiMandMabinV.J.,(2014),“ExploringConstraintsin
projects: A Construction Industry case study” Proceedings of
the Joint Conference of New Zealand Statistical Association
and Operations ResearchSocietyofNewZealand2014,Paper
No. 24.
[5]MuhweziL. , Acai J. and Otim G.,(2014), “An Assessmentof
the Factors Causing Delays on BuildingConstructionProjects
in Uganda” International JournalofConstructionEngineering
and Management, Vol 3,No. 1,pp - 13-23.
[6]Rahman H. A, Takim R and Min W. S.,(2009), “Financial
Related Causes Contributing to Project Delays” Journal of
Retail & Leisure Property, Vol 8,No.3, pp - 225–238.
[7]Simsit Z. T. ,Gunay N. S. and Vayvay O.,(2014), “Theory of
Constraints: A Literature Review” Proceedings of
10thInternational Strategic Management Conference, pp -
930-936.
[8]Wang J. ,Shou W. And Wang X.,(2015), “A Framework of
Total Constraint Management for Improving Work Flow in
Liquefied Natural Gas Construction” 31st Annual ARCOM
Conference, Lincoln, UK, pp - 803-812.
[9]Xiang P; Zhou J; Zhou X; and Ye K.,(2012), “Construction
Project Risk Management Based on the View of Asymmetric
Information” Journal of Construction Engineering and
Management, Vol 138, No.11, pp - 1303-1311.

Contenu connexe

Tendances

Rework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsRework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsBob Prieto
 
Gus Caporusso6 12 Resume
Gus Caporusso6 12 ResumeGus Caporusso6 12 Resume
Gus Caporusso6 12 Resumeguscaporusso
 
Engineering and construction project startup
Engineering and construction project startupEngineering and construction project startup
Engineering and construction project startupBob Prieto
 
pdf 25 NCON Brochure 1.19.2016
pdf 25 NCON Brochure 1.19.2016pdf 25 NCON Brochure 1.19.2016
pdf 25 NCON Brochure 1.19.2016Chris Nash
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET Journal
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 Pang Khai Shuen
 
Bryan.moser
Bryan.moserBryan.moser
Bryan.moserNASAPMC
 
Rethinking Interface Management
Rethinking Interface ManagementRethinking Interface Management
Rethinking Interface ManagementBob Prieto
 
design bid build or Traditional contract shortcomings and alternative method,...
design bid build or Traditional contract shortcomings and alternative method,...design bid build or Traditional contract shortcomings and alternative method,...
design bid build or Traditional contract shortcomings and alternative method,...Tehmas Saeed
 
IRJET- Skills and Competencies Perceived of an Effective Construction Project...
IRJET- Skills and Competencies Perceived of an Effective Construction Project...IRJET- Skills and Competencies Perceived of an Effective Construction Project...
IRJET- Skills and Competencies Perceived of an Effective Construction Project...IRJET Journal
 
- OKAN EKER - MBA - PROJECT
- OKAN EKER - MBA - PROJECT- OKAN EKER - MBA - PROJECT
- OKAN EKER - MBA - PROJECTOkan Eker
 
Attributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a reviewAttributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a reviewA Makwana
 
CE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_ReportCE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_ReportMuhammad Daniyal
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 Pang Khai Shuen
 
PMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_Management
PMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_ManagementPMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_Management
PMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_ManagementMurari Thayi, PgMP, PMP
 
PP1 - Presentation Slides
PP1 - Presentation Slides PP1 - Presentation Slides
PP1 - Presentation Slides Pang Khai Shuen
 
Improving infrastructure project success
Improving infrastructure project successImproving infrastructure project success
Improving infrastructure project successBob Prieto
 

Tendances (20)

Rework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsRework in Engineering & Construction Projects
Rework in Engineering & Construction Projects
 
resume 10.26.16 final
resume 10.26.16 finalresume 10.26.16 final
resume 10.26.16 final
 
Gus Caporusso6 12 Resume
Gus Caporusso6 12 ResumeGus Caporusso6 12 Resume
Gus Caporusso6 12 Resume
 
Engineering and construction project startup
Engineering and construction project startupEngineering and construction project startup
Engineering and construction project startup
 
Planning
PlanningPlanning
Planning
 
Chapter 9
Chapter 9Chapter 9
Chapter 9
 
pdf 25 NCON Brochure 1.19.2016
pdf 25 NCON Brochure 1.19.2016pdf 25 NCON Brochure 1.19.2016
pdf 25 NCON Brochure 1.19.2016
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
Bryan.moser
Bryan.moserBryan.moser
Bryan.moser
 
Rethinking Interface Management
Rethinking Interface ManagementRethinking Interface Management
Rethinking Interface Management
 
design bid build or Traditional contract shortcomings and alternative method,...
design bid build or Traditional contract shortcomings and alternative method,...design bid build or Traditional contract shortcomings and alternative method,...
design bid build or Traditional contract shortcomings and alternative method,...
 
IRJET- Skills and Competencies Perceived of an Effective Construction Project...
IRJET- Skills and Competencies Perceived of an Effective Construction Project...IRJET- Skills and Competencies Perceived of an Effective Construction Project...
IRJET- Skills and Competencies Perceived of an Effective Construction Project...
 
- OKAN EKER - MBA - PROJECT
- OKAN EKER - MBA - PROJECT- OKAN EKER - MBA - PROJECT
- OKAN EKER - MBA - PROJECT
 
Attributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a reviewAttributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a review
 
CE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_ReportCE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_Report
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
PMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_Management
PMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_ManagementPMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_Management
PMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_Management
 
PP1 - Presentation Slides
PP1 - Presentation Slides PP1 - Presentation Slides
PP1 - Presentation Slides
 
Improving infrastructure project success
Improving infrastructure project successImproving infrastructure project success
Improving infrastructure project success
 

Similaire à IRJET- A Review Paper on Quantifay the Different Constraints for Delays in Infrastructure Construction Project Work and Recommending Corrective Measures for Same

To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...Harish Rajmane
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewIRJET Journal
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET Journal
 
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET Journal
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...IRJET Journal
 
Impact of Sustainable Construction on Business Decisions
Impact of Sustainable Construction on Business DecisionsImpact of Sustainable Construction on Business Decisions
Impact of Sustainable Construction on Business DecisionsIRJET Journal
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project managementIRJET Journal
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET Journal
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET Journal
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET Journal
 
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
IRJET- 	  Review: Factors Affecting Scheduling of Multiple ProjectsIRJET- 	  Review: Factors Affecting Scheduling of Multiple Projects
IRJET- Review: Factors Affecting Scheduling of Multiple ProjectsIRJET Journal
 
Building Better_Maximizing Efficiency with Construction Management Software S...
Building Better_Maximizing Efficiency with Construction Management Software S...Building Better_Maximizing Efficiency with Construction Management Software S...
Building Better_Maximizing Efficiency with Construction Management Software S...iFieldsmart Technologies
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IRJET Journal
 
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET Journal
 
Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...IRJET Journal
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET Journal
 
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...IRJET Journal
 

Similaire à IRJET- A Review Paper on Quantifay the Different Constraints for Delays in Infrastructure Construction Project Work and Recommending Corrective Measures for Same (20)

To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
 
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
 
Impact of Sustainable Construction on Business Decisions
Impact of Sustainable Construction on Business DecisionsImpact of Sustainable Construction on Business Decisions
Impact of Sustainable Construction on Business Decisions
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
 
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
IRJET- 	  Review: Factors Affecting Scheduling of Multiple ProjectsIRJET- 	  Review: Factors Affecting Scheduling of Multiple Projects
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
 
Building Better_Maximizing Efficiency with Construction Management Software S...
Building Better_Maximizing Efficiency with Construction Management Software S...Building Better_Maximizing Efficiency with Construction Management Software S...
Building Better_Maximizing Efficiency with Construction Management Software S...
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
 
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction Project
 
Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
 
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
 
Proposal .pdf
Proposal .pdfProposal .pdf
Proposal .pdf
 

Plus de IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

Plus de IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Dernier

Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Christo Ananth
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 

Dernier (20)

Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 

IRJET- A Review Paper on Quantifay the Different Constraints for Delays in Infrastructure Construction Project Work and Recommending Corrective Measures for Same

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 3523 A Review Paper on Quantifay the Different Constraints for Delays in Infrastructure Construction Project Work and Recommending Corrective Measures for Same Avinash Adinath Chougule1, Dr. D.N. Mudgal2, Prof. S.B. Patil3 1PG Student, Civil Engineering Department, Ashokrao Mane Group of Institutions, Vathar, Maharashtra, India, 2Director of Ashokrao Mane Group of Institutions, Vathar, Maharashtra, India, 3PG Co-Ordinator, Civil Engineering Department, Ashokrao Mane Group of Institutions, Vathar, Maharashtra, India. ---------------------------------------------------------------------***---------------------------------------------------------------------- Abstract - The aim and scope of this project is to identify the constraints in infrastructure construction project working environment. If constraints are better understood at the outset, it is believed that better performance can be assured. Identifying and removing constraints from bottleneck activities help to reduce uncertainties in infrastructure construction processes and increases the transparency of project management. This study was carried out based on literature review and a questionnaire survey. Thedataforthis study will be gathering through a detailed questionnaire survey. The questionnaire form is forwarded to various construction industries through email and in personal. The objectives of the study is to successfully reduce the constraints which will help to decrease the unnecessary wastage and loss of both money and time because of inadequate planning. Key Words: Constraints,Bottleneck activities,Quantifay, Workflow, Relative Important Index. 1. INTRODUCTION Constraints becomes an important factors which focuses on the weakest rings in the chain. Constraints are defined as anything that limits a system from attaining higher performance towards its goal. Identifying and removing constraints from bottleneck activities help to reduce uncertainties in construction processes and increases the transparency of project management. Needsandconstraints in a multi-party working situation bring complications in project management. Needs arediversified whentheclientis a large organization such as a public client or a corporate client. However, constraints in construction projects limit their achievement of high performance that we areunaware of the existence of the constraints, or, we tend to put more emphasis on the project goals. The construction working environment involves multi-party participation. Needs and constraints in a multi-party working situation bring complications in project management. These can further develop into conflicts and disputes, which bring cost consequences, direct and indirect, to clientsandcontractors. The project team members have to meet client’s needs on one hand and to overcome constraints on the other hand. With the limited literature for the constraints in the construction working environment, it is important to identify the potential constraints in theconstructionproject, which will help to decrease the unnecessary wastage and loss of both money and time becauseofinadequateplanning. Controlling the constraints is thus a pre-condition for high performance of the project. Constraints is based on the idea that every system has at least one bottleneck which can be defined as any kind of situation that impedes the system to reach high performance level in terms of its purposes. A constraint is defined as anything that limits an organization or entity from moving toward or achieving its goal. Constraints logic forms major portions of the organization's philosophy of continuous improvement. It is applied to identify what factors limit an organizationfromachieving its goals, developing a solution to the problem, and getting the individuals in the process to invent the requisite changesfor themselves. It has been realized that reducing and eliminating critical constraints through better meansoflook ahead planning are the keys to achieving reliable workflow and, consequently, increased productivity. Constraint modeling is an indispensable step in construction planning. Reliable planning depends on effective identification, formulation, and satisfaction of key constraints in production processes. Constraint management helps to optimize production plans, resolve resource conflicts, and increase the availability of resource and information prerequisites. Reducing uncertainties in the workflow requires new methodologies and tools that can deal with other types of constraints rather than only the process constraints. Infrastructure Constructionprojectsarefacinga greater number of uncertainties and more severe risks, which could cause much bigger losses than in the past. Construction projects are subjecttonumerousconstraintsof various types, including contractual due dates, resource limitations, and safety, financial,andmanagerial constraints. Construction projects are characterized by theircomplexity, uniqueness, and the fact that there are various types of constraints imposed by stakeholders. If constraints are better understood at the outset, it is believed that better performance can be assured.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 3524 2. LITERATURE REVIEW Title - Key Constraints Analysis with Integrated Production Scheduler. Author – Chua D. K. H. Identifying and removing constraints from bottleneck activities help to reduce uncertainties in construction processes and increases the transparency of project management. The present means of look-ahead planning do poorly in resolving hidden constraints in the supply chain and information flow. Accordingly, work plans are vulnerable to the uncertainties that result in flow variation. It has been realized that reducing and eliminating critical constraints through bettermeansoflook-aheadplanningare the keys to achieving reliable workflow and, consequently, increased productivity. Constraint modeling is an indispensable step in construction planning. Reliable planning depends on effective identification, formulation, and satisfaction of key constraints in production processes. Constraint management helps to optimize productionplans, resolve resource conflicts, and increase the availability of resource and information prerequisites. Most existing project planning tools are usually based on the critical path method CPM, which, typically, only one type of constraints i.e., the PROCESS constraints concerning precedence relationships of activities, is modeled. The CPM does not provide the means to deal with many hidden constraints regarding resource supply and information acquisition. Without identifying these hidden constraints explicitly, it is hard to control and reduce the workflow uncertainties that result in process variability. Making reliable work plans is important in achieving high productivity and continuous workflow. Existing CPM-based planningtoolslack theability to manage the hidden constraints in the supply chain and information flow with respect to resource and information availabilities. As a result, the quality of production is vulnerable to many uncertainties that are difficult to eliminate or reduce. A new tool, Integrated Production Scheduler, is introduced to ameliorate the reliability of construction look-ahead plans bymodelingtheresource and information constraints in addition to the process constraints for construction processes. Title - Quantification of Delay Factors Using the Relative Importance Index Method for Construction Projects in Turkey. Author – Gunduz M. To identify delay factors on construction projects and analyse these factors with the relative importance index method. The relativeimportancesofthesedelayfactors were quantified by the relative importance index method. The ranking of the factors and groups were demonstrated according to their importance level on delay. To identify the delay factors in construction projects because delays are considered to be a serious problem in the construction industry. The common results of delays are late completion of the project, increased cost, disruption of work, loss of productivity, third-party claims,disputes,andabandonment or terminationofcontracts.Therefore,delaysinconstruction projects give rise to dissatisfaction to all parties involved. Research aimed to (1) identify the delay factors in construction projects, (2) categorize the delay factors in construction projects, (3) quantifythe relativeimportanceof delay factors and to demonstrate the ranking of the factors and groups according to their importance with respect to delays, (4) address the factors and groups contributingmost to delays, and (5) make recommendations in order to minimize or control delays in construction projects. Title- Identification of Constraints in infrastructure Construction Projects to Improve Performance. Author – Lau E. Needs and constraints in a multi-party working situation bring complications in project management. Needs are diversified when the client is a large organization such as a public client or a corporate client. However, constraints in construction projects limit their achievement of high performance. To identify the constraints in construction project working environment and apply the theory of constraints (TOC), which providespractical stepsformaking organizational decisions in situations in which constraints exist. If constraints are better understood at the outset, it is believed that better performance can be assured. Presently clients’ needs in construction are well discussed, but constraints have yet to be understood in context. The constraints in five categories, they are: (1) Economic constraints, (2) Legal constraints, (3) Environmental constraints, (4) Technical constraints, and (5) Social constraints. The impacts of these constraints to the construction project were studied. Developing awareness to managing and controlling the constraints in construction working environment for achieving high performance in the construction working environment. Title – Financial related causes contributing to project delays. Author – Rahman H. Delay in constructionprojectsisa commonphenomenon and a costly problem. The issues of financial related delays in construction projects. It identifies the root causes and scrutinises the suitable mitigation actions of financial- related project delays. Four main factors were identified in the literature, namely late payment, poor cash flow management, insufficient financial resources and financial market instability. The result revealed that poor cash flow management is the most significant factor that leads to a project’s delay followed by late payment, insufficient financial resources and financial market instability.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 3525 Contractors instable financial background, client’s poor financial and business management, difficulties in obtaining loan from financiers andinflationwereidentifiedasthemost significant underlying causes. The clients play the most important role in reducing the impact of financial problems towards the extent of project’s delay. Several suitable mitigation actions were suggested by the respondents. The importance of having more intensive research that give emphasis on clients achieving a well managed cash flow in order to obtain a prompt payment practice in the construction industry. The greater the delay in paymentdue to a contractor, the greater the cash flow problems, the greater the extent of delays. The poorer the cash flow management, the greaterthe cashflowproblems,thegreater the extent of delays. The greater the shortage of financial resources, the greater the cash flow problems, the greater the extent of delays. The greater the instability of financial market, the greater the cash flow problems, the greater the extent of delays. 3. SCOPE Following are the objectives of the proposed dissertation work. a) To study and identify the constraints in construction industry for Residential Building Scheme. b) To identify the major root causes of financial related problems that would lead to delays in project. c) To investigate the opinions of the parties upon the actions that they undertake to manage the financial problems. d) To analyse the causes by using quantitative techniques. e) To give suggestive recommendations in order to reduce the delay problems by considering case study. 4. Methodology For carrying out the proposed work, following methodology will be adopted for data collecting and analysis. a) Collection of preliminary information through literature review. b) Collection of data by surveying amongst the practitioners of building construction. (Engineers, Contractors, Architects, Builders) c) Identifying constraints in delay of construction work. d) Feaslibility study of constraints by using Relative Importance Index Method. e) To give results and conclusion from thedata analysed. 5. CONCLUSION All the papers reviewed above are mainly focuses on to identify the different constraints for delays in construction projects. Identifying and removing constraints from bottleneck activities help to reduce uncertainties in construction processes and increases the transparency of project management. Construction projects are subject to numerous constraints ofvarioustypes,includingcontractual due dates, resource limitations, and safety, financial, and managerial constraints. But the previous study has not covered the effectiveness for particular infra structure construction project. And it is necessary to quantify the different constraints for delays in infrastructure construction project work and also for this, recommending corrective measures for the same. 6. REFERENCES [1]Jacob D.B and McClelland W.T.,(2001),“Theory of Constraints Project Management” Manual of the Goldratt Institute, pp - 1-12. [2]Lorterapong P. and Ussavadilokrit M.,(2013), “Construction Scheduling Using the Constraint Satisfaction Problem Method”Journal of Construction Engineering and Management, Vol 139, No. 4, pp - 414-422. [3]Lau E. and Kong J. J., (2006), “Identification of Constraints in Construction Projects to Improve Performance” The Joint International Conference on Construction, Culture, Innovation and Management, pp - 655-663. [4]MirzaeiMandMabinV.J.,(2014),“ExploringConstraintsin projects: A Construction Industry case study” Proceedings of the Joint Conference of New Zealand Statistical Association and Operations ResearchSocietyofNewZealand2014,Paper No. 24. [5]MuhweziL. , Acai J. and Otim G.,(2014), “An Assessmentof the Factors Causing Delays on BuildingConstructionProjects in Uganda” International JournalofConstructionEngineering and Management, Vol 3,No. 1,pp - 13-23. [6]Rahman H. A, Takim R and Min W. S.,(2009), “Financial Related Causes Contributing to Project Delays” Journal of Retail & Leisure Property, Vol 8,No.3, pp - 225–238. [7]Simsit Z. T. ,Gunay N. S. and Vayvay O.,(2014), “Theory of Constraints: A Literature Review” Proceedings of 10thInternational Strategic Management Conference, pp - 930-936. [8]Wang J. ,Shou W. And Wang X.,(2015), “A Framework of Total Constraint Management for Improving Work Flow in Liquefied Natural Gas Construction” 31st Annual ARCOM Conference, Lincoln, UK, pp - 803-812. [9]Xiang P; Zhou J; Zhou X; and Ye K.,(2012), “Construction Project Risk Management Based on the View of Asymmetric Information” Journal of Construction Engineering and Management, Vol 138, No.11, pp - 1303-1311.