Construction Materials
Management
(COTM 5202)
5. Inventory Control
by
Tadesse Ayalew
Lecturer , EiABC, AAU
BSc. IN CONSTRUCTION TECH. & MANAGEMENT, EiABC,
MARCH 2014
1
5. 1 Inventory cost Components
 The general objective of inventory control is to minimize the
total cost of keeping the inventory while making tradeoffs
among the major categories of costs:
(A) purchase costs,
(B) order cost,
(C) holding costs, and
(D) unavailable cost.
 These cost categories are interrelated since reducing cost in
one category may increase cost in others.
 The costs in all categories generally are subject to
considerable uncertainty.
A) Purchase Costs
 The purchase cost of an item is the unit purchase price
from an external source including transportation and
freight costs.
 For construction materials, it is common to receive
discounts for bulk purchases, so the unit purchase cost
declines as quantity increases.
 Because of this, organizations may consolidate small orders
from a number of different projects to capture such bulk
discounts, in some cases; this is a basic saving to be
derived from a central purchasing office
B) Order Cost
 The order cost reflects the administrative expense of
issuing a purchase order to an outside supplier.
 Order costs are usually only a small portion of total costs
for material management in construction projects,
although ordering may require substantial time.
C) Holding Costs
 The holding costs or carrying costs are primarily the
result of capital costs, handling, storage, obsolescence,
shrinkage and deterioration.
 Capital cost results from the opportunity cost or
financial expense of capital tied up in inventory.
 Handling and storage represent the movement and
protection charges incurred for materials.
C) Holding Costs (Cont….)
 Storage costs also include the disruption caused to other
project activities by large inventories of materials that
get in the way. Obsolescence is the risk that an item will
lose value because of changes in specifications.
 Shrinkage is the decrease in inventory over time due to
theft or loss. Deterioration reflects a change in material
quality due to age or environmental degradation.
D) Unavailability Cost
 The unavailability cost is incurred when a desired
material is not available at the desired time.
 In manufacturing industries, this cost is often called the
stock out or depletion cost.
 Shortages may delay work, thereby wasting labor
resources or delaying the completion of the entire
project.
5.2 Tradeoffs of Costs in Materials Management.
 To illustrate the type of trade-offs encountered in materials
management, suppose that a particular item is to be ordered
for a project. The amount of time required for processing the
order and shipping the item is uncertain.
 Consequently, the project manager must decide how much
lead time to provide in ordering the item. Ordering early and
thereby providing a long lead time will increase the chance
that the item is available when needed but it increases the
cost of inventory and chance of spoilage on site.
5.3 Inventory Model
 There are two types of inventory models
 Deterministic inventory Model (Constant Demand)
 Inventory Model with Probabilistic Demand
The objectives of this model is to determine an optimum
order quantity (EOQ) denoted by Q* such that total
inventory cost is minimized.
TVC= Ordering cost + carrying (holding cost)
Ch
Q
Co
Q
D
2
+TVC =
5.3.1 Deterministic inventory models
Economic order quantity (EOQ) model with constant rate of demand
Minimizing CostsMinimizing Costs
Objective is to minimize total costsObjective is to minimize total costs
Table 11.5Table 11.5
AnnualcostAnnualcost
Order quantityOrder quantity
Curve for totalCurve for total
cost of holdingcost of holding
and setupand setup
Holding costHolding cost
curvecurve
Setup (or order)Setup (or order)
cost curvecost curve
MinimumMinimum
total costtotal cost
OptimalOptimal
orderorder
quantityquantity
Economic order quantity (EOQ) model with
constant rate of demand( Cont…)
 Since for maximum or minimum value of TVC its first
derivatives should be zero
0
2
1
2
=+− ChCo
Q
D
Q* =
Ch
DCo2 = Economic order quantity (EOQ)
 Optimal length of the inventory replenishment cycles time (t*),
optimal inventory between successive orders.
Q*= Annual demand * Reorder cycle time = D*t
 Optimal No of order quantity to be placed in the given
time period (which is assumed to be one year)
Important formulas
D
Q *
Ch
DCo
D
2
*
1t* = =
=
*Q
D
Ch
DCo2
1
N*= D * =
Co
DCh
2
Important formulas (cont…)
 Optimal (minimum) total variable inventory cost (TVC*)
TVC = Ch
Q
Co
Q
D
2
+
CoD.
Ch
DCo2
1
Ch
DCoCh 2
2= * +
Optimal total inventory cost is the sum of variable costs
and fixed costs, so
TC = D.C+TVC*
DCoCh2=
Economic order quantity (EOQ) model
with ware house space constraint
Steps
Step1: for λ=1, compute EOQ for each item separately
by using the formula
Where fi = the storage space required per unit item i and λ
is a non negative Lagrange multiplier
Q*=
fiChi
DiCoi
λ2
2
+
; i =1, 2,
3….n
Step 2: if Qi* (i=1, 2, 3…n) is satisfied the condition,
(Total warehouse space available) then
stops, otherwise go to step three,
Step 3: Increase the value of λ if value of left hand side of
∑fiQi = W is More than available storage space
other wise decrease the value of λ.
 Continue iteration until the condition is satisfied
WfiQi =Σ
Economic order quantity (EOQ) model
with ware house space constraint
(cont…)
Economic order quantity (EOQ) model with
quantity discount
 EOQ model with one price break
 Suppose the following price discount schedule is quoted by
the suppliers in which a price (quantity discount) occurs at
b1 this means,
Quantity Price per unit
0<Q1<b1 C1
b1<Q2 C2
Economic order quantity (EOQ) model with
quantity discount (cont…)
 The optimal purchase quantity can be determined by the procedure
given below
 Step1: consider the lowest price (i.e. C2 ) and determine
Q2* by the basic EOQ formula
Q2*=
 If Q2* lies with in the prescribed range b1<Q2*, then Q2*
is EOQ i.e. Q*= Q2*
rC
DCo
*
2
2
Economic order quantity (EOQ) model with
quantity discount (cont…)
 And the optimal cost TC* associated with Q2* is calculated as
follows:
TC* (=TC2*) = D.C2+
Step2: If Q2* is not equal to or more than b1, then Calculate Q1*
with C1 and corresponding total cost at Q1*. Compare
TC(b1) and TC (Q1*), If TC(b1)>TC(Q1*),then EOQ is
Q*= Q1*.Otherwise Q*= b1 is the required EOQ
)*(
2
2
1
1
rC
b
Co
b
D
+
Economic order quantity (EOQ) model with
quantity discount (cont…)
EOQ model with two price break
 Suppose the following price discount schedule is quoted
by the suppliers in which a price (quantity discount)
occurs at b1 this means,
Quantity Price per unit
0<Q1< b1 C1
b1<Q2< b2 C2
b2< Q3 C3
Economic order quantity (EOQ) model with
quantity discount (cont…)
Notice that C3< C2< C1
The optimal purchase quantity can be determined by the procedure
given below
Step1: a) Consider the lowest price (i.e. C3) and determine Q3* by
the basic EOQ formula
b) If Q3* > b2 , then EOQ (Q*) = Q3* and the optimal cost
TC (Q3*) is the cost associated with Q3*
c) If Q3*< b2, then go to step 2
Economic order quantity (EOQ) model with quantity
discount (cont…)
Step2: a) Calculate Q2* is based on price C2.
b) Compare Q2* with b1and if b1< Q2* < b2 then compare TC (Q2*) and TC
(b2). If TC (Q2*)> TC (b2), then EOQ= b2. Otherwise EOQ = (Q2*)
c) If Q3*< b1as well as b2then go to step three.
Step3: Calculate Q1* is based on price C1and compare, TC (b1), TC (b2) and
TC (Q1*) to find EOQ the quantity with lowest cost will naturally
be the required EOQ
An EOQ ExampleAn EOQ Example
Determine optimal number of units to orderDetermine optimal number of units to order
D = 1,000 unitsD = 1,000 units
Co = $10 per orderCo = $10 per order
H = $.50 per unit per yearH = $.50 per unit per year
Q* =Q* =
2DCo2DCo
HH
Q* =Q* =
2(1,000)(10)2(1,000)(10)
0.500.50
= 40,000 = 200 units= 40,000 = 200 units
An EOQ ExampleAn EOQ Example
Determine optimal number of needles to orderDetermine optimal number of needles to order
D = 1,000 unitsD = 1,000 units Q*Q* = 200 units= 200 units
Co = $10 per orderCo = $10 per order
H = $.50 per unit per yearH = $.50 per unit per year
= N = == N = =
ExpectedExpected
number ofnumber of
ordersorders
DemandDemand
Order quantityOrder quantity
DD
Q*Q*
N = = 5 orders per yearN = = 5 orders per year
1,0001,000
200200
An EOQ ExampleAn EOQ Example
Determine optimal number of needles to orderDetermine optimal number of needles to order
D = 1,000 unitsD = 1,000 units Q*Q* = 200 units= 200 units
S = $10 per orderS = $10 per order NN = 5 orders per year= 5 orders per year
H = $.50 per unit per yearH = $.50 per unit per year
= T == T =
Expected timeExpected time
between ordersbetween orders
Number of workingNumber of working
days per yeardays per year
NN
T = = 50 days between ordersT = = 50 days between orders250250
55
An EOQ ExampleAn EOQ Example
Determine optimal number of needles to orderDetermine optimal number of needles to order
D = 1,000 unitsD = 1,000 units Q*Q* = 200 units= 200 units
S = $10 per orderS = $10 per order NN = 5 orders per year= 5 orders per year
H = $.50 per unit per yearH = $.50 per unit per year TT = 50 days= 50 days
Total annual cost = Setup cost + Holding costTotal annual cost = Setup cost + Holding cost
TC = S + HTC = S + H
DD
QQ
QQ
22
TC = ($10) + ($.50)TC = ($10) + ($.50)
1,0001,000
200200
200200
22
TC = (5)($10) + (100)($.50) = $50 + $50 = $100TC = (5)($10) + (100)($.50) = $50 + $50 = $100
Reorder PointsReorder Points
 EOQ answers the “how much” questionEOQ answers the “how much” question
 The reorder point (ROP) tells when to orderThe reorder point (ROP) tells when to order
ROP =ROP =
Lead time for a newLead time for a new
order in daysorder in days
DemandDemand
per dayper day
= d x L= d x L
d =d =
DD
Number of working days in a yearNumber of working days in a year
Reorder Point CurveReorder Point Curve
Q*Q*
ROPROP
(units)(units)
Inventorylevel(units)Inventorylevel(units)
Time (days)Time (days)
Figure 12.5Figure 12.5 Lead time = LLead time = L
Slope = units/day = dSlope = units/day = d
Reorder Point ExampleReorder Point Example
Demand = 8,000 DVDs per yearDemand = 8,000 DVDs per year
250 working day year250 working day year
Lead time for orders is 3 working daysLead time for orders is 3 working days
ROP = d x LROP = d x L
d =d =
DD
Number of working days in a yearNumber of working days in a year
= 8,000/250 = 32 units= 8,000/250 = 32 units
= 32 units per day x 3 days = 96 units= 32 units per day x 3 days = 96 units
Quantity Discount ModelsQuantity Discount Models
DiscountDiscount
NumberNumber Discount QuantityDiscount Quantity Discount (%)Discount (%)
DiscountDiscount
Price (P)Price (P)
11 00 toto 999999 no discountno discount $5.00$5.00
22 1,0001,000 toto 1,9991,999 44 $4.80$4.80
33 2,0002,000 and overand over 55 $4.75$4.75
Table 12.2Table 12.2
A typical quantity discount scheduleA typical quantity discount schedule
Quantity Discount ExampleQuantity Discount Example
Calculate Q* for every discountCalculate Q* for every discount
Q* =
2DS
IP
QQ11* = = 700 cars order* = = 700 cars order
2(5,000)(49)2(5,000)(49)
(.2)(5.00)(.2)(5.00)
QQ22* = = 714 cars order* = = 714 cars order
2(5,000)(49)2(5,000)(49)
(.2)(4.80)(.2)(4.80)
QQ33* = = 718 cars order* = = 718 cars order
2(5,000)(49)2(5,000)(49)
(.2)(4.75)(.2)(4.75)
1,000 — adjusted1,000 — adjusted
2,000 — adjusted2,000 — adjusted
Quantity Discount ExampleQuantity Discount Example
DiscountDiscount
NumberNumber
UnitUnit
PricePrice
OrderOrder
QuantityQuantity
AnnualAnnual
ProductProduct
CostCost
AnnualAnnual
OrderingOrdering
CostCost
AnnualAnnual
HoldingHolding
CostCost TotalTotal
11 $5.00$5.00 700700 $25,000$25,000 $350$350 $350$350 $25,700$25,700
22 $4.80$4.80 1,0001,000 $24,000$24,000 $245$245 $480$480 $24,725$24,725
33 $4.75$4.75 2,0002,000 $23.750$23.750 $122.50$122.50 $950$950 $24,822.50$24,822.50
Table 12.3Table 12.3
Choose the price and quantity that gives the lowest totalChoose the price and quantity that gives the lowest total
costcost
Buy 1,000 units at $4.80 per unitBuy 1,000 units at $4.80 per unit
Try the following
Exercises
Exercise 1
The production department of a company requires
3600kg of raw materials for manufacturing of particular
item per year. It has been estimated that cost of
placing an order is 36 birr and the cost of carrying
inventories is 25% of the investment in the inventories.
The price is 10 birr per kg. The purchase manager
whishes to determine an ordering policy for raw
materials.
Exercise 2
A small shop produces three machines part I,II and III in
lots. The shop has only 650m2
of storage space the
appropriate data for three items are given in the following
table
Item I II III
Demand (unit per year) 5000 2000 10000
Procurement cost per order 100 200 75
Cost per unit 10 15 5
Floor space requirements 0.7 0.8 0.4
The shop uses an inventory charge of 20% of average
inventories valuation per year. If no stock out is allowed,
determine the optimal lot size for each item under a given
storage constraints.
Exercise 3
A shopkeeper estimates annual requirement of an item
as 2000 units. He buys from supplier 10 per item and
the cost of ordering is 50 birr each time. If the stock
holding costs are 25% per year of stock value how
frequently should replenish his stock? Further, suppose
the supplier offer 10% discount on order between 400
and 699 item, a 20% discount on order exceeding or
equal to 700 can the shopkeeper reduce his cost by
taking advantages from either of the discount ?
Thank You

Contenu connexe

Tendances

Material management in construction jeemi
Material management in construction jeemiMaterial management in construction jeemi
Material management in construction jeemiArfan Afzal
 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
Material Management: Inventory Control & QC Techniques
Material Management: Inventory Control & QC TechniquesMaterial Management: Inventory Control & QC Techniques
Material Management: Inventory Control & QC TechniquesS.Vijaya Bhaskar
 
APPLICATION OF ABC ANALYSIS FOR MATERIAL MANAGEMENT OF RESIDENTIAL BUILDING
APPLICATION OF ABC ANALYSIS FOR MATERIAL MANAGEMENT OF RESIDENTIAL BUILDINGAPPLICATION OF ABC ANALYSIS FOR MATERIAL MANAGEMENT OF RESIDENTIAL BUILDING
APPLICATION OF ABC ANALYSIS FOR MATERIAL MANAGEMENT OF RESIDENTIAL BUILDINGSagar Kaptan
 
Types of resources in civil engineering field
Types of resources in civil engineering fieldTypes of resources in civil engineering field
Types of resources in civil engineering fieldswetha110
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in constructionMahSobeh
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineeringKailash Chander
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contractssrinivas2036
 
What is Manpower Planning Organizing Staffing Important objectives of staffin...
What is Manpower Planning Organizing Staffing Important objectives of staffin...What is Manpower Planning Organizing Staffing Important objectives of staffin...
What is Manpower Planning Organizing Staffing Important objectives of staffin...SANJEEV Wazir
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.NAVNEET KUMAR JHA
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimationDhavalMithaiwala
 

Tendances (20)

Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
Material management in construction jeemi
Material management in construction jeemiMaterial management in construction jeemi
Material management in construction jeemi
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Material Management: Inventory Control & QC Techniques
Material Management: Inventory Control & QC TechniquesMaterial Management: Inventory Control & QC Techniques
Material Management: Inventory Control & QC Techniques
 
APPLICATION OF ABC ANALYSIS FOR MATERIAL MANAGEMENT OF RESIDENTIAL BUILDING
APPLICATION OF ABC ANALYSIS FOR MATERIAL MANAGEMENT OF RESIDENTIAL BUILDINGAPPLICATION OF ABC ANALYSIS FOR MATERIAL MANAGEMENT OF RESIDENTIAL BUILDING
APPLICATION OF ABC ANALYSIS FOR MATERIAL MANAGEMENT OF RESIDENTIAL BUILDING
 
Types of resources in civil engineering field
Types of resources in civil engineering fieldTypes of resources in civil engineering field
Types of resources in civil engineering field
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in construction
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
 
Ready mix concrete
Ready mix concreteReady mix concrete
Ready mix concrete
 
Estimating & Costing - I
Estimating & Costing - IEstimating & Costing - I
Estimating & Costing - I
 
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
114 site layout
114 site layout114 site layout
114 site layout
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
What is Manpower Planning Organizing Staffing Important objectives of staffin...
What is Manpower Planning Organizing Staffing Important objectives of staffin...What is Manpower Planning Organizing Staffing Important objectives of staffin...
What is Manpower Planning Organizing Staffing Important objectives of staffin...
 
Etendering
EtenderingEtendering
Etendering
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
 
Public Procurement and Contract - Theory and practice in Nepal_2013
Public Procurement and Contract - Theory and practice in Nepal_2013Public Procurement and Contract - Theory and practice in Nepal_2013
Public Procurement and Contract - Theory and practice in Nepal_2013
 

Similaire à inventory control for construction

inventory-management
inventory-managementinventory-management
inventory-managementrajesh.pal45
 
Ch14 Inventory Management
Ch14  Inventory ManagementCh14  Inventory Management
Ch14 Inventory Managementajithsrc
 
Inventory Management Inventory management
Inventory Management Inventory managementInventory Management Inventory management
Inventory Management Inventory managementsakshi0503sakshi
 
Inventory control
Inventory controlInventory control
Inventory controlR A Shah
 
Session 6
Session 6Session 6
Session 6thangv
 
Managing Inventory In SC Lect#12 in.pptx
Managing Inventory In SC Lect#12 in.pptxManaging Inventory In SC Lect#12 in.pptx
Managing Inventory In SC Lect#12 in.pptxSahilAgrawal80
 
Managing Inventory In SC Lect#12 in.pptx
Managing Inventory In SC Lect#12 in.pptxManaging Inventory In SC Lect#12 in.pptx
Managing Inventory In SC Lect#12 in.pptxSahilAgrawal80
 
C9 inventory management
C9 inventory managementC9 inventory management
C9 inventory managementhakimizaki
 
C9 inventory management
C9 inventory managementC9 inventory management
C9 inventory managementhakimizaki
 
OM_4.ppt
OM_4.pptOM_4.ppt
OM_4.pptsengar3
 
Topic 4 Inventory Management Model.pptx
Topic 4 Inventory Management Model.pptxTopic 4 Inventory Management Model.pptx
Topic 4 Inventory Management Model.pptxHassanHani5
 
24867879 inventory-management-control-lecture-3
24867879 inventory-management-control-lecture-324867879 inventory-management-control-lecture-3
24867879 inventory-management-control-lecture-3Harshawardhan Thakare
 
Akuntansi Manajemen Edisi 8 oleh Hansen & Mowen Bab 14
Akuntansi Manajemen Edisi 8 oleh Hansen & Mowen Bab 14Akuntansi Manajemen Edisi 8 oleh Hansen & Mowen Bab 14
Akuntansi Manajemen Edisi 8 oleh Hansen & Mowen Bab 14Dwi Wahyu
 

Similaire à inventory control for construction (20)

Ch14. inventory management
Ch14. inventory managementCh14. inventory management
Ch14. inventory management
 
inventory-management
inventory-managementinventory-management
inventory-management
 
Ch14 Inventory Management
Ch14  Inventory ManagementCh14  Inventory Management
Ch14 Inventory Management
 
Inventory Management Inventory management
Inventory Management Inventory managementInventory Management Inventory management
Inventory Management Inventory management
 
Eoq model
Eoq modelEoq model
Eoq model
 
Inventory 1.1
Inventory 1.1Inventory 1.1
Inventory 1.1
 
Inventory control
Inventory controlInventory control
Inventory control
 
Chapter 6_OM
Chapter 6_OMChapter 6_OM
Chapter 6_OM
 
Session 6
Session 6Session 6
Session 6
 
Managing Inventory In SC Lect#12 in.pptx
Managing Inventory In SC Lect#12 in.pptxManaging Inventory In SC Lect#12 in.pptx
Managing Inventory In SC Lect#12 in.pptx
 
Managing Inventory In SC Lect#12 in.pptx
Managing Inventory In SC Lect#12 in.pptxManaging Inventory In SC Lect#12 in.pptx
Managing Inventory In SC Lect#12 in.pptx
 
C9 inventory management
C9 inventory managementC9 inventory management
C9 inventory management
 
C9 inventory management
C9 inventory managementC9 inventory management
C9 inventory management
 
5. INVENTORY MANAGEMENT.ppt
5. INVENTORY MANAGEMENT.ppt5. INVENTORY MANAGEMENT.ppt
5. INVENTORY MANAGEMENT.ppt
 
ECONOMIC ORDER QTY
ECONOMIC ORDER QTYECONOMIC ORDER QTY
ECONOMIC ORDER QTY
 
OM_4.ppt
OM_4.pptOM_4.ppt
OM_4.ppt
 
Topic 4 Inventory Management Model.pptx
Topic 4 Inventory Management Model.pptxTopic 4 Inventory Management Model.pptx
Topic 4 Inventory Management Model.pptx
 
24867879 inventory-management-control-lecture-3
24867879 inventory-management-control-lecture-324867879 inventory-management-control-lecture-3
24867879 inventory-management-control-lecture-3
 
5A-INVENTORY MGT.ppt
5A-INVENTORY MGT.ppt5A-INVENTORY MGT.ppt
5A-INVENTORY MGT.ppt
 
Akuntansi Manajemen Edisi 8 oleh Hansen & Mowen Bab 14
Akuntansi Manajemen Edisi 8 oleh Hansen & Mowen Bab 14Akuntansi Manajemen Edisi 8 oleh Hansen & Mowen Bab 14
Akuntansi Manajemen Edisi 8 oleh Hansen & Mowen Bab 14
 

Dernier

data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spaintimesproduction05
 
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICSUNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICSrknatarajan
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdfSuman Jyoti
 

Dernier (20)

data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spain
 
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICSUNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 

inventory control for construction

  • 1. Construction Materials Management (COTM 5202) 5. Inventory Control by Tadesse Ayalew Lecturer , EiABC, AAU BSc. IN CONSTRUCTION TECH. & MANAGEMENT, EiABC, MARCH 2014 1
  • 2. 5. 1 Inventory cost Components  The general objective of inventory control is to minimize the total cost of keeping the inventory while making tradeoffs among the major categories of costs: (A) purchase costs, (B) order cost, (C) holding costs, and (D) unavailable cost.  These cost categories are interrelated since reducing cost in one category may increase cost in others.  The costs in all categories generally are subject to considerable uncertainty.
  • 3. A) Purchase Costs  The purchase cost of an item is the unit purchase price from an external source including transportation and freight costs.  For construction materials, it is common to receive discounts for bulk purchases, so the unit purchase cost declines as quantity increases.  Because of this, organizations may consolidate small orders from a number of different projects to capture such bulk discounts, in some cases; this is a basic saving to be derived from a central purchasing office
  • 4. B) Order Cost  The order cost reflects the administrative expense of issuing a purchase order to an outside supplier.  Order costs are usually only a small portion of total costs for material management in construction projects, although ordering may require substantial time.
  • 5. C) Holding Costs  The holding costs or carrying costs are primarily the result of capital costs, handling, storage, obsolescence, shrinkage and deterioration.  Capital cost results from the opportunity cost or financial expense of capital tied up in inventory.  Handling and storage represent the movement and protection charges incurred for materials.
  • 6. C) Holding Costs (Cont….)  Storage costs also include the disruption caused to other project activities by large inventories of materials that get in the way. Obsolescence is the risk that an item will lose value because of changes in specifications.  Shrinkage is the decrease in inventory over time due to theft or loss. Deterioration reflects a change in material quality due to age or environmental degradation.
  • 7. D) Unavailability Cost  The unavailability cost is incurred when a desired material is not available at the desired time.  In manufacturing industries, this cost is often called the stock out or depletion cost.  Shortages may delay work, thereby wasting labor resources or delaying the completion of the entire project.
  • 8. 5.2 Tradeoffs of Costs in Materials Management.  To illustrate the type of trade-offs encountered in materials management, suppose that a particular item is to be ordered for a project. The amount of time required for processing the order and shipping the item is uncertain.  Consequently, the project manager must decide how much lead time to provide in ordering the item. Ordering early and thereby providing a long lead time will increase the chance that the item is available when needed but it increases the cost of inventory and chance of spoilage on site.
  • 9. 5.3 Inventory Model  There are two types of inventory models  Deterministic inventory Model (Constant Demand)  Inventory Model with Probabilistic Demand
  • 10. The objectives of this model is to determine an optimum order quantity (EOQ) denoted by Q* such that total inventory cost is minimized. TVC= Ordering cost + carrying (holding cost) Ch Q Co Q D 2 +TVC = 5.3.1 Deterministic inventory models Economic order quantity (EOQ) model with constant rate of demand
  • 11. Minimizing CostsMinimizing Costs Objective is to minimize total costsObjective is to minimize total costs Table 11.5Table 11.5 AnnualcostAnnualcost Order quantityOrder quantity Curve for totalCurve for total cost of holdingcost of holding and setupand setup Holding costHolding cost curvecurve Setup (or order)Setup (or order) cost curvecost curve MinimumMinimum total costtotal cost OptimalOptimal orderorder quantityquantity
  • 12. Economic order quantity (EOQ) model with constant rate of demand( Cont…)  Since for maximum or minimum value of TVC its first derivatives should be zero 0 2 1 2 =+− ChCo Q D Q* = Ch DCo2 = Economic order quantity (EOQ)
  • 13.  Optimal length of the inventory replenishment cycles time (t*), optimal inventory between successive orders. Q*= Annual demand * Reorder cycle time = D*t  Optimal No of order quantity to be placed in the given time period (which is assumed to be one year) Important formulas D Q * Ch DCo D 2 * 1t* = = = *Q D Ch DCo2 1 N*= D * = Co DCh 2
  • 14. Important formulas (cont…)  Optimal (minimum) total variable inventory cost (TVC*) TVC = Ch Q Co Q D 2 + CoD. Ch DCo2 1 Ch DCoCh 2 2= * + Optimal total inventory cost is the sum of variable costs and fixed costs, so TC = D.C+TVC* DCoCh2=
  • 15. Economic order quantity (EOQ) model with ware house space constraint Steps Step1: for λ=1, compute EOQ for each item separately by using the formula Where fi = the storage space required per unit item i and λ is a non negative Lagrange multiplier Q*= fiChi DiCoi λ2 2 + ; i =1, 2, 3….n
  • 16. Step 2: if Qi* (i=1, 2, 3…n) is satisfied the condition, (Total warehouse space available) then stops, otherwise go to step three, Step 3: Increase the value of λ if value of left hand side of ∑fiQi = W is More than available storage space other wise decrease the value of λ.  Continue iteration until the condition is satisfied WfiQi =Σ Economic order quantity (EOQ) model with ware house space constraint (cont…)
  • 17. Economic order quantity (EOQ) model with quantity discount  EOQ model with one price break  Suppose the following price discount schedule is quoted by the suppliers in which a price (quantity discount) occurs at b1 this means, Quantity Price per unit 0<Q1<b1 C1 b1<Q2 C2
  • 18. Economic order quantity (EOQ) model with quantity discount (cont…)  The optimal purchase quantity can be determined by the procedure given below  Step1: consider the lowest price (i.e. C2 ) and determine Q2* by the basic EOQ formula Q2*=  If Q2* lies with in the prescribed range b1<Q2*, then Q2* is EOQ i.e. Q*= Q2* rC DCo * 2 2
  • 19. Economic order quantity (EOQ) model with quantity discount (cont…)  And the optimal cost TC* associated with Q2* is calculated as follows: TC* (=TC2*) = D.C2+ Step2: If Q2* is not equal to or more than b1, then Calculate Q1* with C1 and corresponding total cost at Q1*. Compare TC(b1) and TC (Q1*), If TC(b1)>TC(Q1*),then EOQ is Q*= Q1*.Otherwise Q*= b1 is the required EOQ )*( 2 2 1 1 rC b Co b D +
  • 20. Economic order quantity (EOQ) model with quantity discount (cont…) EOQ model with two price break  Suppose the following price discount schedule is quoted by the suppliers in which a price (quantity discount) occurs at b1 this means, Quantity Price per unit 0<Q1< b1 C1 b1<Q2< b2 C2 b2< Q3 C3
  • 21. Economic order quantity (EOQ) model with quantity discount (cont…) Notice that C3< C2< C1 The optimal purchase quantity can be determined by the procedure given below Step1: a) Consider the lowest price (i.e. C3) and determine Q3* by the basic EOQ formula b) If Q3* > b2 , then EOQ (Q*) = Q3* and the optimal cost TC (Q3*) is the cost associated with Q3* c) If Q3*< b2, then go to step 2
  • 22. Economic order quantity (EOQ) model with quantity discount (cont…) Step2: a) Calculate Q2* is based on price C2. b) Compare Q2* with b1and if b1< Q2* < b2 then compare TC (Q2*) and TC (b2). If TC (Q2*)> TC (b2), then EOQ= b2. Otherwise EOQ = (Q2*) c) If Q3*< b1as well as b2then go to step three. Step3: Calculate Q1* is based on price C1and compare, TC (b1), TC (b2) and TC (Q1*) to find EOQ the quantity with lowest cost will naturally be the required EOQ
  • 23. An EOQ ExampleAn EOQ Example Determine optimal number of units to orderDetermine optimal number of units to order D = 1,000 unitsD = 1,000 units Co = $10 per orderCo = $10 per order H = $.50 per unit per yearH = $.50 per unit per year Q* =Q* = 2DCo2DCo HH Q* =Q* = 2(1,000)(10)2(1,000)(10) 0.500.50 = 40,000 = 200 units= 40,000 = 200 units
  • 24. An EOQ ExampleAn EOQ Example Determine optimal number of needles to orderDetermine optimal number of needles to order D = 1,000 unitsD = 1,000 units Q*Q* = 200 units= 200 units Co = $10 per orderCo = $10 per order H = $.50 per unit per yearH = $.50 per unit per year = N = == N = = ExpectedExpected number ofnumber of ordersorders DemandDemand Order quantityOrder quantity DD Q*Q* N = = 5 orders per yearN = = 5 orders per year 1,0001,000 200200
  • 25. An EOQ ExampleAn EOQ Example Determine optimal number of needles to orderDetermine optimal number of needles to order D = 1,000 unitsD = 1,000 units Q*Q* = 200 units= 200 units S = $10 per orderS = $10 per order NN = 5 orders per year= 5 orders per year H = $.50 per unit per yearH = $.50 per unit per year = T == T = Expected timeExpected time between ordersbetween orders Number of workingNumber of working days per yeardays per year NN T = = 50 days between ordersT = = 50 days between orders250250 55
  • 26. An EOQ ExampleAn EOQ Example Determine optimal number of needles to orderDetermine optimal number of needles to order D = 1,000 unitsD = 1,000 units Q*Q* = 200 units= 200 units S = $10 per orderS = $10 per order NN = 5 orders per year= 5 orders per year H = $.50 per unit per yearH = $.50 per unit per year TT = 50 days= 50 days Total annual cost = Setup cost + Holding costTotal annual cost = Setup cost + Holding cost TC = S + HTC = S + H DD QQ QQ 22 TC = ($10) + ($.50)TC = ($10) + ($.50) 1,0001,000 200200 200200 22 TC = (5)($10) + (100)($.50) = $50 + $50 = $100TC = (5)($10) + (100)($.50) = $50 + $50 = $100
  • 27. Reorder PointsReorder Points  EOQ answers the “how much” questionEOQ answers the “how much” question  The reorder point (ROP) tells when to orderThe reorder point (ROP) tells when to order ROP =ROP = Lead time for a newLead time for a new order in daysorder in days DemandDemand per dayper day = d x L= d x L d =d = DD Number of working days in a yearNumber of working days in a year
  • 28. Reorder Point CurveReorder Point Curve Q*Q* ROPROP (units)(units) Inventorylevel(units)Inventorylevel(units) Time (days)Time (days) Figure 12.5Figure 12.5 Lead time = LLead time = L Slope = units/day = dSlope = units/day = d
  • 29. Reorder Point ExampleReorder Point Example Demand = 8,000 DVDs per yearDemand = 8,000 DVDs per year 250 working day year250 working day year Lead time for orders is 3 working daysLead time for orders is 3 working days ROP = d x LROP = d x L d =d = DD Number of working days in a yearNumber of working days in a year = 8,000/250 = 32 units= 8,000/250 = 32 units = 32 units per day x 3 days = 96 units= 32 units per day x 3 days = 96 units
  • 30. Quantity Discount ModelsQuantity Discount Models DiscountDiscount NumberNumber Discount QuantityDiscount Quantity Discount (%)Discount (%) DiscountDiscount Price (P)Price (P) 11 00 toto 999999 no discountno discount $5.00$5.00 22 1,0001,000 toto 1,9991,999 44 $4.80$4.80 33 2,0002,000 and overand over 55 $4.75$4.75 Table 12.2Table 12.2 A typical quantity discount scheduleA typical quantity discount schedule
  • 31. Quantity Discount ExampleQuantity Discount Example Calculate Q* for every discountCalculate Q* for every discount Q* = 2DS IP QQ11* = = 700 cars order* = = 700 cars order 2(5,000)(49)2(5,000)(49) (.2)(5.00)(.2)(5.00) QQ22* = = 714 cars order* = = 714 cars order 2(5,000)(49)2(5,000)(49) (.2)(4.80)(.2)(4.80) QQ33* = = 718 cars order* = = 718 cars order 2(5,000)(49)2(5,000)(49) (.2)(4.75)(.2)(4.75) 1,000 — adjusted1,000 — adjusted 2,000 — adjusted2,000 — adjusted
  • 32. Quantity Discount ExampleQuantity Discount Example DiscountDiscount NumberNumber UnitUnit PricePrice OrderOrder QuantityQuantity AnnualAnnual ProductProduct CostCost AnnualAnnual OrderingOrdering CostCost AnnualAnnual HoldingHolding CostCost TotalTotal 11 $5.00$5.00 700700 $25,000$25,000 $350$350 $350$350 $25,700$25,700 22 $4.80$4.80 1,0001,000 $24,000$24,000 $245$245 $480$480 $24,725$24,725 33 $4.75$4.75 2,0002,000 $23.750$23.750 $122.50$122.50 $950$950 $24,822.50$24,822.50 Table 12.3Table 12.3 Choose the price and quantity that gives the lowest totalChoose the price and quantity that gives the lowest total costcost Buy 1,000 units at $4.80 per unitBuy 1,000 units at $4.80 per unit
  • 34. Exercise 1 The production department of a company requires 3600kg of raw materials for manufacturing of particular item per year. It has been estimated that cost of placing an order is 36 birr and the cost of carrying inventories is 25% of the investment in the inventories. The price is 10 birr per kg. The purchase manager whishes to determine an ordering policy for raw materials.
  • 35. Exercise 2 A small shop produces three machines part I,II and III in lots. The shop has only 650m2 of storage space the appropriate data for three items are given in the following table Item I II III Demand (unit per year) 5000 2000 10000 Procurement cost per order 100 200 75 Cost per unit 10 15 5 Floor space requirements 0.7 0.8 0.4 The shop uses an inventory charge of 20% of average inventories valuation per year. If no stock out is allowed, determine the optimal lot size for each item under a given storage constraints.
  • 36. Exercise 3 A shopkeeper estimates annual requirement of an item as 2000 units. He buys from supplier 10 per item and the cost of ordering is 50 birr each time. If the stock holding costs are 25% per year of stock value how frequently should replenish his stock? Further, suppose the supplier offer 10% discount on order between 400 and 699 item, a 20% discount on order exceeding or equal to 700 can the shopkeeper reduce his cost by taking advantages from either of the discount ?