54   Chapter 2
exam questions
1. Which of the following is NOT a Project Constraint?
QualityA.	
ScaleB.	
TimeC.	
CostD.	
2. A project manager is running a data center installation project. He finds that his stakeholder is
angry because he’s run over his budget because the staff turned out to be more expensive than
planned. The stakeholder’s unhappy that when the project is over, the servers won’t have as much
drive space as he needs. Which of the following constraints was not affected by this problem?
QualityA.	
ResourceB.	
TimeC.	
D.	 Cost
3. Which of the following is NOT an example of operational work?
Building a purchase order system for accounts payableA.	
Submitting weekly purchase orders through a purchase order systemB.	
Deploying weekly anti-virus software updatesC.	
Yearly staff performance evaluationsD.	
4. You’re managing a project to build a new accounting system. One of the accountants in another
department really likes the current system and is refusing to be trained on the new one. What is
the BEST way to handle this situation?
Refuse to work with him because he’s being difficultA.	
Appeal to the accountant’s manager and ask to have him required to take trainingB.	
Get a special dispensation so that the accountant doesn’t have to go to the trainingC.	
Work with him to understand his concerns and do what you can to help alleviate them withoutD.	
compromising your project
5. Which of the following is used for identifying people who are impacted by the project?
Resource ListA.	
Stakeholder RegisterB.	
Enterprise Environmental FactorsC.	
Project PlanD.	
Exam Questions
Download at Boykma.Com
you are here 4   55
organizations, constraints, and projects
6. Your manager asks you where to find a list of projects that should be managed together. What is
the BEST place to find this information?
Project PlanA.	
Project CharterB.	
Portfolio CharterC.	
Program CharterD.	
7. You want to know specifically which business goal a group of projects and programs are going to
accomplish. Which is the best place to look for this information?
Project PlanA.	
Project CharterB.	
Portfolio CharterC.	
Program CharterD.	
8. A project coordinator is having trouble securing programmers for her project. Every time she asks
her boss to give a resource to the project he says that they are too busy to help out with her project.
Which type of organization is she working in?
FunctionalA.	
Weak MatrixB.	
Strong MatrixC.	
ProjectizedD.	
9. A project manager is having trouble securing programmers for her project. Every time she asks
the programming manager for resources for her project, he says they’re all assigned to other work.
So she is constantly having to go over his head to overrule him. Which type of organization is she
working for?
FunctionalA.	
Weak MatrixB.	
Strong MatrixC.	
ProjectizedD.	
Exam Questions
Download at Boykma.Com
56   Chapter 2
exam answers
Exam Questions
Answers
1. Answer: B
Scale is not a project constraint. The constraints are Scope, Time, Cost, Quality, Resource, and Risk.
2. Answer: C
There is no mention of the project being late or missing its deadlines in the example. The project was over
budget, which affects the project’s cost. The project won’t meet the stakeholder’s requirements, which is a
quality problem. And the staff was more expensive than planned, which is a resource problem.
3. Answer: A
Building a purchase order system for accounts payable is a project. It’s a temporary effort that has a unique
result.
4.Answer: D
When a stakeholder is negatively impacted by your project, you need to manage his expectations and help
him to buy into your project.
5. Answer: B
The stakeholder register is where you identify all of the people who are impacted by your project.
6. Answer: D
A program is a group of projects that should be managed together because of interdependencies. A
program charter fits the description in this question.
7. Answer: C
A portfolio charter will give the business goal that a group of projects and programs will accomplish as part
of a portfolio.
Download at Boykma.Com
you are here 4   57
organizations, constraints, and projects
8. Answer: A
Since the project manager has to ask permission from the functional manager and can’t overrule him, she’s
working in a functional organization.
9. Answer: C
The Project Manager in this scenario can overrule the functional manager, so she’s working in a Strong Matrix
organization. If it were a projectized organization, she wouldn’t have to get permission from the functional
manager at all because she’d be the person with authority to assign resources to projects.
Exam Questions
Answers
Download at Boykma.Com

Contenu connexe

Tendances

09 pmp human resource management exam
09 pmp human resource  management exam09 pmp human resource  management exam
09 pmp human resource management exam
Jamil Faraj , PMP
 
Project initiation
Project initiationProject initiation
Project initiation
ukrulz4u
 
1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bank
Baskar El
 

Tendances (20)

09 pmp human resource management exam
09 pmp human resource  management exam09 pmp human resource  management exam
09 pmp human resource management exam
 
11 pmp risk management exam
11 pmp risk management exam11 pmp risk management exam
11 pmp risk management exam
 
Pm study project risk management test
Pm study project  risk management testPm study project  risk management test
Pm study project risk management test
 
07 pmp cost management exam
07 pmp cost management exam07 pmp cost management exam
07 pmp cost management exam
 
Pmp test 02
Pmp test 02Pmp test 02
Pmp test 02
 
08 pmp quality management exam
08 pmp quality management exam08 pmp quality management exam
08 pmp quality management exam
 
Lecture 1. general introduction to project management
Lecture 1. general introduction to project management Lecture 1. general introduction to project management
Lecture 1. general introduction to project management
 
Pmi sp questions with answers
Pmi sp questions with answersPmi sp questions with answers
Pmi sp questions with answers
 
Pmp4
Pmp4Pmp4
Pmp4
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Pmp6
Pmp6Pmp6
Pmp6
 
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management FrameworkProject Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
 
Pmp3
Pmp3Pmp3
Pmp3
 
1
11
1
 
Project initiation
Project initiationProject initiation
Project initiation
 
Pmp1
Pmp1Pmp1
Pmp1
 
1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bank
 
Risk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ansRisk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ans
 
Project Management Principles and Process
Project Management Principles and ProcessProject Management Principles and Process
Project Management Principles and Process
 
PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS
 

En vedette

La nouvelle certification Portfolio Management Professional (PfMP)
La nouvelle certification Portfolio Management Professional (PfMP)La nouvelle certification Portfolio Management Professional (PfMP)
La nouvelle certification Portfolio Management Professional (PfMP)
PMI-Montréal
 

En vedette (13)

175 pmp sample_questions
175 pmp sample_questions175 pmp sample_questions
175 pmp sample_questions
 
La nouvelle certification Portfolio Management Professional (PfMP)
La nouvelle certification Portfolio Management Professional (PfMP)La nouvelle certification Portfolio Management Professional (PfMP)
La nouvelle certification Portfolio Management Professional (PfMP)
 
13 pmp professional responsibility exam
13 pmp professional responsibility exam13 pmp professional responsibility exam
13 pmp professional responsibility exam
 
Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.
 
Project Management Course slide 1
Project Management Course slide 1Project Management Course slide 1
Project Management Course slide 1
 
Le chef de projet et le business analyste
Le chef de projet et le business analysteLe chef de projet et le business analyste
Le chef de projet et le business analyste
 
2
22
2
 
Pmp5
Pmp5Pmp5
Pmp5
 
Capm exam prep-questions_2010_ol
Capm exam prep-questions_2010_olCapm exam prep-questions_2010_ol
Capm exam prep-questions_2010_ol
 
Présentation standards 2015 04-02
Présentation standards 2015 04-02Présentation standards 2015 04-02
Présentation standards 2015 04-02
 
Pmp : management des parties prenantes
Pmp : management des parties prenantesPmp : management des parties prenantes
Pmp : management des parties prenantes
 
Certification PMP - Retour d'Expérience en 12 points (Lessons Learned in French)
Certification PMP - Retour d'Expérience en 12 points (Lessons Learned in French)Certification PMP - Retour d'Expérience en 12 points (Lessons Learned in French)
Certification PMP - Retour d'Expérience en 12 points (Lessons Learned in French)
 
Enactus ensem 01 dec13
Enactus ensem  01 dec13Enactus ensem  01 dec13
Enactus ensem 01 dec13
 

Similaire à 02 pmp project life cycle exam

1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx
jackiewalcutt
 
PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1
Daniel Hucks
 
Question 1  Doing procurement functions electronically is termed.docx
Question 1  Doing procurement functions electronically is termed.docxQuestion 1  Doing procurement functions electronically is termed.docx
Question 1  Doing procurement functions electronically is termed.docx
IRESH3
 

Similaire à 02 pmp project life cycle exam (20)

Session 8 Everything You Should Know About PMP & CAPM Certifications
Session 8 Everything You Should Know About PMP & CAPM CertificationsSession 8 Everything You Should Know About PMP & CAPM Certifications
Session 8 Everything You Should Know About PMP & CAPM Certifications
 
9 Common Challenges in the Software Development Process
9 Common Challenges in the Software Development Process9 Common Challenges in the Software Development Process
9 Common Challenges in the Software Development Process
 
Pmp test 03
Pmp test 03Pmp test 03
Pmp test 03
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
 
Assignment .pdf
Assignment .pdfAssignment .pdf
Assignment .pdf
 
PgMP
PgMP PgMP
PgMP
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
Pmp Five Sample Questions
Pmp Five Sample QuestionsPmp Five Sample Questions
Pmp Five Sample Questions
 
PMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfPMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdf
 
PMP® Sample Questions 3
PMP® Sample Questions 3PMP® Sample Questions 3
PMP® Sample Questions 3
 
PMP Certificate- introduction
PMP Certificate- introductionPMP Certificate- introduction
PMP Certificate- introduction
 
1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdf
 
Session 3 gdas pmp study group presentation
Session 3   gdas pmp study group presentationSession 3   gdas pmp study group presentation
Session 3 gdas pmp study group presentation
 
FREE CBAP v3 Simulation Question test-set 01
FREE CBAP v3 Simulation Question test-set 01FREE CBAP v3 Simulation Question test-set 01
FREE CBAP v3 Simulation Question test-set 01
 
PMP Exam Sample Questions 4
PMP Exam Sample Questions 4PMP Exam Sample Questions 4
PMP Exam Sample Questions 4
 
PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1
 
Free PMP® Practice Exam Questions
 Free PMP® Practice Exam Questions Free PMP® Practice Exam Questions
Free PMP® Practice Exam Questions
 
Question 1  Doing procurement functions electronically is termed.docx
Question 1  Doing procurement functions electronically is termed.docxQuestion 1  Doing procurement functions electronically is termed.docx
Question 1  Doing procurement functions electronically is termed.docx
 

Plus de Jamil Faraj , PMP

10 pmp communication management exam
10 pmp communication  management exam10 pmp communication  management exam
10 pmp communication management exam
Jamil Faraj , PMP
 

Plus de Jamil Faraj , PMP (11)

Corona-virus PMP study plan
Corona-virus PMP study planCorona-virus PMP study plan
Corona-virus PMP study plan
 
PMP Study Plan by Jamil Faraj, PMP
PMP Study Plan by Jamil Faraj, PMPPMP Study Plan by Jamil Faraj, PMP
PMP Study Plan by Jamil Faraj, PMP
 
Jamil Faraj CV 2020
Jamil Faraj CV 2020Jamil Faraj CV 2020
Jamil Faraj CV 2020
 
Jamil faraj hassan CV
Jamil faraj hassan CVJamil faraj hassan CV
Jamil faraj hassan CV
 
PMP ITTOs Quick Review
PMP ITTOs Quick Review PMP ITTOs Quick Review
PMP ITTOs Quick Review
 
Jamil pmp Certificate 2020
Jamil pmp Certificate 2020Jamil pmp Certificate 2020
Jamil pmp Certificate 2020
 
Jamil Faraj CV- English
Jamil Faraj CV- EnglishJamil Faraj CV- English
Jamil Faraj CV- English
 
Pmp Formula Pocket_Guide
Pmp Formula Pocket_GuidePmp Formula Pocket_Guide
Pmp Formula Pocket_Guide
 
دورة وظيفة العمر
دورة وظيفة العمردورة وظيفة العمر
دورة وظيفة العمر
 
06 pmp time management exam
06 pmp time  management exam06 pmp time  management exam
06 pmp time management exam
 
10 pmp communication management exam
10 pmp communication  management exam10 pmp communication  management exam
10 pmp communication management exam
 

Dernier

Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
panagenda
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
WSO2
 

Dernier (20)

Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challenges
 
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu SubbuApidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Ransomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdfRansomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdf
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 

02 pmp project life cycle exam

  • 1. 54   Chapter 2 exam questions 1. Which of the following is NOT a Project Constraint? QualityA. ScaleB. TimeC. CostD. 2. A project manager is running a data center installation project. He finds that his stakeholder is angry because he’s run over his budget because the staff turned out to be more expensive than planned. The stakeholder’s unhappy that when the project is over, the servers won’t have as much drive space as he needs. Which of the following constraints was not affected by this problem? QualityA. ResourceB. TimeC. D. Cost 3. Which of the following is NOT an example of operational work? Building a purchase order system for accounts payableA. Submitting weekly purchase orders through a purchase order systemB. Deploying weekly anti-virus software updatesC. Yearly staff performance evaluationsD. 4. You’re managing a project to build a new accounting system. One of the accountants in another department really likes the current system and is refusing to be trained on the new one. What is the BEST way to handle this situation? Refuse to work with him because he’s being difficultA. Appeal to the accountant’s manager and ask to have him required to take trainingB. Get a special dispensation so that the accountant doesn’t have to go to the trainingC. Work with him to understand his concerns and do what you can to help alleviate them withoutD. compromising your project 5. Which of the following is used for identifying people who are impacted by the project? Resource ListA. Stakeholder RegisterB. Enterprise Environmental FactorsC. Project PlanD. Exam Questions Download at Boykma.Com
  • 2. you are here 4   55 organizations, constraints, and projects 6. Your manager asks you where to find a list of projects that should be managed together. What is the BEST place to find this information? Project PlanA. Project CharterB. Portfolio CharterC. Program CharterD. 7. You want to know specifically which business goal a group of projects and programs are going to accomplish. Which is the best place to look for this information? Project PlanA. Project CharterB. Portfolio CharterC. Program CharterD. 8. A project coordinator is having trouble securing programmers for her project. Every time she asks her boss to give a resource to the project he says that they are too busy to help out with her project. Which type of organization is she working in? FunctionalA. Weak MatrixB. Strong MatrixC. ProjectizedD. 9. A project manager is having trouble securing programmers for her project. Every time she asks the programming manager for resources for her project, he says they’re all assigned to other work. So she is constantly having to go over his head to overrule him. Which type of organization is she working for? FunctionalA. Weak MatrixB. Strong MatrixC. ProjectizedD. Exam Questions Download at Boykma.Com
  • 3. 56   Chapter 2 exam answers Exam Questions Answers 1. Answer: B Scale is not a project constraint. The constraints are Scope, Time, Cost, Quality, Resource, and Risk. 2. Answer: C There is no mention of the project being late or missing its deadlines in the example. The project was over budget, which affects the project’s cost. The project won’t meet the stakeholder’s requirements, which is a quality problem. And the staff was more expensive than planned, which is a resource problem. 3. Answer: A Building a purchase order system for accounts payable is a project. It’s a temporary effort that has a unique result. 4.Answer: D When a stakeholder is negatively impacted by your project, you need to manage his expectations and help him to buy into your project. 5. Answer: B The stakeholder register is where you identify all of the people who are impacted by your project. 6. Answer: D A program is a group of projects that should be managed together because of interdependencies. A program charter fits the description in this question. 7. Answer: C A portfolio charter will give the business goal that a group of projects and programs will accomplish as part of a portfolio. Download at Boykma.Com
  • 4. you are here 4   57 organizations, constraints, and projects 8. Answer: A Since the project manager has to ask permission from the functional manager and can’t overrule him, she’s working in a functional organization. 9. Answer: C The Project Manager in this scenario can overrule the functional manager, so she’s working in a Strong Matrix organization. If it were a projectized organization, she wouldn’t have to get permission from the functional manager at all because she’d be the person with authority to assign resources to projects. Exam Questions Answers Download at Boykma.Com