SlideShare une entreprise Scribd logo
1  sur  14
Page 1
QUESTION BANK
PROBLEMS ON LEVELLING
1. The following consecutive readings were taken with dumpy level on 5 m leveling staff at 20 m
intervals. 0.385, 1.030, 1.925, 2.825, 3.730, 4.685, 0.625, 2.005, 3.110, 4.485. The very first
reading on a point whose RL was 208.125 m. The level was shifted after sixth reading.
Calculate the gradient of the line joining first and last point. Use rise and fall method.
(10 Mks)
Point B.S. I.S. F.S. Rise Fall R.L. Remark
Arithmetical
Checks
Sample Calculation:
Page 2
2. Following staff reading were recorded in a leveling work along a hill slope. 3.075, 2.270,
1.900, 3.785, 3.015, 2.490, 2.065, 0.880, 3.310, 2.195, 1.175, 0.540, 2.785, 1.790, 0.895,
3.300, 2.665 and 1.685. Levelling staff used was 4 m length. The first reading was taken on
B.M. having RL = 500.00 m. calculate RL’s of other staff positions by Rise and Fall
Method. Apply arithmetical checks.
Point B.S. I.S. F.S. Rise Fall R.L. Remark
Arithmetical
Checks
Sample Calculation:
Page 3
3. Fill up the missing entries and complete the page of the level book: (10 Mks)
Point B.S. I.S. F.S. Rise Fall R.L. Remark
A 3.00 A B.M. I
B C B 1.00 101.00 C.P.1
C 2.00 0.5 D
D E F 101.500
E I 2.5 G H C.P.2
F 1.5 3.0 2.00 J C.P.3
G 3.5 K L
H M N 97.500 B.M. II
Arithmetical
Checks
Ans:
Point B.S. I.S. F.S. Rise Fall R.L. Remark
A 3.00 B.M. I
B 1.00 101.00 C.P.1
C 2.00 0.5
D 101.500
E 2.5 C.P.2
F 1.5 3.0 2.00 C.P.3
G 3.5
H 97.500 B.M. II
Arithmetical
Checks
Sample Calculation:
Page 4
4. The following consecutive readings were taken with a leveling instrument at interval of 20
m. 2.375, 1.730, 0.615, 3.450, 2.835, 2.070, 1.835, 0.985, 0.435, 1.630, 2.255 and 3.630 m.
T he instrument was shifted after fourth and eighth readings. The last reading was taken on
a B.M. of R.L. 110.200 m. Find the RLs of all the points.
(10 Mks)
By Rise and Fall Method:
Point B.S. I.S. F.S. Rise Fall R.L. Remark
Arithmetical
Checks
Sample Calculation:
Page 5
By Collimation Plane Method:
Point B.S. I.S. F.S. Height of
Instrument
Or
Collimation
R.L. Remark
Arithmetical
Checks
Sample Calculation:
Page 6
5. Following staff readings were observed with level. The instrument was shifted after fourth
and seventh reading. Enter readings in a tabular form and calculate reduced levels of all
stations by Rise and Fall method assuming R. L. of first station as 500.000 m station.
1, 2, 3, 4, 1.5, 2.5, 3.5, 0.5, 1 10
By Rise and Fall Method:
Point B.S. I.S. F.S. Rise Fall R.L. Remark
Arithmetical
Checks
Sample Calculation:
Page 7
6. The following staff readings were taken on a hill slope in a leveling work.
3.075, 2.270, 1.900, 3.785, 2.490, 2.065, 0.880, 3.310, 2.195, 1.175, 0.540, 2.785, 1.790,
0.895, 3.300, 2.665and 1.685.
Levelling staff used was 4 m length. The first reading was taken on B.M., having RL =
500.00 m. Calculate RL’s of ofther staff positions by Rise and fall methid. Apply
arithmetical checks.
By Rise and Fall Method:
Point B.S. I.S. F.S. Rise Fall R.L. Remark
Arithmetical
Checks
Sample Calculation:
Page 8
7. The following staff readings were taken with a dumpy level. The instrument was shifted
after 4th, 7th and 10th readings. The RLs of the starting BM is 100.00 m. Enter the readings
in tabular form and reduce the level by Rise and Fall method. Apply arithmetical checks.
1.00, 2.00, 3.00, 1.00, 2.00, 3.00, 4.00, 0.50, 1.50, 2.50, 3.50, 1.00
By Rise and Fall Method:
Point B.S. I.S. F.S. Rise Fall R.L. Remark
Arithmetical
Checks
Sample Calculation:
Page 9
By Collimation Plane Method:
Point B.S. I.S. F.S. Height of
Instrument
Or
Collimation
R.L. Remark
Arithmetical
Checks
Sample Calculation:
Page 10
8. During fly leveling the following observation were made:
B.S. = 0.650, 2.155, 1.405, 2.655, 2.435 m
F.S. = 2.455, 1.305, 0.555, 2.405 m
The first reading was taken on a BM of RL 90.500 m from the last BS. It is required to set
four pegs each at a distance of 30 m on a following gradient of 1 in 100. Calculate the RLs
of these four pegs.
By Rise and Fall Method:
Point B.S. I.S. F.S. Rise Fall R.L. Remark
Arithmetical
Checks
Sample Calculation:
Page 11
9. Calculate the RL of last station, if the RL of first station is 500 m. The staff readings
observed is as below: 5.00 (staff inverted), 2.00, 3.00, 4.00 (staff inverted), 1.00, 2.00, 3.00,
4.00. Enter the data in standard leveling table. Apply Arithmetical checks. (Rise and Fall
method).
By Rise and Fall Method:
Point B.S. I.S. F.S. Rise Fall R.L. Remark
Arithmetical
Checks
Sample Calculation:
Page 12
18. Calculate the reduced level of last station, If the reduced level of first station is 500 m. The
staff readings observed are as shown; below: (in meter). 1.000 (Staff inverted), 2.000,
3.000,4.000 (Instrument shifted), 1.000,2.000, 3.000, 4.000. Enter the data in a standard
levelling table. Apply Arithmetic checks (Use Rise and Fall method).
Station B.S. I.S. F.S. Rise Fall R.L. Remark
1 2.285 232.46 BM1
2 1.65 2.265 X X X
3 2.105 X X
4 X 1.96 X X X
5 2.05 1.925 0.3 X X
6 X X 232.255 BM2
7 1.69 X 0.34 X X
8 2.865 2.1 X X X
-
9 X X 233.425 BM3
Ans:
Station B.S. I.S. F.S. Rise Fall R.L. Remark
1 2.285 232.46 BM1
2 1.65 2.265
3 2.105
4 1.96
5 2.05 1.925 0.3
6 232.255 BM2
7 1.69 0.34
8 2.865 2.1
-
9 233.425 BM3
Page 13
10. The following consecutive readings were taken with a leveling instrument at interval of 20
m. 2.375, 1.730, 0.615, 3.450, 2.835, 2.070, 1.835, 0.985, 0.435, 1.630, 2.255 and 3.630 m.
The instrument was shifted after fourth and eighth readings. The last reading was taken on
a B.M. of R.L. 110.200 m. Find the RLs of all the points. (10)
11. The following consecutive readings were taken with a leveling instrument on 5 m leveling
staff at 20 m interval. 0.385, 1.030, 1.925, 2.825, 3.730, 4.685, 0.625, 2.005, 3.110, 4.485.
The very first reading on a point whose RL was 208.125 m. The level was shifted after
sixth reading. Calculate the gradient of the line joining first and last point. Use Rise and
Fall method. (10)
12. The following consecutive readings were taken with a leveling instrument at interval of 20
m. 2.375, 1.730, 0.615, 3.450, 2.835, 2.070, 1.835, 0.985, 0.435, 1.630, 2.255 and 3.630 m.
The instrument was shifted after fourth and eighth readings. The last reading was taken on a
B.M. of R.L. 110.200 m. Find the RLs of all the points.
13. Following staff readings were observed with level. The instrument was shifted after
fourth and seventh reading. Enter readings in a tabular form and calculate reduced levels
of all stations by Plane collimation method, assuming R.L of first station as 500 m. Find
gradient of a line joining first station and last station.
1, 2,3, 4,1.5,2.5,3.5,0.5,1 (08)
14. The following consecutive readings were taken with a leveling instrument at interval of 20
m. 2.375, 1.730, 0.615, 3.450, 2.835, 2.070, 1.835, 0.985, 0.435, 1.630, 2.255 and 3.630 m.
The instrument was shifted after fourth and eighth readings. The last reading was taken on a
B.M. of R.L. 110.200 m. Find the RLs of all the points. (10 Mks)
15. The following consecutive readings were taken with a leveling instrument on 5 m leveling
staff at 20 m interval. 0.385, 1.030, 1.925, 2.825, 3.730, 4.685, 0.625, 2.005, 3.110, 4.485.
The very first reading on a point whose RL was 208.125 m. The level was shifted after
sixth reading. Calculate the gradient of the line joining first and last point. Use Rise and
Fall method. (10 Mks)
16. Following staff readings were recorded in a levelling work along a hill slope. 3.075, 2.270,
1.900, 3.785, 3.015, 2.490, 2.065, 0.880, 3.310, 2.195, 1.175, 0.540, 2.785, 1.790, 0.895,
3.300, 2.665, and 1.685. Levelling staff used was 4 m length. The first reading was taken
Page 14
on B.M., having R.L. = 500.00 m. Calculate RL's of other staff positions by Rise and Fall
Method. Apply arithmetical check. (10)
17. During Fly levelling operation; the following observations were made:
BS 0.650; 2.155; 1.405; 2.655; 2.435 m
FS 2.455; 1.305; 0.555; 2.405 m
The first backsight reading was taken on a B .M. of R.L. 90.500 m from the last backsight;
it is required to set four pegs each at a distance of 30 m on a falling gradient of 1 in 100.
Calculate the RL's of these four pegs.
19. Following staff readings were observed with level. The instrument was
shifted after fourth and seventh reading. Enter readings in a tabular form
and calculate reduced levels of all stations, assuming R.L. of first station as
500m. 1, 2, 3, 4, 1.5, 2.5, 3.5, 0.5, 1. (7)
20. The following reading was taken on a continuously sloping ground at 30 m interval 4.000,
2.000, 1.000, 4.000, 3.000, and 2.000. The R.L. of starting point was 500.000 m Rule out
page of levelling field book and enters the above readings. Carry out reduction of levels by
rise and fall method. Apply usual arithmetic checks. Determine the gradient of the line
joining the first and last point.

Contenu connexe

Tendances

Types of obstacles in chain surveying
Types of obstacles in chain surveyingTypes of obstacles in chain surveying
Types of obstacles in chain surveyingkazi abir
 
instruments of levelling
instruments of levellinginstruments of levelling
instruments of levellingNIKUL PITHVA
 
Site Surveying Levelling
Site Surveying Levelling Site Surveying Levelling
Site Surveying Levelling Darren Lee
 
Theodolites
TheodolitesTheodolites
Theodolitesillpa
 
Chain surveying.1
Chain surveying.1Chain surveying.1
Chain surveying.1Decentumang
 
Surveying - Module iii-levelling only note
Surveying - Module  iii-levelling only noteSurveying - Module  iii-levelling only note
Surveying - Module iii-levelling only noteSHAMJITH KM
 
1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & RangingRakesh Verma
 
Trial pit n borehole
Trial pit n boreholeTrial pit n borehole
Trial pit n boreholeFiQahh AmiNn
 
PROBLEMS ON BEARINGS
PROBLEMS ON BEARINGSPROBLEMS ON BEARINGS
PROBLEMS ON BEARINGSPralhad Kore
 
Site surveying report1
Site surveying report1Site surveying report1
Site surveying report1Est
 
Linear measurement
Linear measurementLinear measurement
Linear measurementKHUSHBU SHAH
 
Chain Surveying 2020.ppt
 Chain Surveying 2020.ppt Chain Surveying 2020.ppt
Chain Surveying 2020.pptAsadKhan606012
 
Project 1- Levelling
Project 1- Levelling Project 1- Levelling
Project 1- Levelling seenyee
 
Theodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversingTheodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversingDolat Ram
 

Tendances (20)

Types of obstacles in chain surveying
Types of obstacles in chain surveyingTypes of obstacles in chain surveying
Types of obstacles in chain surveying
 
instruments of levelling
instruments of levellinginstruments of levelling
instruments of levelling
 
Contour map hw problems
Contour map hw problemsContour map hw problems
Contour map hw problems
 
Traversing
TraversingTraversing
Traversing
 
Site Surveying Levelling
Site Surveying Levelling Site Surveying Levelling
Site Surveying Levelling
 
Theodolites
TheodolitesTheodolites
Theodolites
 
Chain surveying.1
Chain surveying.1Chain surveying.1
Chain surveying.1
 
Theodolite Traversing
Theodolite TraversingTheodolite Traversing
Theodolite Traversing
 
Surveying - Module iii-levelling only note
Surveying - Module  iii-levelling only noteSurveying - Module  iii-levelling only note
Surveying - Module iii-levelling only note
 
Tacheometry ppt
Tacheometry pptTacheometry ppt
Tacheometry ppt
 
1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging
 
Trial pit n borehole
Trial pit n boreholeTrial pit n borehole
Trial pit n borehole
 
PROBLEMS ON BEARINGS
PROBLEMS ON BEARINGSPROBLEMS ON BEARINGS
PROBLEMS ON BEARINGS
 
Site surveying report1
Site surveying report1Site surveying report1
Site surveying report1
 
Angular measurement for surveying
Angular measurement for surveyingAngular measurement for surveying
Angular measurement for surveying
 
Linear measurement
Linear measurementLinear measurement
Linear measurement
 
Chain Surveying 2020.ppt
 Chain Surveying 2020.ppt Chain Surveying 2020.ppt
Chain Surveying 2020.ppt
 
Levelling report
Levelling reportLevelling report
Levelling report
 
Project 1- Levelling
Project 1- Levelling Project 1- Levelling
Project 1- Levelling
 
Theodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversingTheodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversing
 

Similaire à Levelling

Levelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodLevelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodManicka Mamallan Andavar
 
engineering survey 1 report levelling
engineering survey 1 report levellingengineering survey 1 report levelling
engineering survey 1 report levellingYASMINE HASLAN
 
Levelling_1.pptx
Levelling_1.pptxLevelling_1.pptx
Levelling_1.pptxKvsghgd
 
Ss report 1
Ss report 1Ss report 1
Ss report 1Shen Sin
 
Site Surveying Report 1 (Levelling)
Site Surveying Report 1 (Levelling)Site Surveying Report 1 (Levelling)
Site Surveying Report 1 (Levelling)Haziq1511
 
REPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdf
REPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdfREPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdf
REPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdfMuhammadMuazzam16
 
Site survey Fieldwork1 (levelling)
Site survey Fieldwork1 (levelling)Site survey Fieldwork1 (levelling)
Site survey Fieldwork1 (levelling)Sheng Zhe
 
Profiles (longitudinal section) & cross sections
Profiles (longitudinal section) & cross sectionsProfiles (longitudinal section) & cross sections
Profiles (longitudinal section) & cross sectionsBahzad5
 
SWE 112 soil and water conservation engineering
SWE 112 soil and water conservation engineeringSWE 112 soil and water conservation engineering
SWE 112 soil and water conservation engineeringMelusinaNorwood
 
Ss report 1 ----levelling eport
Ss report 1 ----levelling eportSs report 1 ----levelling eport
Ss report 1 ----levelling eportMELVIN tan
 
Scale and its types
Scale and its types Scale and its types
Scale and its types Self
 
chapter 3 up to booking method.pdf
chapter 3 up to booking method.pdfchapter 3 up to booking method.pdf
chapter 3 up to booking method.pdfLeulDamtew
 
Assignment 1 - Levelling
Assignment 1 - LevellingAssignment 1 - Levelling
Assignment 1 - LevellingKai Yun Pang
 
Levelling final
Levelling finalLevelling final
Levelling finalseenyee
 
Scales in Engineering
Scales in EngineeringScales in Engineering
Scales in EngineeringKushal Patel
 

Similaire à Levelling (20)

Levelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodLevelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument method
 
Ss report 1
Ss report 1Ss report 1
Ss report 1
 
engineering survey 1 report levelling
engineering survey 1 report levellingengineering survey 1 report levelling
engineering survey 1 report levelling
 
Levelling_1.pptx
Levelling_1.pptxLevelling_1.pptx
Levelling_1.pptx
 
Ss report 1
Ss report 1Ss report 1
Ss report 1
 
Site Surveying Report 1 (Levelling)
Site Surveying Report 1 (Levelling)Site Surveying Report 1 (Levelling)
Site Surveying Report 1 (Levelling)
 
LEVELING.pdf
LEVELING.pdfLEVELING.pdf
LEVELING.pdf
 
Leveling
Leveling Leveling
Leveling
 
REPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdf
REPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdfREPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdf
REPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdf
 
Site survey Fieldwork1 (levelling)
Site survey Fieldwork1 (levelling)Site survey Fieldwork1 (levelling)
Site survey Fieldwork1 (levelling)
 
Profiles (longitudinal section) & cross sections
Profiles (longitudinal section) & cross sectionsProfiles (longitudinal section) & cross sections
Profiles (longitudinal section) & cross sections
 
Ss report 1
Ss report 1Ss report 1
Ss report 1
 
SWE 112 soil and water conservation engineering
SWE 112 soil and water conservation engineeringSWE 112 soil and water conservation engineering
SWE 112 soil and water conservation engineering
 
Ss report 1 ----levelling eport
Ss report 1 ----levelling eportSs report 1 ----levelling eport
Ss report 1 ----levelling eport
 
Scale and its types
Scale and its types Scale and its types
Scale and its types
 
chapter 3 up to booking method.pdf
chapter 3 up to booking method.pdfchapter 3 up to booking method.pdf
chapter 3 up to booking method.pdf
 
minesurvey.pptx
minesurvey.pptxminesurvey.pptx
minesurvey.pptx
 
Assignment 1 - Levelling
Assignment 1 - LevellingAssignment 1 - Levelling
Assignment 1 - Levelling
 
Levelling final
Levelling finalLevelling final
Levelling final
 
Scales in Engineering
Scales in EngineeringScales in Engineering
Scales in Engineering
 

Plus de Pralhad Kore

Transportation engineering
Transportation engineeringTransportation engineering
Transportation engineeringPralhad Kore
 
Chapter wise question papers_bce
Chapter wise question papers_bceChapter wise question papers_bce
Chapter wise question papers_bcePralhad Kore
 
Design of staircase_practical_example
Design of staircase_practical_exampleDesign of staircase_practical_example
Design of staircase_practical_examplePralhad Kore
 
Presentation "Use of coupler Splices for Reinforcement"
Presentation "Use of coupler Splices for Reinforcement"Presentation "Use of coupler Splices for Reinforcement"
Presentation "Use of coupler Splices for Reinforcement"Pralhad Kore
 
Guidelines_for_building_design
Guidelines_for_building_designGuidelines_for_building_design
Guidelines_for_building_designPralhad Kore
 
Strength of materials_I
Strength of materials_IStrength of materials_I
Strength of materials_IPralhad Kore
 
Presentation_on_Cellwise_Braced_frames
Presentation_on_Cellwise_Braced_framesPresentation_on_Cellwise_Braced_frames
Presentation_on_Cellwise_Braced_framesPralhad Kore
 
List of various_IRCs_&_sps
List of various_IRCs_&_spsList of various_IRCs_&_sps
List of various_IRCs_&_spsPralhad Kore
 
Analysis of multi storey building frames subjected to gravity and seismic loa...
Analysis of multi storey building frames subjected to gravity and seismic loa...Analysis of multi storey building frames subjected to gravity and seismic loa...
Analysis of multi storey building frames subjected to gravity and seismic loa...Pralhad Kore
 
Seismic response of _reinforced_concrete_concentrically_a_braced_frames
Seismic  response  of _reinforced_concrete_concentrically_a_braced_framesSeismic  response  of _reinforced_concrete_concentrically_a_braced_frames
Seismic response of _reinforced_concrete_concentrically_a_braced_framesPralhad Kore
 
Use of mechanical_splices_for_reinforcing_steel
Use of mechanical_splices_for_reinforcing_steelUse of mechanical_splices_for_reinforcing_steel
Use of mechanical_splices_for_reinforcing_steelPralhad Kore
 
Guide lines bridge_design
Guide lines bridge_designGuide lines bridge_design
Guide lines bridge_designPralhad Kore
 
Dissertation report
Dissertation reportDissertation report
Dissertation reportPralhad Kore
 
Seismic response of cellwise braced reinforced concrete frames
Seismic response of cellwise braced reinforced concrete framesSeismic response of cellwise braced reinforced concrete frames
Seismic response of cellwise braced reinforced concrete framesPralhad Kore
 
Chaper wise qpapers_bce
Chaper wise qpapers_bceChaper wise qpapers_bce
Chaper wise qpapers_bcePralhad Kore
 
Earthquake analysis by Response Spectrum Method
Earthquake analysis by Response Spectrum MethodEarthquake analysis by Response Spectrum Method
Earthquake analysis by Response Spectrum MethodPralhad Kore
 
Earthquake analysis by psudeo static method
Earthquake analysis by psudeo static methodEarthquake analysis by psudeo static method
Earthquake analysis by psudeo static methodPralhad Kore
 

Plus de Pralhad Kore (20)

Transportation engineering
Transportation engineeringTransportation engineering
Transportation engineering
 
Chapter wise question papers_bce
Chapter wise question papers_bceChapter wise question papers_bce
Chapter wise question papers_bce
 
Design of staircase_practical_example
Design of staircase_practical_exampleDesign of staircase_practical_example
Design of staircase_practical_example
 
Presentation "Use of coupler Splices for Reinforcement"
Presentation "Use of coupler Splices for Reinforcement"Presentation "Use of coupler Splices for Reinforcement"
Presentation "Use of coupler Splices for Reinforcement"
 
Guidelines_for_building_design
Guidelines_for_building_designGuidelines_for_building_design
Guidelines_for_building_design
 
Strength of materials_I
Strength of materials_IStrength of materials_I
Strength of materials_I
 
Presentation_on_Cellwise_Braced_frames
Presentation_on_Cellwise_Braced_framesPresentation_on_Cellwise_Braced_frames
Presentation_on_Cellwise_Braced_frames
 
Study of MORT_&_H
Study of MORT_&_HStudy of MORT_&_H
Study of MORT_&_H
 
List of various_IRCs_&_sps
List of various_IRCs_&_spsList of various_IRCs_&_sps
List of various_IRCs_&_sps
 
Analysis of multi storey building frames subjected to gravity and seismic loa...
Analysis of multi storey building frames subjected to gravity and seismic loa...Analysis of multi storey building frames subjected to gravity and seismic loa...
Analysis of multi storey building frames subjected to gravity and seismic loa...
 
Seismic response of _reinforced_concrete_concentrically_a_braced_frames
Seismic  response  of _reinforced_concrete_concentrically_a_braced_framesSeismic  response  of _reinforced_concrete_concentrically_a_braced_frames
Seismic response of _reinforced_concrete_concentrically_a_braced_frames
 
Use of mechanical_splices_for_reinforcing_steel
Use of mechanical_splices_for_reinforcing_steelUse of mechanical_splices_for_reinforcing_steel
Use of mechanical_splices_for_reinforcing_steel
 
Guide lines bridge_design
Guide lines bridge_designGuide lines bridge_design
Guide lines bridge_design
 
Dissertation report
Dissertation reportDissertation report
Dissertation report
 
Seismic response of cellwise braced reinforced concrete frames
Seismic response of cellwise braced reinforced concrete framesSeismic response of cellwise braced reinforced concrete frames
Seismic response of cellwise braced reinforced concrete frames
 
Water Management
Water ManagementWater Management
Water Management
 
Chaper wise qpapers_bce
Chaper wise qpapers_bceChaper wise qpapers_bce
Chaper wise qpapers_bce
 
Basic Loads Cases
Basic Loads CasesBasic Loads Cases
Basic Loads Cases
 
Earthquake analysis by Response Spectrum Method
Earthquake analysis by Response Spectrum MethodEarthquake analysis by Response Spectrum Method
Earthquake analysis by Response Spectrum Method
 
Earthquake analysis by psudeo static method
Earthquake analysis by psudeo static methodEarthquake analysis by psudeo static method
Earthquake analysis by psudeo static method
 

Dernier

VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoordharasingh5698
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfRagavanV2
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 

Dernier (20)

VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 

Levelling

  • 1. Page 1 QUESTION BANK PROBLEMS ON LEVELLING 1. The following consecutive readings were taken with dumpy level on 5 m leveling staff at 20 m intervals. 0.385, 1.030, 1.925, 2.825, 3.730, 4.685, 0.625, 2.005, 3.110, 4.485. The very first reading on a point whose RL was 208.125 m. The level was shifted after sixth reading. Calculate the gradient of the line joining first and last point. Use rise and fall method. (10 Mks) Point B.S. I.S. F.S. Rise Fall R.L. Remark Arithmetical Checks Sample Calculation:
  • 2. Page 2 2. Following staff reading were recorded in a leveling work along a hill slope. 3.075, 2.270, 1.900, 3.785, 3.015, 2.490, 2.065, 0.880, 3.310, 2.195, 1.175, 0.540, 2.785, 1.790, 0.895, 3.300, 2.665 and 1.685. Levelling staff used was 4 m length. The first reading was taken on B.M. having RL = 500.00 m. calculate RL’s of other staff positions by Rise and Fall Method. Apply arithmetical checks. Point B.S. I.S. F.S. Rise Fall R.L. Remark Arithmetical Checks Sample Calculation:
  • 3. Page 3 3. Fill up the missing entries and complete the page of the level book: (10 Mks) Point B.S. I.S. F.S. Rise Fall R.L. Remark A 3.00 A B.M. I B C B 1.00 101.00 C.P.1 C 2.00 0.5 D D E F 101.500 E I 2.5 G H C.P.2 F 1.5 3.0 2.00 J C.P.3 G 3.5 K L H M N 97.500 B.M. II Arithmetical Checks Ans: Point B.S. I.S. F.S. Rise Fall R.L. Remark A 3.00 B.M. I B 1.00 101.00 C.P.1 C 2.00 0.5 D 101.500 E 2.5 C.P.2 F 1.5 3.0 2.00 C.P.3 G 3.5 H 97.500 B.M. II Arithmetical Checks Sample Calculation:
  • 4. Page 4 4. The following consecutive readings were taken with a leveling instrument at interval of 20 m. 2.375, 1.730, 0.615, 3.450, 2.835, 2.070, 1.835, 0.985, 0.435, 1.630, 2.255 and 3.630 m. T he instrument was shifted after fourth and eighth readings. The last reading was taken on a B.M. of R.L. 110.200 m. Find the RLs of all the points. (10 Mks) By Rise and Fall Method: Point B.S. I.S. F.S. Rise Fall R.L. Remark Arithmetical Checks Sample Calculation:
  • 5. Page 5 By Collimation Plane Method: Point B.S. I.S. F.S. Height of Instrument Or Collimation R.L. Remark Arithmetical Checks Sample Calculation:
  • 6. Page 6 5. Following staff readings were observed with level. The instrument was shifted after fourth and seventh reading. Enter readings in a tabular form and calculate reduced levels of all stations by Rise and Fall method assuming R. L. of first station as 500.000 m station. 1, 2, 3, 4, 1.5, 2.5, 3.5, 0.5, 1 10 By Rise and Fall Method: Point B.S. I.S. F.S. Rise Fall R.L. Remark Arithmetical Checks Sample Calculation:
  • 7. Page 7 6. The following staff readings were taken on a hill slope in a leveling work. 3.075, 2.270, 1.900, 3.785, 2.490, 2.065, 0.880, 3.310, 2.195, 1.175, 0.540, 2.785, 1.790, 0.895, 3.300, 2.665and 1.685. Levelling staff used was 4 m length. The first reading was taken on B.M., having RL = 500.00 m. Calculate RL’s of ofther staff positions by Rise and fall methid. Apply arithmetical checks. By Rise and Fall Method: Point B.S. I.S. F.S. Rise Fall R.L. Remark Arithmetical Checks Sample Calculation:
  • 8. Page 8 7. The following staff readings were taken with a dumpy level. The instrument was shifted after 4th, 7th and 10th readings. The RLs of the starting BM is 100.00 m. Enter the readings in tabular form and reduce the level by Rise and Fall method. Apply arithmetical checks. 1.00, 2.00, 3.00, 1.00, 2.00, 3.00, 4.00, 0.50, 1.50, 2.50, 3.50, 1.00 By Rise and Fall Method: Point B.S. I.S. F.S. Rise Fall R.L. Remark Arithmetical Checks Sample Calculation:
  • 9. Page 9 By Collimation Plane Method: Point B.S. I.S. F.S. Height of Instrument Or Collimation R.L. Remark Arithmetical Checks Sample Calculation:
  • 10. Page 10 8. During fly leveling the following observation were made: B.S. = 0.650, 2.155, 1.405, 2.655, 2.435 m F.S. = 2.455, 1.305, 0.555, 2.405 m The first reading was taken on a BM of RL 90.500 m from the last BS. It is required to set four pegs each at a distance of 30 m on a following gradient of 1 in 100. Calculate the RLs of these four pegs. By Rise and Fall Method: Point B.S. I.S. F.S. Rise Fall R.L. Remark Arithmetical Checks Sample Calculation:
  • 11. Page 11 9. Calculate the RL of last station, if the RL of first station is 500 m. The staff readings observed is as below: 5.00 (staff inverted), 2.00, 3.00, 4.00 (staff inverted), 1.00, 2.00, 3.00, 4.00. Enter the data in standard leveling table. Apply Arithmetical checks. (Rise and Fall method). By Rise and Fall Method: Point B.S. I.S. F.S. Rise Fall R.L. Remark Arithmetical Checks Sample Calculation:
  • 12. Page 12 18. Calculate the reduced level of last station, If the reduced level of first station is 500 m. The staff readings observed are as shown; below: (in meter). 1.000 (Staff inverted), 2.000, 3.000,4.000 (Instrument shifted), 1.000,2.000, 3.000, 4.000. Enter the data in a standard levelling table. Apply Arithmetic checks (Use Rise and Fall method). Station B.S. I.S. F.S. Rise Fall R.L. Remark 1 2.285 232.46 BM1 2 1.65 2.265 X X X 3 2.105 X X 4 X 1.96 X X X 5 2.05 1.925 0.3 X X 6 X X 232.255 BM2 7 1.69 X 0.34 X X 8 2.865 2.1 X X X - 9 X X 233.425 BM3 Ans: Station B.S. I.S. F.S. Rise Fall R.L. Remark 1 2.285 232.46 BM1 2 1.65 2.265 3 2.105 4 1.96 5 2.05 1.925 0.3 6 232.255 BM2 7 1.69 0.34 8 2.865 2.1 - 9 233.425 BM3
  • 13. Page 13 10. The following consecutive readings were taken with a leveling instrument at interval of 20 m. 2.375, 1.730, 0.615, 3.450, 2.835, 2.070, 1.835, 0.985, 0.435, 1.630, 2.255 and 3.630 m. The instrument was shifted after fourth and eighth readings. The last reading was taken on a B.M. of R.L. 110.200 m. Find the RLs of all the points. (10) 11. The following consecutive readings were taken with a leveling instrument on 5 m leveling staff at 20 m interval. 0.385, 1.030, 1.925, 2.825, 3.730, 4.685, 0.625, 2.005, 3.110, 4.485. The very first reading on a point whose RL was 208.125 m. The level was shifted after sixth reading. Calculate the gradient of the line joining first and last point. Use Rise and Fall method. (10) 12. The following consecutive readings were taken with a leveling instrument at interval of 20 m. 2.375, 1.730, 0.615, 3.450, 2.835, 2.070, 1.835, 0.985, 0.435, 1.630, 2.255 and 3.630 m. The instrument was shifted after fourth and eighth readings. The last reading was taken on a B.M. of R.L. 110.200 m. Find the RLs of all the points. 13. Following staff readings were observed with level. The instrument was shifted after fourth and seventh reading. Enter readings in a tabular form and calculate reduced levels of all stations by Plane collimation method, assuming R.L of first station as 500 m. Find gradient of a line joining first station and last station. 1, 2,3, 4,1.5,2.5,3.5,0.5,1 (08) 14. The following consecutive readings were taken with a leveling instrument at interval of 20 m. 2.375, 1.730, 0.615, 3.450, 2.835, 2.070, 1.835, 0.985, 0.435, 1.630, 2.255 and 3.630 m. The instrument was shifted after fourth and eighth readings. The last reading was taken on a B.M. of R.L. 110.200 m. Find the RLs of all the points. (10 Mks) 15. The following consecutive readings were taken with a leveling instrument on 5 m leveling staff at 20 m interval. 0.385, 1.030, 1.925, 2.825, 3.730, 4.685, 0.625, 2.005, 3.110, 4.485. The very first reading on a point whose RL was 208.125 m. The level was shifted after sixth reading. Calculate the gradient of the line joining first and last point. Use Rise and Fall method. (10 Mks) 16. Following staff readings were recorded in a levelling work along a hill slope. 3.075, 2.270, 1.900, 3.785, 3.015, 2.490, 2.065, 0.880, 3.310, 2.195, 1.175, 0.540, 2.785, 1.790, 0.895, 3.300, 2.665, and 1.685. Levelling staff used was 4 m length. The first reading was taken
  • 14. Page 14 on B.M., having R.L. = 500.00 m. Calculate RL's of other staff positions by Rise and Fall Method. Apply arithmetical check. (10) 17. During Fly levelling operation; the following observations were made: BS 0.650; 2.155; 1.405; 2.655; 2.435 m FS 2.455; 1.305; 0.555; 2.405 m The first backsight reading was taken on a B .M. of R.L. 90.500 m from the last backsight; it is required to set four pegs each at a distance of 30 m on a falling gradient of 1 in 100. Calculate the RL's of these four pegs. 19. Following staff readings were observed with level. The instrument was shifted after fourth and seventh reading. Enter readings in a tabular form and calculate reduced levels of all stations, assuming R.L. of first station as 500m. 1, 2, 3, 4, 1.5, 2.5, 3.5, 0.5, 1. (7) 20. The following reading was taken on a continuously sloping ground at 30 m interval 4.000, 2.000, 1.000, 4.000, 3.000, and 2.000. The R.L. of starting point was 500.000 m Rule out page of levelling field book and enters the above readings. Carry out reduction of levels by rise and fall method. Apply usual arithmetic checks. Determine the gradient of the line joining the first and last point.