About ITSM Academy
     Welcome!
        Accredited Education                                                                                      Since 2003 - Tens of Thousands
                                                                                                                    Trained and Certified
                Certified Process Design Engineer (CPDE)
                                                                                                                   ITSM Professional Diplomas
                ITIL® Foundation                                                                                      Change/Support/SLM
                ITIL Capability (OSA|PPO|RCV|SOA)
                                                                                                                     Public Classes throughout U S
                                                                                                                                                U.S.
                ITIL Lifecycle (SS|SD|ST|SO|CSI)                                                                    Corporate On-Site Classes
                ITIL Managing Across the Lifecycle (MALC)                                                           Virtual Classes
                ITIL Service Manager Bridge                                                                         Courseware Li
                                                                                                                      C            Licensing
                                                                                                                                         i
                ISO/IEC 20000 Foundation                                                                              Corporate & Partner (GEM)
                MOF Foundation                                                                                    Alumni Program
        P ti l V l Add W k h
         Practical, Value-Add Workshops                                                                            PMI Global Ed
                                                                                                                        Gl b l Education P d
                                                                                                                                         Provider
                ITSM Leadership                                                                                   Federal Government (GSA)
                ITIL, MOF, ISO 20K Overviews                                                                       Contractor
                And more!                                                                                         C ifi d W
                                                                                                                    Certified Woman-Owned
                                                                                                                                    O      d

ITIL® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries
The Change Management Makeover and how the
 Standard Change Model Galvanized Success
 Implementing ITIL Change Management Best Practices in a Global
 Organization V6


Paul Fibkins
February 17 2011
F b       17,
Agenda
 g


1. Change Management Makeover – The ITIL Journey
       g      g                                y
Taking the Next Step - Standard Change Models
2. Proposal/Rationale
3. Approach
4. Governance
5. Process/Procedural definition
6. Communication
7.
7 Results
8. Keys to success
9. Things to avoid

3                 Citi Internal
The Makeover and the ITIL Journey - Goals Objectives and Scope
                                    Goals, Objectives,

  Goals
          Improve results: enhance service quality and performance though streamlined
          I             l      h         i      li     d    f          h h       li d
          service offerings and strategic business alignment
          Integrate global, standardized change management organization for optimal control
          and increased efficiency
          Leverage ITIL (v3) methodologies to instill industry leading
                                                      industry-leading
          best practices and standards

  Objectives
          Demonstrate success and improvement
          Develop and implement global standard process and procedures
          Enhance and simplify the change management tool – enable the process
          Orchestrate international awareness initiative to facilitate global roll-out

  Scope
          Manages changes for 50,000 user
          Control 400,000 requests for change (RFCs) annually spanning all regions and every
          site/location
          Manage CSI effort as a project


  4                        Citi Internal
The Makeover and the ITIL Journey - Project Management
                                               y      j        g
               Discipline
               ITIL Project Lifecycle and                                                                                              Communication, Tools and
               Methodology                                                                                                             Control
                Activities unique to the PIP Lifecycle:
                Justify project and           Engage Regions,                          Design process positions,
                                                                                                                      Build software
               assign process owner           Global Functions                         procedures, and training
     ate
Initia




                                                                     Im p le m e n t




                                                                                       Test process, procedures,
               Define target metrics: Discover best practice,                                  software
                   effectiveness,     local recommendations.
    ne




                efficiency, control
Defin




                                       CTI




                                                                                                                   Measure Process
                                                                     C lo s u r e




                                   Design target process and                              Deploy process,
               Assess and Mitigate
                              g                                                         procedures,
                                                                                        procedures software           Success
Design
     n




                                   automation requirements.
                                   a tomation req irements
                  Process Risk
                                       Justify variations.
                                                                                           CTI
                                  UK GCIB

                                      Japan                 Global

                                   Mexico                                   BAU



                                                                                                                                          ITIL TRAINING
           5                                                           Citi Internal
The Makeover and the ITIL Journey - Project Phases




  6              Citi Internal
The Makeover and the ITIL Journey - Implementation Project Summary

              Global Service Enhancement,
      Process Improvement, and Business Alignment
              Improvement



                                    Assessment & Planning
                                                        g
                                                               CBT and Media




          RCSA Standardization



                                                Global Road Show

                    Virtual Change
                         7.02




  7                 Citi Internal
The Makeover and the ITIL Journey - Project Value and Success

  Cost-Benefit Analysis
      – Cost: $
              $100 M
          • Includes computer-based training, all printed documentation and flyers, prizes/giveaways,
            technological costs, and associated travel
      – Return - financial
          • $10 MM dollar savings through incident reductions in 2009
          • $4 MM dollar savings in 2010
      – Return - qualitative
          •   Sev 1’s caused by change dropped 60%
          •   Up to
              U t 45% reduction i process execution ti
                          d ti in                  ti time
          •   Up to 80% reduction in metric compilation and reporting
          •   VOE up15%

  Key Successes
      – 5 sigma service quality amidst ever-increasing change volumes
      – 100 process improvements from Post-Implementations Reviews (PIRs)
      – 100% successful audits (No findings) through reinforced controls



  8                          Citi Internal
The Makeover and the ITIL Journey - Service Quality
                                y                 y


•    Adoption of ITIL best practices improved overall service quality even
     as change volumes continued to rise
    – Service impacts are down 68% while change volume is up 70%
    – The outage trend continues downward while change volume
        continues to increase
    – ITIL best practices contribute to the success of the company




9                   Citi Internal
The Makeover and the ITIL Journey - Project Management Discipline


  Quality
                              Adopted the ITIL IT Best Practice Framework to support IT Education Training and Continuous Service and Process Improvement..
                                                                                           Education,                                         Improvement
  Performance
                              ITIL has provided a visible framework to further quality service and process improvement.
  Framework

                                                                                                                               The Change Management ITIL based Process Flow
                                                                                                                                              CIT IGROUP INFORM ATION T ECHNOLOGY GLOBAL CHANGE MANAGEM ENT PROCESS

                                                                                                                                                                          Environment                                                                                                                                                                                                                                                                    RFC Logged and Change
                                                                                                                                                                         compromised                                                                                                                                                                                                                                                                       Requestor Notified
                                                                                                                                                                                                                                                                                                                                                                                                                                                     Not
                                                                                                                                                                                                                                                                                                                                                                                                 CMDB                                                acceptable
                                                                                                                                                                                    Change                  Submitted RFC
                                                                                                                                                                 Change fails
                                                                                                                                                                                  unauthorized
                                                                                                                                                                                                                                                                                                                                                                                                 Status
                                                                                                                               Change Requestor                                                          Work Order Request                                                                                                                                                                    notification
                                                                                                                                                                                                                                                                                                                                                                                                                                                Acceptable
                                                                                                                                                                               6.1
                                                                                                                                                                                                               Request Incomplete / Invalid
                                                                                                                                                      Identify Need     Complete, Submit, &
                                                                                                                                                                                                                                                                                                                                                                                                                    6.7.1                    6.7.2
                                                                                                                                                       for Change           Log RFC
                                                                                                                                                                                                                                                                                                                                                                                                              Validate Change            Close Change



                                                                                                                                                                                        RFC Status Notification

                                                                                                                                                                                                Filtered RFC                                                                                                                                                 RFC Status                   RFC Logged and Change
                                                                                                                                                                                                                         Not Approved            Reassign RFC                                                                                                Notification                    Requestor Notified
                                                                                                                                                                                                                                   CM Not                                                            6.2.3
                                                                                                                                                                                6.2.1                                                                                              Urgent                                                                                               Not
                                                                                                                                                                                                                                   Responsible                                                  Follow Urgent                                     6.5.1                                 approved                                                             Process complete
                                                                                                                                                                           Filter Requests                                                                                                       Procedure                                  Approve Minor or
                                                                                                                                                                                                                                                                                                                                             Medium Change                                                                                   6.7.3
                                                                                                                                                                                                                                                                                                                                                                                                                                         Conduct PIR
                                                                                                                             Change Coordinator
                                                                                                                                                                                                      Follow                   Prioritized RFC
                                                                                                                                                                                                                                                                                                                                                                                    Approved        PSA
                                                                                                                                                                                                      normal proce ss
                                                                                                                                                                                                                     6.2.2                                                                          6.2.4                                                                   6.5.2
                                                                                                                                                                                                                                                                                                                                                                                                    FSC
                                                                                                                                                                                                                Validate Initial                                                               Follow Change                                                          Validate Minor or
                                                                                                                                                                                                                   Priority                                                                   Model Procedures                                                        Medium Schedule
                                                                                                                                                                                                                                                                              Model Exists

                                                                                                                                                                                                                                             Normal Change

                                                                                                                                                                                                                                                              6.3.1
                                                                                                                                                                                                                                                     Validate / update Risk
                                                                                                                                                                                                                                                         and Category

                                                                                                                                                                                                                                                                                                                           yes
                                                                                                                                                                                                                                                                       Minor or
                                                                                                                                                                                                                                                                       Medium                    6.3.5
                                                                                                                                                                                                                                                                                             Review Minor /         Build, Test
                                                                                                                                                                                                                                                                                              Medium Plan           complete?
                                                                                                                                Change Manager

                                                                                                                                                                                                                                         Significant or Major                                                         no
                                                                                                                                                                                                                                                             6.3.3
                                                                                                                                                                                                                                                    Send Major / Significant

            ITIL is a IT industry best practice framework and Service Management Lifecycle                                                                                                                                                          RFCs to CAB, Chair CAB




            1.      The ITIL Core of 5 books and a lifecycle
                                                                                                                                                                                                                                                                                                                                           RFC Logged and Change
                                                                                                                                                                                                                                                                                                                                             Requestor Notified
                                                                                                                                                                                                                                                              6.3.4
                                                                                                                                                                                                                                                                                                                                  no
                                                                                                                                                                                                                                                         Review Major /                                             Build, Test
                                                                                                                                                                                                                                                         Significant Plan                                           complete?


            2.       Education, Training and certification components                                                                                                                                                                                                                                                      yes
                                                                                                                                                                                                                                                                                                                                   RFC Status
                                                                                                                                                                                                                                                                                                                                   Notification
                                                                                                                                                                                                                                                                                                                                                         Not
                                                                                                                                                                                                                                                                                                                                                         Approved


            3.      Service Management has 5 lifecycle phases (Strategy, Design, Transition, Operations and Continuous          Change Advisory
                                                                                                                                  Board (CAB)
                                                                                                                                                                                                                                                                                                                         6.5.3
                                                                                                                                                                                                                                                                                                                 Approve Major or
                                                                                                                                                                                                                                                                                                                 Significant Change



                    Service Improvement-CSI)
                    S i I                 CSI)                                                                                                                                                                                                                                                                                    PSA
                                                                                                                                                                                                                                                                                                                                                         Approved

                                                                                                                                                                                                                                                                                                                                                      6.5.4
                                                                                                                                                                                                                                                                                                                                               Validate Major or
                                                                                                                                                                                                                                                                                                                                              Significant Schedule

            4.      Has 20 Processes associated with the various life cycle phases                                                                                                                                                                                                                                                FSC


                                                                                                                                                                                                                                                                                                                                                                                                                           Not Working &


            5.      Built upon Deming Model service and quality improvement. Continuous Quality Control and
                                                                                                                                                                                                                                                                                                                                                                                                                           Can Back-out            6.6.2
                                                                                                                                                                                                                                                                                                                                                                                                                                             Implement Back-out
                                                                                                                                                                                                                                                                                                                                                                                                                       Working                      Plan

                                                                                                                                                                                                                                                                                                                                                                            6.6.1
                                                                                                                                                                                                                                                                                                                                                                                                                                                   6.6.3

                    Improvement.                                                                                           Change Implemente r /
                                                                                                                           Change Domain Expert
                                                                                                                                                                                                                                                                                                                                                                     Implement Change                                                           Impleme nt
                                                                                                                                                                                                                                                                                                                                                                                                                                Not Working & Remediation Plan
                                                                                                                                                                                                                                                                                                                                                                                                                                Can't Back-out



            6.      Citi has adopted and adapted the CSI framework, process best practices in Change, Incident , Problem
                                                                                                                                                                                                                                                                                                                                                                                                                                                 Incident
                                                                                                                                                                                                                                                                                                                                                                                                                                                Management
                                                                                                                                                                                                                                                                                                                                                                                         Not Working &                     Not Working &
                                                                                                                                                                                                                                                                                                                                                                                         Have Time to Repair               window closed




                    and Release as well as a comprehensive education and training program supporting a process and                             Change Management Sub-processes

                                                                                                                                                   6.1 Complete, Submit, & Log RFC           6.2 Filter & Prioritize RFC
                                                                                                                                                                                             6.2 Filter & Prioritize Change               6.3 Categorize Change                          6.4 Build & Test Change                       6.5 Approve & Schedule Change                 6.6 Implement Change                         6.7 Review, Analyze, & Close Change



                    service improvement culture.




            In sourced ITIL Education and Training Services
            In-sourced
                                                                                                                               Performance and Quality Service Trends
       1.    Delivering ITIL V3 Certification and Overview classes in Dallas, Warren, Weehawken, New
             Castle, Silver Spring, Melville, Tampa, Fort Lauderdale, Sioux Falls, The Lakes, and Delaware
             Ohio
       2.    Piloted Virtual Web-based Overview classes in September and October
       3.    500 student learners will complete V3 Yellow Belt Certification and 600 will completeV3
             Overview training by YE 2010
       4.    Adding advanced Black Belt Capability level training in 2011:
                    1.
                    1     OSA - Operational Support and Analysis
                    2.    CSI - Continual Service Improvement Lifecycle
                    3.    RCV - Release Control and Validation
The Makeover and the ITIL Journey - What’s Next?


•     Metrics reflected the positive impact of ITIL on the CM process;
      however, feedback indicated customers felt there were opportunities
      to improve the efficiency of the process
     –   ‘The process takes too long; we want to spend more time
          The
         developing code and less time raising changes’
     –   ‘ Can we optimize application/service time to market?’
     –   ‘How about Implementing a ‘fast track’ process for repeatable low
         risk, low impact changes?’
     –   ‘Is it possible to achieve efficient management of standard
          Is
         changes’
•     The spigot was turned on, voices were heard and, building on the
      success of the ITIL implementation began a new global initiative to
                          implementation,
      look at ways to improve the efficiency of the global process
11                    Citi Internal
Taking the Next Step - Standard Change Models -
Proposal/Rationale
Proposal
•   Drive a Change Management standard that targets business-sensitive
                                                       business sensitive
    optimization and improved efficiencies while maintaining a stable operating
    environment.
   – Define a global standard for classification of change types, approvals
        required and automation of workflows, where feasible
                                   workflows         feasible.
   – Implement Standard Change Model (SCM)

Rationale
•   A global, standard change management f   framework optimizes and streamlines
    processes, increases efficiency and delivery time to market and instill a stable
    operations environment
•   Definitive Gartner recommendation – Application Development and Operations
                                          pp                p              p
    Production Control change workflow should maximize the use of Standard
    Change Models
   – Industry guidance suggests 80% of Normal changes can be processed
       more efficiently as Standard changes reducing processing time and cost


12                   Citi Internal
Taking the Next Step - Standard Change Models –
Approach
• Building on prior ITIL rollout, assembled a virtual global work stream representing
  all technology groups and business sectors and regions galvanized to support
  Application Development productivity improvement goals
• Developed the Standard Change Model definition and criteria
• Id tifi d low risk, l
  Identified l   i k low i
                         impact, repeatable changes th t meet th criteria
                              t       t bl h        that    t the it i
• Implemented a role based, risk driven change process designed to:
     – Replace “one size fits all” change categorization
         p                             g      g
     – Reduce information required for raising changes and associated time spent
       with review and approval
     – Reduce administrative costs and overhead through pre-approval, replacing
                                                        pre approval
       on-demand approval
     – Improve time-to-market and business response agility
     – Retain/improve risk and control sensitivity while providing process
       improvement
13                    Citi Internal
Taking the Next Step - Standard Change Models -
    Governance
•        Implemented work stream governance process to ensure global standardization
•        Work stream empowered the SCM project team to develop the overall process,
         define tool requirements to support it and create procedural documentation
•        Licensing process documented to ensure pre-approval from all stakeholders
•        Regional and Global CAB groups review all licenses and approve for
         implementation.




    14                    Citi Internal
Taking the Next Step - Standard Change Models -
Process/Procedural Definition
•    Project team met in person for a one week offsite to develop the overall
     process
     –   Used process definition to develop the business requirements for
         the supporting tool functionality
•    Process designed to maintain controls and increase productivity and
     included:
     –   Definition and criteria
     –   Process flows
     –   Licensing and pre-authorization process
     –   Entitlements and authorization process flow
     –   Simplified RFC processing
     –   Notification
     –   Cost model to identify productivity savings
     –   Metrics and reporting
15                    Citi Internal
Taking the Next Step - Standard Change Models -
    Communication

•        Project team members were our SCM Champions and used various
         methods to get the word out:
         –   Email communication
         –   Targeted focus group meetings
         –   Collaboration tools, such as SharePoint and Virtual meetings
         –   Standard presentations outlining the process
         –   Posters/handouts designed to provide high level overviews and to
             catch the eye




    16                    Citi Internal
Taking the Next Step - Standard Change Models -
 Results
• Implemented IT industry leading best practice change paradigm: the
  Standard Change
• Governance enabled via a licensing method
   • activated 150 SCM Licenses
• E
  Executed 2,000 highly efficient - error f
        t d 2 000 hi hl ffi i t           free RFCs
                                               RFC
• Realized $200 M in productivity saves (productivity savings for a Standard
  change vs. a Normal change)
• Testimonials:
      – “The groups have been very happy with the reduced lead time and overall efficiency of the
        process .”
      – “All parties involved (including the groups performing deployments) have viewed SCMs as
         All
        very much a positive step forward.”
      – ”Using the SCM process significantly reduces turnaround time, reduces email volumes to
        senior management requesting approvals and allows for a more efficient risk and impact
        assessment to be performed on these types of activities Not only does this reduce the
                                                         activities.
        cost of a change, but it also gives time back to the requester to focus on BAU/Projects.”

 17                         Citi Internal
Taking the Next Step - Standard Change Models -
Keys to Success


•    Build
     B ild on a base with confidence
                b     ith    fid
•    Gain Senior Management support and buy-in from all groups
•    Set realistic due dates; don’t rush the process
                              don t
•    Solicit Compliance review and support of the process; assure change
     requestor groups that the process meets corporate standards
•    Do not over-engineer the process; keep it simple
            over engineer
•    Focus on communication; market the process and corresponding
     procedures; keep areas aware of progress and success
•    Solicit feedback to constantly review and improve the process
•    Produce metrics to measure results
     –   “If you are not keeping score, it’s only practice – person unknown
          If                     score it s       practice”

18                   Citi Internal
Global Work Stream Governance
  Provides oversight of software
   engineering p
     g        g processes, methodologies
                          ,           g
   and tools across the application                          Production Assurance
   development lifecycle in support of
   Production Assurance processes.

                                                                        PA Change
                                                                     Management Work
                                                                         Stream
       Key PA CM Work Stream 2010 Goal:                                                           PA CM Work Stream Purpose and Direction:
       Identify and implement standard change models
                                                                                                   Execute charter and governance structure
        to address defined, repeatable, low-risk changes,
        which account for up to 50% of workload                                                    Define Global CM process strategy, policies and
       Reduce information required for raising changes                                             standards (strategic and tactical)
        and associated time spent reviewing and signing-
        off                                                                                        Coordinate programs and projects related to Global
       Implement role based, risk driven change                                                    CM goals, including adherence to CIOC di ti
                                                                                                           l i l di      dh       t        direction
        processes                                                                                  Represent sector/region within global SME
                                                                                                    community



        CM SME
       Community
                                                                   
                                                                  
            Re-branded Global Change                                                                                 Current CM Steering Committee
          Management Steering Committee                 CM Tactical Operating Committee and Project                  members have been re-oriented to
                                                                           Teams                                     the Tactical Operating Committee
                                                                                                                     and Project Team structure.

Active Project Teams as of March 31, 2010:
1. Standard Change Models
2. CM Tool Solutions Group                      
                                                               
                                                                                             
                                                                                                             
                                                                                                              
                                          Execute Global Continuous Service Improvement Plans under the
                                           direction of the SEPG PA CM Work Stream
Figure 1 – PA CM Work Stream
Governance Model                          Responsible for program implementation within a sector/region

 19                                          Citi Internal
Standard Change Model – Summary Definition
     Standard Change Summary Definition
     A Standard Change is a change to services and infrastructure that follows an established path,
     is relatively common, and is the accepted solution to a specific requirement or set of
     requirements.
           i

     Examples might include application parameter changes, table changes, scheduled repetitive
     changes, an upgrade of a PC in order to make use of specific software, new starters within an
     organization, and PC, software and network connections for temporary or seasonal changes to
     requirements.

     The crucial elements of a Standard Change are that:

     1.   The tasks are well-known, repeatable, proven and are documented with triggers (i.e.; a rate
          change where the trigger is a communication from the business stating a change is
          needed).

     2.   Change Advisory Board (CAB) approval of the change type is effectively given in advance
          (pre-authorized).

     3.   On a periodic basis (i.e.; quarterly, semi annually) a CAB governance board certifies and
                                                semi-annually)
          licenses the continued use of the Standard Change. Any outages resulting from a Standard
          Change will trigger an immediate suspension and review by the CAB.

     4.   The change type is not a project and does not require project approval, prioritization or funding
          through a formal business/IT prioritization and/or Project Management process. Please note:
          Changes that meet the Standard Change criteria that result from project deliverables are allowed
          until the project is closed.

     5.   The change type has a well established and well-understood risk and impact and            has passed
          the risk assessment criteria for a Standard Change (i.e.; including but not limited       to:
          established, tested and documented back out plan; pre and post-implementation             testing is
          possible; version control and a release repository is in place; stand-alone change        with no
          downstream impact; historically a low risk/low impact change).

     6.   It is always recorded with an RFC.

     7.   The change is automated or can be automated (may be a manual change now but
          automation is desirable).

     8.   The Change Success Rate (CSR) metric is verifiable. Standard Changes have a high success
          rate and no outages caused by change. Any outages resulting from a Standard Change will
          trigger an immediate suspension and review by the CAB.
20                               Citi Internal
Standard Change Model – Qualification Criteria


 Standard Change Qualification Criteria

 To qualify as a Standard Change, the following pre-defined attributes must be proven and can
 be applied:

 1.   Dependencies are known.

 2.   Stability is in place. No known existing problems exist (as confirmed by Problem
      Management). Suspension triggered by an Incident remains in place until all outstanding
      problems are resolved.

 3.   Post-implementation validation is possible on every change.

 4.   Tested prior to Standard Change Model acceptance.
             p                     g            p

 5.   Deployed during an approved implementation window as agreed to by the business.

 6.   Peer review approval carried out (auditable quality and technical authorization of the change
      as part of the pre-approval process).

 7.   Standard implementation process is documented and regularly reviewed by the team /
      department accountable for the standard change
                                              change.

 8.   User impact is known (notification of change channel in place to communicate to end users
      prior to release into production)

 9.   Pre-approved by all stakeholders.

 Once the approach has been established and documented, a Standard Change process should
 be developed and promulgated to ensure that such changes are efficiently processed to support
 the organization’s business needs.

 Standard Changes are authorized by the Change Advisory Board (CAB) or licenses renewed
 periodically based on quality and efficiency metrics.
21                            Citi Internal
Production Assurance Change Management Work Stream – Mission Statement
The mission of the SEPG PA Change Management Work Stream is to develop and maintain a standardized, integrated, stable, end-to-end Change Management
process and framework. As part of this process, the SEPG PA CM Work Stream is responsible for ensuring that our process standards:
         Meet corporate objectives as set forth by the CIO Council
         Meet regulatory expectations for risk management
         Are internally consistent and in alignment across IT disciplines

                         PA CM Charter                                                                            PA CM Members & Responsibilities

Implement processes designed to standardize and simplify                                              SEPG PA CM Work Stream members are empowered to make decisions
attainment of common CM goals across regions and sectors in                                           on behalf of their sector, region or function. They manage the review
support of CIO Council Technology Governance objectives. These                                        calendar of upcoming standards, coordinate and track ongoing
strategic and tactical objectives may be directed from the                                            activities of the Tactical Operating Committee, track and manage the
regulators, from the Chief IT Risk Officer in response to an evolving                                 list of ongoing initiatives. The team also operationally coordinates
control issue, the SEPG PA CM Work Stream in response to an                                           updates to the physical standards documents and their publication,
alignment issue with the current Change Management process or                                         and reviews the wording of the CM IT Policy Standard for consistency
from the CIO Council in response to an organizational objective.
f     h               l                               l b                                             and completeness before submission to the CIOC.
                                                                                                                              f



                                                                               PA CM
                  High-Level SCM Process                                  Accomplishments                               Next Steps and Timeline
Major activities related to the SCM Process:                            Assembled Work Stream         SCM Phase 2 rollout activities (business requirements for new and
                                                                        team; established Charter              enhanced VC/Infoman SCM functionality; license rollout to 200
                                                                        and Governance process                 applications/change types; updated process & procedure
                                                                        Standardized the RFC record            documentation; training module availability; Lunch & Learn
                                                                        closure policy                         activities) – July 1 – October 30, 2010
                                                                        Developed plans for                    Rollout RFC Lifecycle globally; monitor results – September 9,
                                                                        Standard Change Model                  2010
                                                                        (SCM) rollout; identified     Review and update Global Change Management Policy to ensure
                                                                        Phase 1 pilot candidates               consistency, Audit and Regulatory transparency and retention
                                                                        Established 2010 Work                  of risk policies and controls – September 30, 2010
                                                                        Stream goals                           Implement additional VC/Infoman enhancements and
                                                                        Completed SCM Phase 1                  complete Phase 2 pilot activities – November 1 – December
                                                                        Business Requirements and              31, 2010
                                                                        SCM Pilot project plan        Implement the Follow the Sun change management support model –
                                                                        Completed SCM Phase 1                  December 31, 2010
                                                                        pilot; initiated Phase 2      Rollout Standard Change processing globally – January 1, 2011
                                                                        activities



                                                22 Internal
                                                Citi
Overall Change Process Flow with SCM
            g




             May be authorized/
             licensed in advance by
   SCM       a defined CAB
 supports
  straight
 through
processing




23
23                   Citi Internal
Standard Change Model Overview
SCM Definition
A Standard Change is a change to services and infrastructure 
that follows an established path, is relatively common, and is 
the accepted solution to a specific requirement or set of 
requirements.

The crucial elements of a standard change are:
The tasks are well known, repeatable, proven and are 
documented with triggers.
Change Advisory Board (CAB) approval of the change is given 
in advance (pre‐authorized).
On a periodic basis, a CAB governance board certifies the 
continued use of the Standard Change.  
The change type is not a project and does not require 
project approval, prioritization of funding through a formal 
business/IT prioritization and/or Project Management 
process.
The change type has a well‐established and well‐understood 
risk and impact and has passed the risk assessment criteria 
for a standard change.
It is always recorded with an RFC
The change is automated or can be automated.
The Change Success Rate (CSR) metric is verifiable.  Standard 
Changes have a high success rate and no outages caused by 
change.  Any outages resulting from a Standard Change will 
trigger an immediate suspension and review by the CAB.

SCM Qualification Criteria
To qualify as a Standard Change, the following pre‐defined 
attributes must be proven and can be applied:

Dependencies are known
Stability is in place.  No known problems exist (as confirmed 
by Problem Management).
Post‐implementation validation is possible on every change.
Tested prior to SCM acceptance.
Deployed during an approved implementation window.
Peer review approval carried out.
Standard implementation process is documented and 
regularly reviewed by the team/dept accountable for the 
standard change.                                                   
User impact is known (change notification channel in place).
Pre‐approved by all stakeholders

SCM Priority/Category
Change Priority is 3; Change Category is Standard.



                                                          24          Citi Internal
TIME FOR CHANGE
          ARE YOU tired and frustrated with                         DO YOU want to raise your                       DO YOU want to reduce 
                                                                    Virtual Change on potentially 
                                                                    Virtual Change on potentially                   the time i k
                                                                                                                     h i      it takes to raise 
                                                                                                                                            i
          chasing approvers on simple, low 
                                                                    deploy the same day?
          risk frequent changes?                                                                                    a Virtual Change?
                                    Interested? Here’s how to get an SCM Licence?
           Standard Change Model (SCM) is a NEW type of record in Virtual Change available now for 
                   streamlining the change process for repeatable low risk/impact changes
                                                              What’s in it for YOU?



                                               The STANDARD CHANGE MODEL is for YOU!
           IS MY CHANGE SCM READY?                                                                  SOME SCM EXAMPLES
Low risk/impact, Stable, Well known, Repeatable, well established and well‐
  Low risk/impact, Stable, Well known, Repeatable, well established and well      SCM candidates  
                                                                                  SCM candidates ‐ OK                 SCM candidates  NOT OK
                                                                                                                      SCM candidates – NOT OK
understood risk and impact                                                         Weekly Database Maintenance       X High risk & dependencies 
                                                                                                                               affecting multiple servers
High success rate (CSR ‐ Change Success Rate) historically                        Space Storage: Add Data files     X Project Management process
Post‐implementation validation  on every change                                   Backup  Miswarehouse              X Project  requires funding
                                                                                         Monthly Full Backup
                                                                                         Monthly Full Backup




                                                                Detailed SCM criteria available via your Change Co‐ordinator (See above)

                                                Apply for your SCM licences NOW!
                   Need More Info?                      Contact: Paul Fibkins -
25                                      Citi Internal   Kathy O’Connor –
The Change Management Makeover and how the
Standard Change Model Galvanized Success

Implementing ITIL Change Management Best Practices in a Global
Organization


February 17, 2011
Thank You ....
Questions?
ITSM Academy Affiliates

Contenu connexe

Tendances

Integrating It Frameworks, Methodologies And Best Practices Into It Delivery ...
Integrating It Frameworks, Methodologies And Best Practices Into It Delivery ...Integrating It Frameworks, Methodologies And Best Practices Into It Delivery ...
Integrating It Frameworks, Methodologies And Best Practices Into It Delivery ...Alan McSweeney
 
ITSM and Service Catalog Overview
ITSM and Service Catalog OverviewITSM and Service Catalog Overview
ITSM and Service Catalog OverviewChristopher Glennon
 
IT Service Catalog vs Service Portfolio
IT Service Catalog vs Service PortfolioIT Service Catalog vs Service Portfolio
IT Service Catalog vs Service PortfolioEvergreen Systems
 
Marlabs Capabilities Overview: Application Maintenance Support Services
Marlabs Capabilities Overview: Application Maintenance Support Services Marlabs Capabilities Overview: Application Maintenance Support Services
Marlabs Capabilities Overview: Application Maintenance Support Services Marlabs
 
June2007 Implementing Itil Problem Mgmt
June2007 Implementing Itil Problem MgmtJune2007 Implementing Itil Problem Mgmt
June2007 Implementing Itil Problem MgmtIT Service and Support
 
History of IT Service Management Practices and Standards
History of IT Service Management Practices and StandardsHistory of IT Service Management Practices and Standards
History of IT Service Management Practices and StandardsRob Akershoek
 
ITIL and ISO 20000: Fundamentals and necessary compliance Synergies
ITIL and ISO 20000: Fundamentals and necessary compliance SynergiesITIL and ISO 20000: Fundamentals and necessary compliance Synergies
ITIL and ISO 20000: Fundamentals and necessary compliance SynergiesPECB
 
Itil & Process Concepts Awareness Tadawul 5 Of March 2007
Itil & Process Concepts Awareness Tadawul 5 Of March 2007Itil & Process Concepts Awareness Tadawul 5 Of March 2007
Itil & Process Concepts Awareness Tadawul 5 Of March 2007Abdulaziz AlFaify
 
Managed Services Model For IT Services
Managed Services Model For IT Services Managed Services Model For IT Services
Managed Services Model For IT Services Ajay Rathi
 
ITIL4 – 26.11.2020
ITIL4 – 26.11.2020ITIL4 – 26.11.2020
ITIL4 – 26.11.2020itSMF Belgium
 
Business Process Management 101 Training
Business Process Management 101 TrainingBusiness Process Management 101 Training
Business Process Management 101 TrainingFranco Pang
 
Integrating ITSM Frameworks, Standards and Processes - ITSM Academy Webinar
Integrating ITSM Frameworks, Standards and Processes - ITSM Academy WebinarIntegrating ITSM Frameworks, Standards and Processes - ITSM Academy Webinar
Integrating ITSM Frameworks, Standards and Processes - ITSM Academy WebinarITSM Academy, Inc.
 
Introduction to COBIT 2019 and IT management
Introduction to COBIT 2019 and IT managementIntroduction to COBIT 2019 and IT management
Introduction to COBIT 2019 and IT managementChristian F. Nissen
 
Change Management - ITIL
Change Management - ITILChange Management - ITIL
Change Management - ITILconnorsmaureen
 
IT Service Catalog Taxonomy Essentials
IT Service Catalog Taxonomy EssentialsIT Service Catalog Taxonomy Essentials
IT Service Catalog Taxonomy EssentialsEvergreen Systems
 
ITSM Project
ITSM ProjectITSM Project
ITSM ProjectOleksandr
 
An Introduction to Benefits Realization Management
An Introduction to Benefits Realization ManagementAn Introduction to Benefits Realization Management
An Introduction to Benefits Realization ManagementCraig Letavec
 

Tendances (20)

Integrating It Frameworks, Methodologies And Best Practices Into It Delivery ...
Integrating It Frameworks, Methodologies And Best Practices Into It Delivery ...Integrating It Frameworks, Methodologies And Best Practices Into It Delivery ...
Integrating It Frameworks, Methodologies And Best Practices Into It Delivery ...
 
ITSM and Service Catalog Overview
ITSM and Service Catalog OverviewITSM and Service Catalog Overview
ITSM and Service Catalog Overview
 
IT Service Catalog vs Service Portfolio
IT Service Catalog vs Service PortfolioIT Service Catalog vs Service Portfolio
IT Service Catalog vs Service Portfolio
 
Marlabs Capabilities Overview: Application Maintenance Support Services
Marlabs Capabilities Overview: Application Maintenance Support Services Marlabs Capabilities Overview: Application Maintenance Support Services
Marlabs Capabilities Overview: Application Maintenance Support Services
 
June2007 Implementing Itil Problem Mgmt
June2007 Implementing Itil Problem MgmtJune2007 Implementing Itil Problem Mgmt
June2007 Implementing Itil Problem Mgmt
 
History of IT Service Management Practices and Standards
History of IT Service Management Practices and StandardsHistory of IT Service Management Practices and Standards
History of IT Service Management Practices and Standards
 
ITIL and ISO 20000: Fundamentals and necessary compliance Synergies
ITIL and ISO 20000: Fundamentals and necessary compliance SynergiesITIL and ISO 20000: Fundamentals and necessary compliance Synergies
ITIL and ISO 20000: Fundamentals and necessary compliance Synergies
 
Itil & Process Concepts Awareness Tadawul 5 Of March 2007
Itil & Process Concepts Awareness Tadawul 5 Of March 2007Itil & Process Concepts Awareness Tadawul 5 Of March 2007
Itil & Process Concepts Awareness Tadawul 5 Of March 2007
 
ITSM Presentation
ITSM PresentationITSM Presentation
ITSM Presentation
 
Managed Services Model For IT Services
Managed Services Model For IT Services Managed Services Model For IT Services
Managed Services Model For IT Services
 
ITIL4 – 26.11.2020
ITIL4 – 26.11.2020ITIL4 – 26.11.2020
ITIL4 – 26.11.2020
 
Business Process Management 101 Training
Business Process Management 101 TrainingBusiness Process Management 101 Training
Business Process Management 101 Training
 
Integrating ITSM Frameworks, Standards and Processes - ITSM Academy Webinar
Integrating ITSM Frameworks, Standards and Processes - ITSM Academy WebinarIntegrating ITSM Frameworks, Standards and Processes - ITSM Academy Webinar
Integrating ITSM Frameworks, Standards and Processes - ITSM Academy Webinar
 
Itil Mind Maps
Itil Mind MapsItil Mind Maps
Itil Mind Maps
 
Introduction to COBIT 2019 and IT management
Introduction to COBIT 2019 and IT managementIntroduction to COBIT 2019 and IT management
Introduction to COBIT 2019 and IT management
 
ITIL for Dummies
ITIL for DummiesITIL for Dummies
ITIL for Dummies
 
Change Management - ITIL
Change Management - ITILChange Management - ITIL
Change Management - ITIL
 
IT Service Catalog Taxonomy Essentials
IT Service Catalog Taxonomy EssentialsIT Service Catalog Taxonomy Essentials
IT Service Catalog Taxonomy Essentials
 
ITSM Project
ITSM ProjectITSM Project
ITSM Project
 
An Introduction to Benefits Realization Management
An Introduction to Benefits Realization ManagementAn Introduction to Benefits Realization Management
An Introduction to Benefits Realization Management
 

En vedette

Change Management ITIL
Change Management ITILChange Management ITIL
Change Management ITILSave10
 
Change Management PPT Slides
Change Management PPT SlidesChange Management PPT Slides
Change Management PPT SlidesYodhia Antariksa
 
Change management strategy ppt
Change management strategy pptChange management strategy ppt
Change management strategy pptsonips
 
ITIL V3 New Process Maps
ITIL V3 New Process MapsITIL V3 New Process Maps
ITIL V3 New Process Mapscityfan
 
Engineering Change Management - Overview and Best Practices
Engineering Change Management - Overview and Best PracticesEngineering Change Management - Overview and Best Practices
Engineering Change Management - Overview and Best PracticesShobhit Singhal
 
Itil change management kpi
Itil change management kpiItil change management kpi
Itil change management kpikometinegarcia
 
Change management journey scorecard
Change management journey scorecardChange management journey scorecard
Change management journey scorecardthechangesource
 
Prosci Change Measurement Framework and Scorecard - Draft
Prosci Change Measurement Framework and Scorecard - DraftProsci Change Measurement Framework and Scorecard - Draft
Prosci Change Measurement Framework and Scorecard - DraftTim Creasey
 
ITIL foundations - Complete introduction to ITIL phases, lifecycle and processes
ITIL foundations - Complete introduction to ITIL phases, lifecycle and processesITIL foundations - Complete introduction to ITIL phases, lifecycle and processes
ITIL foundations - Complete introduction to ITIL phases, lifecycle and processesRichard Grieman
 
Agile and ITIL Continuous Delivery
Agile and ITIL Continuous DeliveryAgile and ITIL Continuous Delivery
Agile and ITIL Continuous DeliveryMartin Jackson
 
Release Management
Release Management Release Management
Release Management Vyom Labs
 
ITIL v3 Foundation Presentation
ITIL v3 Foundation PresentationITIL v3 Foundation Presentation
ITIL v3 Foundation PresentationWajahat Rajab
 
Change Management
Change ManagementChange Management
Change ManagementEstragon
 

En vedette (20)

Change Management ITIL
Change Management ITILChange Management ITIL
Change Management ITIL
 
Change Management PPT Slides
Change Management PPT SlidesChange Management PPT Slides
Change Management PPT Slides
 
Change management strategy ppt
Change management strategy pptChange management strategy ppt
Change management strategy ppt
 
ITIL PPT
ITIL PPTITIL PPT
ITIL PPT
 
Change management
Change managementChange management
Change management
 
ITIL V3 New Process Maps
ITIL V3 New Process MapsITIL V3 New Process Maps
ITIL V3 New Process Maps
 
Change Management In Organisations
Change Management In  OrganisationsChange Management In  Organisations
Change Management In Organisations
 
Engineering Change Management - Overview and Best Practices
Engineering Change Management - Overview and Best PracticesEngineering Change Management - Overview and Best Practices
Engineering Change Management - Overview and Best Practices
 
Itil change management kpi
Itil change management kpiItil change management kpi
Itil change management kpi
 
Change management journey scorecard
Change management journey scorecardChange management journey scorecard
Change management journey scorecard
 
Prosci Change Measurement Framework and Scorecard - Draft
Prosci Change Measurement Framework and Scorecard - DraftProsci Change Measurement Framework and Scorecard - Draft
Prosci Change Measurement Framework and Scorecard - Draft
 
ITIL foundations - Complete introduction to ITIL phases, lifecycle and processes
ITIL foundations - Complete introduction to ITIL phases, lifecycle and processesITIL foundations - Complete introduction to ITIL phases, lifecycle and processes
ITIL foundations - Complete introduction to ITIL phases, lifecycle and processes
 
Agile and ITIL Continuous Delivery
Agile and ITIL Continuous DeliveryAgile and ITIL Continuous Delivery
Agile and ITIL Continuous Delivery
 
Release Management
Release Management Release Management
Release Management
 
Change Management
Change ManagementChange Management
Change Management
 
Change Management - Foundation
Change Management - FoundationChange Management - Foundation
Change Management - Foundation
 
ITIL v3 Foundation Presentation
ITIL v3 Foundation PresentationITIL v3 Foundation Presentation
ITIL v3 Foundation Presentation
 
Change Management
Change ManagementChange Management
Change Management
 
Incident Management
Incident ManagementIncident Management
Incident Management
 
Change Management
Change Management  Change Management
Change Management
 

Similaire à Implementing ITIL Change Management

Peeps Eye View of IT Service Management
Peeps Eye View of IT Service ManagementPeeps Eye View of IT Service Management
Peeps Eye View of IT Service ManagementITSM Academy, Inc.
 
Using Six Sigma to Drive Tangible Service Desk Improvement and Savings
Using Six Sigma to Drive Tangible Service Desk Improvement and SavingsUsing Six Sigma to Drive Tangible Service Desk Improvement and Savings
Using Six Sigma to Drive Tangible Service Desk Improvement and SavingsITSM Academy, Inc.
 
We Don't Like our Service Management Tool
We Don't Like our Service Management ToolWe Don't Like our Service Management Tool
We Don't Like our Service Management ToolITSM Academy, Inc.
 
CPDE - Certified Process Design Engineer Highlights
CPDE - Certified Process Design Engineer HighlightsCPDE - Certified Process Design Engineer Highlights
CPDE - Certified Process Design Engineer HighlightsITSM Academy, Inc.
 
ITIL Continual Service Improvement - ITSM Academy Webinar
ITIL Continual Service Improvement - ITSM Academy Webinar  ITIL Continual Service Improvement - ITSM Academy Webinar
ITIL Continual Service Improvement - ITSM Academy Webinar ITSM Academy, Inc.
 
ITIL Service Strategy - ITSM Academy Webinar
ITIL Service Strategy - ITSM Academy Webinar ITIL Service Strategy - ITSM Academy Webinar
ITIL Service Strategy - ITSM Academy Webinar ITSM Academy, Inc.
 
ITSM Academy Webinar Leveraging Process Design
ITSM Academy Webinar Leveraging Process DesignITSM Academy Webinar Leveraging Process Design
ITSM Academy Webinar Leveraging Process DesignITSM Academy, Inc.
 
Putting the PRO in PROcess Design - ITSM Academy Webinar
Putting the PRO in PROcess Design - ITSM Academy WebinarPutting the PRO in PROcess Design - ITSM Academy Webinar
Putting the PRO in PROcess Design - ITSM Academy WebinarITSM Academy, Inc.
 
Building ITIL Training & Communication Plans
Building ITIL Training & Communication PlansBuilding ITIL Training & Communication Plans
Building ITIL Training & Communication PlansITSM Academy, Inc.
 
Incident Metrics at University of Miami
Incident Metrics at University of MiamiIncident Metrics at University of Miami
Incident Metrics at University of MiamiITSM Academy, Inc.
 
QAI -ITSM Practice Presentation
QAI -ITSM Practice PresentationQAI -ITSM Practice Presentation
QAI -ITSM Practice PresentationQAIites
 
Our Leaflet ISO 20000 EXIN - TEAM Professional Services
Our Leaflet ISO 20000 EXIN - TEAM Professional ServicesOur Leaflet ISO 20000 EXIN - TEAM Professional Services
Our Leaflet ISO 20000 EXIN - TEAM Professional ServicesTEAM Professional Services
 
Ongoing Implementation of a Configuration Management System (CMS)
Ongoing Implementation of a Configuration Management System (CMS) Ongoing Implementation of a Configuration Management System (CMS)
Ongoing Implementation of a Configuration Management System (CMS) ITSM Academy, Inc.
 
ITSM Academy Webinar - Process Maturity, It's Not About the Numbers
ITSM Academy Webinar -  Process Maturity, It's Not About the NumbersITSM Academy Webinar -  Process Maturity, It's Not About the Numbers
ITSM Academy Webinar - Process Maturity, It's Not About the NumbersITSM Academy, Inc.
 
Using Six Sigma to Drive Service Desk Improvements
Using Six Sigma to Drive Service Desk ImprovementsUsing Six Sigma to Drive Service Desk Improvements
Using Six Sigma to Drive Service Desk Improvementskirkholmes11
 
Wake Forest University CAB an ITSM Academy Webinar
Wake Forest University CAB an ITSM Academy WebinarWake Forest University CAB an ITSM Academy Webinar
Wake Forest University CAB an ITSM Academy WebinarITSM Academy, Inc.
 
How to Create an Undisputable Service Management Business Case
How to Create an Undisputable Service Management Business CaseHow to Create an Undisputable Service Management Business Case
How to Create an Undisputable Service Management Business CaseITSM Academy, Inc.
 

Similaire à Implementing ITIL Change Management (20)

ITIL 2011 Explained
ITIL 2011 ExplainedITIL 2011 Explained
ITIL 2011 Explained
 
ISO 20K is Not Scary
ISO 20K is Not ScaryISO 20K is Not Scary
ISO 20K is Not Scary
 
Peeps Eye View of IT Service Management
Peeps Eye View of IT Service ManagementPeeps Eye View of IT Service Management
Peeps Eye View of IT Service Management
 
Using Six Sigma to Drive Tangible Service Desk Improvement and Savings
Using Six Sigma to Drive Tangible Service Desk Improvement and SavingsUsing Six Sigma to Drive Tangible Service Desk Improvement and Savings
Using Six Sigma to Drive Tangible Service Desk Improvement and Savings
 
We Don't Like our Service Management Tool
We Don't Like our Service Management ToolWe Don't Like our Service Management Tool
We Don't Like our Service Management Tool
 
CPDE - Certified Process Design Engineer Highlights
CPDE - Certified Process Design Engineer HighlightsCPDE - Certified Process Design Engineer Highlights
CPDE - Certified Process Design Engineer Highlights
 
ITIL Continual Service Improvement - ITSM Academy Webinar
ITIL Continual Service Improvement - ITSM Academy Webinar  ITIL Continual Service Improvement - ITSM Academy Webinar
ITIL Continual Service Improvement - ITSM Academy Webinar
 
ITIL Service Strategy - ITSM Academy Webinar
ITIL Service Strategy - ITSM Academy Webinar ITIL Service Strategy - ITSM Academy Webinar
ITIL Service Strategy - ITSM Academy Webinar
 
About ITIL Foundation
About ITIL FoundationAbout ITIL Foundation
About ITIL Foundation
 
ITSM Academy Webinar Leveraging Process Design
ITSM Academy Webinar Leveraging Process DesignITSM Academy Webinar Leveraging Process Design
ITSM Academy Webinar Leveraging Process Design
 
Putting the PRO in PROcess Design - ITSM Academy Webinar
Putting the PRO in PROcess Design - ITSM Academy WebinarPutting the PRO in PROcess Design - ITSM Academy Webinar
Putting the PRO in PROcess Design - ITSM Academy Webinar
 
Building ITIL Training & Communication Plans
Building ITIL Training & Communication PlansBuilding ITIL Training & Communication Plans
Building ITIL Training & Communication Plans
 
Incident Metrics at University of Miami
Incident Metrics at University of MiamiIncident Metrics at University of Miami
Incident Metrics at University of Miami
 
QAI -ITSM Practice Presentation
QAI -ITSM Practice PresentationQAI -ITSM Practice Presentation
QAI -ITSM Practice Presentation
 
Our Leaflet ISO 20000 EXIN - TEAM Professional Services
Our Leaflet ISO 20000 EXIN - TEAM Professional ServicesOur Leaflet ISO 20000 EXIN - TEAM Professional Services
Our Leaflet ISO 20000 EXIN - TEAM Professional Services
 
Ongoing Implementation of a Configuration Management System (CMS)
Ongoing Implementation of a Configuration Management System (CMS) Ongoing Implementation of a Configuration Management System (CMS)
Ongoing Implementation of a Configuration Management System (CMS)
 
ITSM Academy Webinar - Process Maturity, It's Not About the Numbers
ITSM Academy Webinar -  Process Maturity, It's Not About the NumbersITSM Academy Webinar -  Process Maturity, It's Not About the Numbers
ITSM Academy Webinar - Process Maturity, It's Not About the Numbers
 
Using Six Sigma to Drive Service Desk Improvements
Using Six Sigma to Drive Service Desk ImprovementsUsing Six Sigma to Drive Service Desk Improvements
Using Six Sigma to Drive Service Desk Improvements
 
Wake Forest University CAB an ITSM Academy Webinar
Wake Forest University CAB an ITSM Academy WebinarWake Forest University CAB an ITSM Academy Webinar
Wake Forest University CAB an ITSM Academy Webinar
 
How to Create an Undisputable Service Management Business Case
How to Create an Undisputable Service Management Business CaseHow to Create an Undisputable Service Management Business Case
How to Create an Undisputable Service Management Business Case
 

Plus de ITSM Academy, Inc.

SRE Roundtable with 4 DevOps Ambassadors
SRE Roundtable with 4 DevOps AmbassadorsSRE Roundtable with 4 DevOps Ambassadors
SRE Roundtable with 4 DevOps AmbassadorsITSM Academy, Inc.
 
How to improve Customer and Employee Experience with IT Service Management
How to improve Customer and Employee Experience with IT Service ManagementHow to improve Customer and Employee Experience with IT Service Management
How to improve Customer and Employee Experience with IT Service ManagementITSM Academy, Inc.
 
ITIL® 4 DSV - Drive Stakeholder Value
ITIL® 4 DSV - Drive Stakeholder ValueITIL® 4 DSV - Drive Stakeholder Value
ITIL® 4 DSV - Drive Stakeholder ValueITSM Academy, Inc.
 
ITIL® 4 HVIT - High Velocity IT
ITIL® 4 HVIT - High Velocity ITITIL® 4 HVIT - High Velocity IT
ITIL® 4 HVIT - High Velocity ITITSM Academy, Inc.
 
Adding Value with Change Management
Adding Value with Change ManagementAdding Value with Change Management
Adding Value with Change ManagementITSM Academy, Inc.
 
Is this the End of ITIL? NO, it is the end-to-end of ITIL!
Is this the End of ITIL? NO, it is the end-to-end of ITIL!Is this the End of ITIL? NO, it is the end-to-end of ITIL!
Is this the End of ITIL? NO, it is the end-to-end of ITIL!ITSM Academy, Inc.
 
Artificial Intelligence (AI) & The Future of Employee Service
Artificial Intelligence (AI) & The Future of Employee ServiceArtificial Intelligence (AI) & The Future of Employee Service
Artificial Intelligence (AI) & The Future of Employee ServiceITSM Academy, Inc.
 
Change Control in ITIL4: So Much More Than a New Name
Change Control in ITIL4: So Much More Than a New NameChange Control in ITIL4: So Much More Than a New Name
Change Control in ITIL4: So Much More Than a New NameITSM Academy, Inc.
 
Introducing “The V*A*L*U*E Formula: Do more with less and reduce stress"
Introducing “The V*A*L*U*E Formula: Do more with less and reduce stress"Introducing “The V*A*L*U*E Formula: Do more with less and reduce stress"
Introducing “The V*A*L*U*E Formula: Do more with less and reduce stress"ITSM Academy, Inc.
 
The Anatomy of XLA: eXperience Level Agreements
The Anatomy of XLA: eXperience Level AgreementsThe Anatomy of XLA: eXperience Level Agreements
The Anatomy of XLA: eXperience Level AgreementsITSM Academy, Inc.
 
DevSecOps - Blue is the new Green
DevSecOps - Blue is the new GreenDevSecOps - Blue is the new Green
DevSecOps - Blue is the new GreenITSM Academy, Inc.
 
Mapping Your Journey to ITIL Island
Mapping Your Journey to ITIL IslandMapping Your Journey to ITIL Island
Mapping Your Journey to ITIL IslandITSM Academy, Inc.
 
More on ITIL 4. The Conversation Continues
More on ITIL 4. The Conversation ContinuesMore on ITIL 4. The Conversation Continues
More on ITIL 4. The Conversation ContinuesITSM Academy, Inc.
 
Ask Me Anything - Lean Edition
Ask Me Anything - Lean EditionAsk Me Anything - Lean Edition
Ask Me Anything - Lean EditionITSM Academy, Inc.
 
Modernizing Service Management Processes with Self-Service Access
Modernizing Service Management Processes with Self-Service AccessModernizing Service Management Processes with Self-Service Access
Modernizing Service Management Processes with Self-Service AccessITSM Academy, Inc.
 
Service Portfolio - Preparing for the Future of your Organization
Service Portfolio - Preparing for the Future of your OrganizationService Portfolio - Preparing for the Future of your Organization
Service Portfolio - Preparing for the Future of your OrganizationITSM Academy, Inc.
 
Status Quo or Status Whoa? with Brad Utterback, an ITSM Academy Webinar
Status Quo or Status Whoa? with Brad Utterback, an ITSM Academy WebinarStatus Quo or Status Whoa? with Brad Utterback, an ITSM Academy Webinar
Status Quo or Status Whoa? with Brad Utterback, an ITSM Academy WebinarITSM Academy, Inc.
 

Plus de ITSM Academy, Inc. (20)

SRE Roundtable with 4 DevOps Ambassadors
SRE Roundtable with 4 DevOps AmbassadorsSRE Roundtable with 4 DevOps Ambassadors
SRE Roundtable with 4 DevOps Ambassadors
 
How to improve Customer and Employee Experience with IT Service Management
How to improve Customer and Employee Experience with IT Service ManagementHow to improve Customer and Employee Experience with IT Service Management
How to improve Customer and Employee Experience with IT Service Management
 
ITIL® 4 DSV - Drive Stakeholder Value
ITIL® 4 DSV - Drive Stakeholder ValueITIL® 4 DSV - Drive Stakeholder Value
ITIL® 4 DSV - Drive Stakeholder Value
 
ITIL® 4 HVIT - High Velocity IT
ITIL® 4 HVIT - High Velocity ITITIL® 4 HVIT - High Velocity IT
ITIL® 4 HVIT - High Velocity IT
 
ITIL4 and ServiceNow
ITIL4 and ServiceNowITIL4 and ServiceNow
ITIL4 and ServiceNow
 
Adding Value with Change Management
Adding Value with Change ManagementAdding Value with Change Management
Adding Value with Change Management
 
Is this the End of ITIL? NO, it is the end-to-end of ITIL!
Is this the End of ITIL? NO, it is the end-to-end of ITIL!Is this the End of ITIL? NO, it is the end-to-end of ITIL!
Is this the End of ITIL? NO, it is the end-to-end of ITIL!
 
Artificial Intelligence (AI) & The Future of Employee Service
Artificial Intelligence (AI) & The Future of Employee ServiceArtificial Intelligence (AI) & The Future of Employee Service
Artificial Intelligence (AI) & The Future of Employee Service
 
Change Control in ITIL4: So Much More Than a New Name
Change Control in ITIL4: So Much More Than a New NameChange Control in ITIL4: So Much More Than a New Name
Change Control in ITIL4: So Much More Than a New Name
 
Introducing “The V*A*L*U*E Formula: Do more with less and reduce stress"
Introducing “The V*A*L*U*E Formula: Do more with less and reduce stress"Introducing “The V*A*L*U*E Formula: Do more with less and reduce stress"
Introducing “The V*A*L*U*E Formula: Do more with less and reduce stress"
 
The Anatomy of XLA: eXperience Level Agreements
The Anatomy of XLA: eXperience Level AgreementsThe Anatomy of XLA: eXperience Level Agreements
The Anatomy of XLA: eXperience Level Agreements
 
DevSecOps - Blue is the new Green
DevSecOps - Blue is the new GreenDevSecOps - Blue is the new Green
DevSecOps - Blue is the new Green
 
Mapping Your Journey to ITIL Island
Mapping Your Journey to ITIL IslandMapping Your Journey to ITIL Island
Mapping Your Journey to ITIL Island
 
More on ITIL 4. The Conversation Continues
More on ITIL 4. The Conversation ContinuesMore on ITIL 4. The Conversation Continues
More on ITIL 4. The Conversation Continues
 
ITIL 4. The Next Evolution
ITIL 4. The Next EvolutionITIL 4. The Next Evolution
ITIL 4. The Next Evolution
 
Ask Me Anything - Lean Edition
Ask Me Anything - Lean EditionAsk Me Anything - Lean Edition
Ask Me Anything - Lean Edition
 
Innovate ITIL with DevOps
Innovate ITIL with DevOpsInnovate ITIL with DevOps
Innovate ITIL with DevOps
 
Modernizing Service Management Processes with Self-Service Access
Modernizing Service Management Processes with Self-Service AccessModernizing Service Management Processes with Self-Service Access
Modernizing Service Management Processes with Self-Service Access
 
Service Portfolio - Preparing for the Future of your Organization
Service Portfolio - Preparing for the Future of your OrganizationService Portfolio - Preparing for the Future of your Organization
Service Portfolio - Preparing for the Future of your Organization
 
Status Quo or Status Whoa? with Brad Utterback, an ITSM Academy Webinar
Status Quo or Status Whoa? with Brad Utterback, an ITSM Academy WebinarStatus Quo or Status Whoa? with Brad Utterback, an ITSM Academy Webinar
Status Quo or Status Whoa? with Brad Utterback, an ITSM Academy Webinar
 

Dernier

Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxKatpro Technologies
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEarley Information Science
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Paola De la Torre
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processorsdebabhi2
 

Dernier (20)

Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 

Implementing ITIL Change Management

  • 1. About ITSM Academy Welcome!  Accredited Education  Since 2003 - Tens of Thousands Trained and Certified  Certified Process Design Engineer (CPDE)  ITSM Professional Diplomas  ITIL® Foundation  Change/Support/SLM  ITIL Capability (OSA|PPO|RCV|SOA)  Public Classes throughout U S U.S.  ITIL Lifecycle (SS|SD|ST|SO|CSI)  Corporate On-Site Classes  ITIL Managing Across the Lifecycle (MALC)  Virtual Classes  ITIL Service Manager Bridge  Courseware Li C Licensing i  ISO/IEC 20000 Foundation  Corporate & Partner (GEM)  MOF Foundation  Alumni Program  P ti l V l Add W k h Practical, Value-Add Workshops  PMI Global Ed Gl b l Education P d Provider  ITSM Leadership  Federal Government (GSA)  ITIL, MOF, ISO 20K Overviews Contractor  And more!  C ifi d W Certified Woman-Owned O d ITIL® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries
  • 2. The Change Management Makeover and how the Standard Change Model Galvanized Success Implementing ITIL Change Management Best Practices in a Global Organization V6 Paul Fibkins February 17 2011 F b 17,
  • 3. Agenda g 1. Change Management Makeover – The ITIL Journey g g y Taking the Next Step - Standard Change Models 2. Proposal/Rationale 3. Approach 4. Governance 5. Process/Procedural definition 6. Communication 7. 7 Results 8. Keys to success 9. Things to avoid 3 Citi Internal
  • 4. The Makeover and the ITIL Journey - Goals Objectives and Scope Goals, Objectives, Goals Improve results: enhance service quality and performance though streamlined I l h i li d f h h li d service offerings and strategic business alignment Integrate global, standardized change management organization for optimal control and increased efficiency Leverage ITIL (v3) methodologies to instill industry leading industry-leading best practices and standards Objectives Demonstrate success and improvement Develop and implement global standard process and procedures Enhance and simplify the change management tool – enable the process Orchestrate international awareness initiative to facilitate global roll-out Scope Manages changes for 50,000 user Control 400,000 requests for change (RFCs) annually spanning all regions and every site/location Manage CSI effort as a project 4 Citi Internal
  • 5. The Makeover and the ITIL Journey - Project Management y j g Discipline ITIL Project Lifecycle and Communication, Tools and Methodology Control Activities unique to the PIP Lifecycle: Justify project and Engage Regions, Design process positions, Build software assign process owner Global Functions procedures, and training ate Initia Im p le m e n t Test process, procedures, Define target metrics: Discover best practice, software effectiveness, local recommendations. ne efficiency, control Defin CTI Measure Process C lo s u r e Design target process and Deploy process, Assess and Mitigate g procedures, procedures software Success Design n automation requirements. a tomation req irements Process Risk Justify variations. CTI UK GCIB Japan Global Mexico BAU ITIL TRAINING 5 Citi Internal
  • 6. The Makeover and the ITIL Journey - Project Phases 6 Citi Internal
  • 7. The Makeover and the ITIL Journey - Implementation Project Summary Global Service Enhancement, Process Improvement, and Business Alignment Improvement Assessment & Planning g CBT and Media RCSA Standardization Global Road Show Virtual Change 7.02 7 Citi Internal
  • 8. The Makeover and the ITIL Journey - Project Value and Success Cost-Benefit Analysis – Cost: $ $100 M • Includes computer-based training, all printed documentation and flyers, prizes/giveaways, technological costs, and associated travel – Return - financial • $10 MM dollar savings through incident reductions in 2009 • $4 MM dollar savings in 2010 – Return - qualitative • Sev 1’s caused by change dropped 60% • Up to U t 45% reduction i process execution ti d ti in ti time • Up to 80% reduction in metric compilation and reporting • VOE up15% Key Successes – 5 sigma service quality amidst ever-increasing change volumes – 100 process improvements from Post-Implementations Reviews (PIRs) – 100% successful audits (No findings) through reinforced controls 8 Citi Internal
  • 9. The Makeover and the ITIL Journey - Service Quality y y • Adoption of ITIL best practices improved overall service quality even as change volumes continued to rise – Service impacts are down 68% while change volume is up 70% – The outage trend continues downward while change volume continues to increase – ITIL best practices contribute to the success of the company 9 Citi Internal
  • 10. The Makeover and the ITIL Journey - Project Management Discipline Quality Adopted the ITIL IT Best Practice Framework to support IT Education Training and Continuous Service and Process Improvement.. Education, Improvement Performance ITIL has provided a visible framework to further quality service and process improvement. Framework The Change Management ITIL based Process Flow CIT IGROUP INFORM ATION T ECHNOLOGY GLOBAL CHANGE MANAGEM ENT PROCESS Environment RFC Logged and Change compromised Requestor Notified Not CMDB acceptable Change Submitted RFC Change fails unauthorized Status Change Requestor Work Order Request notification Acceptable 6.1 Request Incomplete / Invalid Identify Need Complete, Submit, & 6.7.1 6.7.2 for Change Log RFC Validate Change Close Change RFC Status Notification Filtered RFC RFC Status RFC Logged and Change Not Approved Reassign RFC Notification Requestor Notified CM Not 6.2.3 6.2.1 Urgent Not Responsible Follow Urgent 6.5.1 approved Process complete Filter Requests Procedure Approve Minor or Medium Change 6.7.3 Conduct PIR Change Coordinator Follow Prioritized RFC Approved PSA normal proce ss 6.2.2 6.2.4 6.5.2 FSC Validate Initial Follow Change Validate Minor or Priority Model Procedures Medium Schedule Model Exists Normal Change 6.3.1 Validate / update Risk and Category yes Minor or Medium 6.3.5 Review Minor / Build, Test Medium Plan complete? Change Manager Significant or Major no 6.3.3 Send Major / Significant ITIL is a IT industry best practice framework and Service Management Lifecycle RFCs to CAB, Chair CAB 1. The ITIL Core of 5 books and a lifecycle RFC Logged and Change Requestor Notified 6.3.4 no Review Major / Build, Test Significant Plan complete? 2. Education, Training and certification components yes RFC Status Notification Not Approved 3. Service Management has 5 lifecycle phases (Strategy, Design, Transition, Operations and Continuous Change Advisory Board (CAB) 6.5.3 Approve Major or Significant Change Service Improvement-CSI) S i I CSI) PSA Approved 6.5.4 Validate Major or Significant Schedule 4. Has 20 Processes associated with the various life cycle phases FSC Not Working & 5. Built upon Deming Model service and quality improvement. Continuous Quality Control and Can Back-out 6.6.2 Implement Back-out Working Plan 6.6.1 6.6.3 Improvement. Change Implemente r / Change Domain Expert Implement Change Impleme nt Not Working & Remediation Plan Can't Back-out 6. Citi has adopted and adapted the CSI framework, process best practices in Change, Incident , Problem Incident Management Not Working & Not Working & Have Time to Repair window closed and Release as well as a comprehensive education and training program supporting a process and Change Management Sub-processes 6.1 Complete, Submit, & Log RFC 6.2 Filter & Prioritize RFC 6.2 Filter & Prioritize Change 6.3 Categorize Change 6.4 Build & Test Change 6.5 Approve & Schedule Change 6.6 Implement Change 6.7 Review, Analyze, & Close Change service improvement culture. In sourced ITIL Education and Training Services In-sourced Performance and Quality Service Trends 1. Delivering ITIL V3 Certification and Overview classes in Dallas, Warren, Weehawken, New Castle, Silver Spring, Melville, Tampa, Fort Lauderdale, Sioux Falls, The Lakes, and Delaware Ohio 2. Piloted Virtual Web-based Overview classes in September and October 3. 500 student learners will complete V3 Yellow Belt Certification and 600 will completeV3 Overview training by YE 2010 4. Adding advanced Black Belt Capability level training in 2011: 1. 1 OSA - Operational Support and Analysis 2. CSI - Continual Service Improvement Lifecycle 3. RCV - Release Control and Validation
  • 11. The Makeover and the ITIL Journey - What’s Next? • Metrics reflected the positive impact of ITIL on the CM process; however, feedback indicated customers felt there were opportunities to improve the efficiency of the process – ‘The process takes too long; we want to spend more time The developing code and less time raising changes’ – ‘ Can we optimize application/service time to market?’ – ‘How about Implementing a ‘fast track’ process for repeatable low risk, low impact changes?’ – ‘Is it possible to achieve efficient management of standard Is changes’ • The spigot was turned on, voices were heard and, building on the success of the ITIL implementation began a new global initiative to implementation, look at ways to improve the efficiency of the global process 11 Citi Internal
  • 12. Taking the Next Step - Standard Change Models - Proposal/Rationale Proposal • Drive a Change Management standard that targets business-sensitive business sensitive optimization and improved efficiencies while maintaining a stable operating environment. – Define a global standard for classification of change types, approvals required and automation of workflows, where feasible workflows feasible. – Implement Standard Change Model (SCM) Rationale • A global, standard change management f framework optimizes and streamlines processes, increases efficiency and delivery time to market and instill a stable operations environment • Definitive Gartner recommendation – Application Development and Operations pp p p Production Control change workflow should maximize the use of Standard Change Models – Industry guidance suggests 80% of Normal changes can be processed more efficiently as Standard changes reducing processing time and cost 12 Citi Internal
  • 13. Taking the Next Step - Standard Change Models – Approach • Building on prior ITIL rollout, assembled a virtual global work stream representing all technology groups and business sectors and regions galvanized to support Application Development productivity improvement goals • Developed the Standard Change Model definition and criteria • Id tifi d low risk, l Identified l i k low i impact, repeatable changes th t meet th criteria t t bl h that t the it i • Implemented a role based, risk driven change process designed to: – Replace “one size fits all” change categorization p g g – Reduce information required for raising changes and associated time spent with review and approval – Reduce administrative costs and overhead through pre-approval, replacing pre approval on-demand approval – Improve time-to-market and business response agility – Retain/improve risk and control sensitivity while providing process improvement 13 Citi Internal
  • 14. Taking the Next Step - Standard Change Models - Governance • Implemented work stream governance process to ensure global standardization • Work stream empowered the SCM project team to develop the overall process, define tool requirements to support it and create procedural documentation • Licensing process documented to ensure pre-approval from all stakeholders • Regional and Global CAB groups review all licenses and approve for implementation. 14 Citi Internal
  • 15. Taking the Next Step - Standard Change Models - Process/Procedural Definition • Project team met in person for a one week offsite to develop the overall process – Used process definition to develop the business requirements for the supporting tool functionality • Process designed to maintain controls and increase productivity and included: – Definition and criteria – Process flows – Licensing and pre-authorization process – Entitlements and authorization process flow – Simplified RFC processing – Notification – Cost model to identify productivity savings – Metrics and reporting 15 Citi Internal
  • 16. Taking the Next Step - Standard Change Models - Communication • Project team members were our SCM Champions and used various methods to get the word out: – Email communication – Targeted focus group meetings – Collaboration tools, such as SharePoint and Virtual meetings – Standard presentations outlining the process – Posters/handouts designed to provide high level overviews and to catch the eye 16 Citi Internal
  • 17. Taking the Next Step - Standard Change Models - Results • Implemented IT industry leading best practice change paradigm: the Standard Change • Governance enabled via a licensing method • activated 150 SCM Licenses • E Executed 2,000 highly efficient - error f t d 2 000 hi hl ffi i t free RFCs RFC • Realized $200 M in productivity saves (productivity savings for a Standard change vs. a Normal change) • Testimonials: – “The groups have been very happy with the reduced lead time and overall efficiency of the process .” – “All parties involved (including the groups performing deployments) have viewed SCMs as All very much a positive step forward.” – ”Using the SCM process significantly reduces turnaround time, reduces email volumes to senior management requesting approvals and allows for a more efficient risk and impact assessment to be performed on these types of activities Not only does this reduce the activities. cost of a change, but it also gives time back to the requester to focus on BAU/Projects.” 17 Citi Internal
  • 18. Taking the Next Step - Standard Change Models - Keys to Success • Build B ild on a base with confidence b ith fid • Gain Senior Management support and buy-in from all groups • Set realistic due dates; don’t rush the process don t • Solicit Compliance review and support of the process; assure change requestor groups that the process meets corporate standards • Do not over-engineer the process; keep it simple over engineer • Focus on communication; market the process and corresponding procedures; keep areas aware of progress and success • Solicit feedback to constantly review and improve the process • Produce metrics to measure results – “If you are not keeping score, it’s only practice – person unknown If score it s practice” 18 Citi Internal
  • 19. Global Work Stream Governance Provides oversight of software engineering p g g processes, methodologies , g and tools across the application Production Assurance development lifecycle in support of Production Assurance processes. PA Change Management Work Stream Key PA CM Work Stream 2010 Goal: PA CM Work Stream Purpose and Direction: Identify and implement standard change models  Execute charter and governance structure to address defined, repeatable, low-risk changes, which account for up to 50% of workload  Define Global CM process strategy, policies and Reduce information required for raising changes standards (strategic and tactical) and associated time spent reviewing and signing- off  Coordinate programs and projects related to Global Implement role based, risk driven change CM goals, including adherence to CIOC di ti l i l di dh t direction processes  Represent sector/region within global SME community CM SME Community       Re-branded Global Change Current CM Steering Committee Management Steering Committee CM Tactical Operating Committee and Project members have been re-oriented to Teams the Tactical Operating Committee and Project Team structure. Active Project Teams as of March 31, 2010: 1. Standard Change Models 2. CM Tool Solutions Group           Execute Global Continuous Service Improvement Plans under the direction of the SEPG PA CM Work Stream Figure 1 – PA CM Work Stream Governance Model  Responsible for program implementation within a sector/region 19 Citi Internal
  • 20. Standard Change Model – Summary Definition Standard Change Summary Definition A Standard Change is a change to services and infrastructure that follows an established path, is relatively common, and is the accepted solution to a specific requirement or set of requirements. i Examples might include application parameter changes, table changes, scheduled repetitive changes, an upgrade of a PC in order to make use of specific software, new starters within an organization, and PC, software and network connections for temporary or seasonal changes to requirements. The crucial elements of a Standard Change are that: 1. The tasks are well-known, repeatable, proven and are documented with triggers (i.e.; a rate change where the trigger is a communication from the business stating a change is needed). 2. Change Advisory Board (CAB) approval of the change type is effectively given in advance (pre-authorized). 3. On a periodic basis (i.e.; quarterly, semi annually) a CAB governance board certifies and semi-annually) licenses the continued use of the Standard Change. Any outages resulting from a Standard Change will trigger an immediate suspension and review by the CAB. 4. The change type is not a project and does not require project approval, prioritization or funding through a formal business/IT prioritization and/or Project Management process. Please note: Changes that meet the Standard Change criteria that result from project deliverables are allowed until the project is closed. 5. The change type has a well established and well-understood risk and impact and has passed the risk assessment criteria for a Standard Change (i.e.; including but not limited to: established, tested and documented back out plan; pre and post-implementation testing is possible; version control and a release repository is in place; stand-alone change with no downstream impact; historically a low risk/low impact change). 6. It is always recorded with an RFC. 7. The change is automated or can be automated (may be a manual change now but automation is desirable). 8. The Change Success Rate (CSR) metric is verifiable. Standard Changes have a high success rate and no outages caused by change. Any outages resulting from a Standard Change will trigger an immediate suspension and review by the CAB. 20 Citi Internal
  • 21. Standard Change Model – Qualification Criteria Standard Change Qualification Criteria To qualify as a Standard Change, the following pre-defined attributes must be proven and can be applied: 1. Dependencies are known. 2. Stability is in place. No known existing problems exist (as confirmed by Problem Management). Suspension triggered by an Incident remains in place until all outstanding problems are resolved. 3. Post-implementation validation is possible on every change. 4. Tested prior to Standard Change Model acceptance. p g p 5. Deployed during an approved implementation window as agreed to by the business. 6. Peer review approval carried out (auditable quality and technical authorization of the change as part of the pre-approval process). 7. Standard implementation process is documented and regularly reviewed by the team / department accountable for the standard change change. 8. User impact is known (notification of change channel in place to communicate to end users prior to release into production) 9. Pre-approved by all stakeholders. Once the approach has been established and documented, a Standard Change process should be developed and promulgated to ensure that such changes are efficiently processed to support the organization’s business needs. Standard Changes are authorized by the Change Advisory Board (CAB) or licenses renewed periodically based on quality and efficiency metrics. 21 Citi Internal
  • 22. Production Assurance Change Management Work Stream – Mission Statement The mission of the SEPG PA Change Management Work Stream is to develop and maintain a standardized, integrated, stable, end-to-end Change Management process and framework. As part of this process, the SEPG PA CM Work Stream is responsible for ensuring that our process standards: Meet corporate objectives as set forth by the CIO Council Meet regulatory expectations for risk management Are internally consistent and in alignment across IT disciplines PA CM Charter PA CM Members & Responsibilities Implement processes designed to standardize and simplify SEPG PA CM Work Stream members are empowered to make decisions attainment of common CM goals across regions and sectors in on behalf of their sector, region or function. They manage the review support of CIO Council Technology Governance objectives. These calendar of upcoming standards, coordinate and track ongoing strategic and tactical objectives may be directed from the activities of the Tactical Operating Committee, track and manage the regulators, from the Chief IT Risk Officer in response to an evolving list of ongoing initiatives. The team also operationally coordinates control issue, the SEPG PA CM Work Stream in response to an updates to the physical standards documents and their publication, alignment issue with the current Change Management process or and reviews the wording of the CM IT Policy Standard for consistency from the CIO Council in response to an organizational objective. f h l l b and completeness before submission to the CIOC. f PA CM High-Level SCM Process Accomplishments Next Steps and Timeline Major activities related to the SCM Process: Assembled Work Stream SCM Phase 2 rollout activities (business requirements for new and team; established Charter enhanced VC/Infoman SCM functionality; license rollout to 200 and Governance process applications/change types; updated process & procedure Standardized the RFC record documentation; training module availability; Lunch & Learn closure policy activities) – July 1 – October 30, 2010 Developed plans for Rollout RFC Lifecycle globally; monitor results – September 9, Standard Change Model 2010 (SCM) rollout; identified Review and update Global Change Management Policy to ensure Phase 1 pilot candidates consistency, Audit and Regulatory transparency and retention Established 2010 Work of risk policies and controls – September 30, 2010 Stream goals Implement additional VC/Infoman enhancements and Completed SCM Phase 1 complete Phase 2 pilot activities – November 1 – December Business Requirements and 31, 2010 SCM Pilot project plan Implement the Follow the Sun change management support model – Completed SCM Phase 1 December 31, 2010 pilot; initiated Phase 2 Rollout Standard Change processing globally – January 1, 2011 activities 22 Internal Citi
  • 23. Overall Change Process Flow with SCM g May be authorized/ licensed in advance by SCM a defined CAB supports straight through processing 23 23 Citi Internal
  • 24. Standard Change Model Overview SCM Definition A Standard Change is a change to services and infrastructure  that follows an established path, is relatively common, and is  the accepted solution to a specific requirement or set of  requirements. The crucial elements of a standard change are: The tasks are well known, repeatable, proven and are  documented with triggers. Change Advisory Board (CAB) approval of the change is given  in advance (pre‐authorized). On a periodic basis, a CAB governance board certifies the  continued use of the Standard Change.   The change type is not a project and does not require  project approval, prioritization of funding through a formal  business/IT prioritization and/or Project Management  process. The change type has a well‐established and well‐understood  risk and impact and has passed the risk assessment criteria  for a standard change. It is always recorded with an RFC The change is automated or can be automated. The Change Success Rate (CSR) metric is verifiable.  Standard  Changes have a high success rate and no outages caused by  change.  Any outages resulting from a Standard Change will  trigger an immediate suspension and review by the CAB. SCM Qualification Criteria To qualify as a Standard Change, the following pre‐defined  attributes must be proven and can be applied: Dependencies are known Stability is in place.  No known problems exist (as confirmed  by Problem Management). Post‐implementation validation is possible on every change. Tested prior to SCM acceptance. Deployed during an approved implementation window. Peer review approval carried out. Standard implementation process is documented and  regularly reviewed by the team/dept accountable for the  standard change.   User impact is known (change notification channel in place). Pre‐approved by all stakeholders SCM Priority/Category Change Priority is 3; Change Category is Standard. 24 Citi Internal
  • 25. TIME FOR CHANGE ARE YOU tired and frustrated with  DO YOU want to raise your  DO YOU want to reduce  Virtual Change on potentially  Virtual Change on potentially the time i k h i it takes to raise  i chasing approvers on simple, low  deploy the same day? risk frequent changes? a Virtual Change? Interested? Here’s how to get an SCM Licence? Standard Change Model (SCM) is a NEW type of record in Virtual Change available now for  streamlining the change process for repeatable low risk/impact changes What’s in it for YOU? The STANDARD CHANGE MODEL is for YOU! IS MY CHANGE SCM READY? SOME SCM EXAMPLES Low risk/impact, Stable, Well known, Repeatable, well established and well‐ Low risk/impact, Stable, Well known, Repeatable, well established and well SCM candidates   SCM candidates ‐ OK SCM candidates  NOT OK SCM candidates – NOT OK understood risk and impact    Weekly Database Maintenance  X High risk & dependencies  affecting multiple servers High success rate (CSR ‐ Change Success Rate) historically  Space Storage: Add Data files X Project Management process Post‐implementation validation  on every change  Backup  Miswarehouse  X Project  requires funding Monthly Full Backup Monthly Full Backup Detailed SCM criteria available via your Change Co‐ordinator (See above) Apply for your SCM licences NOW! Need More Info? Contact: Paul Fibkins - 25 Citi Internal Kathy O’Connor –
  • 26. The Change Management Makeover and how the Standard Change Model Galvanized Success Implementing ITIL Change Management Best Practices in a Global Organization February 17, 2011 Thank You .... Questions?