SlideShare une entreprise Scribd logo
1  sur  23
Presented By
Malik Sameeullah
School of Renewable Energy and Efficiency
NATIONAL INSTITUTE OF TECHNOLOGY, KURUKSHETRA 1
Contents
 Introduction
 Economical Parameter for Engineering Project
 Net Present Value
 Payback Period
 Technical Parameter of SPV Lamp
 Data Analysis for SPV Lamp
 Result and Conclusion
2
Introduction
 Renewable system have a potential of meeting energy
demand in an environment friendly manner
 There is a financial, technical and social issue related
to RET
 Financing which is a crucial element for any project
 Socio-Cost benefit analysis is used to judge the
financial feasibility of RET
 Detail discussion on payback period and NPV in
upcoming slide
 Cost benefit analysis of Solar PV Lantern is done using
relevant data
3
Economical Parameter For Engineering Project
 When the purpose of an economic analysis is to help make a
decision, there are several key managerial indicators or
economic parameters that are considered. common decision
criteria are:
1. Net Present Value: The Net Present Value is defined as the
different between the present value of the cost inflows and
the present value of the cash outflows.
2. Payback Period: It is defined as the time required to
recover the initial investment in a project from operations.
3. Internal Rate of Return: IRR is discount rate that equates
PV(Inflows) = PV(Outflows)
4. Profit to Investment Ratio
4
Payback Period
 Time take to recover the investment
 For simple payback period with zero interest rate, payback
period (n) is given by:
𝒏=𝟎
𝒏 𝒔𝒑
𝑩 𝒏 − 𝑪 𝒏 ≥ 𝟎
Where 𝐵𝑛= cash benefit
𝐶 𝑛=cash expenses
𝑛 𝑠𝑝payback period usually less than 𝑛 𝑚𝑎𝑥
Example: A solar water heater will cost Rs. 600000 and life of 15 year.
Annual electricity saving is of Rs. 85000. Then calculate payback period?
Solution: 𝑆𝑖𝑚𝑝𝑙𝑒 𝑝𝑎𝑦𝑏𝑎𝑐𝑘 𝑝𝑒𝑟𝑖𝑜𝑑 =
𝐼𝑛𝑖𝑡𝑖𝑎𝑙 𝐼𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡
𝑁𝑒𝑡 𝐴𝑛𝑛𝑢𝑎𝑙 𝑆𝑎𝑣𝑖𝑛𝑔
=
600000
85000
= 7.06 𝑦𝑒𝑎𝑟𝑠
5
 Simple Payback period formula modified if we
consider changing value of money with time.
 Let there is interest rate (i) on initial investment
𝐶 𝑜. Then payback period formula is:
(𝐵 − 𝐶)
(1 + 𝑖)
+
(𝐵 − 𝐶)
(1 + 𝑖)2
+
(𝐵 − 𝐶)
(1 + 𝑖)3
+ … +
𝐵 − 𝐶
1 + 𝑖 𝑛
= 𝐶 𝑜
 Calculated payback period is compared with life cycle of
project. It suggest whether project is financially acceptable
or not
 Basic reason of its popularity:
1. It is very easy to understand
2. It reduce the complexity of calculation by giving the expected time
of investor money recovery
6
Net Present Value
 The difference between the present value of
benefits and the cost resulting from investment is
NPV of investment
 It value indicate the financial position of investor
 For long term project. It is a mean to calculate the
financial feasibility of project in real time
 In mathematical term:
𝑁𝑃𝑉 = 𝑗=0
𝑛 (𝐵 𝑗−𝐶 𝑗)
(1+𝑖) 𝑗
7
𝑁𝑃𝑉 = 𝐵0 − 𝐶0 +
𝑗=1
𝑛
(𝐵𝑗 − 𝐶𝑗)
(1 + 𝑖) 𝑗
 As initial benefit is zero, so 𝐵0 = 0
𝑁𝑃𝑉 = −𝐶0 + 𝑗=1
𝑛 (𝐵 𝑗−𝐶 𝑗)
(1+𝑖) 𝑗
Here 𝐶0is the initial investment
 If we assume that 𝐵𝑗 − 𝐶𝑗 = 𝐵 − 𝐶 then:
𝑁𝑃𝑉 = −𝐶0 + (𝐵 − 𝐶) 𝑗=1
𝑛 1
(1+𝑖) 𝑗
 𝑁𝑃𝑉 = −𝐶0 + 𝐵 − 𝐶 [
1+𝑖 𝑛−1
𝑖 1+𝑖 𝑛 ]
8
 NPV>0, accept the project
 NPV= 0, remain indifferent
 NPV<0, reject the project
Features of NPV:
 It consider the time value of money in it computation
through the interest rate I
 It concentrate the value of cash at a particular point in
time
 NPV give the actual present benefit or loss
 It computation is straight forward
9
Solar Photovoltaic Lanterns
 SPV lanterns are widely excepted for domestic lighting
in rural and sub urban area.
 Several incentives have been introduce by GOI to
promote SPV lantern
 There is direct subsidy and soft installment facility to
purchase SPV lanterns
 Large scale acceptance of SPV lantern depend upon a
variety of socio-techno- economics factor
 As initial cost of SPV lantern is higher than other
domestic lighting option
 Financial viability analysis is play a crucial role in its
dissemination
10
Design parameter of Solar Photovoltaic Lanterns
 The main part of SPV Lantern:
1. PV module
2. Storage battery
3. Charge regulator
4. Light source (CFL, LED)
5. Other auxiliary item (Mobile charging port)
 The size of SPV lantern can be specified in two way:
1. Power rating of module/CFL
2. Capacity of battery
 Generally mono-crystalline silicon solar module of rating
between 6-15 peak Watts is used
 Similarly, wattage of CFL/LED in the range of 2-9 W.
11
 The size of module (in peak Watts 𝑊𝑃 ) corresponding to
particular power rating of LED may be estimated as:
𝑊𝑃 =
𝑊𝑙 ∗ ℎ
𝐼 𝐺 ∗ 𝜂 𝑏 ∗ 𝜂𝑖
 Where 𝑊𝑙 is the power rating of LED
 h=daily hour of operation
 𝜂 𝑏and 𝜂𝑖is the efficiency of battery and charger
 𝐼 𝐺 is the annual mean daily global solar radiation in 𝑘𝑊ℎ 𝑚2 𝑑𝑎𝑦
 The battery storage capacity S in Ah is given by:
𝑆 =
𝐿𝐸𝐷 𝑃𝑜𝑤𝑒𝑟 ∗ ℎ𝑜𝑢𝑟 𝑜𝑓 𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑜𝑛 ∗ 𝑛𝑜. 𝑜𝑓 𝑑𝑎𝑦 𝑜𝑓 𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑜𝑛
𝐵𝑎𝑡𝑡𝑒𝑟𝑦 𝑣𝑜𝑙𝑡𝑎𝑔𝑒 ∗ 𝑐ℎ𝑎𝑟𝑔𝑒𝑟 𝑎𝑛𝑑 𝑏𝑎𝑡𝑡𝑒𝑟𝑦 𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑐𝑦 ∗ max 𝐷𝑂𝐷
Note: DOD is the maximum percentage of battery energy which can be used
(when battery is fully charged)
12
Capital cost of Lantern
Lamp (LED) Module Battery (12V) Cost of
charge
regulato
r (Rs)
Cost of
cable and
housing
(Rs)
Total
compone
nt Cost
(Rs)
Approx
Market
Cost
(Rs)
Power
rating
(W)
Cost
(Rs)
Ratin
g
(𝑊𝑃)
Cost
(Rs)
Capacit
y (Ah)
Cos
t
(Rs)
3 250 5 900 6 500 300 250 2200 2750
5 260 8 1440 10 600 300 275 2875 3600
7 265 10 1800 15 700 300 300 3365 4200
9 275 14 2520 18 750 300 325 4170 5210
11 290 16 2880 22 850 300 350 4670 5840
Component-Wise cost of different size SPV Lanterns
• By using the interpolation method, we can develop a relation between Captial
cost of lantern (𝐶𝑐) and power rating of CFL (W)
• As clearly indicate in table, there is two type of component: fixed cost and
variable cost depend upon rating
• 𝐶𝑐 = 1366 𝑊0.6
13
0
1000
2000
3000
4000
5000
6000
7000
0 2 4 6 8 10 12
CostofLantern(Rs)
Power Rating of CFL (W)
Cost of Lantern
Linear (Cost of Lantern)
0
500
1000
1500
2000
2500
0 1 2 3 4 5 6
CapitalCost(Rs)
Hours of Operation (h))
Capital Cost (Rs)
Linear (Capital Cost (Rs))
Graph between cost of
Lantern and Power rating
of CFL
Graph between capital
cost of lantern and
hours of operation
Courtesy: Financial Evaluation of Renewable Energy Technology
by S P Garg
14
Operation and Maintenance cost
 SPV Lantern designed as maintenance free unit during
its life time
 For charging it need to expose panel and system to the
sun during day and bring it back to the point of use
 As the system is designed for rural area, there is no
charge spent on labor.
 Useful life of SPV lantern is reported to be 20 year,
which is the life of module and housing
 Useful life of battery, CFL and electronics item in the
range of 3-8 year.
 So there is little bit maintenance charge involved
15
Financial Evaluation of Lantern
 There is two way of financial evaluation
1. The cost per hour of illumination (𝐶ℎ𝑙)
2. The cost per unit useful energy (𝐶 𝑢𝑢)
• The cost per hour of illumination (𝐶ℎ𝑙) : It is obtained by
dividing the annualized cost of the SPV lantern with the
total duration of lighting provided by it during a year
𝐶ℎ𝑙 =
𝐶𝑐 𝑅 𝑑, 𝑡 𝑠 + 𝐶 𝑚
𝑁0 ∗ ℎ
 Where 𝑅(𝑑, 𝑡 𝑠) is the capital recovery factor
 𝑁𝑜is the number of day in which lantern use
 𝐶 𝑚 is the annual maintenance cost
16
• The cost per unit useful energy (𝐶 𝑢𝑢): It is obtained as the
ratio of annualized cost of the lantern to the amount of
energy delivered by it.
𝐶 𝑢𝑢 =
103
[𝐶𝑐 ∗ 𝑅 𝑑, 𝑡 𝑠 + 𝐶 𝑚]
𝑁𝑜 ∗ ℎ ∗ 𝜙
• Fuel Cost of Conventional Lamp:
𝐵𝑎 = 𝑁𝑜 ∗ ℎ ∗ 𝑟𝑓 ∗ 𝑝 𝑓
Where 𝑟𝑓 hourly consumption rate
𝑝 𝑓 the market price of fuel
Market price of fuel is escalating at an annual rate e. The present worth
benefit to user is given by Present Worth Factor (𝑃(𝑑, 𝑒, 𝑡 𝑠))
• NPV of the investment in the SPV may be calculated as:
𝑁𝑃𝑉 = 𝐵𝑎 𝑃 𝑑, 𝑒, 𝑡 𝑠 − 𝐶 𝑚 𝑃 𝑑, 𝑡 𝑠 − (𝐶𝑐 − 𝜎)
Where 𝐶𝑐 is the capital cost and 𝜎 is the government subsidy
17
Battery
21%
Module
53%
Charge
regulator
15%
Housin
g
9%
Lamp
2%
Battery
42%
Module
35%
Charge
Regulator
14%
Housin
g
6%
Lamp
3%
Capital Cost Annualized Capital
Cost
Percentage Contribution of the component of the capital and annualized
capital cost of SPV Lantern
18
 When condition are identical, two hurricane lantern are
needed to provide similar illumination as given by 3 W SPV.
 Light output of 11 W SPV Lantern is comparable to a
petromax lantern
 Market price of kerosene is Rs 40/liter and after subsidy it
cost Rs 14/ liter approx.
 1 liter is used to light one hurricane lantern for approx 40
hour
2 Hurricane lanterns 3 W SPV
lantern
Petromax 11 W SPV
lantern
Subsidized
Kerosene
Market
Price of
Kerosene
Subsidized
Kerosene
Market
Price of
Kerosene
𝐶ℎ𝑙
(Rs/hr)
0.63 1.8 0.23 0.58 1.65 0.61
Comparison of Cost per hour of illumination of SPV lantern with conventional
lantern
19
 Assume SPV lamp operate for 4 hour every day
for 300 days a year, It save about 60 liters of
Kerosene.
 3-5 W SPV Lamp cost approx. Rs. 2000 and
average life of 3 year
 Net Saving=(Fuel saving cost) – (Initial
investment cost)
 For subsidized kerosene, net saving come out to
be Rs 520 and for non subsidized kerosene, net
saving is Rs 5200.
20
Conclusion
 For acceptability of any project, payback period
and cost base analysis must show positive.
 Most of the renewable energy projects are not
financial viable, we consider only the net profit
 Social issue and GHG policy allow renewable
energy to make there own platform.
 SPV lantern which provide a option of clean
light in rural area are financial viable and
socially acceptable.
 Result show that SPV lantern have a good
market potential. 21
References
1. A. K. Sinha, Chiranjib Bhattacharjee, “Cost Benefit
Analysis of Solar Powered LED Based Lighting System
for NIT Silchar”, Third International conference on Power
System, Kharagpur, Dec-2009
2. “The Economics of Money, Banking and Financial
Markets”, Frederic S. Mishkin, 7th Edition Pearson,
Boston.
3. “Financial Evaluation of Renewable Energy
Technologies”, H. P. Garg, 1st Edition Macmillan, New
Delhi
22
Contact Info: malik_sameeullah@rediffmail.com
23

Contenu connexe

Tendances

A quick guide to off grid solar power systems design
A quick guide to off grid solar power systems designA quick guide to off grid solar power systems design
A quick guide to off grid solar power systems designMathy Mpassy Isinki
 
Presentation on a grid connected Solar PV system
Presentation on a grid connected Solar PV systemPresentation on a grid connected Solar PV system
Presentation on a grid connected Solar PV systemashmomio
 
ppt on the Solar energy
ppt on the Solar energyppt on the Solar energy
ppt on the Solar energyYuvraj Singh
 
Hybrid Solar-Wind Power System
Hybrid Solar-Wind Power SystemHybrid Solar-Wind Power System
Hybrid Solar-Wind Power SystemSwapnil Nakate
 
Design off grid solar PV system
Design off grid solar PV systemDesign off grid solar PV system
Design off grid solar PV systemRajesh Pindoriya
 
Solar photovoltaic technology
Solar photovoltaic technologySolar photovoltaic technology
Solar photovoltaic technologyEr Madhuri More
 
Photovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - DesignPhotovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - DesignLeonardo ENERGY
 
Solar photovoltaic powerpoint
Solar photovoltaic powerpointSolar photovoltaic powerpoint
Solar photovoltaic powerpointWilliam Wallace
 
Grid connected pv solar power plant
Grid connected pv solar power plantGrid connected pv solar power plant
Grid connected pv solar power plantAnujkumar985
 
Hybrid solar wind power generation system
Hybrid solar wind power generation systemHybrid solar wind power generation system
Hybrid solar wind power generation systemHemanth Duru
 
Solar energy presentation what factors does neeed to it
Solar energy presentation what factors does neeed to itSolar energy presentation what factors does neeed to it
Solar energy presentation what factors does neeed to itMurali Krishna B
 
Solar Concentrators
Solar ConcentratorsSolar Concentrators
Solar ConcentratorsWaqas Tariq
 
Introduction to Off Grid Solar Power system
Introduction to Off Grid Solar Power systemIntroduction to Off Grid Solar Power system
Introduction to Off Grid Solar Power systemShoeb Ali Khan
 
Mme solar off grid &on grid solar system -
Mme solar off grid &on grid solar system - Mme solar off grid &on grid solar system -
Mme solar off grid &on grid solar system - mme
 
Rural electrification through solar and wind hybrid system
Rural electrification through solar and wind hybrid systemRural electrification through solar and wind hybrid system
Rural electrification through solar and wind hybrid systemnissy marla
 

Tendances (20)

A quick guide to off grid solar power systems design
A quick guide to off grid solar power systems designA quick guide to off grid solar power systems design
A quick guide to off grid solar power systems design
 
Presentation on a grid connected Solar PV system
Presentation on a grid connected Solar PV systemPresentation on a grid connected Solar PV system
Presentation on a grid connected Solar PV system
 
Solar off grid
Solar off gridSolar off grid
Solar off grid
 
ppt on the Solar energy
ppt on the Solar energyppt on the Solar energy
ppt on the Solar energy
 
Hybrid Solar-Wind Power System
Hybrid Solar-Wind Power SystemHybrid Solar-Wind Power System
Hybrid Solar-Wind Power System
 
Design off grid solar PV system
Design off grid solar PV systemDesign off grid solar PV system
Design off grid solar PV system
 
Solar photovoltaic technology
Solar photovoltaic technologySolar photovoltaic technology
Solar photovoltaic technology
 
Solar PV System
Solar PV SystemSolar PV System
Solar PV System
 
Photovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - DesignPhotovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - Design
 
Solar photovoltaic powerpoint
Solar photovoltaic powerpointSolar photovoltaic powerpoint
Solar photovoltaic powerpoint
 
Solarpowerplant
SolarpowerplantSolarpowerplant
Solarpowerplant
 
Grid connected pv solar power plant
Grid connected pv solar power plantGrid connected pv solar power plant
Grid connected pv solar power plant
 
Hybrid solar wind power generation system
Hybrid solar wind power generation systemHybrid solar wind power generation system
Hybrid solar wind power generation system
 
Solar energy presentation what factors does neeed to it
Solar energy presentation what factors does neeed to itSolar energy presentation what factors does neeed to it
Solar energy presentation what factors does neeed to it
 
Solar Concentrators
Solar ConcentratorsSolar Concentrators
Solar Concentrators
 
Introduction to Off Grid Solar Power system
Introduction to Off Grid Solar Power systemIntroduction to Off Grid Solar Power system
Introduction to Off Grid Solar Power system
 
Solar PV Systems Notes
Solar PV Systems NotesSolar PV Systems Notes
Solar PV Systems Notes
 
Mme solar off grid &on grid solar system -
Mme solar off grid &on grid solar system - Mme solar off grid &on grid solar system -
Mme solar off grid &on grid solar system -
 
Solar power plant
Solar power plantSolar power plant
Solar power plant
 
Rural electrification through solar and wind hybrid system
Rural electrification through solar and wind hybrid systemRural electrification through solar and wind hybrid system
Rural electrification through solar and wind hybrid system
 

En vedette

Cost benefit analysis of renewable energy
Cost benefit analysis of renewable energyCost benefit analysis of renewable energy
Cost benefit analysis of renewable energyMalik Sameeullah
 
Pay back period ..chapter solution to problems...
Pay back period ..chapter solution to problems...Pay back period ..chapter solution to problems...
Pay back period ..chapter solution to problems...mianmohsinmumtazshb
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital BudgetingDayasagar S
 
Ghana | May-16 | Off-grid energy opportunities in West Africa
Ghana | May-16 | Off-grid energy opportunities in West AfricaGhana | May-16 | Off-grid energy opportunities in West Africa
Ghana | May-16 | Off-grid energy opportunities in West AfricaSmart Villages
 
RENEWABLE ENERGY IN INDIA
RENEWABLE ENERGY IN INDIARENEWABLE ENERGY IN INDIA
RENEWABLE ENERGY IN INDIARadhika Miglani
 
Renewable energy potential for india
Renewable energy potential for indiaRenewable energy potential for india
Renewable energy potential for indiaRajkumar Viral
 
Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India sanjeev jain
 
Make in india and future of renewable energy
Make in india and future of renewable energyMake in india and future of renewable energy
Make in india and future of renewable energyManoj Bhambu
 
Value of Solar Tariff Methodology: Proposed Approach
Value of Solar Tariff Methodology: Proposed ApproachValue of Solar Tariff Methodology: Proposed Approach
Value of Solar Tariff Methodology: Proposed ApproachJohn Farrell
 
A Generalized Multistage Economic Planning Model for Distribution System Cont...
A Generalized Multistage Economic Planning Model for Distribution System Cont...A Generalized Multistage Economic Planning Model for Distribution System Cont...
A Generalized Multistage Economic Planning Model for Distribution System Cont...IJERD Editor
 
National economic planning in the capitalist system
National economic planning in the capitalist systemNational economic planning in the capitalist system
National economic planning in the capitalist systemFernando Alcoforado
 
Renewable energy : POTENTIAL and UTILIZATION IN INDIA
Renewable energy : POTENTIAL and UTILIZATION IN INDIARenewable energy : POTENTIAL and UTILIZATION IN INDIA
Renewable energy : POTENTIAL and UTILIZATION IN INDIAdhruvinpatel223187
 
Solar Energy Assessment for Community Energy Planning
Solar Energy Assessment for Community Energy PlanningSolar Energy Assessment for Community Energy Planning
Solar Energy Assessment for Community Energy PlanningLeonardo ENERGY
 
Course on Regulation and Sustainable Energy in Developing Countries - Session 4
Course on Regulation and Sustainable Energy in Developing Countries - Session 4Course on Regulation and Sustainable Energy in Developing Countries - Session 4
Course on Regulation and Sustainable Energy in Developing Countries - Session 4Leonardo ENERGY
 
New York School of Finance Brochure
New York School of Finance BrochureNew York School of Finance Brochure
New York School of Finance BrochurePaul Pignataro
 

En vedette (20)

Cost benefit analysis of renewable energy
Cost benefit analysis of renewable energyCost benefit analysis of renewable energy
Cost benefit analysis of renewable energy
 
Payback Analysis
Payback AnalysisPayback Analysis
Payback Analysis
 
Pay back period ..chapter solution to problems...
Pay back period ..chapter solution to problems...Pay back period ..chapter solution to problems...
Pay back period ..chapter solution to problems...
 
Energy scenario in India
Energy scenario in IndiaEnergy scenario in India
Energy scenario in India
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
 
Ghana | May-16 | Off-grid energy opportunities in West Africa
Ghana | May-16 | Off-grid energy opportunities in West AfricaGhana | May-16 | Off-grid energy opportunities in West Africa
Ghana | May-16 | Off-grid energy opportunities in West Africa
 
Eng economics
Eng economicsEng economics
Eng economics
 
Renewable energy in india
Renewable energy in india Renewable energy in india
Renewable energy in india
 
RENEWABLE ENERGY IN INDIA
RENEWABLE ENERGY IN INDIARENEWABLE ENERGY IN INDIA
RENEWABLE ENERGY IN INDIA
 
Renewable energy potential for india
Renewable energy potential for indiaRenewable energy potential for india
Renewable energy potential for india
 
Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India
 
Make in india and future of renewable energy
Make in india and future of renewable energyMake in india and future of renewable energy
Make in india and future of renewable energy
 
Value of Solar Tariff Methodology: Proposed Approach
Value of Solar Tariff Methodology: Proposed ApproachValue of Solar Tariff Methodology: Proposed Approach
Value of Solar Tariff Methodology: Proposed Approach
 
A Generalized Multistage Economic Planning Model for Distribution System Cont...
A Generalized Multistage Economic Planning Model for Distribution System Cont...A Generalized Multistage Economic Planning Model for Distribution System Cont...
A Generalized Multistage Economic Planning Model for Distribution System Cont...
 
National economic planning in the capitalist system
National economic planning in the capitalist systemNational economic planning in the capitalist system
National economic planning in the capitalist system
 
Renewable energy : POTENTIAL and UTILIZATION IN INDIA
Renewable energy : POTENTIAL and UTILIZATION IN INDIARenewable energy : POTENTIAL and UTILIZATION IN INDIA
Renewable energy : POTENTIAL and UTILIZATION IN INDIA
 
Solar Energy Assessment for Community Energy Planning
Solar Energy Assessment for Community Energy PlanningSolar Energy Assessment for Community Energy Planning
Solar Energy Assessment for Community Energy Planning
 
Course on Regulation and Sustainable Energy in Developing Countries - Session 4
Course on Regulation and Sustainable Energy in Developing Countries - Session 4Course on Regulation and Sustainable Energy in Developing Countries - Session 4
Course on Regulation and Sustainable Energy in Developing Countries - Session 4
 
New York School of Finance Brochure
New York School of Finance BrochureNew York School of Finance Brochure
New York School of Finance Brochure
 
CV AG - list of projects
CV AG - list of projectsCV AG - list of projects
CV AG - list of projects
 

Similaire à Pay back period and cost base analysis of solar PV Lantern

Opportunity of Analysis and Assessment of CDM Potential in Residential Area
Opportunity of Analysis and Assessment of CDM Potential in Residential AreaOpportunity of Analysis and Assessment of CDM Potential in Residential Area
Opportunity of Analysis and Assessment of CDM Potential in Residential AreaIRJET Journal
 
Estimation & Analysis of a 5KWP Solar Photovoltaic Power Plant at JIS College...
Estimation & Analysis of a 5KWP Solar Photovoltaic Power Plant at JIS College...Estimation & Analysis of a 5KWP Solar Photovoltaic Power Plant at JIS College...
Estimation & Analysis of a 5KWP Solar Photovoltaic Power Plant at JIS College...IRJET Journal
 
A Solar System to reduce the Power Crisis in Bangladesh through Electric Vehi...
A Solar System to reduce the Power Crisis in Bangladesh through Electric Vehi...A Solar System to reduce the Power Crisis in Bangladesh through Electric Vehi...
A Solar System to reduce the Power Crisis in Bangladesh through Electric Vehi...IOSR Journals
 
IRJET- Implementing Zero Energy Efficiency in Residential Building
IRJET-  	  Implementing Zero Energy Efficiency in Residential BuildingIRJET-  	  Implementing Zero Energy Efficiency in Residential Building
IRJET- Implementing Zero Energy Efficiency in Residential BuildingIRJET Journal
 
الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان...
 الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان... الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان...
الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان...Egyptian Engineers Association
 
A Path Towards Energy Efficient India-Unnat Jyoti by Affordable LEDs for All ...
A Path Towards Energy Efficient India-Unnat Jyoti by Affordable LEDs for All ...A Path Towards Energy Efficient India-Unnat Jyoti by Affordable LEDs for All ...
A Path Towards Energy Efficient India-Unnat Jyoti by Affordable LEDs for All ...Rohit vijay
 
Energy auditing, monitoring&amp; targeting, and management
Energy auditing, monitoring&amp; targeting, and managementEnergy auditing, monitoring&amp; targeting, and management
Energy auditing, monitoring&amp; targeting, and managementkiranpatilsjce
 
An agent based approach to virtual powerplants with wind power generation and...
An agent based approach to virtual powerplants with wind power generation and...An agent based approach to virtual powerplants with wind power generation and...
An agent based approach to virtual powerplants with wind power generation and...Arjun Anil
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 4
Principles of Power Systems V.K Mehta Complete Book - Chapter 4Principles of Power Systems V.K Mehta Complete Book - Chapter 4
Principles of Power Systems V.K Mehta Complete Book - Chapter 4Power System Operation
 
RESI-SOLAR for Investors
RESI-SOLAR for InvestorsRESI-SOLAR for Investors
RESI-SOLAR for InvestorsAvish Thakral
 
Energy management and cost optimization using solar energy
Energy management and cost optimization using solar energy Energy management and cost optimization using solar energy
Energy management and cost optimization using solar energy Sudipta Ambal
 
Profitability of frequency_regulation_by_electric_car
Profitability of frequency_regulation_by_electric_carProfitability of frequency_regulation_by_electric_car
Profitability of frequency_regulation_by_electric_carZedrickKhan2
 
Experimental performance of pv fed led lighting system employing particle swa...
Experimental performance of pv fed led lighting system employing particle swa...Experimental performance of pv fed led lighting system employing particle swa...
Experimental performance of pv fed led lighting system employing particle swa...eSAT Publishing House
 
Experimental performance of pv fed led lighting system employing particle swa...
Experimental performance of pv fed led lighting system employing particle swa...Experimental performance of pv fed led lighting system employing particle swa...
Experimental performance of pv fed led lighting system employing particle swa...eSAT Journals
 
THE ULTIMATE RENEWABLE RESOURCE - SOLAR POWER
THE ULTIMATE RENEWABLE RESOURCE - SOLAR POWERTHE ULTIMATE RENEWABLE RESOURCE - SOLAR POWER
THE ULTIMATE RENEWABLE RESOURCE - SOLAR POWERDv Nareshkumar
 
Sizing of Hybrid PV/Battery Power System in Sohag city
Sizing of Hybrid PV/Battery Power System in Sohag citySizing of Hybrid PV/Battery Power System in Sohag city
Sizing of Hybrid PV/Battery Power System in Sohag cityiosrjce
 
On Grid Off Grid SPV plant
On Grid Off Grid SPV plant On Grid Off Grid SPV plant
On Grid Off Grid SPV plant SyedAjmalAndrabi
 
Energy Manager_MRV article pdf
Energy Manager_MRV article pdfEnergy Manager_MRV article pdf
Energy Manager_MRV article pdfAvijit Choudhury
 

Similaire à Pay back period and cost base analysis of solar PV Lantern (20)

Opportunity of Analysis and Assessment of CDM Potential in Residential Area
Opportunity of Analysis and Assessment of CDM Potential in Residential AreaOpportunity of Analysis and Assessment of CDM Potential in Residential Area
Opportunity of Analysis and Assessment of CDM Potential in Residential Area
 
Estimation & Analysis of a 5KWP Solar Photovoltaic Power Plant at JIS College...
Estimation & Analysis of a 5KWP Solar Photovoltaic Power Plant at JIS College...Estimation & Analysis of a 5KWP Solar Photovoltaic Power Plant at JIS College...
Estimation & Analysis of a 5KWP Solar Photovoltaic Power Plant at JIS College...
 
A Solar System to reduce the Power Crisis in Bangladesh through Electric Vehi...
A Solar System to reduce the Power Crisis in Bangladesh through Electric Vehi...A Solar System to reduce the Power Crisis in Bangladesh through Electric Vehi...
A Solar System to reduce the Power Crisis in Bangladesh through Electric Vehi...
 
IRJET- Implementing Zero Energy Efficiency in Residential Building
IRJET-  	  Implementing Zero Energy Efficiency in Residential BuildingIRJET-  	  Implementing Zero Energy Efficiency in Residential Building
IRJET- Implementing Zero Energy Efficiency in Residential Building
 
الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان...
 الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان... الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان...
الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان...
 
A Path Towards Energy Efficient India-Unnat Jyoti by Affordable LEDs for All ...
A Path Towards Energy Efficient India-Unnat Jyoti by Affordable LEDs for All ...A Path Towards Energy Efficient India-Unnat Jyoti by Affordable LEDs for All ...
A Path Towards Energy Efficient India-Unnat Jyoti by Affordable LEDs for All ...
 
Energy auditing, monitoring&amp; targeting, and management
Energy auditing, monitoring&amp; targeting, and managementEnergy auditing, monitoring&amp; targeting, and management
Energy auditing, monitoring&amp; targeting, and management
 
08279156
0827915608279156
08279156
 
An agent based approach to virtual powerplants with wind power generation and...
An agent based approach to virtual powerplants with wind power generation and...An agent based approach to virtual powerplants with wind power generation and...
An agent based approach to virtual powerplants with wind power generation and...
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 4
Principles of Power Systems V.K Mehta Complete Book - Chapter 4Principles of Power Systems V.K Mehta Complete Book - Chapter 4
Principles of Power Systems V.K Mehta Complete Book - Chapter 4
 
RESI-SOLAR for Investors
RESI-SOLAR for InvestorsRESI-SOLAR for Investors
RESI-SOLAR for Investors
 
Energy management and cost optimization using solar energy
Energy management and cost optimization using solar energy Energy management and cost optimization using solar energy
Energy management and cost optimization using solar energy
 
Profitability of frequency_regulation_by_electric_car
Profitability of frequency_regulation_by_electric_carProfitability of frequency_regulation_by_electric_car
Profitability of frequency_regulation_by_electric_car
 
Experimental performance of pv fed led lighting system employing particle swa...
Experimental performance of pv fed led lighting system employing particle swa...Experimental performance of pv fed led lighting system employing particle swa...
Experimental performance of pv fed led lighting system employing particle swa...
 
Experimental performance of pv fed led lighting system employing particle swa...
Experimental performance of pv fed led lighting system employing particle swa...Experimental performance of pv fed led lighting system employing particle swa...
Experimental performance of pv fed led lighting system employing particle swa...
 
THE ULTIMATE RENEWABLE RESOURCE - SOLAR POWER
THE ULTIMATE RENEWABLE RESOURCE - SOLAR POWERTHE ULTIMATE RENEWABLE RESOURCE - SOLAR POWER
THE ULTIMATE RENEWABLE RESOURCE - SOLAR POWER
 
I010626370
I010626370I010626370
I010626370
 
Sizing of Hybrid PV/Battery Power System in Sohag city
Sizing of Hybrid PV/Battery Power System in Sohag citySizing of Hybrid PV/Battery Power System in Sohag city
Sizing of Hybrid PV/Battery Power System in Sohag city
 
On Grid Off Grid SPV plant
On Grid Off Grid SPV plant On Grid Off Grid SPV plant
On Grid Off Grid SPV plant
 
Energy Manager_MRV article pdf
Energy Manager_MRV article pdfEnergy Manager_MRV article pdf
Energy Manager_MRV article pdf
 

Dernier

UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdfSuman Jyoti
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLManishPatel169454
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Christo Ananth
 

Dernier (20)

UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 

Pay back period and cost base analysis of solar PV Lantern

  • 1. Presented By Malik Sameeullah School of Renewable Energy and Efficiency NATIONAL INSTITUTE OF TECHNOLOGY, KURUKSHETRA 1
  • 2. Contents  Introduction  Economical Parameter for Engineering Project  Net Present Value  Payback Period  Technical Parameter of SPV Lamp  Data Analysis for SPV Lamp  Result and Conclusion 2
  • 3. Introduction  Renewable system have a potential of meeting energy demand in an environment friendly manner  There is a financial, technical and social issue related to RET  Financing which is a crucial element for any project  Socio-Cost benefit analysis is used to judge the financial feasibility of RET  Detail discussion on payback period and NPV in upcoming slide  Cost benefit analysis of Solar PV Lantern is done using relevant data 3
  • 4. Economical Parameter For Engineering Project  When the purpose of an economic analysis is to help make a decision, there are several key managerial indicators or economic parameters that are considered. common decision criteria are: 1. Net Present Value: The Net Present Value is defined as the different between the present value of the cost inflows and the present value of the cash outflows. 2. Payback Period: It is defined as the time required to recover the initial investment in a project from operations. 3. Internal Rate of Return: IRR is discount rate that equates PV(Inflows) = PV(Outflows) 4. Profit to Investment Ratio 4
  • 5. Payback Period  Time take to recover the investment  For simple payback period with zero interest rate, payback period (n) is given by: 𝒏=𝟎 𝒏 𝒔𝒑 𝑩 𝒏 − 𝑪 𝒏 ≥ 𝟎 Where 𝐵𝑛= cash benefit 𝐶 𝑛=cash expenses 𝑛 𝑠𝑝payback period usually less than 𝑛 𝑚𝑎𝑥 Example: A solar water heater will cost Rs. 600000 and life of 15 year. Annual electricity saving is of Rs. 85000. Then calculate payback period? Solution: 𝑆𝑖𝑚𝑝𝑙𝑒 𝑝𝑎𝑦𝑏𝑎𝑐𝑘 𝑝𝑒𝑟𝑖𝑜𝑑 = 𝐼𝑛𝑖𝑡𝑖𝑎𝑙 𝐼𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡 𝑁𝑒𝑡 𝐴𝑛𝑛𝑢𝑎𝑙 𝑆𝑎𝑣𝑖𝑛𝑔 = 600000 85000 = 7.06 𝑦𝑒𝑎𝑟𝑠 5
  • 6.  Simple Payback period formula modified if we consider changing value of money with time.  Let there is interest rate (i) on initial investment 𝐶 𝑜. Then payback period formula is: (𝐵 − 𝐶) (1 + 𝑖) + (𝐵 − 𝐶) (1 + 𝑖)2 + (𝐵 − 𝐶) (1 + 𝑖)3 + … + 𝐵 − 𝐶 1 + 𝑖 𝑛 = 𝐶 𝑜  Calculated payback period is compared with life cycle of project. It suggest whether project is financially acceptable or not  Basic reason of its popularity: 1. It is very easy to understand 2. It reduce the complexity of calculation by giving the expected time of investor money recovery 6
  • 7. Net Present Value  The difference between the present value of benefits and the cost resulting from investment is NPV of investment  It value indicate the financial position of investor  For long term project. It is a mean to calculate the financial feasibility of project in real time  In mathematical term: 𝑁𝑃𝑉 = 𝑗=0 𝑛 (𝐵 𝑗−𝐶 𝑗) (1+𝑖) 𝑗 7
  • 8. 𝑁𝑃𝑉 = 𝐵0 − 𝐶0 + 𝑗=1 𝑛 (𝐵𝑗 − 𝐶𝑗) (1 + 𝑖) 𝑗  As initial benefit is zero, so 𝐵0 = 0 𝑁𝑃𝑉 = −𝐶0 + 𝑗=1 𝑛 (𝐵 𝑗−𝐶 𝑗) (1+𝑖) 𝑗 Here 𝐶0is the initial investment  If we assume that 𝐵𝑗 − 𝐶𝑗 = 𝐵 − 𝐶 then: 𝑁𝑃𝑉 = −𝐶0 + (𝐵 − 𝐶) 𝑗=1 𝑛 1 (1+𝑖) 𝑗  𝑁𝑃𝑉 = −𝐶0 + 𝐵 − 𝐶 [ 1+𝑖 𝑛−1 𝑖 1+𝑖 𝑛 ] 8
  • 9.  NPV>0, accept the project  NPV= 0, remain indifferent  NPV<0, reject the project Features of NPV:  It consider the time value of money in it computation through the interest rate I  It concentrate the value of cash at a particular point in time  NPV give the actual present benefit or loss  It computation is straight forward 9
  • 10. Solar Photovoltaic Lanterns  SPV lanterns are widely excepted for domestic lighting in rural and sub urban area.  Several incentives have been introduce by GOI to promote SPV lantern  There is direct subsidy and soft installment facility to purchase SPV lanterns  Large scale acceptance of SPV lantern depend upon a variety of socio-techno- economics factor  As initial cost of SPV lantern is higher than other domestic lighting option  Financial viability analysis is play a crucial role in its dissemination 10
  • 11. Design parameter of Solar Photovoltaic Lanterns  The main part of SPV Lantern: 1. PV module 2. Storage battery 3. Charge regulator 4. Light source (CFL, LED) 5. Other auxiliary item (Mobile charging port)  The size of SPV lantern can be specified in two way: 1. Power rating of module/CFL 2. Capacity of battery  Generally mono-crystalline silicon solar module of rating between 6-15 peak Watts is used  Similarly, wattage of CFL/LED in the range of 2-9 W. 11
  • 12.  The size of module (in peak Watts 𝑊𝑃 ) corresponding to particular power rating of LED may be estimated as: 𝑊𝑃 = 𝑊𝑙 ∗ ℎ 𝐼 𝐺 ∗ 𝜂 𝑏 ∗ 𝜂𝑖  Where 𝑊𝑙 is the power rating of LED  h=daily hour of operation  𝜂 𝑏and 𝜂𝑖is the efficiency of battery and charger  𝐼 𝐺 is the annual mean daily global solar radiation in 𝑘𝑊ℎ 𝑚2 𝑑𝑎𝑦  The battery storage capacity S in Ah is given by: 𝑆 = 𝐿𝐸𝐷 𝑃𝑜𝑤𝑒𝑟 ∗ ℎ𝑜𝑢𝑟 𝑜𝑓 𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑜𝑛 ∗ 𝑛𝑜. 𝑜𝑓 𝑑𝑎𝑦 𝑜𝑓 𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑜𝑛 𝐵𝑎𝑡𝑡𝑒𝑟𝑦 𝑣𝑜𝑙𝑡𝑎𝑔𝑒 ∗ 𝑐ℎ𝑎𝑟𝑔𝑒𝑟 𝑎𝑛𝑑 𝑏𝑎𝑡𝑡𝑒𝑟𝑦 𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑐𝑦 ∗ max 𝐷𝑂𝐷 Note: DOD is the maximum percentage of battery energy which can be used (when battery is fully charged) 12
  • 13. Capital cost of Lantern Lamp (LED) Module Battery (12V) Cost of charge regulato r (Rs) Cost of cable and housing (Rs) Total compone nt Cost (Rs) Approx Market Cost (Rs) Power rating (W) Cost (Rs) Ratin g (𝑊𝑃) Cost (Rs) Capacit y (Ah) Cos t (Rs) 3 250 5 900 6 500 300 250 2200 2750 5 260 8 1440 10 600 300 275 2875 3600 7 265 10 1800 15 700 300 300 3365 4200 9 275 14 2520 18 750 300 325 4170 5210 11 290 16 2880 22 850 300 350 4670 5840 Component-Wise cost of different size SPV Lanterns • By using the interpolation method, we can develop a relation between Captial cost of lantern (𝐶𝑐) and power rating of CFL (W) • As clearly indicate in table, there is two type of component: fixed cost and variable cost depend upon rating • 𝐶𝑐 = 1366 𝑊0.6 13
  • 14. 0 1000 2000 3000 4000 5000 6000 7000 0 2 4 6 8 10 12 CostofLantern(Rs) Power Rating of CFL (W) Cost of Lantern Linear (Cost of Lantern) 0 500 1000 1500 2000 2500 0 1 2 3 4 5 6 CapitalCost(Rs) Hours of Operation (h)) Capital Cost (Rs) Linear (Capital Cost (Rs)) Graph between cost of Lantern and Power rating of CFL Graph between capital cost of lantern and hours of operation Courtesy: Financial Evaluation of Renewable Energy Technology by S P Garg 14
  • 15. Operation and Maintenance cost  SPV Lantern designed as maintenance free unit during its life time  For charging it need to expose panel and system to the sun during day and bring it back to the point of use  As the system is designed for rural area, there is no charge spent on labor.  Useful life of SPV lantern is reported to be 20 year, which is the life of module and housing  Useful life of battery, CFL and electronics item in the range of 3-8 year.  So there is little bit maintenance charge involved 15
  • 16. Financial Evaluation of Lantern  There is two way of financial evaluation 1. The cost per hour of illumination (𝐶ℎ𝑙) 2. The cost per unit useful energy (𝐶 𝑢𝑢) • The cost per hour of illumination (𝐶ℎ𝑙) : It is obtained by dividing the annualized cost of the SPV lantern with the total duration of lighting provided by it during a year 𝐶ℎ𝑙 = 𝐶𝑐 𝑅 𝑑, 𝑡 𝑠 + 𝐶 𝑚 𝑁0 ∗ ℎ  Where 𝑅(𝑑, 𝑡 𝑠) is the capital recovery factor  𝑁𝑜is the number of day in which lantern use  𝐶 𝑚 is the annual maintenance cost 16
  • 17. • The cost per unit useful energy (𝐶 𝑢𝑢): It is obtained as the ratio of annualized cost of the lantern to the amount of energy delivered by it. 𝐶 𝑢𝑢 = 103 [𝐶𝑐 ∗ 𝑅 𝑑, 𝑡 𝑠 + 𝐶 𝑚] 𝑁𝑜 ∗ ℎ ∗ 𝜙 • Fuel Cost of Conventional Lamp: 𝐵𝑎 = 𝑁𝑜 ∗ ℎ ∗ 𝑟𝑓 ∗ 𝑝 𝑓 Where 𝑟𝑓 hourly consumption rate 𝑝 𝑓 the market price of fuel Market price of fuel is escalating at an annual rate e. The present worth benefit to user is given by Present Worth Factor (𝑃(𝑑, 𝑒, 𝑡 𝑠)) • NPV of the investment in the SPV may be calculated as: 𝑁𝑃𝑉 = 𝐵𝑎 𝑃 𝑑, 𝑒, 𝑡 𝑠 − 𝐶 𝑚 𝑃 𝑑, 𝑡 𝑠 − (𝐶𝑐 − 𝜎) Where 𝐶𝑐 is the capital cost and 𝜎 is the government subsidy 17
  • 18. Battery 21% Module 53% Charge regulator 15% Housin g 9% Lamp 2% Battery 42% Module 35% Charge Regulator 14% Housin g 6% Lamp 3% Capital Cost Annualized Capital Cost Percentage Contribution of the component of the capital and annualized capital cost of SPV Lantern 18
  • 19.  When condition are identical, two hurricane lantern are needed to provide similar illumination as given by 3 W SPV.  Light output of 11 W SPV Lantern is comparable to a petromax lantern  Market price of kerosene is Rs 40/liter and after subsidy it cost Rs 14/ liter approx.  1 liter is used to light one hurricane lantern for approx 40 hour 2 Hurricane lanterns 3 W SPV lantern Petromax 11 W SPV lantern Subsidized Kerosene Market Price of Kerosene Subsidized Kerosene Market Price of Kerosene 𝐶ℎ𝑙 (Rs/hr) 0.63 1.8 0.23 0.58 1.65 0.61 Comparison of Cost per hour of illumination of SPV lantern with conventional lantern 19
  • 20.  Assume SPV lamp operate for 4 hour every day for 300 days a year, It save about 60 liters of Kerosene.  3-5 W SPV Lamp cost approx. Rs. 2000 and average life of 3 year  Net Saving=(Fuel saving cost) – (Initial investment cost)  For subsidized kerosene, net saving come out to be Rs 520 and for non subsidized kerosene, net saving is Rs 5200. 20
  • 21. Conclusion  For acceptability of any project, payback period and cost base analysis must show positive.  Most of the renewable energy projects are not financial viable, we consider only the net profit  Social issue and GHG policy allow renewable energy to make there own platform.  SPV lantern which provide a option of clean light in rural area are financial viable and socially acceptable.  Result show that SPV lantern have a good market potential. 21
  • 22. References 1. A. K. Sinha, Chiranjib Bhattacharjee, “Cost Benefit Analysis of Solar Powered LED Based Lighting System for NIT Silchar”, Third International conference on Power System, Kharagpur, Dec-2009 2. “The Economics of Money, Banking and Financial Markets”, Frederic S. Mishkin, 7th Edition Pearson, Boston. 3. “Financial Evaluation of Renewable Energy Technologies”, H. P. Garg, 1st Edition Macmillan, New Delhi 22