Group Project:
Public Transport Study for Kajang – Bangi – Putrajaya –
                           Kajang–          Putrajaya–
               Bandar Seri Putra - Nilai




                    Asmah Bt. Hamim           P60159
                    Noor Hazlin Bt. Abd Rahim P60840
Objectives
   To study public transport demand in Kajang – Bangi – Putrajaya – Bandar Seri
Putra – Nilai corridor.

 To determine the most desired line for public transport between the zones that
connecting the corridor.

 To propose the suitable and sustainable public transportation system in the
corridor.
Study Area
Existing Road Linkage




                          Kajang Silk Highway
                                                      Lekas Highway




 North-South Expressway
    (PLUS Highway)




   Grandsaga Highway

                                                SKVE Highway
Existing Public Transport
a. Bus & Taxi Services

 i) Hentian Kajang (Jln. Reko)   ii) Perhentian Bas & Teksi Nilai




                                                  iii) Putrajaya Sentral
b. KTM Komuter

                       Study Area




                 KTM Komuter Route Map
c. Taxi




          Kajang Taxi Terminal
Public Transport Problems Statement
 Lack of public transport integration, existing buses is outdated, have poor-
accessibility especially in the Kajang and Bangi area.
 Unsuitable location for Kajang Town bus stop point.
Public Transport Problems Statement
 Main public transport terminal is far from komuter station and it’s shared
between Kajang and Bangi.
 Putrajaya location is far away from other facilities. No public transport to
connect between nearest places (Kajang and Bangi) and Putrajaya.
 Services of KTM Komuter are bad.
 KTM    Komuter    station   condition   cannot    accommodate   the   increasing
passenger’s demands. It has very limited parking.
Public Transport Problems Statement
 Public transportation services unavailable at Bandar Seri Putra.
 No public transport services to Nilai 3 and no terminal at Nilai 3 except mini
bus.
Recommended Action Plans
Action 1: Traffic Management


                                        Intersection 2




                                        Intersection 1




                        Two Intersections at Jalan Reko
Intersection 1                             Intersection 2



Traffic congestion happened at these two intersections especially on peak hours.
Extending the slip road lane to SILK Highway from UKM without using traffic light and
introducing turn left from highway to Kajang without using traffic signal will reduce
the congested and safety to user.
Roundabout 1



                                     Roundabout 2



                        Two Roundabouts Nearby Seksyen 15, Bangi


The introduction of traffic signal control at this roundabout, will allow the right turning
maneuvers to be accommodated at this important location especially during evening peak.
It is can reduce the extent of circuitous trips undertaken on this section of the
urban road network.
Recommended Action Plans
Action 2: Central Area Bus Management Scheme



                       Objectives of scheme



    Improve the accessibility
                                         Encourage bus usage
        of bus services
Recommended Action Plans
                                   Jln. Cheras
                             Bus lane




                    Jln. Stadium




                                                             Jln. Semenyih
    Jln. Sg. Chua   Jln. Mendaling       Jln. Besar




                                                 Jln. Reko




                                     Bus Lane Route
Recommended Action Plans
  - Jalan Bukit must restrict to other type of vehicle except bus, school bus
   and taxi.

  - Relocation of the bus station and taxi stand from Jalan Besar to Jalan
   Bukit nearby Kajang KTM Station

                                             Proposed new location for
                                             BRT Transit Central and taxi
                                             stand
Traffic Modelling
             Trip Generation




             Trip Distribution




               Modal Split




            Trip Assignment
Trip Assignment


   Kajang-     Bangi-     Putrajaya-   Bdr Seri
    Bangi     Putrajaya   Bdr Seri     Putra-Nilai
                          Putra
  (87,824)/   (59,585)/    (32,250)/    (16,251)/
  (100,164)   (74,651)     (42,313)      (11,717)
Long Term Public Transport Plan

                              - Double-line LRT from Kajang to
                               Bandar Baru Bangi, Putrajaya,
                               Bandar Seri Putra and Nilai.




   Light Rail Transit (LRT)
Light Rapid Transit (LRT)
                            Near Hulu
                                                            At Kajang KTM Komuter
                          Langat District
                                                                    Station
                             Office

     NearAlamanda,                             Near Seksyen 7
       Putrajaya

                     Near Sg.
                      Merab

                       Near Kg.             Near Pekan
                     Teras Jernang            Bangi

                                                                  Near Bandar Seri
                                                                       Putra




                                                         At Batang Benar
                                                         KTM Komuter
                                                             Station


                                             At Nilai KTM
                                            Komuter Station


                         LRT Route and Stations
Bus Rapid Transit (BRT)
                                                   Near Kajang Specialist Hospital




              Near Satay Hj. Samuri
                                                     Near Kajang Police Station
Near intersection Jalan                                                              Near Metro Point
          7/1




                   In front Plaza Metro Kajang




                                                                            Near Kajang KTM Komuter
                                                                             (proposed BRT Transit
                          At Hentian Kajang, Jln. Reko                               Central)

                                   BRT Route and Stations at Kajang Town
Bus Rapid Transit (BRT)


                 Near Nilai 3


                                        Near Nilai Impian




                      Near Nilai
                    Industrial Area




                                      Near Nilai KTM Komuter
                                              Station

            BRT Route and Stations at Nilai
Bus Rapid Transit (BRT)


                          BRT Stop




 BRT Transit Central
Feeder Bus
Feeder bus services are designed to pick up passengers in a certain locality, and
take them to a transfer point where they make an onward journey on a trunk service.
Provide bus service to LRT and KTM station. In this study, feeder bus proposed to
zones that have LRT services; Nilai, Bandar Sri Putra, Putrajaya, Bandar Baru Bangi
and Kajang. Feeder buses may act as part of a wider local network, or a regional
coach network.
5. near Kajang Specialist Hospital
                                       4. near Satay Hj. Samuri
                                                                                6. near Kajang Police
                             3. near intersection Jln. 7/1                              Station
                                                                                            7. near Metro Point
                                      2. in front Plaza Metro Kajang                        8. near Kajang KTM Komuter Station

                                             2. near Seksyen 7, Bangi              1. at Kajang KTM Komuter
                                                                                              Station
                            3. near Hulu
                           Langat District                                         1. at Hentian Kajang, Jln. Reko
4. nearAlamanda,               Office
    Putrajaya


                        5. near Sg.
                          Merab
                           6. near Kg.
                          Teras Jernang

                                                             7. near Pekan Bangi
 Legend:-

             Proposed Location of
             LRT Station                                                                  8. Near Bandar Seri Putra

             Proposed Location of
             BRT Station at Nilai

             Proposed Location
             BRT Station at Kajang Town

            BRT Station                                             4. near Nilai 3
                                                                                                                     Overall Layout of Proposed
            LRT Station                                                3. near Nilai Impian
                                                                                                                     Public Transport in Study
            LRT Line                                                                                                 Area
                                                                  2. near Nilai Industrial Area
            BRT Line at Nilai
                                                         1. near KTM Komuter Station                        9. at Batang Benar
            BRT Line at Kajang Town                                                                        KTM Komuter Station
                                                                      10. at Nilai
                                                                     KTM Komuter
                                                                        Station
Cost Estimation
Cost Estimation for Action Plans
1) 2 Intersections at Jalan Reko
   Cost estimation for extend and add lane for 1 intersection
   Length                          =            300 m
   Width                           =               3 m
   Excavation depth                =             0.3 m
   Area volume                     =            270 m3

   Sand/Crusher Run                =           25.00 RM/m3
   Pavement                        =           30.00 RM/m3
   Compaction                      =           30.00 RM/m3
   Excavation work                 =           25.00 RM/m3
                                   =         110.00 RM/m3
   Others (kerb, lanscape,         =      20,000.00 RM
   signboard)
   Sum of cost                     =         49,700 RM          X 2 = RM 99,400.00
Cost Estimation
Cost Estimation for Action Plans

2) 2 Roundabout Nearby Seksyen 15, Bangi
   Estimate for traffic light at 2 roundabout = 12nos x RM 300,000.00 = RM
   3,600,000.00

3) Bus lanes at Kajang Town
  - Use existing asphalt on bus way = 20km x RM 450,000.00 = RM 9,000,000.00
  - New asphalt on single lane busway = 4km x RM 2,200,000.00 = RM
   8,800,000.00
  - Bus way with fully colorized lanes = 24km x RM 150,000.00 = RM 3,600,000.00
   Total Cost Estimation for Bus Lanes at Kajang Town = RM 21,400,000.00
4) BRT Transit Central and Taxi Stand
  Built BRT Transit Central = RM 7,000,000.00
  Total of Cost Estimate for Action Plans = RM 32,099,400.00
Cost Estimation
Cost Estimation for Long Term Plans

1) Light Rapid Transit
  - Railway = 60km x RM 50,000,000.00 = RM 3,000,000,000.00
  - Station = 10nos x RM 5,000,000.00 = RM 50,000,000.00
  Total Cost Estimation for LRT = RM 3,050,000,000.00

2) BRT at Kajang
   - Station (3m wide) = 14nos x RM 600,000.00 = RM 8,400,000.00
   - Air conditioned inside station = 14nos x RM 100,000.00 = RM 1,400,000.00
   - Sliding door (8 door per station) = 14nos x RM 120,000.00 = RM 1,680,000.00
   - Station identification post = 14 nos x RM 2,500.00 = RM 35,000.00
   - Fare system (complete set) = 14nos x RM 1,500,000.00 = RM 21,000,000.00
   - Pedestrian crosswalk with signal = 7nos x RM 60,000.00 = RM 420,000.00
- GPS system = RM 3,000.000.00
   Total Cost Estimation for BRT at Kajang = RM 32,935,000.00

3) BRT at Nilai
  - Use existing asphalt on busway = 20km x RM 450,000.00 = RM 9,000,000.00
  - New asphalt on single lane busway = 5km x RM 2,200,000.00 = RM
    11,000,000.00
   - Busway with fully colourised lanes = 25km x RM 150,000.00 = RM 3,750.000.00
   - Station (3m wide) = 8nos x RM 600,000.00 = RM 4,800,000.00
   - Air conditioned inside station = 8nos x RM 100,000.00 = RM 800,000.00
   - Sliding door (8 door per station) = 8nos x RM 120,000.00 = RM 960,000.00
   - Station identification post = 8nos x RM 2,500.00 = RM 20,000.00
   - Fare system (complete set) = 8nos x RM 1,500,000.00 = RM 12,000,000.00
   - Pedestrian crosswalk with signal = 4nos x RM 60,000.00 = RM 240,000.00
   - GPS system = RM 3,000.000.00
   Total Cost Estimation for BRT at Nilai = RM 45,570,000.00
4) Feeder Bus
  Feeder bus = 50nos x RM 700,000.00 = RM 35,000,000.00


Total of Cost Estimate for Long Term Plans = RM 3,163,505,000.00
Conclusion
1) LRT for Kajang - Bandar Baru Bangi – Putrajaya – Bandar Seri Putra - Nilai
2) BRT for Nilai – Nilai 3 and Kajang Town


-   The public’s attitude and willingness to shift to different modes of transport have
    been identified as an important step in the improvement process.

-   Financial backing and support from the government is also important in ensuring
    the success of the public transport network in this area.
Public Transport Study

Contenu connexe

Similaire à Public Transport Study

UKM-Urban final presentation
UKM-Urban final presentationUKM-Urban final presentation
UKM-Urban final presentationMalek Algadi
 
A study for: (Public transport demand and requirement in 2020 for Kajang-Bang...
A study for: (Public transport demand and requirement in 2020 for Kajang-Bang...A study for: (Public transport demand and requirement in 2020 for Kajang-Bang...
A study for: (Public transport demand and requirement in 2020 for Kajang-Bang...عبد الله الساجر
 
A study for: (Public transport demand and requirement in 2020 for Kajang-Bang...
A study for: (Public transport demand and requirement in 2020 for Kajang-Bang...A study for: (Public transport demand and requirement in 2020 for Kajang-Bang...
A study for: (Public transport demand and requirement in 2020 for Kajang-Bang...p71089
 
Urban presentation
Urban presentationUrban presentation
Urban presentationsarah_hazim
 
MRT TRANSPORTATION
MRT TRANSPORTATION MRT TRANSPORTATION
MRT TRANSPORTATION Shadina Shah
 
KA6564 Assignment 4 - Urban Public Transport Report
KA6564 Assignment 4 - Urban Public Transport ReportKA6564 Assignment 4 - Urban Public Transport Report
KA6564 Assignment 4 - Urban Public Transport Reportarmada7000
 
Development plane of urban transportation in Malaysia
Development plane of urban transportation in MalaysiaDevelopment plane of urban transportation in Malaysia
Development plane of urban transportation in Malaysiaengrasha
 
SPAD_ASLI_29FEB2016
SPAD_ASLI_29FEB2016SPAD_ASLI_29FEB2016
SPAD_ASLI_29FEB2016Norma Nun
 
Training report on JMRC
Training report on JMRCTraining report on JMRC
Training report on JMRCtushar garg
 
MRT REPORT TPT 250
MRT REPORT TPT 250MRT REPORT TPT 250
MRT REPORT TPT 250Shadina Shah
 
Bengaluru Suburban Rail Brochure - 4 page
Bengaluru Suburban Rail Brochure - 4 pageBengaluru Suburban Rail Brochure - 4 page
Bengaluru Suburban Rail Brochure - 4 pageKhader Syed
 
Sustainable Transport Trends & Opportunities for Indian Cities - Planning for...
Sustainable Transport Trends & Opportunities for Indian Cities - Planning for...Sustainable Transport Trends & Opportunities for Indian Cities - Planning for...
Sustainable Transport Trends & Opportunities for Indian Cities - Planning for...WRI Ross Center for Sustainable Cities
 

Similaire à Public Transport Study (20)

Urban presentation
Urban presentationUrban presentation
Urban presentation
 
Urban transportation
Urban transportationUrban transportation
Urban transportation
 
UKM-Urban final presentation
UKM-Urban final presentationUKM-Urban final presentation
UKM-Urban final presentation
 
URBAN TRANSPORT DEVELOPMENT PLANNING
URBAN TRANSPORT DEVELOPMENT PLANNINGURBAN TRANSPORT DEVELOPMENT PLANNING
URBAN TRANSPORT DEVELOPMENT PLANNING
 
A study for: (Public transport demand and requirement in 2020 for Kajang-Bang...
A study for: (Public transport demand and requirement in 2020 for Kajang-Bang...A study for: (Public transport demand and requirement in 2020 for Kajang-Bang...
A study for: (Public transport demand and requirement in 2020 for Kajang-Bang...
 
A study for: (Public transport demand and requirement in 2020 for Kajang-Bang...
A study for: (Public transport demand and requirement in 2020 for Kajang-Bang...A study for: (Public transport demand and requirement in 2020 for Kajang-Bang...
A study for: (Public transport demand and requirement in 2020 for Kajang-Bang...
 
UKM-Urban presentation
UKM-Urban presentationUKM-Urban presentation
UKM-Urban presentation
 
Urban presentation
Urban presentationUrban presentation
Urban presentation
 
MRT TRANSPORTATION
MRT TRANSPORTATION MRT TRANSPORTATION
MRT TRANSPORTATION
 
KA6564 Assignment 4 - Urban Public Transport Report
KA6564 Assignment 4 - Urban Public Transport ReportKA6564 Assignment 4 - Urban Public Transport Report
KA6564 Assignment 4 - Urban Public Transport Report
 
Final
FinalFinal
Final
 
Urban presentation
Urban presentationUrban presentation
Urban presentation
 
Development plane of urban transportation in Malaysia
Development plane of urban transportation in MalaysiaDevelopment plane of urban transportation in Malaysia
Development plane of urban transportation in Malaysia
 
SEM 1 PRESENTATION
SEM 1 PRESENTATIONSEM 1 PRESENTATION
SEM 1 PRESENTATION
 
SPAD_ASLI_29FEB2016
SPAD_ASLI_29FEB2016SPAD_ASLI_29FEB2016
SPAD_ASLI_29FEB2016
 
Training report on JMRC
Training report on JMRCTraining report on JMRC
Training report on JMRC
 
MRT REPORT TPT 250
MRT REPORT TPT 250MRT REPORT TPT 250
MRT REPORT TPT 250
 
Bengaluru Suburban Rail Brochure - 4 page
Bengaluru Suburban Rail Brochure - 4 pageBengaluru Suburban Rail Brochure - 4 page
Bengaluru Suburban Rail Brochure - 4 page
 
Jaipur Metro Project
Jaipur Metro ProjectJaipur Metro Project
Jaipur Metro Project
 
Sustainable Transport Trends & Opportunities for Indian Cities - Planning for...
Sustainable Transport Trends & Opportunities for Indian Cities - Planning for...Sustainable Transport Trends & Opportunities for Indian Cities - Planning for...
Sustainable Transport Trends & Opportunities for Indian Cities - Planning for...
 

Dernier

Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...Sapna Thakur
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...fonyou31
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajanpragatimahajan3
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024Janet Corral
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 

Dernier (20)

Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajan
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 

Public Transport Study

  • 1. Group Project: Public Transport Study for Kajang – Bangi – Putrajaya – Kajang– Putrajaya– Bandar Seri Putra - Nilai Asmah Bt. Hamim P60159 Noor Hazlin Bt. Abd Rahim P60840
  • 2. Objectives  To study public transport demand in Kajang – Bangi – Putrajaya – Bandar Seri Putra – Nilai corridor.  To determine the most desired line for public transport between the zones that connecting the corridor.  To propose the suitable and sustainable public transportation system in the corridor.
  • 4. Existing Road Linkage Kajang Silk Highway Lekas Highway North-South Expressway (PLUS Highway) Grandsaga Highway SKVE Highway
  • 5. Existing Public Transport a. Bus & Taxi Services i) Hentian Kajang (Jln. Reko) ii) Perhentian Bas & Teksi Nilai iii) Putrajaya Sentral
  • 6. b. KTM Komuter Study Area KTM Komuter Route Map
  • 7. c. Taxi Kajang Taxi Terminal
  • 8. Public Transport Problems Statement  Lack of public transport integration, existing buses is outdated, have poor- accessibility especially in the Kajang and Bangi area.  Unsuitable location for Kajang Town bus stop point.
  • 9. Public Transport Problems Statement  Main public transport terminal is far from komuter station and it’s shared between Kajang and Bangi.  Putrajaya location is far away from other facilities. No public transport to connect between nearest places (Kajang and Bangi) and Putrajaya.  Services of KTM Komuter are bad.  KTM Komuter station condition cannot accommodate the increasing passenger’s demands. It has very limited parking.
  • 10. Public Transport Problems Statement  Public transportation services unavailable at Bandar Seri Putra.  No public transport services to Nilai 3 and no terminal at Nilai 3 except mini bus.
  • 11. Recommended Action Plans Action 1: Traffic Management Intersection 2 Intersection 1 Two Intersections at Jalan Reko
  • 12. Intersection 1 Intersection 2 Traffic congestion happened at these two intersections especially on peak hours. Extending the slip road lane to SILK Highway from UKM without using traffic light and introducing turn left from highway to Kajang without using traffic signal will reduce the congested and safety to user.
  • 13. Roundabout 1 Roundabout 2 Two Roundabouts Nearby Seksyen 15, Bangi The introduction of traffic signal control at this roundabout, will allow the right turning maneuvers to be accommodated at this important location especially during evening peak. It is can reduce the extent of circuitous trips undertaken on this section of the urban road network.
  • 14. Recommended Action Plans Action 2: Central Area Bus Management Scheme Objectives of scheme Improve the accessibility Encourage bus usage of bus services
  • 15. Recommended Action Plans Jln. Cheras Bus lane Jln. Stadium Jln. Semenyih Jln. Sg. Chua Jln. Mendaling Jln. Besar Jln. Reko Bus Lane Route
  • 16. Recommended Action Plans - Jalan Bukit must restrict to other type of vehicle except bus, school bus and taxi. - Relocation of the bus station and taxi stand from Jalan Besar to Jalan Bukit nearby Kajang KTM Station Proposed new location for BRT Transit Central and taxi stand
  • 17. Traffic Modelling Trip Generation Trip Distribution Modal Split Trip Assignment
  • 18. Trip Assignment Kajang- Bangi- Putrajaya- Bdr Seri Bangi Putrajaya Bdr Seri Putra-Nilai Putra (87,824)/ (59,585)/ (32,250)/ (16,251)/ (100,164) (74,651) (42,313) (11,717)
  • 19. Long Term Public Transport Plan - Double-line LRT from Kajang to Bandar Baru Bangi, Putrajaya, Bandar Seri Putra and Nilai. Light Rail Transit (LRT)
  • 20. Light Rapid Transit (LRT) Near Hulu At Kajang KTM Komuter Langat District Station Office NearAlamanda, Near Seksyen 7 Putrajaya Near Sg. Merab Near Kg. Near Pekan Teras Jernang Bangi Near Bandar Seri Putra At Batang Benar KTM Komuter Station At Nilai KTM Komuter Station LRT Route and Stations
  • 21. Bus Rapid Transit (BRT) Near Kajang Specialist Hospital Near Satay Hj. Samuri Near Kajang Police Station Near intersection Jalan Near Metro Point 7/1 In front Plaza Metro Kajang Near Kajang KTM Komuter (proposed BRT Transit At Hentian Kajang, Jln. Reko Central) BRT Route and Stations at Kajang Town
  • 22. Bus Rapid Transit (BRT) Near Nilai 3 Near Nilai Impian Near Nilai Industrial Area Near Nilai KTM Komuter Station BRT Route and Stations at Nilai
  • 23. Bus Rapid Transit (BRT) BRT Stop BRT Transit Central
  • 24. Feeder Bus Feeder bus services are designed to pick up passengers in a certain locality, and take them to a transfer point where they make an onward journey on a trunk service. Provide bus service to LRT and KTM station. In this study, feeder bus proposed to zones that have LRT services; Nilai, Bandar Sri Putra, Putrajaya, Bandar Baru Bangi and Kajang. Feeder buses may act as part of a wider local network, or a regional coach network.
  • 25. 5. near Kajang Specialist Hospital 4. near Satay Hj. Samuri 6. near Kajang Police 3. near intersection Jln. 7/1 Station 7. near Metro Point 2. in front Plaza Metro Kajang 8. near Kajang KTM Komuter Station 2. near Seksyen 7, Bangi 1. at Kajang KTM Komuter Station 3. near Hulu Langat District 1. at Hentian Kajang, Jln. Reko 4. nearAlamanda, Office Putrajaya 5. near Sg. Merab 6. near Kg. Teras Jernang 7. near Pekan Bangi Legend:- Proposed Location of LRT Station 8. Near Bandar Seri Putra Proposed Location of BRT Station at Nilai Proposed Location BRT Station at Kajang Town BRT Station 4. near Nilai 3 Overall Layout of Proposed LRT Station 3. near Nilai Impian Public Transport in Study LRT Line Area 2. near Nilai Industrial Area BRT Line at Nilai 1. near KTM Komuter Station 9. at Batang Benar BRT Line at Kajang Town KTM Komuter Station 10. at Nilai KTM Komuter Station
  • 26. Cost Estimation Cost Estimation for Action Plans 1) 2 Intersections at Jalan Reko Cost estimation for extend and add lane for 1 intersection Length = 300 m Width = 3 m Excavation depth = 0.3 m Area volume = 270 m3 Sand/Crusher Run = 25.00 RM/m3 Pavement = 30.00 RM/m3 Compaction = 30.00 RM/m3 Excavation work = 25.00 RM/m3 = 110.00 RM/m3 Others (kerb, lanscape, = 20,000.00 RM signboard) Sum of cost = 49,700 RM X 2 = RM 99,400.00
  • 27. Cost Estimation Cost Estimation for Action Plans 2) 2 Roundabout Nearby Seksyen 15, Bangi Estimate for traffic light at 2 roundabout = 12nos x RM 300,000.00 = RM 3,600,000.00 3) Bus lanes at Kajang Town - Use existing asphalt on bus way = 20km x RM 450,000.00 = RM 9,000,000.00 - New asphalt on single lane busway = 4km x RM 2,200,000.00 = RM 8,800,000.00 - Bus way with fully colorized lanes = 24km x RM 150,000.00 = RM 3,600,000.00 Total Cost Estimation for Bus Lanes at Kajang Town = RM 21,400,000.00 4) BRT Transit Central and Taxi Stand Built BRT Transit Central = RM 7,000,000.00 Total of Cost Estimate for Action Plans = RM 32,099,400.00
  • 28. Cost Estimation Cost Estimation for Long Term Plans 1) Light Rapid Transit - Railway = 60km x RM 50,000,000.00 = RM 3,000,000,000.00 - Station = 10nos x RM 5,000,000.00 = RM 50,000,000.00 Total Cost Estimation for LRT = RM 3,050,000,000.00 2) BRT at Kajang - Station (3m wide) = 14nos x RM 600,000.00 = RM 8,400,000.00 - Air conditioned inside station = 14nos x RM 100,000.00 = RM 1,400,000.00 - Sliding door (8 door per station) = 14nos x RM 120,000.00 = RM 1,680,000.00 - Station identification post = 14 nos x RM 2,500.00 = RM 35,000.00 - Fare system (complete set) = 14nos x RM 1,500,000.00 = RM 21,000,000.00 - Pedestrian crosswalk with signal = 7nos x RM 60,000.00 = RM 420,000.00
  • 29. - GPS system = RM 3,000.000.00 Total Cost Estimation for BRT at Kajang = RM 32,935,000.00 3) BRT at Nilai - Use existing asphalt on busway = 20km x RM 450,000.00 = RM 9,000,000.00 - New asphalt on single lane busway = 5km x RM 2,200,000.00 = RM 11,000,000.00 - Busway with fully colourised lanes = 25km x RM 150,000.00 = RM 3,750.000.00 - Station (3m wide) = 8nos x RM 600,000.00 = RM 4,800,000.00 - Air conditioned inside station = 8nos x RM 100,000.00 = RM 800,000.00 - Sliding door (8 door per station) = 8nos x RM 120,000.00 = RM 960,000.00 - Station identification post = 8nos x RM 2,500.00 = RM 20,000.00 - Fare system (complete set) = 8nos x RM 1,500,000.00 = RM 12,000,000.00 - Pedestrian crosswalk with signal = 4nos x RM 60,000.00 = RM 240,000.00 - GPS system = RM 3,000.000.00 Total Cost Estimation for BRT at Nilai = RM 45,570,000.00
  • 30. 4) Feeder Bus Feeder bus = 50nos x RM 700,000.00 = RM 35,000,000.00 Total of Cost Estimate for Long Term Plans = RM 3,163,505,000.00
  • 31. Conclusion 1) LRT for Kajang - Bandar Baru Bangi – Putrajaya – Bandar Seri Putra - Nilai 2) BRT for Nilai – Nilai 3 and Kajang Town - The public’s attitude and willingness to shift to different modes of transport have been identified as an important step in the improvement process. - Financial backing and support from the government is also important in ensuring the success of the public transport network in this area.