METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                             RIESGO EN EL IPSFA



                                       INDICE
PRELIMINARES                                                      4

METODOLOGÍA PARA LA ADMINISTRACION DEL RIESGO EN EL IPSFA         4

1. OBJETIVOS DE LA ADMINISTRACIÓN DEL RIESGO                      5

GENERAL                                                           5

ESPECIFICOS                                                       5

2. MARCO NORMATIVO                                                5

3. MARCO CONCEPTUAL                                               6

4. METODOLOGÍA                                                    7

LINEAS GENERALES                                                  8

Compromiso Gerencial                                              8

Conformación de un equipo de trabajo                              8

Capacitación en la metodología                                    8

4.1 PLANIFICACIÓN DE LA ADMINISTRACIÓN DEL RIESGO                 8

4.2 VALORACIÓN DEL RIESGO                                         9

4.2.1 Identificación del riesgo                                   9

Formato de identificación de riesgos                              10

Clasificación del riesgo                                          10

4.2.2 Análisis del riesgo                                         11

Análisis cualitativo                                              12

Análisis cuantitativo                                             12


                                              RIESGO
ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL        Página 1
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                              RIESGO EN EL IPSFA


Evaluación de los riesgos                                           14

4.2.3 Determinación del nivel del riesgo                            16

Calificación de los controles                                       16

Criterios para evaluar la efectividad de los controles              16

Criterios para evaluar el nivel del riesgo                          17

Resultado Nivel de riesgo                                           17

4.3 MANEJO DEL RIESGO                                               18

4.3.1 Consideración de Acciones                                     18

Evitar el riesgo                                                    18

Reducir el riesgo                                                   18

Dispersar y atomizar el riesgo                                      19

Transferir el riesgo                                                19

Asumir el riesgo                                                    19

4.3.2 Elaboración del Mapa de Riesgos                               19

MAPA DE RIESGOS                                                     20

Descripción del Mapa de riesgos                                     20

4.3.3 Implementación de acciones                                    21

4.5 MONITOREO                                                       21

5. DIAGRAMAS DE LA ADMINISTRACION DEL RIESGO                        22


ETAPA DE PLANIFICACION                                              23



                                              RIESGO
ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL          Página 2
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                           RIESGO EN EL IPSFA


EATAPA DE VALORACION DEL RIESGO                                  23

ETAPA DE MANEJO DEL RIESGO                                       24

ETAPA DE MONITOREO                                               25

6. DEFINICIÓN DE TÉRMINOS                                        26




                                              RIESGO
ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL       Página 3
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                             RIESGO EN EL IPSFA


PRELIMINARES
       El riesgo esta relacionado con todo el quehacer de la especie humana, de
manera que no hay actividad de la vida, los negocios o de cualquier asunto que no
incluya el riesgo, es por ello que el ser humano desde sus inicios buscó maneras
de protegerse contra las eventualidades y desarrolló modos de sortear, disminuir o
asumir riesgos a través de acciones preventivas.
      Así mismo, la administración pública y en especial el Instituto de Previsión
Social de la Fuerza Armada no son ajenas al riesgo y deben buscar como
manejarlos partiendo de la base de su razón de ser y su compromiso con el
Estado; por esto, se debe tener en cuenta que los riesgos no sólo son de carácter
económico y están directamente relacionados con entidades financieras,
aseguradoras o con lo que se ha denominado riesgos profesionales, sino que
hacen parte de cualquier gestión que se realice.
        La Auditoría Interna del IPSFA en ejercicio de su competencia de la
evaluación del Sistema de Control Interno del Instituto y aún más el de contribuir
en desarrollo de su Cultura ha estimado necesario compilar la presente
información, tomada de otros Estados que han tenido un desarrollo importante en
esta área, y la presenta en forma de guía metodológica de forma tal que pueda ser
utilizada como referencia en el empeño gerencial de lograr desarrollar la
ADMINISTRACION DEL RIESGO en el Instituto.
       Es importante advertir, que en lo relativo al manejo de los indicadores en el
área de la Administración del Riesgo, la presente guía metodológica la limita a una
modesta mención, toda vez que la misma merece que sea atendida por separado,
cuando se trate lo relativo a las técnicas construcción de los indicadores de
gestión, validos también para la Administración del Riesgo.
METODOLOGÍA PARA LA ADMINISTRACION DEL RIESGO EN EL IPSFA
        La Administración del Riesgo se presenta como una herramienta que le
permita a la administración hacer un manejo adecuado del mismo desde la
planificación, por lo cual, se aspira que el usuario de ella, pueda identificar,
analizar y manejar permanentemente el riesgo, garantizando el cumplimiento de
los objetivos institucionales, la supervivencia de la entidad y fortaleciendo
continuamente la credibilidad de la misma ante el afiliado.
Para efectos de esta metodología, se va a considerar el riesgo, como toda
posibilidad de ocurrencia de aquella situación que pueda entorpecer el normal
desarrollo de las funciones de la entidad y le impidan el logro de sus objetivos.



                                              RIESGO
ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL                             Página 4
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                             RIESGO EN EL IPSFA


       Es conveniente aclarar que la presente metodología resulta ser una
compilación de diversas instituciones de otros Estados que han avanzado
considerablemente en el modelo de Administración del riesgo, toda vez que en
Venezuela apenas estamos desarrollando nuestras primeras experiencias y aún
no se recibe información oficial sobre la materia. Sin embargo la misma no agota
la materia de Administración de Riesgo y menos invalida otros modelos de
administración existentes, información que no solo es aceptada por el compilador
del presente trabajo, sino por el contrario se estimula al desarrollo de la
investigación en esta área, de manera de complementar la información aquí
contenida.
1. OBJETIVOS DE LA ADMINISTRACIÓN DEL RIESGO
GENERAL
       Facilitar el cumplimiento de la misión y objetivos de la institución a través de
la prevención y administración de los riesgos.
ESPECIFICOS
      Generar una visión sistémica acerca de la administración y evaluación de
riesgos.
      Servir como herramienta de trabajo a la administración activa en su meta de
protección de los recursos del Estado.
       Introducir dentro de los procesos y procedimientos la administración del
riesgo.
        Involucrar y comprometer a todos los funcionarias y funcionarias del
instituto, en la búsqueda de acciones encaminadas a prevenir y administrar los
riesgos.
      Propender porque cada entidad interactúe con otras, para fortalecer su
desarrollo.
      Asegurar el cumplimiento de normas, leyes y regulaciones.
2. MARCO NORMATIVO
       El Manual de Normas de Control Interno sobre un modelo Genérico de la
Administración Central y Descentralizada Funcionalmente (Gaceta Oficial No
38.282 del 28 de septiembre de 2005), dictado por la Superintendencia Nacional
de Auditoría Interna, órgano rector del sistema de control interno del sector
publico, de acuerdo a las previsiones del Artículo 5 de la Ley Orgánica de
Administración Financiera del Sector Público, en nombre del Estado venezolano

                                              RIESGO
ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL                                Página 5
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                             RIESGO EN EL IPSFA


reconoce la aplicación del Modelo COSO como herramienta de control de la
administración pública, con la cual se suma a la nueva filosofía de gobierno del
Control Fiscal (Sistema Nacional de Control Fiscal Venezolano). Con ello reconoce
la aplicación del componente del sistema denominado: “Administración y
Valoración del riesgo”, de esta manera da entrada en toda la administración
pública al “Riesgo” como herramienta para ser tomada en cuenta en la
planificación pública.
3. MARCO CONCEPTUAL
       La administración pública al ocuparse de los fenómenos de organización y
gestión, no puede ser ajena a las herramientas disponibles y a las nuevas
tendencias en administración, para lo cual requiere estar en constante
actualización y estar abierta al cambio y a la aplicación de diferentes instrumentos
que le permitan a las entidades ser cada vez más eficientes, por lo que se hace
necesario tener en cuenta todos aquellos hechos o factores que puedan afectar en
un momento determinado el cumplimiento de los objetivos institucionales.
       Por lo anterior, se hace necesario introducir el concepto de administración
del riesgo en el instituto, teniendo en cuenta que todas las organizaciones
independientemente de su naturaleza, tamaño y razón de ser están
permanentemente expuestos a diferentes riesgos que pueden poner en peligro su
existencia. Desde la perspectiva del control, el modelo COSO interpreta que la
eficiencia del control es la reducción de los riesgos, es decir: el propósito principal
del control es la eliminación o reducción de los riesgos, es lograr que el proceso y
sus controles garanticen, de manera razonable que los riesgos están minimizados
o se están reduciendo y por lo tanto, que los objetivos de la organización y en este
caso del instituto, van a ser alcanzados.
       Para el caso particular del IPSFA, dada la diversidad y particularidad de las
dependencias en cuanto a sus funciones, estructura, manejo presupuestario,
contacto con la ciudadanía y compromiso social entre otros, es preciso identificar o
precisar las áreas, los procesos, los procedimientos, las instancias y controles
dentro de los cuales puede actuarse e incurrirse en riesgos que atentan contra la
buena gestión y la obtención de resultados para tener un adecuado manejo del
riesgo.
       Igualmente, es importante tener en cuenta que los riesgos están
determinados por factores de carácter externo, también denominados del entorno
y factores de carácter interno.



                                              RIESGO
ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL                                Página 6
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                             RIESGO EN EL IPSFA


        Entre los factores externos se destacan: la normatividad en la medida que
se hace parte de un Estado social de derecho; a manera de ejemplo se pueden
mencionar cambios constitucionales, legales, reglamentarios o cualquier otra
normativa superior al instituto de producirse; jurisprudenciales como los que se
expresan en sentencias que declaran sin efecto normas que venían aplicándose y
que en un momento determinado pueden afectar las funciones específicas del
instituto y por lo tanto sus objetivos. También pueden mencionarse las reformas a
la administración y los constantes recortes presupuestales que afectan la
capacidad de gestión de la entidad, lo cual sumado a la reducción o eliminación
total del presupuesto de inversión, obliga a considerar en todo momento el riesgo
que tendría el IPSFA de no poder cumplir con su objeto social.
       Entre los factores internos se destacan: el manejo de los recursos, la
estructura organizacional, los controles existentes, los procesos y procedimientos,
la disponibilidad presupuestaria, la forma como se vinculan las personas a la
entidad, los intereses de los directivos, el nivel del talento humano, la motivación y
los niveles salariales, entre otros.
      Es así como se hace necesario además de la identificación de factores y
riesgos en las entidades, su análisis, valoración e implementación de un plan de
manejo el cual se materialice en un mapa de Riesgos, al cual se le haga una
evaluación y monitoreo permanentes.
      Para llevar a cabo dicho proceso se considera importante señalar el papel
de la Oficina de Coordinadora de Control Interno del instituto, coordinar para que
en las gerencias se implementen políticas de administración del riesgo y se
conformen equipos de trabajo que apoyen dicho proceso y propendan por que se
implementen mecanismos reales para la administración del riesgo.
       Igualmente estimular para que la identificación y el análisis del riesgo sean
un proceso permanente e interactivo entre la administración y las coordinaciones
de control interno o quien haga sus veces con miras a establecer acciones
efectivas, representadas en actividades de control, acordadas entre los
responsables de las áreas o procesos y dichas oficinas.
4. METODOLOGÍA
       El IPSFA al igual que el resto de entidades de la administración pública
tiene unos objetivos institucionales definidos por su norma de constitución y
demás normas que la involucran, los cuales debe desarrollar a través de
diferentes planes, programas y proyectos. El cumplimiento de dichos objetivos se
puede ver afectado por la presencia de riesgos, razón por la cual se hace

                                              RIESGO
ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL                               Página 7
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                             RIESGO EN EL IPSFA


necesario contar con una metodología para administrar los mismos dentro de la
organización.
       En este sentido y partiendo de la razón de ser de la entidad, la
administración del riesgo debe ser una política institucional definida, respaldada
por la Gerencia, de tal forma que se comprometa a manejar el tema dentro de la
misma.
LINEAS GENERALES
       Las etapas sugeridas para una adecuada Administración del Riesgo son las
siguientes:
Compromiso Gerencial:
       Para el éxito en la Implementación de una adecuada administración del
riesgo, es indispensable el compromiso de la alta gerencia como encargada, en
primera instancia, de definir las políticas y en segunda instancia de estimular la
cultura de la identificación y prevención del riesgo. Para lograrlo es importante la
definición de canales directos de comunicación y el apoyo a todas las acciones
emprendidas en este sentido, propiciando los espacios y asignando los recursos
necesarios.
Conformación de un equipo de trabajo:
       Es importante conformar un equipo de trabajo que junto con la Coordinación
de Control Interno se encargue de liderar el proceso de administración del riesgo
dentro de la gerencia y cuente con un canal directo de comunicación con la alta
dirección. Dicho equipo lo deben integrar personas de diferentes áreas que
conozcan muy bien la entidad y la dependencia en particular, el funcionamiento de
los diferentes procesos para que se facilite la administración del riesgo y la
construcción de los mapas de riesgos institucionales.
Capacitación en la metodología:
       Definido el equipo o equipos de trabajo, la Gerencia y la Coordinación de
Control interno deben velar por la capacitación de sus integrantes en la
metodología de la administración del riesgo, para lo cual se podrá contar con el
apoyo de las diferentes instituciones del estado en materia de Control Fiscal
incluyendo la Auditoría interna del IPSFA.
4.1 PLANIFICACIÓN DE LA ADMINISTRACIÓN DEL RIESGO
       Como cualquier otro proceso, la administración del riesgo debe planificarse
y programarse de manera que haga parte de todo el quehacer de la entidad.
Para el diseño de esta planificación es fundamental tener claridad en la misión de
la entidad, en sus objetivos y tener una visión sistémica de manera que no se
                                              RIESGO
ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL                             Página 8
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                             RIESGO EN EL IPSFA


perciba la administración del riesgo como algo aislado. Igualmente es necesario
conocer sobre el tema de riesgos y la metodología propuesta.
        Dicha planificación debe contener: ¿Cuándo va a empezar a manejarse el
tema dentro de la entidad?, ¿Quiénes van a participar directamente en el
proceso?, ¿Cuándo van a realizarse las capacitaciones y a quién van a ir
dirigidas? y ¿Cómo se va a articular el tema dentro de la planificación y con los
procesos?, ¿Cómo se conducir el seguimiento?, entre otros.
4.2 VALORACIÓN DEL RIESGO
       La valoración del riesgo consta de tres etapas: la identificación, el análisis y
la determinación del nivel del riesgo. Estas etapas son de singular interés para
desarrollar con éxito la administración del riesgo e implementar una política al
respecto en la entidad; para cada una de ellas se sugiere tener en cuenta la mayor
cantidad de datos disponibles y contar con la participación de las personas que
ejecutan los procesos para lograr que las acciones determinadas alcancen los
niveles de efectividad esperados.
4.2.1 Identificación del riesgo
       El proceso de la identificación del riesgo debe ser permanente e interactivo
integrado al proceso de planificación y debe partir de la claridad de los objetivos
estratégicos de la entidad para la obtención de resultados.
      Previa la identificación de los riesgos es importante tener en cuenta tal
como se mencionó anteriormente, los factores que pueden incidir en la aparición
de los mismos, los cuales pueden ser externos e internos y llegar a afectar la
organización en cualquier momento.
       Debe considerarse además de los factores previamente citados, factores
externos relacionados con la entidad como son: económicos, sociales, de orden
público, políticos, legales y cambios tecnológicos, entre otros y como factores
internos: la naturaleza de las actividades de la entidad, la estructura
organizacional, los sistemas de información, los procesos y procedimientos y los
recursos económicos.
       Para la identificación se recomienda la aplicación de varias herramientas y
técnicas como por ejemplo: entrevistas estructuradas con expertos en el área de
interés, reuniones con directivos y con personas de todos los niveles en la entidad,
evaluaciones individuales usando cuestionarios, lluvias de ideas con los servidores
de la entidad, entrevistas e indagaciones con personas ajenas a la entidad, usar
diagramas de flujo, análisis de escenarios y hacer revisiones periódicas de
factores económicos y tecnológicos que puedan afectar la organización, entre
                                              RIESGO
ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL                                Página 9
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                             RIESGO EN EL IPSFA


otros. Igualmente pueden utilizarse diferentes fuentes de información de la
entidad, tales como registros históricos, experiencias significativas registradas,
opiniones de especialistas y expertos, informes de años anteriores, los cuales
pueden proporcionar información importante, la técnica utilizada dependerá de las
necesidades y naturaleza de la dependencia.
       Una manera de visualizar los riesgos es a través de la utilización del
formato de identificación de riesgos el cual permite hacer un inventario de los
mismos, definiendo en primera instancia los riesgos, posteriormente presentando
una descripción de cada uno de estos, las causas y finalmente definiendo las
posibles consecuencias. Es importante centrarse en los riesgos más significativos
para la dependencia.
                     Formato de identificación de riesgos
                                                                POSIBLES
ACTIVIDAD      RIESGO        DESCRIPCIÓN        CAUSAS
                                                             CONSECUENCIAS


Actividad: Paso del proceso al cual se le esta aplicando las técnicas de
Administración del Riesgo

Riesgo: Posibilidad de ocurrencia de aquella situación que pueda entorpecer el
normal desarrollo de las funciones de la entidad y le impidan el logro de sus
objetivos.

Descripción: Se refiere a las características generales o las formas en que se
observa o manifiesta el riesgo identificado.
Causas: Identificar el agente generador del riesgo

Posibles consecuencias: Corresponde a los posibles efectos ocasionados por el
riesgo, los cuales se pueden traducir en daños de tipo económico, social,
administrativo, entre otros.
Clasificación del riesgo
        Durante el proceso de identificación del riesgo se recomienda hacer una
clasificación de los mismos teniendo en cuenta los siguientes conceptos:
Riesgo Estratégico: Se asocia con la forma en que se administra la Entidad. El manejo
del riesgo estratégico se enfoca a asuntos globales relacionados con la misión y el
cumplimiento de los objetivos estratégicos, la clara definición de políticas, diseño y
conceptualización de la entidad por parte de la alta gerencia
                                              RIESGO
ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL                             Página 10
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                             RIESGO EN EL IPSFA


Riesgos Operativos: Comprende los riesgos relacionados tanto con la parte operativa
como técnica de la entidad, incluye riesgos provenientes de deficiencias en los
sistemas de información y comunicación, en la definición de los procesos, en la
estructura de la entidad, la desarticulación entre dependencias, lo cual conduce a
ineficiencias, oportunidades de corrupción e incumplimiento de los compromisos
institucionales.
Riesgos de Control: Están directamente relacionados con inadecuados o inexistentes
puntos de control y en otros casos, con puntos de controles obsoletos, inoperantes
o poco efectivos.
Riesgos Financieros: Se relacionan con el manejo de los recursos de la entidad que
incluye, la ejecución presupuestal, la elaboración de los estados financieros, los
pagos, manejos de excedentes de tesorería y el manejo sobre los bienes de cada
entidad. De la eficiencia y transparencia en el manejo de los recursos, así como su
interacción con las demás áreas dependerá en gran parte el éxito o fracaso de
toda entidad.
Riesgos de Cumplimiento: Se asocian con la capacidad de la entidad para cumplir con
los requisitos legales, contractuales, de ética pública y en general con su
compromiso ante la comunidad.
Riesgos de Tecnología: Se asocian con la capacidad de la Entidad para que la
tecnología disponible satisfaga las necesidades actuales y futuras de la entidad y
soporten el cumplimiento de la misión.
4.2.2 Análisis del riesgo
       El objetivo del análisis es el de establecer una valoración y evaluación de
los riesgos con base en la información obtenida en el formato de identificación de
riesgos elaborados en la etapa de identificación, con el fin de obtener información
para establecer el nivel de riesgo y las acciones que se van a implementar. El
análisis del riesgo dependerá de la información sobre el mismo, de su causa y la
disponibilidad de datos. Para adelantarlo es necesario diseñar escalas que pueden
ser cuantitativas o cualitativas. Se han establecido dos aspectos para realizar el
análisis de los riesgos identificados:
Probabilidad: la posibilidad de ocurrencia del riesgo; esta puede ser medida con
criterios de frecuencia o teniendo en cuenta la presencia de factores internos y
externos que pueden propiciar el riesgo, aunque éste no se haya materializado.
Impacto: consecuencias que puede ocasionar a la organización la materialización
del riesgo.
                                              RIESGO
ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL                           Página 11
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                             RIESGO EN EL IPSFA


A continuación se presentan algunos ejemplos de las escalas que pueden
implementarse para analizar los riesgos.
Análisis cualitativo:
       Se refiere a la utilización de formas descriptivas para presentar la magnitud
de consecuencias potenciales y la posibilidad de ocurrencia. Se diseñan escalas
ajustadas a las circunstancias de acuerdo a las necesidades particulares de cada
organización o el concepto particular del riesgo evaluado.
      Escala de medida cualitativa de PROBABILIDAD: se deben establecer las
categorías a utilizar y la descripción de cada una de ellas, con el fin de que cada
persona que aplique la escala mida a través de ella los mismos ítems, por
ejemplo:
ALTA: es muy factible que el hecho se presente.
MEDIA: es factible que el hecho se presente.
BAJA: es muy poco factible que el hecho se presente.
Ese mismo diseño puede aplicarse para la escala de medida cualitativa de
IMPACTO, estableciendo las categorías y la descripción, por ejemplo:
ALTO: Si el hecho llegara a presentarse, tendría alto impacto o efecto sobre la
entidad.
MEDIO: Si el hecho llegara a presentarse tendría medio impacto o efecto en la
entidad.
BAJO: Si el hecho llegara a presentarse tendría bajo impacto o efecto en la
entidad.
       Con base en los ejemplos anteriormente expuestos, los equipos de trabajo
en coordinación con los encargados de adelantar los procesos pueden construir
sus propias escalas de acuerdo a la naturaleza de la entidad y a las características
de los procesos y procedimientos, de forma que estas escalas se ajusten al
análisis de los riesgos identificados.
Análisis cuantitativo:
        Este análisis contempla valores numéricos para los cuales se pueden
construir tablas; la calidad depende de lo exactas y completas que estén las cifras
utilizadas. La forma en la cual la probabilidad y el impacto son expresada y las


                                              RIESGO
ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL                            Página 12
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                                RIESGO EN EL IPSFA


  formas por las cuales ellos se combinan para proveer el nivel de riesgo puede
  variar de acuerdo al tipo de riesgo.
  Ejemplo de escala de impacto:



 IMPACTO         VALORACÍON                             CARACTERISTICA

  Bajo               1, 2, 3           No afecta la operación del proceso ni su desempeño.

                                       Permite la operación del proceso, bajo condiciones de
  Medio              4, 5, 6
                                                       desempeño reducido.


                                       Afecta la operación segura del proceso y/o involucra el
   Alto            7, 8, 9, 10
                                             incumplimiento de regulaciones existentes.




  Ejemplo de escala de probabilidad:

FRECUENCIA       VALORACÍON                            CARACTERISTICA


                                        Ha ocurrido al menos 1 vez en los últimos cinco (5)
   Baja              1, 2, 3
                                                              años.


                                        Ha ocurrido al menos 1 vez en los últimos dos (2)
  Media              4, 5, 6
                                                             años.


   Alta            7, 8, 9, 10          Ha ocurrido al menos 1 vez en el último semestre.




                                                RIESGO
  ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
  INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL                               Página 13
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                             RIESGO EN EL IPSFA


       Al igual que para determinar las escalas cualitativas, el diseño de las
escalas cuantitativas debe contar con la participación de las personas encargadas
de los procesos y con el grupo encargado de liderar la administración del riesgo.
Evaluación de los riesgos
      Una vez realizado el análisis de los riesgos con base en los aspectos de
probabilidad e impacto, se recomienda utilizar la matriz de evaluación que permite
determinar cuales requieren de un tratamiento inmediato.
                                  Matriz de evaluación de riesgos
                     Frecuencia




              ALTA
                                       A            B
              BAJA                     C            D
                                             Impacto
                                          BAJO    ALTO
       Cuando se ubican los riesgos en la matriz se define cuáles de ellos
requieren acciones inmediatas, que en este caso son los del cuadrante B, es decir
los de alto impacto y alta probabilidad. Los que no requieren acciones
inmediatas (pero desde luego requieren que se formulen) son los ubicados en el
cuadrante C bajo impacto y baja probabilidad. Respecto a los ubicados en las
casillas A y D, es la entidad la que debe seleccionar de acuerdo a la naturaleza
del riesgo cuáles van a trabajar primero, los de alto impacto pero baja
probabilidad o los de alta probabilidad y bajo impacto, ya que estos pueden
ser peligrosos para el logro de los objetivos institucionales, por las consecuencias
que presentan en el caso de los ubicados en la casilla D, o por lo constante de su
presencia en el caso de la casilla A.
       Cuantitativamente la evaluación del riesgo es el producto automático,
realizado mediante una formula matemática que resulta de la relación entre el
impacto y la probabilidad del riesgo evaluado.
       Multiplicadas estas dos calificaciones, grado de ocurrencia o frecuencia por
la relevancia del riesgo, nos arroja una calificación o ponderación final por riesgo
sobre una escala de 100 puntos donde se establece que a una mayor calificación
mayor es el riesgo.


                                              RIESGO
ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL                            Página 14
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                                      RIESGO EN EL IPSFA


       La matriz de evaluación del riesgo cuando se trate de la realización de un
análisis cuantitativo se representará en el eje (x, y), donde los valores
representado en el eje de las abscisas (horizontal) corresponden a los valores del
nivel del impacto y los valores del eje de las coordenadas (vertical) representa los
valores del nivel de la probabilidad




       La representación de la cuantificación obtenida en la matriz o grafico,
permite la observar el resultado de la evaluación del riesgo identificado, esta
información podrá ser registrada en el formato que se viene elaborando de la
siguiente forma:

                                                                                                             PROBABILIDAD
                                                  POSIBLES CONSECUENCIAS




                                                                                                                                        EVALUACION DEL RIESGO
                                                                                   IMPACTO
                           DESCRIPCIÓN
    ACTIVIDAD




                                         CAUSAS
                  RIESGO




                                                                           VALOR


                                                                                             NIVEL


                                                                                                     VALOR


                                                                                                                            NIVEL




                                              RIESGO
ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL                                                                                     Página 15
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                             RIESGO EN EL IPSFA


4.2.3 Determinación del nivel del riesgo (Valoración del Riesgo)
       La determinación del nivel de riesgo es el resultado de confrontar el
impacto y la probabilidad (evaluación del riesgo obtenida) con los controles
existentes en los diferentes procesos y procedimientos que se realizan. Para
adelantar esta etapa se deben tener muy claros los puntos de control existentes
en los diferentes procesos, los cuales permiten obtener información para efectos
de tomar decisiones, estos niveles de riesgo pueden ser:
ALTO: Cuando el riesgo hace altamente vulnerable a la entidad o unidad.
(Impacto y probabilidad alta vs controles)
MEDIO: Cuando el riesgo presenta una vulnerabilidad media. (Impacto alto -
probabilidad baja o Impacto bajo – probabilidad alta vs controles).
BAJO: Cuando el riesgo presenta vulnerabilidad baja. (Impacto y probabilidad
baja vs controles).
Calificación de los controles:
      Para la evaluación de los controles existentes de cada uno de los riesgos,
es necesario establecer si son preventivos o correctivos y responder las siguientes
preguntas:
¿Están documentados?
¿Se están aplicando en la actualidad?
¿Son efectivos en minimizar el riesgo?
Criterios para evaluar la efectividad de los controles existentes
   •   Cuando no existen controles,
       La probabilidad de ocurrencia es alta.
   •   Cuando los controles existentes no son efectivos,
       La probabilidad de ocurrencia es alta
   •   Cuando los controles        existentes   son   efectivos,   pero   no   están
       documentados,
       La probabilidad de ocurrencia es media


                                              RIESGO
ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL                            Página 16
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                             RIESGO EN EL IPSFA


   •   Cuando los controles son efectivos y están documentados,
       La probabilidad de ocurrencia es baja
Criterios para evaluar el nivel del riesgo
   •   Cuando la evaluación de los controles es alta, aumenta el nivel del riesgo.
   •   Cuando la evaluación de los controles existentes es media:
       Si la evaluación del riesgo es baja, el nivel del riesgo se ubica en medio.
       Si la evaluación de riesgo es media, el nivel de riesgo pudiera mantenerse
       en medio si su referencia marcadora es la probabilidad (probabilidad alta-
       impacto bajo); si su referencia marcadora es el impacto (impacto alto-
       probabilidad baja) el nivel del riesgo pudiera aumentar a alto.
       Si la evaluación del riesgo es alta, el nivel de riesgo es alto.
   •   Cuando la evaluación de los controles existentes baja, disminuye el nivel de
       riesgo
Un ejemplo de la determinación del nivel del riesgo y del grado de exposición al
mismo:
Riesgo: Perdida de información debido a la entrada de un virus en la red de
información de la entidad.
Probabilidad: Alta, porque todos los computadores de la entidad están
conectados a la red de Internet e intranet.
Impacto: Alto, porque la pérdida de información traería consecuencias graves
para el quehacer de la entidad.
Controles existentes: la entidad tiene establecidos controles semanales
haciendo Backus o copias de seguridad y vacunando todos los programas y
equipos; además guarda la información más relevante desconectada de la red en
un centro de información.
Resultado Nivel de riesgo:
Medio por los controles establecidos
       Lo anterior significa que a pesar de que la probabilidad y el impacto son
altos confrontado con los controles, se puede afirmar que el nivel de riesgo es

                                              RIESGO
ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL                              Página 17
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                                     RIESGO EN EL IPSFA


        medio y por lo tanto las acciones que se implementen entrarán a reforzar los
        controles existentes y a valorar la efectividad de los mismos.
                Siguiendo con la elaboración del formato y partiendo de la evaluación del
        Riesgo obtenido, se incluye lo relativo a la evaluación de controles existentes, la
        identificación del control, si el mismo existe, si está documentado, si se aplica, si
        es efectivo, y la correspondiente evaluación del control de acuerdo a la aplicación
        de los criterios para evaluar la efectividad de los controles existentes, finalmente
        la valoración del Riesgo de acuerdo a los criterios desarrollados para evaluar el
        nivel del riesgo.

                                     CONTROLES EXISTENTES
EVALUACION                                                                              VALORACION
                                     DOCUMEN                        EVALUACION DEL
DEL RIESGO   CONTROL        EXISTE     TADO    APLICA   EFECTIVO                        DEL RIESGO
                                                                       CONTROL


        4.3 MANEJO DEL RIESGO
               Cualquier esfuerzo que emprendan las entidades en torno a la valoración
        del riesgo llega a ser en vano, si no culmina en un adecuado manejo y control de
        los mismos.
        4.3.1 Consideración de Acciones
               Para el manejo de los riesgos se deben analizar las posibles acciones a
        emprender las cuales deben ser factibles y efectivas, tales como: la
        implementación de políticas, definición de estándares, optimización de procesos y
        procedimientos y cambios físicos entre otros.
        Se pueden tener en cuenta alguna de las siguientes opciones, las cuales pueden
        considerarse cada una de ellas independientemente, interrelacionadas o en
        conjunto.

        Evitar el riesgo:
               Es siempre la primera alternativa a considerar. Se logra cuando en los
        procesos se genera cambios sustanciales por mejoramiento, rediseño o
        eliminación, resultado de unos adecuados controles y acciones emprendidas. Un
        ejemplo de esto puede ser el control de calidad, manejo de los insumos,
        mantenimiento preventivo de los equipos, desarrollo tecnológico, etc.

        Reducir el riesgo:
              Si el riesgo no puede ser evitado porque crea grandes dificultades
        operacionales, el siguiente paso es reducirlo al más bajo nivel posible. La

                                                      RIESGO
        ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
        INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL                             Página 18
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                             RIESGO EN EL IPSFA


reducción del riesgo es probablemente el método más sencillo y económico para
superar las debilidades antes de aplicar medidas más costosas y difíciles. Se
consigue mediante la optimización de los procedimientos y la implementación de
controles.
Ejemplo: Planes de contingencia.

Dispersar y atomizar el riesgo:
       Se logra mediante la distribución o localización del riesgo en diversos
lugares. Es así como por ejemplo, la información de gran importancia se puede
duplicar y almacenar en un lugar distante y de ubicación segura, en vez de dejarla
concentrada en un solo lugar.

Transferir el riesgo:
       Hace referencia a buscar respaldo y compartir con otro parte del riesgo
como por ejemplo tomar pólizas de seguros, esta técnica es usada para eliminar el
riesgo de un lugar y pasarlo a otro o de un grupo a otro. Así mismo, el riesgo
puede ser minimizado compartiéndolo con otro grupo o dependencia.

Asumir el riesgo:
       Luego de que el riesgo ha sido reducido o transferido puede quedar un
riesgo residual que se mantiene, en este caso el gerente del proceso simplemente
acepta la pérdida residual probable y elabora planes de contingencia para su
manejo.
       Una vez establecidas cuales de las anteriores opciones de manejo del
riesgo se van a concretar, estas deben evaluarse con relación al beneficio costo
para proceder a elaborar el mapa de riesgos, el cual permitirá visualizar todo el
proceso de valoración, análisis y manejo de los riesgos.
4.3.2 Elaboración del Mapa de Riesgos
        Para la consolidación del Mapa de Riesgos, adicional a las consideraciones
expuestas, es necesario identificar las causas que los pueden ocasionar, lo cual
facilita el proceso de definición de acciones para mitigar los mismos.
La selección de las acciones más convenientes debe considerar la viabilidad
jurídica, técnica, institucional, financiera y económica y se puede realizar con base
en los siguientes factores:
a) El nivel del riesgo
b) El balance entre el costo de la implementación de cada acción contra el
beneficio de la misma.


                                              RIESGO
ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL                             Página 19
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                                      RIESGO EN EL IPSFA


Así mismo en el Mapa de Riesgos se deben identificar los controles existentes, las
áreas o dependencias responsables de llevar a cabo las acciones, definir un
cronograma y unos indicadores que permitan verificar el cumplimiento para tomar
medidas correctivas cuando sea necesario. (Ver formato)
                                                                     MAPA DE RIESGOS
                                                  Consecuencias




                                                                                           Evaluación del




                                                                                                                        Valoración del




                                                                                                                                                    Responsables
                                                                            Probabilidad




                                                                                                                                                                   Cronograma
                          Descripción




                                                                                                                                                                                Indicadores
                                                                                                            Controles
    Actividad




                                                                                                                                         Acciones
                                                                                                            existente
                                                                  Impacto
                                        Causas
                 Riesgo




                                                                                               riesgo




                                                                                                                            riesgo
                                                 Descripción del Mapa de riesgos

Actividad: Paso del proceso al cual se le esta aplicando las técnicas de
Administración del Riesgo

Riesgo: posibilidad de ocurrencia de aquella situación que pueda entorpecer el
normal desarrollo de las funciones de la entidad y le impidan el logro de sus
objetivos.
Descripción: Las características generales o las formas como se observa el
riesgo en la actividad

Consecuencias: Posibles efectos ocasionados por el riesgo, los cuales se
pueden traducir en daños de tipo económico, social administrativo, etc.

Impacto: consecuencias que puede ocasionar a la organización la materialización
del riesgo.
Probabilidad entendida como la posibilidad de ocurrencia del riesgo; esta puede
ser medida con criterios de frecuencia o teniendo en cuenta la presencia de
factores internos y externos que pueden propiciar el riesgo aunque este no se
haya presentado nunca.
Control existente: especificar cuál es el control que la entidad tiene
implementado para combatir, minimizar o prevenir el riesgo.



                                              RIESGO
ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL                                                                                                                                 Página 20
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                             RIESGO EN EL IPSFA


Nivel de riesgo: El resultado de la aplicación de la escala escogida para
determinar el nivel de riesgo de acuerdo a la posibilidad de ocurrencia, teniendo
en cuenta los controles existentes.
Causas: Son los medios, circunstancias y agentes que generan los riesgos.
Acciones: es la aplicación concreta de las opciones del manejo del riesgo que
entrarán a prevenir o a reducir el riesgo y harán parte del plan de manejo del
riesgo.
Responsables: Son las dependencias o áreas encargadas de adelantar las
acciones propuestas.
Cronograma: son las fechas establecidas para implementar las acciones por
parte del grupo de trabajo.
Indicadores: se consignan los indicadores diseñados para evaluar el desarrollo
de las acciones implementadas.
      Finalmente, partiendo de que el fin último de la administración del riesgo es
propender por el cumplimiento de la misión y objetivos institucionales, los cuales
están consignados en la planeación anual de la entidad, se sugiere articular el
mapa de riesgos con la planeación de manera que no sean planes aislados sino
complementarios.
4.3.3 Implementación de acciones
       Definido el Mapa de Riesgos con sus acciones, responsables y
cronogramas, es fundamental comenzar a ejecutar dichas acciones con el fin de
determinar su efectividad en el menor tiempo posible.
4.5 MONITOREO
      Una vez diseñado y validado el plan para administrar los riesgos, en el
mapa de riesgos, es necesario monitorearlo teniendo en cuenta que estos nunca
dejan de representar una amenaza para la organización.
       El monitoreo es esencial para asegurar que las acciones se están llevando
a cabo y evaluar la eficiencia en su implementación adelantando revisiones sobre
la marcha para evidenciar todas aquellas situaciones o factores que pueden estar
influyendo en la aplicación de las acciones preventivas.
       El monitoreo debe estar a cargo de los responsables de las diferentes áreas
con el apoyo de las Oficinas Coordinadora de Control Interno y su finalidad
principal será la de aplicar y sugerir los correctivos y ajustes necesarios para
                                              RIESGO
ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL                           Página 21
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                            RIESGO EN EL IPSFA


asegurar un efectivo manejo del riesgo. La Oficina Coordinadora de Control
Interno dentro de su función asesora comunicará y presentará luego del
monitoreo, sus resultados y propuestas de mejoramiento y tratamiento a las
situaciones detectadas.
5. DIAGRAMAS DE LA ADMINISTRACIÓN DEL RIESGO
       A continuación se presenta un diagrama que consolida todo el proceso de
administración del riesgo y puede facilitar la comprensión del mismo al momento
de llevar a cabo la tarea de levantamiento del Mapa de Riesgos.


                        ETAPA DE PLANIFICACION




                                             IDENTIFICAR LA MISION
CONOCIMIENTO GENERAL DE
    LA INSTITUCION                         IDENTIFICAR LOS OBJETIVOS

                                           IDENTIFICAR LOS PROCESOS




                                      DEFINIR LOS OBJETIVOS EN MATERIA DE
    DISEÑO DEL PLAN                       ADMINISTRACION DE RIESGOS

                                    DISEÑO DE CRONOGRAMAS DE ACTIVIDADES

                                     CAPACITACION EN LA METODOLOGIA




                                              RIESGO
ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL                        Página 22
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                                RIESGO EN EL IPSFA


                      ETAPA DE VALORACION DEL RIESGO


                                    IDENTIFICACION DE LOS FACTORES INTERNOS Y
                                                    EXTERNOS
IDENTIFICACION DEL RIESGO
                                    ELABORACION DEL FORMATO IDENTIFICACION
                                                  DEL RIESGO

                                          CLASIFICACION DE LOS RIESGOS

                                       MEDIR IMPACTO Y PROBALIDAD

                                     JERARQUIZAR LOS RIESGOS ACORDE
                                              CON LA ESCALA
 EVALUACION DEL RIESGO                     DE MEDICIÓN DEFINIDA
                                          (COMENZANDO POR LOS
                                           DE MAYOR IMPACTO Y
                                              PROBABILIDAD)



                                        IDENTIFICAR LOS CONTROLES
                                           EXISTENTES PARA CADA
                                            UNO DE LOS RIESGOS
                                              SELECCIONADOS

   DETERMINACIÓN                       CONFRONTAR EL IMPACTO Y LA
    DEL NIVEL DE                        PROBABILIDAD FRENTE A LOS
      RIESGO                              CONTROLES EXISTENTES

                                         SELECCIONAR LOS RIESGOS
                                            DE MAYOR INCIDENCIA
                                           PARA EL CUMPLIMIENTO
                                             DE LOS OBJETIVOS




                                                  RIESGO
    ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
    INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL                 Página 23
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                              RIESGO EN EL IPSFA


                      ETAPA DE MANEJO DEL RIESGO




                                         ESTUDIO DE POSIBLES
CONSIDERACIONES Y ACCIONES              ACCIONES PARA MITIGAR
                                             LOS RIESGOS




                                    DEFINICIÓN DE LAS CAUSAS QUE
                                       PROPICIAN LOS RIESGOS

                                       DEFINICIÓN DE ACCIONES
                                      PARA MITIGAR LOS RIESGOS
 ELABORACION DEL MAPA DE
         RIESGO                        ANÁLISIS COSTO BENEFICIO
                                           DE LAS ACCIONES

                                         PROCESAMIENTO DEL
                                         FORMATO DE MAPA DE
                                              RIESGOS




                                   EJECUCIÓN DE LOS COMPROMISOS
  IMPLEMENTACION DE LAS                     ADQUIRIDOS
        ACCIONES                     SEGUIMIENTO A LAS ACCIONES
                                         POR PARTE DE LOS
                                           RESPONSABLES




                                                RIESGO
  ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
  INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL             Página 24
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                                RIESGO EN EL IPSFA


                            ETAPA DE MONITOREO




                                    DEFINIR LOS RIESGOS A LOS CUALES
                                       SE VA A HACER SEGUIMIENTO
ELABORACION DE UN PLAN DE
      SEGUIMIENTO                       ELABORAR CRONOGRAMA
                                           DE SEGUIMIENTO

                                      DEFINICIÓN DE RESPONSABLES
                                            DEL SEGUIMIENTO




                                      REVISIÓN DE LOS COMPROMISOS
                                             ADQUIRIDOS PARA
                                           MITIGAR LOS RIESGOS
EJECUCION DEL SEGUIMIENTO                     SELECCIONADOS

                                   VERIFICACIÓN DE LA IMPLEMENTACIÓN
                                                 DE LAS
                                              ACTIVIDADES




                                          CONSOLIDACIÓN DE LA
                                             INFORMACIÓN
   PRESENTACIÓN DE
    RESULTADOS Y                     PRESENTACIÓN DE SUGERENCIAS
     PROPUESTAS                          Y RECOMENDACIONES

                                        ELABORACIÓN DEL INFORME




                                                  RIESGO
    ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
    INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL             Página 25
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                             RIESGO EN EL IPSFA


6. DEFINICIÓN DE TÉRMINOS
Administración de riesgos: Una rama de administración que aborda las
consecuencias del riesgo. Consta de dos etapas:
i El diagnóstico o valoración, mediante Identificación, Análisis y determinación del
Nivel, y
ii El manejo o la administración propiamente dicha, en que se elabora, ejecuta y
hace seguimiento al Plan de manejo que contiene las Técnicas de Administración
del Riesgo propuestas por el grupo de trabajo, evaluadas y aceptadas por la alta
dirección.
• Análisis de Beneficio-Costo: Una herramienta de Administración de Riesgos
usada para tomar decisiones sobre las técnicas propuestas por el grupo para la
administración de los riesgos, en la cual se valoran y comparan los costos,
financieros y económicos, de implementar la medida, contra los beneficios
generados por la misma. Una medida de administración de riesgos será aceptada
siempre que el beneficio valorado supere al costo.
• Análisis de riesgos: Determinar el Impacto y la Probabilidad del riesgo.
• Causa: Son los medios, circunstancias y agentes que generan los riesgos.
• Control: Es toda acción que tiende a minimizar los riesgos, significa analizar el
desempeño de las operaciones, evidenciando posibles desviaciones frente al
resultado esperado para la adopción de medidas preventivas. Los controles
proporcionan un modelo operacional de seguridad razonable en el logro de los
objetivos.
• Costo: Se entiende por costo las erogaciones, directas e indirectas en que
incurre la entidad en la producción, prestación de un servicio o manejo de un
riesgo.
• Factores de riesgo: Manifestaciones o características medibles u observables
de un proceso que indican la presencia de Riesgo o tienden a aumentar la
exposición, pueden ser internos o externos a la entidad.
• Identificación de riesgos: Establecer la estructura del riesgo; fuentes o
factores, internos o externos, generadores de riesgos; puede hacerse a cualquier
nivel: total entidad, por áreas, por procesos, incluso, bajo el viejo paradigma, por
funciones; desde el nivel estratégico hasta el más humilde operativo.



                                              RIESGO
ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL                              Página 26
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                             RIESGO EN EL IPSFA


Impacto: consecuencias que puede ocasionar a la organización la materialización
del riesgo.
• Indicador: es la valoración de una o más variables que informa sobre una
situación y soporta la toma de decisiones, es un criterio de medición y de
evaluación cuantitativa o cualitativa.
• Mapas de riesgos: herramienta metodológica que permite hacer un inventario
de los riesgos ordenada y sistemáticamente, definiéndolos, haciendo la
descripción de cada uno de estos y las posibles consecuencias
• Nivel de riesgo (determinación del): Es el resultado de confrontar el impacto y
la probabilidad, con los controles existentes.
• Plan de contingencia: Parte del plan de manejo de riesgos que contiene las
acciones a ejecutar en caso de la materialización del riesgo, con el fin de dar
continuidad a los objetivos de la entidad.
• Plan de manejo de riesgos: Plan de acción propuesto por el grupo de trabajo,
cuya evaluación de beneficio costo resulta positiva y es aprobado por la gerencia.
• Plan de mejoramiento: Parte del plan de manejo que contiene las técnicas de
administración del riesgo orientadas a prevenir, evitar, reducir, dispersar, transferir
o asumir riesgos.
• Probabilidad: Una medida (expresada como porcentaje o razón) para estimar la
posibilidad de que ocurra un incidente o evento. Contando con registros, puede
estimarse a partir de su Frecuencia histórica mediante modelos estadísticos de
mayor o menor complejidad.
• Responsables: Son las dependencias o áreas encargadas de adelantar las
acciones propuestas.
• Retroalimentación: Información sistemática sobre los resultados alcanzados en
la ejecución de un plan, que sirven para actualizar y mejorar la planeación futura.
• Riesgo: posibilidad de ocurrencia de toda aquella situación que pueda
entorpecer el normal desarrollo de las funciones de la entidad y le impidan el logro
de sus objetivos.
• Riesgo absoluto: el máximo riesgo sin los efectos mitigantes de la
administración del riesgo.



                                              RIESGO
ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL                              Página 27
METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009
                             RIESGO EN EL IPSFA


Riesgo residual: es el riesgo que queda cuando las técnicas de administración
del riesgo han sido aplicadas.
• Seguimiento: Recolección regular y sistemática sobre la ejecución del plan, que
sirven para actualizar y mejorar la planeación futura.
• Sistema: Conjunto de cosas o partes coordinadas, ordenadamente relacionadas
entre sí, que contribuyen a un determinado objetivo.
• Técnicas para manejar el riesgo: Evitar o prevenir, reducir, dispersar, transferir
y asumir riesgos.
• Valoración del riesgo: Primera fase en la administración de riesgos, diagnóstico
que consta de la identificación, análisis y determinación del nivel de riesgo.




                        Rafael María Contreras Acevedo
                                  CI 4208526




                                              RIESGO
ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL
INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL                            Página 28

Contenu connexe

Tendances

Modelos planificacion estratégica
Modelos planificacion estratégicaModelos planificacion estratégica
Modelos planificacion estratégicagabrielagomez2011
 
Sesion 2 gestión del riesgo...
Sesion 2  gestión del riesgo...Sesion 2  gestión del riesgo...
Sesion 2 gestión del riesgo...idea
 
6 GestióN De Riesgos
6   GestióN De Riesgos6   GestióN De Riesgos
6 GestióN De Riesgosequisoide
 
Mapas Conceptuales Administración Finaciera
Mapas Conceptuales Administración FinacieraMapas Conceptuales Administración Finaciera
Mapas Conceptuales Administración Finacierapipponba
 
Manajemen Risiko 17 resiko operasional & perubahan kurs
Manajemen Risiko 17 resiko operasional & perubahan kursManajemen Risiko 17 resiko operasional & perubahan kurs
Manajemen Risiko 17 resiko operasional & perubahan kursJudianto Nugroho
 
Planeación estratégica
Planeación estratégicaPlaneación estratégica
Planeación estratégicaGunBlade
 
Administracion del capital del trabajo
Administracion del capital del trabajoAdministracion del capital del trabajo
Administracion del capital del trabajoloktita
 
(1)conceptos generales de planeacion estrategica
(1)conceptos generales de planeacion estrategica(1)conceptos generales de planeacion estrategica
(1)conceptos generales de planeacion estrategicaMarco Gamarra
 
ANÁLISIS DE RIESO Y TEORIA ACTUAL DE RIESGO
ANÁLISIS DE RIESO Y TEORIA ACTUAL DE RIESGOANÁLISIS DE RIESO Y TEORIA ACTUAL DE RIESGO
ANÁLISIS DE RIESO Y TEORIA ACTUAL DE RIESGOJose Miranda
 
Bases datos eventos_perdida_riesgos_operacionales
Bases datos eventos_perdida_riesgos_operacionales Bases datos eventos_perdida_riesgos_operacionales
Bases datos eventos_perdida_riesgos_operacionales IDDEA
 
Riesgo de cartera (diapositiva)
Riesgo de cartera (diapositiva)Riesgo de cartera (diapositiva)
Riesgo de cartera (diapositiva)Pepe Salva Ruiz
 
ADMINISTRACION INTEGRAL DE RIESGOS
ADMINISTRACION INTEGRAL DE RIESGOSADMINISTRACION INTEGRAL DE RIESGOS
ADMINISTRACION INTEGRAL DE RIESGOSAnabel Montalvo
 
Semana 9 riesgo operativo
Semana  9   riesgo operativoSemana  9   riesgo operativo
Semana 9 riesgo operativogutyr
 

Tendances (20)

Unidad 2 interes compuesto
Unidad 2  interes compuestoUnidad 2  interes compuesto
Unidad 2 interes compuesto
 
Modon GIS final draft
Modon GIS final draftModon GIS final draft
Modon GIS final draft
 
Modelos planificacion estratégica
Modelos planificacion estratégicaModelos planificacion estratégica
Modelos planificacion estratégica
 
Sesion 2 gestión del riesgo...
Sesion 2  gestión del riesgo...Sesion 2  gestión del riesgo...
Sesion 2 gestión del riesgo...
 
6 GestióN De Riesgos
6   GestióN De Riesgos6   GestióN De Riesgos
6 GestióN De Riesgos
 
Mapas Conceptuales Administración Finaciera
Mapas Conceptuales Administración FinacieraMapas Conceptuales Administración Finaciera
Mapas Conceptuales Administración Finaciera
 
Manajemen Risiko 17 resiko operasional & perubahan kurs
Manajemen Risiko 17 resiko operasional & perubahan kursManajemen Risiko 17 resiko operasional & perubahan kurs
Manajemen Risiko 17 resiko operasional & perubahan kurs
 
Planeación estratégica
Planeación estratégicaPlaneación estratégica
Planeación estratégica
 
Administracion del capital del trabajo
Administracion del capital del trabajoAdministracion del capital del trabajo
Administracion del capital del trabajo
 
(1)conceptos generales de planeacion estrategica
(1)conceptos generales de planeacion estrategica(1)conceptos generales de planeacion estrategica
(1)conceptos generales de planeacion estrategica
 
ANÁLISIS DE RIESO Y TEORIA ACTUAL DE RIESGO
ANÁLISIS DE RIESO Y TEORIA ACTUAL DE RIESGOANÁLISIS DE RIESO Y TEORIA ACTUAL DE RIESGO
ANÁLISIS DE RIESO Y TEORIA ACTUAL DE RIESGO
 
Investigación operativa
Investigación operativaInvestigación operativa
Investigación operativa
 
Teknik Teknik Manajemen Risiko
Teknik Teknik Manajemen RisikoTeknik Teknik Manajemen Risiko
Teknik Teknik Manajemen Risiko
 
Bases datos eventos_perdida_riesgos_operacionales
Bases datos eventos_perdida_riesgos_operacionales Bases datos eventos_perdida_riesgos_operacionales
Bases datos eventos_perdida_riesgos_operacionales
 
ADMINISTRACION RIESGO
ADMINISTRACION RIESGOADMINISTRACION RIESGO
ADMINISTRACION RIESGO
 
Lineas de espera
Lineas de esperaLineas de espera
Lineas de espera
 
Riesgo de cartera (diapositiva)
Riesgo de cartera (diapositiva)Riesgo de cartera (diapositiva)
Riesgo de cartera (diapositiva)
 
ADMINISTRACION INTEGRAL DE RIESGOS
ADMINISTRACION INTEGRAL DE RIESGOSADMINISTRACION INTEGRAL DE RIESGOS
ADMINISTRACION INTEGRAL DE RIESGOS
 
Administración de Riesgos
Administración de RiesgosAdministración de Riesgos
Administración de Riesgos
 
Semana 9 riesgo operativo
Semana  9   riesgo operativoSemana  9   riesgo operativo
Semana 9 riesgo operativo
 

En vedette

Planificacion de auditoria
Planificacion de auditoriaPlanificacion de auditoria
Planificacion de auditoriaRafael Contreras
 
Subsidios, dependen de donde vengan
Subsidios, dependen de donde venganSubsidios, dependen de donde vengan
Subsidios, dependen de donde venganRafael Contreras
 
Diagnostico experimental aproximado de la justica militar de venezuela susten...
Diagnostico experimental aproximado de la justica militar de venezuela susten...Diagnostico experimental aproximado de la justica militar de venezuela susten...
Diagnostico experimental aproximado de la justica militar de venezuela susten...Rafael Contreras
 
Les métiers du futur du management
Les métiers du futur du managementLes métiers du futur du management
Les métiers du futur du managementLes Propulseurs
 
10 Good Reasons: NetApp for Finance
10 Good Reasons: NetApp for Finance10 Good Reasons: NetApp for Finance
10 Good Reasons: NetApp for FinanceNetApp
 
Wykonawcy przyszłości - platformy motywacyjne
Wykonawcy przyszłości - platformy motywacyjneWykonawcy przyszłości - platformy motywacyjne
Wykonawcy przyszłości - platformy motywacyjneGrzegorz Osóbka
 
Penn Athletics Deepening the Connection case study
Penn Athletics Deepening the Connection case studyPenn Athletics Deepening the Connection case study
Penn Athletics Deepening the Connection case studyFred Popp
 
สรุป วิชาโลก ดาราศาสตร์ และอวกาศ
สรุป วิชาโลก ดาราศาสตร์ และอวกาศสรุป วิชาโลก ดาราศาสตร์ และอวกาศ
สรุป วิชาโลก ดาราศาสตร์ และอวกาศสิปป์แสง สุขผล
 
Holly Springs Surgery Center
Holly Springs Surgery CenterHolly Springs Surgery Center
Holly Springs Surgery CenterJoe Sziabowski
 
PLANT RESIDENT MICROORGANISM IN DISEASE MANAGEMNT
PLANT RESIDENT MICROORGANISM IN DISEASE MANAGEMNTPLANT RESIDENT MICROORGANISM IN DISEASE MANAGEMNT
PLANT RESIDENT MICROORGANISM IN DISEASE MANAGEMNTajjit kumar
 
10 Things You Didn’t Know About Mobile Email from Litmus & HubSpot
 10 Things You Didn’t Know About Mobile Email from Litmus & HubSpot 10 Things You Didn’t Know About Mobile Email from Litmus & HubSpot
10 Things You Didn’t Know About Mobile Email from Litmus & HubSpotHubSpot
 
Modern Prospecting Techniques for Connecting with Prospects (from Sales Hacke...
Modern Prospecting Techniques for Connecting with Prospects (from Sales Hacke...Modern Prospecting Techniques for Connecting with Prospects (from Sales Hacke...
Modern Prospecting Techniques for Connecting with Prospects (from Sales Hacke...HubSpot
 
Behind the Scenes: Launching HubSpot Tokyo
Behind the Scenes: Launching HubSpot TokyoBehind the Scenes: Launching HubSpot Tokyo
Behind the Scenes: Launching HubSpot TokyoHubSpot
 
Why People Block Ads (And What It Means for Marketers and Advertisers) [New R...
Why People Block Ads (And What It Means for Marketers and Advertisers) [New R...Why People Block Ads (And What It Means for Marketers and Advertisers) [New R...
Why People Block Ads (And What It Means for Marketers and Advertisers) [New R...HubSpot
 

En vedette (18)

Planificacion de auditoria
Planificacion de auditoriaPlanificacion de auditoria
Planificacion de auditoria
 
Subsidios, dependen de donde vengan
Subsidios, dependen de donde venganSubsidios, dependen de donde vengan
Subsidios, dependen de donde vengan
 
Diagnostico experimental aproximado de la justica militar de venezuela susten...
Diagnostico experimental aproximado de la justica militar de venezuela susten...Diagnostico experimental aproximado de la justica militar de venezuela susten...
Diagnostico experimental aproximado de la justica militar de venezuela susten...
 
Les métiers du futur du management
Les métiers du futur du managementLes métiers du futur du management
Les métiers du futur du management
 
10 Good Reasons: NetApp for Finance
10 Good Reasons: NetApp for Finance10 Good Reasons: NetApp for Finance
10 Good Reasons: NetApp for Finance
 
Phylum antropoda-zoology
Phylum antropoda-zoologyPhylum antropoda-zoology
Phylum antropoda-zoology
 
Wykonawcy przyszłości - platformy motywacyjne
Wykonawcy przyszłości - platformy motywacyjneWykonawcy przyszłości - platformy motywacyjne
Wykonawcy przyszłości - platformy motywacyjne
 
API Driven Development 2016-10-27
API Driven Development 2016-10-27API Driven Development 2016-10-27
API Driven Development 2016-10-27
 
Penn Athletics Deepening the Connection case study
Penn Athletics Deepening the Connection case studyPenn Athletics Deepening the Connection case study
Penn Athletics Deepening the Connection case study
 
สรุป วิชาโลก ดาราศาสตร์ และอวกาศ
สรุป วิชาโลก ดาราศาสตร์ และอวกาศสรุป วิชาโลก ดาราศาสตร์ และอวกาศ
สรุป วิชาโลก ดาราศาสตร์ และอวกาศ
 
Political Transformations in Network Societies - the fifth estate
Political Transformations in Network Societies - the fifth estatePolitical Transformations in Network Societies - the fifth estate
Political Transformations in Network Societies - the fifth estate
 
BOARD, ALIMENTACIÓN, PUERTOS, BUSES, OVERCLOKING, GPUS Y ALGO MÁS
BOARD, ALIMENTACIÓN, PUERTOS, BUSES, OVERCLOKING, GPUS Y ALGO MÁSBOARD, ALIMENTACIÓN, PUERTOS, BUSES, OVERCLOKING, GPUS Y ALGO MÁS
BOARD, ALIMENTACIÓN, PUERTOS, BUSES, OVERCLOKING, GPUS Y ALGO MÁS
 
Holly Springs Surgery Center
Holly Springs Surgery CenterHolly Springs Surgery Center
Holly Springs Surgery Center
 
PLANT RESIDENT MICROORGANISM IN DISEASE MANAGEMNT
PLANT RESIDENT MICROORGANISM IN DISEASE MANAGEMNTPLANT RESIDENT MICROORGANISM IN DISEASE MANAGEMNT
PLANT RESIDENT MICROORGANISM IN DISEASE MANAGEMNT
 
10 Things You Didn’t Know About Mobile Email from Litmus & HubSpot
 10 Things You Didn’t Know About Mobile Email from Litmus & HubSpot 10 Things You Didn’t Know About Mobile Email from Litmus & HubSpot
10 Things You Didn’t Know About Mobile Email from Litmus & HubSpot
 
Modern Prospecting Techniques for Connecting with Prospects (from Sales Hacke...
Modern Prospecting Techniques for Connecting with Prospects (from Sales Hacke...Modern Prospecting Techniques for Connecting with Prospects (from Sales Hacke...
Modern Prospecting Techniques for Connecting with Prospects (from Sales Hacke...
 
Behind the Scenes: Launching HubSpot Tokyo
Behind the Scenes: Launching HubSpot TokyoBehind the Scenes: Launching HubSpot Tokyo
Behind the Scenes: Launching HubSpot Tokyo
 
Why People Block Ads (And What It Means for Marketers and Advertisers) [New R...
Why People Block Ads (And What It Means for Marketers and Advertisers) [New R...Why People Block Ads (And What It Means for Marketers and Advertisers) [New R...
Why People Block Ads (And What It Means for Marketers and Advertisers) [New R...
 

Similaire à Metologia para la administracion del riesgo en las instituciones

EL PERFIL DEL GERENTE DE RIESGOS
EL PERFIL DEL GERENTE DE RIESGOSEL PERFIL DEL GERENTE DE RIESGOS
EL PERFIL DEL GERENTE DE RIESGOSUPAO
 
Adminstracion Del Riesgo Cga
Adminstracion Del Riesgo CgaAdminstracion Del Riesgo Cga
Adminstracion Del Riesgo Cgafdidocar
 
Ponencia "Plan de auditoría interna con base a riesgos".
Ponencia "Plan de auditoría interna con base a riesgos".Ponencia "Plan de auditoría interna con base a riesgos".
Ponencia "Plan de auditoría interna con base a riesgos".GobAnt
 
Gerencia de riesgo
Gerencia de riesgo Gerencia de riesgo
Gerencia de riesgo Cindy Y-g
 
Gerencia de riesgo en la administración
Gerencia de riesgo en la administraciónGerencia de riesgo en la administración
Gerencia de riesgo en la administraciónCindy Y-g
 
Manual curso analisis_riesgos_2012 (1)
Manual curso analisis_riesgos_2012 (1)Manual curso analisis_riesgos_2012 (1)
Manual curso analisis_riesgos_2012 (1)icadefis
 
Metodologia Riesgos para empresas en complejidad
Metodologia Riesgos para empresas en complejidadMetodologia Riesgos para empresas en complejidad
Metodologia Riesgos para empresas en complejidadkrosillono
 
Clase 2 practica
Clase 2 practicaClase 2 practica
Clase 2 practicaRicardo-c
 
plan-trabajo-gestion-riesgos-set2017.pdf
plan-trabajo-gestion-riesgos-set2017.pdfplan-trabajo-gestion-riesgos-set2017.pdf
plan-trabajo-gestion-riesgos-set2017.pdfJianGurkas
 
Presentación de Metodologia y evaluacion de riesgos
Presentación de Metodologia y evaluacion de riesgosPresentación de Metodologia y evaluacion de riesgos
Presentación de Metodologia y evaluacion de riesgosCarlosASolanaNeri
 
Cd equipo 4 fabrizio laveglia
Cd equipo 4 fabrizio lavegliaCd equipo 4 fabrizio laveglia
Cd equipo 4 fabrizio lavegliaFabrizioLaveglia1
 
Investigación sobre la gerencia de riesgos 1
Investigación sobre la gerencia de riesgos 1Investigación sobre la gerencia de riesgos 1
Investigación sobre la gerencia de riesgos 1gutyr
 
Clase II Introducción a la Admon. de Riesgos.pptx.pdf
Clase II Introducción a la Admon. de Riesgos.pptx.pdfClase II Introducción a la Admon. de Riesgos.pptx.pdf
Clase II Introducción a la Admon. de Riesgos.pptx.pdfMARIAJOSEPRIVADOSOLO
 
Caso de Estudio #1 Compliance Risks en Sacyr
Caso de Estudio #1 Compliance Risks en SacyrCaso de Estudio #1 Compliance Risks en Sacyr
Caso de Estudio #1 Compliance Risks en SacyrHernan Huwyler, MBA CPA
 
Saim Corporativo_Curso taller Analisis Causa Raiz.pptx
Saim Corporativo_Curso taller Analisis Causa Raiz.pptxSaim Corporativo_Curso taller Analisis Causa Raiz.pptx
Saim Corporativo_Curso taller Analisis Causa Raiz.pptxgtzamir
 
Riesgo operativo
Riesgo operativoRiesgo operativo
Riesgo operativoSECMA
 
Sistema de administración de riesgos operativos «saro
Sistema de administración de riesgos operativos «saroSistema de administración de riesgos operativos «saro
Sistema de administración de riesgos operativos «saroLina Torrado Rueda
 

Similaire à Metologia para la administracion del riesgo en las instituciones (20)

Riesgos matriz
Riesgos   matrizRiesgos   matriz
Riesgos matriz
 
EL PERFIL DEL GERENTE DE RIESGOS
EL PERFIL DEL GERENTE DE RIESGOSEL PERFIL DEL GERENTE DE RIESGOS
EL PERFIL DEL GERENTE DE RIESGOS
 
Adminstracion Del Riesgo Cga
Adminstracion Del Riesgo CgaAdminstracion Del Riesgo Cga
Adminstracion Del Riesgo Cga
 
Ponencia "Plan de auditoría interna con base a riesgos".
Ponencia "Plan de auditoría interna con base a riesgos".Ponencia "Plan de auditoría interna con base a riesgos".
Ponencia "Plan de auditoría interna con base a riesgos".
 
Riesgos promperu
Riesgos promperuRiesgos promperu
Riesgos promperu
 
Gerencia de riesgo
Gerencia de riesgo Gerencia de riesgo
Gerencia de riesgo
 
Gerencia de riesgo en la administración
Gerencia de riesgo en la administraciónGerencia de riesgo en la administración
Gerencia de riesgo en la administración
 
Trabajo final
Trabajo finalTrabajo final
Trabajo final
 
Manual curso analisis_riesgos_2012 (1)
Manual curso analisis_riesgos_2012 (1)Manual curso analisis_riesgos_2012 (1)
Manual curso analisis_riesgos_2012 (1)
 
Metodologia Riesgos para empresas en complejidad
Metodologia Riesgos para empresas en complejidadMetodologia Riesgos para empresas en complejidad
Metodologia Riesgos para empresas en complejidad
 
Clase 2 practica
Clase 2 practicaClase 2 practica
Clase 2 practica
 
plan-trabajo-gestion-riesgos-set2017.pdf
plan-trabajo-gestion-riesgos-set2017.pdfplan-trabajo-gestion-riesgos-set2017.pdf
plan-trabajo-gestion-riesgos-set2017.pdf
 
Presentación de Metodologia y evaluacion de riesgos
Presentación de Metodologia y evaluacion de riesgosPresentación de Metodologia y evaluacion de riesgos
Presentación de Metodologia y evaluacion de riesgos
 
Cd equipo 4 fabrizio laveglia
Cd equipo 4 fabrizio lavegliaCd equipo 4 fabrizio laveglia
Cd equipo 4 fabrizio laveglia
 
Investigación sobre la gerencia de riesgos 1
Investigación sobre la gerencia de riesgos 1Investigación sobre la gerencia de riesgos 1
Investigación sobre la gerencia de riesgos 1
 
Clase II Introducción a la Admon. de Riesgos.pptx.pdf
Clase II Introducción a la Admon. de Riesgos.pptx.pdfClase II Introducción a la Admon. de Riesgos.pptx.pdf
Clase II Introducción a la Admon. de Riesgos.pptx.pdf
 
Caso de Estudio #1 Compliance Risks en Sacyr
Caso de Estudio #1 Compliance Risks en SacyrCaso de Estudio #1 Compliance Risks en Sacyr
Caso de Estudio #1 Compliance Risks en Sacyr
 
Saim Corporativo_Curso taller Analisis Causa Raiz.pptx
Saim Corporativo_Curso taller Analisis Causa Raiz.pptxSaim Corporativo_Curso taller Analisis Causa Raiz.pptx
Saim Corporativo_Curso taller Analisis Causa Raiz.pptx
 
Riesgo operativo
Riesgo operativoRiesgo operativo
Riesgo operativo
 
Sistema de administración de riesgos operativos «saro
Sistema de administración de riesgos operativos «saroSistema de administración de riesgos operativos «saro
Sistema de administración de riesgos operativos «saro
 

Plus de Rafael Contreras

El problema de la conciencia nacional en venezuela
El problema de la conciencia nacional en venezuelaEl problema de la conciencia nacional en venezuela
El problema de la conciencia nacional en venezuelaRafael Contreras
 
Propuesta para el plan de la patria desde la iniciativa Mentes colonizadas, i...
Propuesta para el plan de la patria desde la iniciativa Mentes colonizadas, i...Propuesta para el plan de la patria desde la iniciativa Mentes colonizadas, i...
Propuesta para el plan de la patria desde la iniciativa Mentes colonizadas, i...Rafael Contreras
 
Sinopsis de la exposición Ideas para el proyecto de conciencia nacional desde...
Sinopsis de la exposición Ideas para el proyecto de conciencia nacional desde...Sinopsis de la exposición Ideas para el proyecto de conciencia nacional desde...
Sinopsis de la exposición Ideas para el proyecto de conciencia nacional desde...Rafael Contreras
 
Mentes colonizadas promoción de charla
Mentes colonizadas promoción de charlaMentes colonizadas promoción de charla
Mentes colonizadas promoción de charlaRafael Contreras
 
Transferencia del control interno a la administraciòn activa
Transferencia del control interno a la administraciòn activaTransferencia del control interno a la administraciòn activa
Transferencia del control interno a la administraciòn activaRafael Contreras
 
Administración de riesgos
Administración de riesgosAdministración de riesgos
Administración de riesgosRafael Contreras
 
Instituto venezolano de justicia accesible
Instituto venezolano de justicia accesibleInstituto venezolano de justicia accesible
Instituto venezolano de justicia accesibleRafael Contreras
 
Algunas consideraciones a tomar en cuenta en la entrega de cargos
Algunas consideraciones a tomar en cuenta en la entrega de cargosAlgunas consideraciones a tomar en cuenta en la entrega de cargos
Algunas consideraciones a tomar en cuenta en la entrega de cargosRafael Contreras
 
Dos ideas para la atención de los factores de riesgos asociados a la situació...
Dos ideas para la atención de los factores de riesgos asociados a la situació...Dos ideas para la atención de los factores de riesgos asociados a la situació...
Dos ideas para la atención de los factores de riesgos asociados a la situació...Rafael Contreras
 
Auto bienvenida a mi nueva situacion militar
Auto bienvenida a mi nueva situacion militarAuto bienvenida a mi nueva situacion militar
Auto bienvenida a mi nueva situacion militarRafael Contreras
 
Porque es necesario mantener el regimen de seguridad social propio para la fu...
Porque es necesario mantener el regimen de seguridad social propio para la fu...Porque es necesario mantener el regimen de seguridad social propio para la fu...
Porque es necesario mantener el regimen de seguridad social propio para la fu...Rafael Contreras
 
Rumbo fiscal (sistema nacional de control fiscal)
Rumbo fiscal (sistema nacional de control fiscal)Rumbo fiscal (sistema nacional de control fiscal)
Rumbo fiscal (sistema nacional de control fiscal)Rafael Contreras
 
Rumbo fiscal (presentación inicial)
Rumbo fiscal (presentación inicial)Rumbo fiscal (presentación inicial)
Rumbo fiscal (presentación inicial)Rafael Contreras
 
Cuadernillo del juez militar de juicio
Cuadernillo del juez militar de juicioCuadernillo del juez militar de juicio
Cuadernillo del juez militar de juicioRafael Contreras
 
Una idea en concreto para el verdadero acceso gratuito a la justicia venezolana
Una idea en concreto para el verdadero acceso gratuito a la justicia venezolanaUna idea en concreto para el verdadero acceso gratuito a la justicia venezolana
Una idea en concreto para el verdadero acceso gratuito a la justicia venezolanaRafael Contreras
 
El militar ante ordenes ilegales
El militar ante ordenes ilegalesEl militar ante ordenes ilegales
El militar ante ordenes ilegalesRafael Contreras
 
Compañeros militares en situacion de retiro, con la verdad ni ofendo ni temo
Compañeros militares en situacion de retiro, con la verdad ni ofendo ni temoCompañeros militares en situacion de retiro, con la verdad ni ofendo ni temo
Compañeros militares en situacion de retiro, con la verdad ni ofendo ni temoRafael Contreras
 

Plus de Rafael Contreras (17)

El problema de la conciencia nacional en venezuela
El problema de la conciencia nacional en venezuelaEl problema de la conciencia nacional en venezuela
El problema de la conciencia nacional en venezuela
 
Propuesta para el plan de la patria desde la iniciativa Mentes colonizadas, i...
Propuesta para el plan de la patria desde la iniciativa Mentes colonizadas, i...Propuesta para el plan de la patria desde la iniciativa Mentes colonizadas, i...
Propuesta para el plan de la patria desde la iniciativa Mentes colonizadas, i...
 
Sinopsis de la exposición Ideas para el proyecto de conciencia nacional desde...
Sinopsis de la exposición Ideas para el proyecto de conciencia nacional desde...Sinopsis de la exposición Ideas para el proyecto de conciencia nacional desde...
Sinopsis de la exposición Ideas para el proyecto de conciencia nacional desde...
 
Mentes colonizadas promoción de charla
Mentes colonizadas promoción de charlaMentes colonizadas promoción de charla
Mentes colonizadas promoción de charla
 
Transferencia del control interno a la administraciòn activa
Transferencia del control interno a la administraciòn activaTransferencia del control interno a la administraciòn activa
Transferencia del control interno a la administraciòn activa
 
Administración de riesgos
Administración de riesgosAdministración de riesgos
Administración de riesgos
 
Instituto venezolano de justicia accesible
Instituto venezolano de justicia accesibleInstituto venezolano de justicia accesible
Instituto venezolano de justicia accesible
 
Algunas consideraciones a tomar en cuenta en la entrega de cargos
Algunas consideraciones a tomar en cuenta en la entrega de cargosAlgunas consideraciones a tomar en cuenta en la entrega de cargos
Algunas consideraciones a tomar en cuenta en la entrega de cargos
 
Dos ideas para la atención de los factores de riesgos asociados a la situació...
Dos ideas para la atención de los factores de riesgos asociados a la situació...Dos ideas para la atención de los factores de riesgos asociados a la situació...
Dos ideas para la atención de los factores de riesgos asociados a la situació...
 
Auto bienvenida a mi nueva situacion militar
Auto bienvenida a mi nueva situacion militarAuto bienvenida a mi nueva situacion militar
Auto bienvenida a mi nueva situacion militar
 
Porque es necesario mantener el regimen de seguridad social propio para la fu...
Porque es necesario mantener el regimen de seguridad social propio para la fu...Porque es necesario mantener el regimen de seguridad social propio para la fu...
Porque es necesario mantener el regimen de seguridad social propio para la fu...
 
Rumbo fiscal (sistema nacional de control fiscal)
Rumbo fiscal (sistema nacional de control fiscal)Rumbo fiscal (sistema nacional de control fiscal)
Rumbo fiscal (sistema nacional de control fiscal)
 
Rumbo fiscal (presentación inicial)
Rumbo fiscal (presentación inicial)Rumbo fiscal (presentación inicial)
Rumbo fiscal (presentación inicial)
 
Cuadernillo del juez militar de juicio
Cuadernillo del juez militar de juicioCuadernillo del juez militar de juicio
Cuadernillo del juez militar de juicio
 
Una idea en concreto para el verdadero acceso gratuito a la justicia venezolana
Una idea en concreto para el verdadero acceso gratuito a la justicia venezolanaUna idea en concreto para el verdadero acceso gratuito a la justicia venezolana
Una idea en concreto para el verdadero acceso gratuito a la justicia venezolana
 
El militar ante ordenes ilegales
El militar ante ordenes ilegalesEl militar ante ordenes ilegales
El militar ante ordenes ilegales
 
Compañeros militares en situacion de retiro, con la verdad ni ofendo ni temo
Compañeros militares en situacion de retiro, con la verdad ni ofendo ni temoCompañeros militares en situacion de retiro, con la verdad ni ofendo ni temo
Compañeros militares en situacion de retiro, con la verdad ni ofendo ni temo
 

Metologia para la administracion del riesgo en las instituciones

  • 1. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA INDICE PRELIMINARES 4 METODOLOGÍA PARA LA ADMINISTRACION DEL RIESGO EN EL IPSFA 4 1. OBJETIVOS DE LA ADMINISTRACIÓN DEL RIESGO 5 GENERAL 5 ESPECIFICOS 5 2. MARCO NORMATIVO 5 3. MARCO CONCEPTUAL 6 4. METODOLOGÍA 7 LINEAS GENERALES 8 Compromiso Gerencial 8 Conformación de un equipo de trabajo 8 Capacitación en la metodología 8 4.1 PLANIFICACIÓN DE LA ADMINISTRACIÓN DEL RIESGO 8 4.2 VALORACIÓN DEL RIESGO 9 4.2.1 Identificación del riesgo 9 Formato de identificación de riesgos 10 Clasificación del riesgo 10 4.2.2 Análisis del riesgo 11 Análisis cualitativo 12 Análisis cuantitativo 12 RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 1
  • 2. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA Evaluación de los riesgos 14 4.2.3 Determinación del nivel del riesgo 16 Calificación de los controles 16 Criterios para evaluar la efectividad de los controles 16 Criterios para evaluar el nivel del riesgo 17 Resultado Nivel de riesgo 17 4.3 MANEJO DEL RIESGO 18 4.3.1 Consideración de Acciones 18 Evitar el riesgo 18 Reducir el riesgo 18 Dispersar y atomizar el riesgo 19 Transferir el riesgo 19 Asumir el riesgo 19 4.3.2 Elaboración del Mapa de Riesgos 19 MAPA DE RIESGOS 20 Descripción del Mapa de riesgos 20 4.3.3 Implementación de acciones 21 4.5 MONITOREO 21 5. DIAGRAMAS DE LA ADMINISTRACION DEL RIESGO 22 ETAPA DE PLANIFICACION 23 RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 2
  • 3. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA EATAPA DE VALORACION DEL RIESGO 23 ETAPA DE MANEJO DEL RIESGO 24 ETAPA DE MONITOREO 25 6. DEFINICIÓN DE TÉRMINOS 26 RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 3
  • 4. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA PRELIMINARES El riesgo esta relacionado con todo el quehacer de la especie humana, de manera que no hay actividad de la vida, los negocios o de cualquier asunto que no incluya el riesgo, es por ello que el ser humano desde sus inicios buscó maneras de protegerse contra las eventualidades y desarrolló modos de sortear, disminuir o asumir riesgos a través de acciones preventivas. Así mismo, la administración pública y en especial el Instituto de Previsión Social de la Fuerza Armada no son ajenas al riesgo y deben buscar como manejarlos partiendo de la base de su razón de ser y su compromiso con el Estado; por esto, se debe tener en cuenta que los riesgos no sólo son de carácter económico y están directamente relacionados con entidades financieras, aseguradoras o con lo que se ha denominado riesgos profesionales, sino que hacen parte de cualquier gestión que se realice. La Auditoría Interna del IPSFA en ejercicio de su competencia de la evaluación del Sistema de Control Interno del Instituto y aún más el de contribuir en desarrollo de su Cultura ha estimado necesario compilar la presente información, tomada de otros Estados que han tenido un desarrollo importante en esta área, y la presenta en forma de guía metodológica de forma tal que pueda ser utilizada como referencia en el empeño gerencial de lograr desarrollar la ADMINISTRACION DEL RIESGO en el Instituto. Es importante advertir, que en lo relativo al manejo de los indicadores en el área de la Administración del Riesgo, la presente guía metodológica la limita a una modesta mención, toda vez que la misma merece que sea atendida por separado, cuando se trate lo relativo a las técnicas construcción de los indicadores de gestión, validos también para la Administración del Riesgo. METODOLOGÍA PARA LA ADMINISTRACION DEL RIESGO EN EL IPSFA La Administración del Riesgo se presenta como una herramienta que le permita a la administración hacer un manejo adecuado del mismo desde la planificación, por lo cual, se aspira que el usuario de ella, pueda identificar, analizar y manejar permanentemente el riesgo, garantizando el cumplimiento de los objetivos institucionales, la supervivencia de la entidad y fortaleciendo continuamente la credibilidad de la misma ante el afiliado. Para efectos de esta metodología, se va a considerar el riesgo, como toda posibilidad de ocurrencia de aquella situación que pueda entorpecer el normal desarrollo de las funciones de la entidad y le impidan el logro de sus objetivos. RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 4
  • 5. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA Es conveniente aclarar que la presente metodología resulta ser una compilación de diversas instituciones de otros Estados que han avanzado considerablemente en el modelo de Administración del riesgo, toda vez que en Venezuela apenas estamos desarrollando nuestras primeras experiencias y aún no se recibe información oficial sobre la materia. Sin embargo la misma no agota la materia de Administración de Riesgo y menos invalida otros modelos de administración existentes, información que no solo es aceptada por el compilador del presente trabajo, sino por el contrario se estimula al desarrollo de la investigación en esta área, de manera de complementar la información aquí contenida. 1. OBJETIVOS DE LA ADMINISTRACIÓN DEL RIESGO GENERAL Facilitar el cumplimiento de la misión y objetivos de la institución a través de la prevención y administración de los riesgos. ESPECIFICOS Generar una visión sistémica acerca de la administración y evaluación de riesgos. Servir como herramienta de trabajo a la administración activa en su meta de protección de los recursos del Estado. Introducir dentro de los procesos y procedimientos la administración del riesgo. Involucrar y comprometer a todos los funcionarias y funcionarias del instituto, en la búsqueda de acciones encaminadas a prevenir y administrar los riesgos. Propender porque cada entidad interactúe con otras, para fortalecer su desarrollo. Asegurar el cumplimiento de normas, leyes y regulaciones. 2. MARCO NORMATIVO El Manual de Normas de Control Interno sobre un modelo Genérico de la Administración Central y Descentralizada Funcionalmente (Gaceta Oficial No 38.282 del 28 de septiembre de 2005), dictado por la Superintendencia Nacional de Auditoría Interna, órgano rector del sistema de control interno del sector publico, de acuerdo a las previsiones del Artículo 5 de la Ley Orgánica de Administración Financiera del Sector Público, en nombre del Estado venezolano RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 5
  • 6. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA reconoce la aplicación del Modelo COSO como herramienta de control de la administración pública, con la cual se suma a la nueva filosofía de gobierno del Control Fiscal (Sistema Nacional de Control Fiscal Venezolano). Con ello reconoce la aplicación del componente del sistema denominado: “Administración y Valoración del riesgo”, de esta manera da entrada en toda la administración pública al “Riesgo” como herramienta para ser tomada en cuenta en la planificación pública. 3. MARCO CONCEPTUAL La administración pública al ocuparse de los fenómenos de organización y gestión, no puede ser ajena a las herramientas disponibles y a las nuevas tendencias en administración, para lo cual requiere estar en constante actualización y estar abierta al cambio y a la aplicación de diferentes instrumentos que le permitan a las entidades ser cada vez más eficientes, por lo que se hace necesario tener en cuenta todos aquellos hechos o factores que puedan afectar en un momento determinado el cumplimiento de los objetivos institucionales. Por lo anterior, se hace necesario introducir el concepto de administración del riesgo en el instituto, teniendo en cuenta que todas las organizaciones independientemente de su naturaleza, tamaño y razón de ser están permanentemente expuestos a diferentes riesgos que pueden poner en peligro su existencia. Desde la perspectiva del control, el modelo COSO interpreta que la eficiencia del control es la reducción de los riesgos, es decir: el propósito principal del control es la eliminación o reducción de los riesgos, es lograr que el proceso y sus controles garanticen, de manera razonable que los riesgos están minimizados o se están reduciendo y por lo tanto, que los objetivos de la organización y en este caso del instituto, van a ser alcanzados. Para el caso particular del IPSFA, dada la diversidad y particularidad de las dependencias en cuanto a sus funciones, estructura, manejo presupuestario, contacto con la ciudadanía y compromiso social entre otros, es preciso identificar o precisar las áreas, los procesos, los procedimientos, las instancias y controles dentro de los cuales puede actuarse e incurrirse en riesgos que atentan contra la buena gestión y la obtención de resultados para tener un adecuado manejo del riesgo. Igualmente, es importante tener en cuenta que los riesgos están determinados por factores de carácter externo, también denominados del entorno y factores de carácter interno. RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 6
  • 7. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA Entre los factores externos se destacan: la normatividad en la medida que se hace parte de un Estado social de derecho; a manera de ejemplo se pueden mencionar cambios constitucionales, legales, reglamentarios o cualquier otra normativa superior al instituto de producirse; jurisprudenciales como los que se expresan en sentencias que declaran sin efecto normas que venían aplicándose y que en un momento determinado pueden afectar las funciones específicas del instituto y por lo tanto sus objetivos. También pueden mencionarse las reformas a la administración y los constantes recortes presupuestales que afectan la capacidad de gestión de la entidad, lo cual sumado a la reducción o eliminación total del presupuesto de inversión, obliga a considerar en todo momento el riesgo que tendría el IPSFA de no poder cumplir con su objeto social. Entre los factores internos se destacan: el manejo de los recursos, la estructura organizacional, los controles existentes, los procesos y procedimientos, la disponibilidad presupuestaria, la forma como se vinculan las personas a la entidad, los intereses de los directivos, el nivel del talento humano, la motivación y los niveles salariales, entre otros. Es así como se hace necesario además de la identificación de factores y riesgos en las entidades, su análisis, valoración e implementación de un plan de manejo el cual se materialice en un mapa de Riesgos, al cual se le haga una evaluación y monitoreo permanentes. Para llevar a cabo dicho proceso se considera importante señalar el papel de la Oficina de Coordinadora de Control Interno del instituto, coordinar para que en las gerencias se implementen políticas de administración del riesgo y se conformen equipos de trabajo que apoyen dicho proceso y propendan por que se implementen mecanismos reales para la administración del riesgo. Igualmente estimular para que la identificación y el análisis del riesgo sean un proceso permanente e interactivo entre la administración y las coordinaciones de control interno o quien haga sus veces con miras a establecer acciones efectivas, representadas en actividades de control, acordadas entre los responsables de las áreas o procesos y dichas oficinas. 4. METODOLOGÍA El IPSFA al igual que el resto de entidades de la administración pública tiene unos objetivos institucionales definidos por su norma de constitución y demás normas que la involucran, los cuales debe desarrollar a través de diferentes planes, programas y proyectos. El cumplimiento de dichos objetivos se puede ver afectado por la presencia de riesgos, razón por la cual se hace RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 7
  • 8. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA necesario contar con una metodología para administrar los mismos dentro de la organización. En este sentido y partiendo de la razón de ser de la entidad, la administración del riesgo debe ser una política institucional definida, respaldada por la Gerencia, de tal forma que se comprometa a manejar el tema dentro de la misma. LINEAS GENERALES Las etapas sugeridas para una adecuada Administración del Riesgo son las siguientes: Compromiso Gerencial: Para el éxito en la Implementación de una adecuada administración del riesgo, es indispensable el compromiso de la alta gerencia como encargada, en primera instancia, de definir las políticas y en segunda instancia de estimular la cultura de la identificación y prevención del riesgo. Para lograrlo es importante la definición de canales directos de comunicación y el apoyo a todas las acciones emprendidas en este sentido, propiciando los espacios y asignando los recursos necesarios. Conformación de un equipo de trabajo: Es importante conformar un equipo de trabajo que junto con la Coordinación de Control Interno se encargue de liderar el proceso de administración del riesgo dentro de la gerencia y cuente con un canal directo de comunicación con la alta dirección. Dicho equipo lo deben integrar personas de diferentes áreas que conozcan muy bien la entidad y la dependencia en particular, el funcionamiento de los diferentes procesos para que se facilite la administración del riesgo y la construcción de los mapas de riesgos institucionales. Capacitación en la metodología: Definido el equipo o equipos de trabajo, la Gerencia y la Coordinación de Control interno deben velar por la capacitación de sus integrantes en la metodología de la administración del riesgo, para lo cual se podrá contar con el apoyo de las diferentes instituciones del estado en materia de Control Fiscal incluyendo la Auditoría interna del IPSFA. 4.1 PLANIFICACIÓN DE LA ADMINISTRACIÓN DEL RIESGO Como cualquier otro proceso, la administración del riesgo debe planificarse y programarse de manera que haga parte de todo el quehacer de la entidad. Para el diseño de esta planificación es fundamental tener claridad en la misión de la entidad, en sus objetivos y tener una visión sistémica de manera que no se RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 8
  • 9. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA perciba la administración del riesgo como algo aislado. Igualmente es necesario conocer sobre el tema de riesgos y la metodología propuesta. Dicha planificación debe contener: ¿Cuándo va a empezar a manejarse el tema dentro de la entidad?, ¿Quiénes van a participar directamente en el proceso?, ¿Cuándo van a realizarse las capacitaciones y a quién van a ir dirigidas? y ¿Cómo se va a articular el tema dentro de la planificación y con los procesos?, ¿Cómo se conducir el seguimiento?, entre otros. 4.2 VALORACIÓN DEL RIESGO La valoración del riesgo consta de tres etapas: la identificación, el análisis y la determinación del nivel del riesgo. Estas etapas son de singular interés para desarrollar con éxito la administración del riesgo e implementar una política al respecto en la entidad; para cada una de ellas se sugiere tener en cuenta la mayor cantidad de datos disponibles y contar con la participación de las personas que ejecutan los procesos para lograr que las acciones determinadas alcancen los niveles de efectividad esperados. 4.2.1 Identificación del riesgo El proceso de la identificación del riesgo debe ser permanente e interactivo integrado al proceso de planificación y debe partir de la claridad de los objetivos estratégicos de la entidad para la obtención de resultados. Previa la identificación de los riesgos es importante tener en cuenta tal como se mencionó anteriormente, los factores que pueden incidir en la aparición de los mismos, los cuales pueden ser externos e internos y llegar a afectar la organización en cualquier momento. Debe considerarse además de los factores previamente citados, factores externos relacionados con la entidad como son: económicos, sociales, de orden público, políticos, legales y cambios tecnológicos, entre otros y como factores internos: la naturaleza de las actividades de la entidad, la estructura organizacional, los sistemas de información, los procesos y procedimientos y los recursos económicos. Para la identificación se recomienda la aplicación de varias herramientas y técnicas como por ejemplo: entrevistas estructuradas con expertos en el área de interés, reuniones con directivos y con personas de todos los niveles en la entidad, evaluaciones individuales usando cuestionarios, lluvias de ideas con los servidores de la entidad, entrevistas e indagaciones con personas ajenas a la entidad, usar diagramas de flujo, análisis de escenarios y hacer revisiones periódicas de factores económicos y tecnológicos que puedan afectar la organización, entre RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 9
  • 10. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA otros. Igualmente pueden utilizarse diferentes fuentes de información de la entidad, tales como registros históricos, experiencias significativas registradas, opiniones de especialistas y expertos, informes de años anteriores, los cuales pueden proporcionar información importante, la técnica utilizada dependerá de las necesidades y naturaleza de la dependencia. Una manera de visualizar los riesgos es a través de la utilización del formato de identificación de riesgos el cual permite hacer un inventario de los mismos, definiendo en primera instancia los riesgos, posteriormente presentando una descripción de cada uno de estos, las causas y finalmente definiendo las posibles consecuencias. Es importante centrarse en los riesgos más significativos para la dependencia. Formato de identificación de riesgos POSIBLES ACTIVIDAD RIESGO DESCRIPCIÓN CAUSAS CONSECUENCIAS Actividad: Paso del proceso al cual se le esta aplicando las técnicas de Administración del Riesgo Riesgo: Posibilidad de ocurrencia de aquella situación que pueda entorpecer el normal desarrollo de las funciones de la entidad y le impidan el logro de sus objetivos. Descripción: Se refiere a las características generales o las formas en que se observa o manifiesta el riesgo identificado. Causas: Identificar el agente generador del riesgo Posibles consecuencias: Corresponde a los posibles efectos ocasionados por el riesgo, los cuales se pueden traducir en daños de tipo económico, social, administrativo, entre otros. Clasificación del riesgo Durante el proceso de identificación del riesgo se recomienda hacer una clasificación de los mismos teniendo en cuenta los siguientes conceptos: Riesgo Estratégico: Se asocia con la forma en que se administra la Entidad. El manejo del riesgo estratégico se enfoca a asuntos globales relacionados con la misión y el cumplimiento de los objetivos estratégicos, la clara definición de políticas, diseño y conceptualización de la entidad por parte de la alta gerencia RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 10
  • 11. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA Riesgos Operativos: Comprende los riesgos relacionados tanto con la parte operativa como técnica de la entidad, incluye riesgos provenientes de deficiencias en los sistemas de información y comunicación, en la definición de los procesos, en la estructura de la entidad, la desarticulación entre dependencias, lo cual conduce a ineficiencias, oportunidades de corrupción e incumplimiento de los compromisos institucionales. Riesgos de Control: Están directamente relacionados con inadecuados o inexistentes puntos de control y en otros casos, con puntos de controles obsoletos, inoperantes o poco efectivos. Riesgos Financieros: Se relacionan con el manejo de los recursos de la entidad que incluye, la ejecución presupuestal, la elaboración de los estados financieros, los pagos, manejos de excedentes de tesorería y el manejo sobre los bienes de cada entidad. De la eficiencia y transparencia en el manejo de los recursos, así como su interacción con las demás áreas dependerá en gran parte el éxito o fracaso de toda entidad. Riesgos de Cumplimiento: Se asocian con la capacidad de la entidad para cumplir con los requisitos legales, contractuales, de ética pública y en general con su compromiso ante la comunidad. Riesgos de Tecnología: Se asocian con la capacidad de la Entidad para que la tecnología disponible satisfaga las necesidades actuales y futuras de la entidad y soporten el cumplimiento de la misión. 4.2.2 Análisis del riesgo El objetivo del análisis es el de establecer una valoración y evaluación de los riesgos con base en la información obtenida en el formato de identificación de riesgos elaborados en la etapa de identificación, con el fin de obtener información para establecer el nivel de riesgo y las acciones que se van a implementar. El análisis del riesgo dependerá de la información sobre el mismo, de su causa y la disponibilidad de datos. Para adelantarlo es necesario diseñar escalas que pueden ser cuantitativas o cualitativas. Se han establecido dos aspectos para realizar el análisis de los riesgos identificados: Probabilidad: la posibilidad de ocurrencia del riesgo; esta puede ser medida con criterios de frecuencia o teniendo en cuenta la presencia de factores internos y externos que pueden propiciar el riesgo, aunque éste no se haya materializado. Impacto: consecuencias que puede ocasionar a la organización la materialización del riesgo. RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 11
  • 12. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA A continuación se presentan algunos ejemplos de las escalas que pueden implementarse para analizar los riesgos. Análisis cualitativo: Se refiere a la utilización de formas descriptivas para presentar la magnitud de consecuencias potenciales y la posibilidad de ocurrencia. Se diseñan escalas ajustadas a las circunstancias de acuerdo a las necesidades particulares de cada organización o el concepto particular del riesgo evaluado. Escala de medida cualitativa de PROBABILIDAD: se deben establecer las categorías a utilizar y la descripción de cada una de ellas, con el fin de que cada persona que aplique la escala mida a través de ella los mismos ítems, por ejemplo: ALTA: es muy factible que el hecho se presente. MEDIA: es factible que el hecho se presente. BAJA: es muy poco factible que el hecho se presente. Ese mismo diseño puede aplicarse para la escala de medida cualitativa de IMPACTO, estableciendo las categorías y la descripción, por ejemplo: ALTO: Si el hecho llegara a presentarse, tendría alto impacto o efecto sobre la entidad. MEDIO: Si el hecho llegara a presentarse tendría medio impacto o efecto en la entidad. BAJO: Si el hecho llegara a presentarse tendría bajo impacto o efecto en la entidad. Con base en los ejemplos anteriormente expuestos, los equipos de trabajo en coordinación con los encargados de adelantar los procesos pueden construir sus propias escalas de acuerdo a la naturaleza de la entidad y a las características de los procesos y procedimientos, de forma que estas escalas se ajusten al análisis de los riesgos identificados. Análisis cuantitativo: Este análisis contempla valores numéricos para los cuales se pueden construir tablas; la calidad depende de lo exactas y completas que estén las cifras utilizadas. La forma en la cual la probabilidad y el impacto son expresada y las RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 12
  • 13. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA formas por las cuales ellos se combinan para proveer el nivel de riesgo puede variar de acuerdo al tipo de riesgo. Ejemplo de escala de impacto: IMPACTO VALORACÍON CARACTERISTICA Bajo 1, 2, 3 No afecta la operación del proceso ni su desempeño. Permite la operación del proceso, bajo condiciones de Medio 4, 5, 6 desempeño reducido. Afecta la operación segura del proceso y/o involucra el Alto 7, 8, 9, 10 incumplimiento de regulaciones existentes. Ejemplo de escala de probabilidad: FRECUENCIA VALORACÍON CARACTERISTICA Ha ocurrido al menos 1 vez en los últimos cinco (5) Baja 1, 2, 3 años. Ha ocurrido al menos 1 vez en los últimos dos (2) Media 4, 5, 6 años. Alta 7, 8, 9, 10 Ha ocurrido al menos 1 vez en el último semestre. RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 13
  • 14. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA Al igual que para determinar las escalas cualitativas, el diseño de las escalas cuantitativas debe contar con la participación de las personas encargadas de los procesos y con el grupo encargado de liderar la administración del riesgo. Evaluación de los riesgos Una vez realizado el análisis de los riesgos con base en los aspectos de probabilidad e impacto, se recomienda utilizar la matriz de evaluación que permite determinar cuales requieren de un tratamiento inmediato. Matriz de evaluación de riesgos Frecuencia ALTA A B BAJA C D Impacto BAJO ALTO Cuando se ubican los riesgos en la matriz se define cuáles de ellos requieren acciones inmediatas, que en este caso son los del cuadrante B, es decir los de alto impacto y alta probabilidad. Los que no requieren acciones inmediatas (pero desde luego requieren que se formulen) son los ubicados en el cuadrante C bajo impacto y baja probabilidad. Respecto a los ubicados en las casillas A y D, es la entidad la que debe seleccionar de acuerdo a la naturaleza del riesgo cuáles van a trabajar primero, los de alto impacto pero baja probabilidad o los de alta probabilidad y bajo impacto, ya que estos pueden ser peligrosos para el logro de los objetivos institucionales, por las consecuencias que presentan en el caso de los ubicados en la casilla D, o por lo constante de su presencia en el caso de la casilla A. Cuantitativamente la evaluación del riesgo es el producto automático, realizado mediante una formula matemática que resulta de la relación entre el impacto y la probabilidad del riesgo evaluado. Multiplicadas estas dos calificaciones, grado de ocurrencia o frecuencia por la relevancia del riesgo, nos arroja una calificación o ponderación final por riesgo sobre una escala de 100 puntos donde se establece que a una mayor calificación mayor es el riesgo. RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 14
  • 15. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA La matriz de evaluación del riesgo cuando se trate de la realización de un análisis cuantitativo se representará en el eje (x, y), donde los valores representado en el eje de las abscisas (horizontal) corresponden a los valores del nivel del impacto y los valores del eje de las coordenadas (vertical) representa los valores del nivel de la probabilidad La representación de la cuantificación obtenida en la matriz o grafico, permite la observar el resultado de la evaluación del riesgo identificado, esta información podrá ser registrada en el formato que se viene elaborando de la siguiente forma: PROBABILIDAD POSIBLES CONSECUENCIAS EVALUACION DEL RIESGO IMPACTO DESCRIPCIÓN ACTIVIDAD CAUSAS RIESGO VALOR NIVEL VALOR NIVEL RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 15
  • 16. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA 4.2.3 Determinación del nivel del riesgo (Valoración del Riesgo) La determinación del nivel de riesgo es el resultado de confrontar el impacto y la probabilidad (evaluación del riesgo obtenida) con los controles existentes en los diferentes procesos y procedimientos que se realizan. Para adelantar esta etapa se deben tener muy claros los puntos de control existentes en los diferentes procesos, los cuales permiten obtener información para efectos de tomar decisiones, estos niveles de riesgo pueden ser: ALTO: Cuando el riesgo hace altamente vulnerable a la entidad o unidad. (Impacto y probabilidad alta vs controles) MEDIO: Cuando el riesgo presenta una vulnerabilidad media. (Impacto alto - probabilidad baja o Impacto bajo – probabilidad alta vs controles). BAJO: Cuando el riesgo presenta vulnerabilidad baja. (Impacto y probabilidad baja vs controles). Calificación de los controles: Para la evaluación de los controles existentes de cada uno de los riesgos, es necesario establecer si son preventivos o correctivos y responder las siguientes preguntas: ¿Están documentados? ¿Se están aplicando en la actualidad? ¿Son efectivos en minimizar el riesgo? Criterios para evaluar la efectividad de los controles existentes • Cuando no existen controles, La probabilidad de ocurrencia es alta. • Cuando los controles existentes no son efectivos, La probabilidad de ocurrencia es alta • Cuando los controles existentes son efectivos, pero no están documentados, La probabilidad de ocurrencia es media RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 16
  • 17. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA • Cuando los controles son efectivos y están documentados, La probabilidad de ocurrencia es baja Criterios para evaluar el nivel del riesgo • Cuando la evaluación de los controles es alta, aumenta el nivel del riesgo. • Cuando la evaluación de los controles existentes es media: Si la evaluación del riesgo es baja, el nivel del riesgo se ubica en medio. Si la evaluación de riesgo es media, el nivel de riesgo pudiera mantenerse en medio si su referencia marcadora es la probabilidad (probabilidad alta- impacto bajo); si su referencia marcadora es el impacto (impacto alto- probabilidad baja) el nivel del riesgo pudiera aumentar a alto. Si la evaluación del riesgo es alta, el nivel de riesgo es alto. • Cuando la evaluación de los controles existentes baja, disminuye el nivel de riesgo Un ejemplo de la determinación del nivel del riesgo y del grado de exposición al mismo: Riesgo: Perdida de información debido a la entrada de un virus en la red de información de la entidad. Probabilidad: Alta, porque todos los computadores de la entidad están conectados a la red de Internet e intranet. Impacto: Alto, porque la pérdida de información traería consecuencias graves para el quehacer de la entidad. Controles existentes: la entidad tiene establecidos controles semanales haciendo Backus o copias de seguridad y vacunando todos los programas y equipos; además guarda la información más relevante desconectada de la red en un centro de información. Resultado Nivel de riesgo: Medio por los controles establecidos Lo anterior significa que a pesar de que la probabilidad y el impacto son altos confrontado con los controles, se puede afirmar que el nivel de riesgo es RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 17
  • 18. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA medio y por lo tanto las acciones que se implementen entrarán a reforzar los controles existentes y a valorar la efectividad de los mismos. Siguiendo con la elaboración del formato y partiendo de la evaluación del Riesgo obtenido, se incluye lo relativo a la evaluación de controles existentes, la identificación del control, si el mismo existe, si está documentado, si se aplica, si es efectivo, y la correspondiente evaluación del control de acuerdo a la aplicación de los criterios para evaluar la efectividad de los controles existentes, finalmente la valoración del Riesgo de acuerdo a los criterios desarrollados para evaluar el nivel del riesgo. CONTROLES EXISTENTES EVALUACION VALORACION DOCUMEN EVALUACION DEL DEL RIESGO CONTROL EXISTE TADO APLICA EFECTIVO DEL RIESGO CONTROL 4.3 MANEJO DEL RIESGO Cualquier esfuerzo que emprendan las entidades en torno a la valoración del riesgo llega a ser en vano, si no culmina en un adecuado manejo y control de los mismos. 4.3.1 Consideración de Acciones Para el manejo de los riesgos se deben analizar las posibles acciones a emprender las cuales deben ser factibles y efectivas, tales como: la implementación de políticas, definición de estándares, optimización de procesos y procedimientos y cambios físicos entre otros. Se pueden tener en cuenta alguna de las siguientes opciones, las cuales pueden considerarse cada una de ellas independientemente, interrelacionadas o en conjunto. Evitar el riesgo: Es siempre la primera alternativa a considerar. Se logra cuando en los procesos se genera cambios sustanciales por mejoramiento, rediseño o eliminación, resultado de unos adecuados controles y acciones emprendidas. Un ejemplo de esto puede ser el control de calidad, manejo de los insumos, mantenimiento preventivo de los equipos, desarrollo tecnológico, etc. Reducir el riesgo: Si el riesgo no puede ser evitado porque crea grandes dificultades operacionales, el siguiente paso es reducirlo al más bajo nivel posible. La RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 18
  • 19. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA reducción del riesgo es probablemente el método más sencillo y económico para superar las debilidades antes de aplicar medidas más costosas y difíciles. Se consigue mediante la optimización de los procedimientos y la implementación de controles. Ejemplo: Planes de contingencia. Dispersar y atomizar el riesgo: Se logra mediante la distribución o localización del riesgo en diversos lugares. Es así como por ejemplo, la información de gran importancia se puede duplicar y almacenar en un lugar distante y de ubicación segura, en vez de dejarla concentrada en un solo lugar. Transferir el riesgo: Hace referencia a buscar respaldo y compartir con otro parte del riesgo como por ejemplo tomar pólizas de seguros, esta técnica es usada para eliminar el riesgo de un lugar y pasarlo a otro o de un grupo a otro. Así mismo, el riesgo puede ser minimizado compartiéndolo con otro grupo o dependencia. Asumir el riesgo: Luego de que el riesgo ha sido reducido o transferido puede quedar un riesgo residual que se mantiene, en este caso el gerente del proceso simplemente acepta la pérdida residual probable y elabora planes de contingencia para su manejo. Una vez establecidas cuales de las anteriores opciones de manejo del riesgo se van a concretar, estas deben evaluarse con relación al beneficio costo para proceder a elaborar el mapa de riesgos, el cual permitirá visualizar todo el proceso de valoración, análisis y manejo de los riesgos. 4.3.2 Elaboración del Mapa de Riesgos Para la consolidación del Mapa de Riesgos, adicional a las consideraciones expuestas, es necesario identificar las causas que los pueden ocasionar, lo cual facilita el proceso de definición de acciones para mitigar los mismos. La selección de las acciones más convenientes debe considerar la viabilidad jurídica, técnica, institucional, financiera y económica y se puede realizar con base en los siguientes factores: a) El nivel del riesgo b) El balance entre el costo de la implementación de cada acción contra el beneficio de la misma. RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 19
  • 20. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA Así mismo en el Mapa de Riesgos se deben identificar los controles existentes, las áreas o dependencias responsables de llevar a cabo las acciones, definir un cronograma y unos indicadores que permitan verificar el cumplimiento para tomar medidas correctivas cuando sea necesario. (Ver formato) MAPA DE RIESGOS Consecuencias Evaluación del Valoración del Responsables Probabilidad Cronograma Descripción Indicadores Controles Actividad Acciones existente Impacto Causas Riesgo riesgo riesgo Descripción del Mapa de riesgos Actividad: Paso del proceso al cual se le esta aplicando las técnicas de Administración del Riesgo Riesgo: posibilidad de ocurrencia de aquella situación que pueda entorpecer el normal desarrollo de las funciones de la entidad y le impidan el logro de sus objetivos. Descripción: Las características generales o las formas como se observa el riesgo en la actividad Consecuencias: Posibles efectos ocasionados por el riesgo, los cuales se pueden traducir en daños de tipo económico, social administrativo, etc. Impacto: consecuencias que puede ocasionar a la organización la materialización del riesgo. Probabilidad entendida como la posibilidad de ocurrencia del riesgo; esta puede ser medida con criterios de frecuencia o teniendo en cuenta la presencia de factores internos y externos que pueden propiciar el riesgo aunque este no se haya presentado nunca. Control existente: especificar cuál es el control que la entidad tiene implementado para combatir, minimizar o prevenir el riesgo. RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 20
  • 21. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA Nivel de riesgo: El resultado de la aplicación de la escala escogida para determinar el nivel de riesgo de acuerdo a la posibilidad de ocurrencia, teniendo en cuenta los controles existentes. Causas: Son los medios, circunstancias y agentes que generan los riesgos. Acciones: es la aplicación concreta de las opciones del manejo del riesgo que entrarán a prevenir o a reducir el riesgo y harán parte del plan de manejo del riesgo. Responsables: Son las dependencias o áreas encargadas de adelantar las acciones propuestas. Cronograma: son las fechas establecidas para implementar las acciones por parte del grupo de trabajo. Indicadores: se consignan los indicadores diseñados para evaluar el desarrollo de las acciones implementadas. Finalmente, partiendo de que el fin último de la administración del riesgo es propender por el cumplimiento de la misión y objetivos institucionales, los cuales están consignados en la planeación anual de la entidad, se sugiere articular el mapa de riesgos con la planeación de manera que no sean planes aislados sino complementarios. 4.3.3 Implementación de acciones Definido el Mapa de Riesgos con sus acciones, responsables y cronogramas, es fundamental comenzar a ejecutar dichas acciones con el fin de determinar su efectividad en el menor tiempo posible. 4.5 MONITOREO Una vez diseñado y validado el plan para administrar los riesgos, en el mapa de riesgos, es necesario monitorearlo teniendo en cuenta que estos nunca dejan de representar una amenaza para la organización. El monitoreo es esencial para asegurar que las acciones se están llevando a cabo y evaluar la eficiencia en su implementación adelantando revisiones sobre la marcha para evidenciar todas aquellas situaciones o factores que pueden estar influyendo en la aplicación de las acciones preventivas. El monitoreo debe estar a cargo de los responsables de las diferentes áreas con el apoyo de las Oficinas Coordinadora de Control Interno y su finalidad principal será la de aplicar y sugerir los correctivos y ajustes necesarios para RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 21
  • 22. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA asegurar un efectivo manejo del riesgo. La Oficina Coordinadora de Control Interno dentro de su función asesora comunicará y presentará luego del monitoreo, sus resultados y propuestas de mejoramiento y tratamiento a las situaciones detectadas. 5. DIAGRAMAS DE LA ADMINISTRACIÓN DEL RIESGO A continuación se presenta un diagrama que consolida todo el proceso de administración del riesgo y puede facilitar la comprensión del mismo al momento de llevar a cabo la tarea de levantamiento del Mapa de Riesgos. ETAPA DE PLANIFICACION IDENTIFICAR LA MISION CONOCIMIENTO GENERAL DE LA INSTITUCION IDENTIFICAR LOS OBJETIVOS IDENTIFICAR LOS PROCESOS DEFINIR LOS OBJETIVOS EN MATERIA DE DISEÑO DEL PLAN ADMINISTRACION DE RIESGOS DISEÑO DE CRONOGRAMAS DE ACTIVIDADES CAPACITACION EN LA METODOLOGIA RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 22
  • 23. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA ETAPA DE VALORACION DEL RIESGO IDENTIFICACION DE LOS FACTORES INTERNOS Y EXTERNOS IDENTIFICACION DEL RIESGO ELABORACION DEL FORMATO IDENTIFICACION DEL RIESGO CLASIFICACION DE LOS RIESGOS MEDIR IMPACTO Y PROBALIDAD JERARQUIZAR LOS RIESGOS ACORDE CON LA ESCALA EVALUACION DEL RIESGO DE MEDICIÓN DEFINIDA (COMENZANDO POR LOS DE MAYOR IMPACTO Y PROBABILIDAD) IDENTIFICAR LOS CONTROLES EXISTENTES PARA CADA UNO DE LOS RIESGOS SELECCIONADOS DETERMINACIÓN CONFRONTAR EL IMPACTO Y LA DEL NIVEL DE PROBABILIDAD FRENTE A LOS RIESGO CONTROLES EXISTENTES SELECCIONAR LOS RIESGOS DE MAYOR INCIDENCIA PARA EL CUMPLIMIENTO DE LOS OBJETIVOS RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 23
  • 24. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA ETAPA DE MANEJO DEL RIESGO ESTUDIO DE POSIBLES CONSIDERACIONES Y ACCIONES ACCIONES PARA MITIGAR LOS RIESGOS DEFINICIÓN DE LAS CAUSAS QUE PROPICIAN LOS RIESGOS DEFINICIÓN DE ACCIONES PARA MITIGAR LOS RIESGOS ELABORACION DEL MAPA DE RIESGO ANÁLISIS COSTO BENEFICIO DE LAS ACCIONES PROCESAMIENTO DEL FORMATO DE MAPA DE RIESGOS EJECUCIÓN DE LOS COMPROMISOS IMPLEMENTACION DE LAS ADQUIRIDOS ACCIONES SEGUIMIENTO A LAS ACCIONES POR PARTE DE LOS RESPONSABLES RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 24
  • 25. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA ETAPA DE MONITOREO DEFINIR LOS RIESGOS A LOS CUALES SE VA A HACER SEGUIMIENTO ELABORACION DE UN PLAN DE SEGUIMIENTO ELABORAR CRONOGRAMA DE SEGUIMIENTO DEFINICIÓN DE RESPONSABLES DEL SEGUIMIENTO REVISIÓN DE LOS COMPROMISOS ADQUIRIDOS PARA MITIGAR LOS RIESGOS EJECUCION DEL SEGUIMIENTO SELECCIONADOS VERIFICACIÓN DE LA IMPLEMENTACIÓN DE LAS ACTIVIDADES CONSOLIDACIÓN DE LA INFORMACIÓN PRESENTACIÓN DE RESULTADOS Y PRESENTACIÓN DE SUGERENCIAS PROPUESTAS Y RECOMENDACIONES ELABORACIÓN DEL INFORME RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 25
  • 26. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA 6. DEFINICIÓN DE TÉRMINOS Administración de riesgos: Una rama de administración que aborda las consecuencias del riesgo. Consta de dos etapas: i El diagnóstico o valoración, mediante Identificación, Análisis y determinación del Nivel, y ii El manejo o la administración propiamente dicha, en que se elabora, ejecuta y hace seguimiento al Plan de manejo que contiene las Técnicas de Administración del Riesgo propuestas por el grupo de trabajo, evaluadas y aceptadas por la alta dirección. • Análisis de Beneficio-Costo: Una herramienta de Administración de Riesgos usada para tomar decisiones sobre las técnicas propuestas por el grupo para la administración de los riesgos, en la cual se valoran y comparan los costos, financieros y económicos, de implementar la medida, contra los beneficios generados por la misma. Una medida de administración de riesgos será aceptada siempre que el beneficio valorado supere al costo. • Análisis de riesgos: Determinar el Impacto y la Probabilidad del riesgo. • Causa: Son los medios, circunstancias y agentes que generan los riesgos. • Control: Es toda acción que tiende a minimizar los riesgos, significa analizar el desempeño de las operaciones, evidenciando posibles desviaciones frente al resultado esperado para la adopción de medidas preventivas. Los controles proporcionan un modelo operacional de seguridad razonable en el logro de los objetivos. • Costo: Se entiende por costo las erogaciones, directas e indirectas en que incurre la entidad en la producción, prestación de un servicio o manejo de un riesgo. • Factores de riesgo: Manifestaciones o características medibles u observables de un proceso que indican la presencia de Riesgo o tienden a aumentar la exposición, pueden ser internos o externos a la entidad. • Identificación de riesgos: Establecer la estructura del riesgo; fuentes o factores, internos o externos, generadores de riesgos; puede hacerse a cualquier nivel: total entidad, por áreas, por procesos, incluso, bajo el viejo paradigma, por funciones; desde el nivel estratégico hasta el más humilde operativo. RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 26
  • 27. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA Impacto: consecuencias que puede ocasionar a la organización la materialización del riesgo. • Indicador: es la valoración de una o más variables que informa sobre una situación y soporta la toma de decisiones, es un criterio de medición y de evaluación cuantitativa o cualitativa. • Mapas de riesgos: herramienta metodológica que permite hacer un inventario de los riesgos ordenada y sistemáticamente, definiéndolos, haciendo la descripción de cada uno de estos y las posibles consecuencias • Nivel de riesgo (determinación del): Es el resultado de confrontar el impacto y la probabilidad, con los controles existentes. • Plan de contingencia: Parte del plan de manejo de riesgos que contiene las acciones a ejecutar en caso de la materialización del riesgo, con el fin de dar continuidad a los objetivos de la entidad. • Plan de manejo de riesgos: Plan de acción propuesto por el grupo de trabajo, cuya evaluación de beneficio costo resulta positiva y es aprobado por la gerencia. • Plan de mejoramiento: Parte del plan de manejo que contiene las técnicas de administración del riesgo orientadas a prevenir, evitar, reducir, dispersar, transferir o asumir riesgos. • Probabilidad: Una medida (expresada como porcentaje o razón) para estimar la posibilidad de que ocurra un incidente o evento. Contando con registros, puede estimarse a partir de su Frecuencia histórica mediante modelos estadísticos de mayor o menor complejidad. • Responsables: Son las dependencias o áreas encargadas de adelantar las acciones propuestas. • Retroalimentación: Información sistemática sobre los resultados alcanzados en la ejecución de un plan, que sirven para actualizar y mejorar la planeación futura. • Riesgo: posibilidad de ocurrencia de toda aquella situación que pueda entorpecer el normal desarrollo de las funciones de la entidad y le impidan el logro de sus objetivos. • Riesgo absoluto: el máximo riesgo sin los efectos mitigantes de la administración del riesgo. RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 27
  • 28. METODOLOGÍA PARA LA ADMINISTRACIÓN DEL 2009 RIESGO EN EL IPSFA Riesgo residual: es el riesgo que queda cuando las técnicas de administración del riesgo han sido aplicadas. • Seguimiento: Recolección regular y sistemática sobre la ejecución del plan, que sirven para actualizar y mejorar la planeación futura. • Sistema: Conjunto de cosas o partes coordinadas, ordenadamente relacionadas entre sí, que contribuyen a un determinado objetivo. • Técnicas para manejar el riesgo: Evitar o prevenir, reducir, dispersar, transferir y asumir riesgos. • Valoración del riesgo: Primera fase en la administración de riesgos, diagnóstico que consta de la identificación, análisis y determinación del nivel de riesgo. Rafael María Contreras Acevedo CI 4208526 RIESGO ES NECESARIO INTRODUCIR LA ADMINISTRACION DEL RIESGO EN EL INSTITUTO COMO HERRAMIENTA DE TRABAJO GERENCIAL Página 28