PMP®
Math Series
Economic Model

PMP is a registered trademark of the Project Management Institute, Inc.

© 2013 iZenBridge | CONFIDENTIAL
Present Value
Net Present Value
Internal Rate of Return

Benefit Cost Ratio
Payback Period

© 2013 iZenBridge | CONFIDENTIAL
The time value of money.

The money you get in 5 years isn’t worth as money
you get today

© 2013 iZenBridge | CONFIDENTIAL
Present Value

© 2013 iZenBridge | CONFIDENTIAL
Present Value
• Value today of the future cash flow
• Present Value = FV / (1 + i)^ n
• i = Discount rate
• n = Period
• FV = Future Cash Inflow/ Outflow

Now

Year 2

Year 1

© 2013 iZenBridge | CONFIDENTIAL

Year 3
Present Value
Year 2 4000
USD

Now
Year 1

•
•
•
•
•

Discount Rate = 10%
PV = 4000 / (1+10/100) ^2
PV = 4000/ (1.1) ^2
PV = 4000 / 1.21
PV = 3305

• It mean 3305 USD earned today is equals to 4000 USD earned
after two year

© 2013 iZenBridge | CONFIDENTIAL
Which Investment Option is Better ?
Option A :
Returns: 4000 USD after 2
years

Option B:
Returns: 3500 USD after 1
years

Discount Rate =
10% per annum

PV = 4000/(1.1) ^2
= 3305 USD

PV = 3500/(1.1)
= 3181 USD

© 2013 iZenBridge | CONFIDENTIAL
Usages of Present Value (PV)
• Used as a base for calculating the Net Present Value (NPV)
• Simple investment decisions can be made using this technique
• Higher the PV the better the investment

© 2013 iZenBridge | CONFIDENTIAL
Net Present Value (NPV)

© 2013 iZenBridge | CONFIDENTIAL
Net Present Value (NPV)
• NPV is a measure of how much money a project can be
expected to return (in today’s present value).
• It’s a Sum of Inflow and outflow in present value term (mean
discounted based on duration)

Now

FV 2 (Year 2)
FV 1 (Year 1)

© 2013 iZenBridge | CONFIDENTIAL
Net Present Value
NPV = Sum (PV)
= Sum (FV / (1 + i)^ n)
i = Discount rate
n = Period
FV = Future Cash Inflow (+) / Outflow (-)

© 2013 iZenBridge | CONFIDENTIAL
Net Present Value
Outflow 1000
USD (Now)

Inflow 4000 USD
(Year 2)
Outflow 1000
USD (Year 1)

• Discount Rate = 10%
• NPV = -1000-1000 /((1+10/100) ^1)
•
+ 4000/((1+10/100)^2)
•
= -1000 – 909 +3306
•
= 1397 (This Project returns 1397 USD in present value
term)

© 2013 iZenBridge | CONFIDENTIAL
Which Project to Select?
• Project A has a duration of 4 years and an NPV of $40,000,
• Project B has a duration of 3 years and an NPV of $45,000,
• Project C has a duration of 6 years and an NPV of $62,000
Which project will you select?

Go with Project C, Time value of money already considered in
NPV so years doesn’t matter

© 2013 iZenBridge | CONFIDENTIAL
Usages of Net Present Value (NPV)
•
•
•
•
•

One of the frequently used tools for project selection
Take in account inflow and outflow of cash
Easy to calculate
A negative value indicates that we are loosing money
Higher the NPV the better the project

© 2013 iZenBridge | CONFIDENTIAL
Internal Rate of Return (IRR)

© 2013 iZenBridge | CONFIDENTIAL
Internal Rate of Return (IRR)
• IRR is a measure of how quickly the money invested in a
project will increase in value. It’s a rate of return which
calculate based on the inflow and outflow of the project.

© 2013 iZenBridge | CONFIDENTIAL
Internal Rate of Return (IRR)
• The rule is same like NPV, the difference is, now we need to
compute the rate (i) which equalizes the cash inflow and
outflow
0 = Sum (FV / (1 + i) ^ n)
i = IRR this is what we calculate
n = period

© 2013 iZenBridge | CONFIDENTIAL
Internal Rate Return (IRR)
Outflow 1000
USD (Now)

Inflow 4000 USD
(Year 2)
Outflow 1000
USD (Year 1)

• 0 = -1000-1000 /((1+i/100) ^1) + 4000/((1+i/100) ^2)
• If we put i = 56, it makes the equation balance, so in this case
IRR = 56%

© 2013 iZenBridge | CONFIDENTIAL
Internal Rate of Return (IRR)
• Which Project you will select?
Project Name

IRR

Investment

Gold

6%

4,500,000

Silver

5.8%

1,700,000

Platinum

5.4 %

2,000,000

Copper

3%

1,000,000

© 2013 iZenBridge | CONFIDENTIAL
Usages of Internal Rate of Return (IRR)
•
•
•
•

Frequently used in Project selection
It does not require assumption of discount rate
Gives the result in % term rather than absolute
Higher the IRR the better the project

© 2013 iZenBridge | CONFIDENTIAL
NPV vs IRR

NPV represents the
project benefit in
absolute term like
100,000 USD

IRR represents the value
in proportion like 10%,
56%

We can get contradictory recommendations
from NPV and IRR, but in exam you do not
get such questions

© 2013 iZenBridge | CONFIDENTIAL
Benefit Cost Ratio

© 2013 iZenBridge | CONFIDENTIAL
Benefit Cost Ratio
• Money project going to make versus its cost.
• Benefit/Cost OR Revenue/cost
• Remember : Revenue is not equals to Profit

© 2013 iZenBridge | CONFIDENTIAL
Benefit Cost Ratio (BCR)
• Greater Benefit<->Greater Ratio <-> Better project

© 2013 iZenBridge | CONFIDENTIAL
Benefit Cost Ratio (BCR)
• Which of the following projects do you select?
• A) Project Gold with a BCR of 0.9
• B) Project Silver with a CBR of 0.9 and cost of $100,000
• C) Project Diamond with a cost of $100,000 and benefits of
$110,000
• D) Project Platinum with a BCR of 1.2
a) 0.9 b) BCR = 1/0.9 = 1.11 c) 11/10 = 1.1 d) 1.2
• Answer: D

© 2013 iZenBridge | CONFIDENTIAL
Usages of Benefit Cost Ratio
•
•
•
•
•

Ratio helps in visualizing the relative value
May calculate considering Time Value of Money
Simple to calculate and explain
Ratio less than 1 indicate we are losing money
Higher the value, the better it is.

© 2013 iZenBridge | CONFIDENTIAL
Payback Period

© 2013 iZenBridge | CONFIDENTIAL
Payback Period
• Time required to get originally invested amount back
• Smaller is better . Earlier we get money, better it is

© 2013 iZenBridge | CONFIDENTIAL
Payback Period
• Project A requires investment of $500,000. The project is
expected to generate $25K per quarter for the first year and
$100K per quarter after that. What is the payback period?

By when I get 500,000 Back?
First Year = 25K + 25K + 25K + 25K = 100K
(still need 400K)
Second Year = 100K + 100K+100K+ 100K =
400K (Done)

© 2013 iZenBridge | CONFIDENTIAL
Usages of Payback Period
•
•
•
•

Helps in looking the investment in time dimension
The sooner we get our money back is better
Usually calculated without considering the time value of money
One can calculate discounted payback period

© 2013 iZenBridge | CONFIDENTIAL
Present
Value
Net Present
Value

Higher is
Better

Internal Rate
of Return

Higher is
Better

Benefit Cost
Ratio

Higher is
Better

Payback
Period

Exam Tip

Higher is
Better

Shorter is
Better

© 2013 iZenBridge | CONFIDENTIAL
Stay Connected
Contact Us
Saket.Bansal@iZenBridge.com
www.iZenBridge.com
forum.izenbridge.com

Join Us @

Linkedin:
www.linkedin.com/company/izenbridge-consultancy-private-limited
Facebook:
https://www.facebook.com/izenbridge
Google+:
https://plus.google.com/+Izenbridge1
© 2013 iZenBridge | CONFIDENTIAL

Contenu connexe

Tendances

The Triple Constraint of Project Management - Lou Bergner
The Triple Constraint of Project Management - Lou BergnerThe Triple Constraint of Project Management - Lou Bergner
The Triple Constraint of Project Management - Lou BergnerMAX Technical Training
 
Project Management, Planning And Analysis Tools
Project Management, Planning And Analysis ToolsProject Management, Planning And Analysis Tools
Project Management, Planning And Analysis Toolsahmad bassiouny
 
Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Project Management Fundamentals | Project Management Simplified | PMP® Traini...Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Project Management Fundamentals | Project Management Simplified | PMP® Traini...Edureka!
 
Project Time Management
Project Time ManagementProject Time Management
Project Time ManagementSerdar Temiz
 
Template kick off-meeting
Template kick off-meeting Template kick off-meeting
Template kick off-meeting Hari Krishna
 
Microsoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sMicrosoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sAbhik Tushar Das
 
PMBOK GUIDE 7th Summary
PMBOK GUIDE 7th Summary PMBOK GUIDE 7th Summary
PMBOK GUIDE 7th Summary Amr Miqdadi
 
Project Management Life Cycle
Project Management Life CycleProject Management Life Cycle
Project Management Life CycleReema
 
Agile vs waterfall
Agile vs waterfallAgile vs waterfall
Agile vs waterfallgosain20
 
Project Stakeholder Management - PMBOK6
Project Stakeholder Management - PMBOK6Project Stakeholder Management - PMBOK6
Project Stakeholder Management - PMBOK6Agus Suhanto
 
Project Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaProject Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaEdureka!
 
Introduction-to-project-management
Introduction-to-project-managementIntroduction-to-project-management
Introduction-to-project-managementSavaş Şakar
 
Terms of reference in Professional Practices
Terms of reference in Professional PracticesTerms of reference in Professional Practices
Terms of reference in Professional PracticesMuhammad Haroon
 
Project communication management
Project communication managementProject communication management
Project communication managementSaad Al Jabri
 

Tendances (20)

Self test engine PSP-PMI-SP
Self test engine PSP-PMI-SPSelf test engine PSP-PMI-SP
Self test engine PSP-PMI-SP
 
The Triple Constraint of Project Management - Lou Bergner
The Triple Constraint of Project Management - Lou BergnerThe Triple Constraint of Project Management - Lou Bergner
The Triple Constraint of Project Management - Lou Bergner
 
Project Management, Planning And Analysis Tools
Project Management, Planning And Analysis ToolsProject Management, Planning And Analysis Tools
Project Management, Planning And Analysis Tools
 
Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Project Management Fundamentals | Project Management Simplified | PMP® Traini...Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Project Management Fundamentals | Project Management Simplified | PMP® Traini...
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Project Stakeholder Management
Project Stakeholder ManagementProject Stakeholder Management
Project Stakeholder Management
 
Template kick off-meeting
Template kick off-meeting Template kick off-meeting
Template kick off-meeting
 
Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
 
PMP Exam Preparation - 200 Questions
PMP Exam Preparation - 200 QuestionsPMP Exam Preparation - 200 Questions
PMP Exam Preparation - 200 Questions
 
Microsoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sMicrosoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner's
 
Project stakeholders
Project stakeholdersProject stakeholders
Project stakeholders
 
PMBOK GUIDE 7th Summary
PMBOK GUIDE 7th Summary PMBOK GUIDE 7th Summary
PMBOK GUIDE 7th Summary
 
Project Management Life Cycle
Project Management Life CycleProject Management Life Cycle
Project Management Life Cycle
 
Agile vs waterfall
Agile vs waterfallAgile vs waterfall
Agile vs waterfall
 
Project Stakeholder Management - PMBOK6
Project Stakeholder Management - PMBOK6Project Stakeholder Management - PMBOK6
Project Stakeholder Management - PMBOK6
 
Project Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaProject Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | Edureka
 
Introduction-to-project-management
Introduction-to-project-managementIntroduction-to-project-management
Introduction-to-project-management
 
Business case
Business case  Business case
Business case
 
Terms of reference in Professional Practices
Terms of reference in Professional PracticesTerms of reference in Professional Practices
Terms of reference in Professional Practices
 
Project communication management
Project communication managementProject communication management
Project communication management
 

En vedette

Internal rate of return(IRR)
Internal rate of return(IRR)Internal rate of return(IRR)
Internal rate of return(IRR)Ulsah T N
 
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...TURKI , PMP
 
Commerce quiz, joint stock company and general
Commerce quiz, joint stock company and generalCommerce quiz, joint stock company and general
Commerce quiz, joint stock company and generaladuadu
 
Example Project: Strategic Project Selection and Accelerated Development by J...
Example Project: Strategic Project Selection and Accelerated Development by J...Example Project: Strategic Project Selection and Accelerated Development by J...
Example Project: Strategic Project Selection and Accelerated Development by J...John Thornton
 
Joint stock company2
Joint stock company2Joint stock company2
Joint stock company2Alok Kumar
 
Negotiation Strategies for Project Managers
Negotiation Strategies for Project ManagersNegotiation Strategies for Project Managers
Negotiation Strategies for Project ManagersRoberto Toledo
 
Joint stock company
Joint stock companyJoint stock company
Joint stock companyrobin11uiu
 
The Mathematics Behind Project Management
The Mathematics Behind Project ManagementThe Mathematics Behind Project Management
The Mathematics Behind Project Managementsystred
 
Difference between Sole Proprietorship, Partnership & Joint Stock Company
Difference between Sole Proprietorship, Partnership & Joint Stock CompanyDifference between Sole Proprietorship, Partnership & Joint Stock Company
Difference between Sole Proprietorship, Partnership & Joint Stock CompanyDhrumil Shah
 
Relationship between IRR & NPV
Relationship between IRR & NPVRelationship between IRR & NPV
Relationship between IRR & NPVZeeshan Ali
 
Why do people share on social media? Global survey results
Why do people share on social media? Global survey resultsWhy do people share on social media? Global survey results
Why do people share on social media? Global survey resultsOgilvy Consulting
 
Net Present Value - NPV
Net Present Value - NPVNet Present Value - NPV
Net Present Value - NPVASAD ALI
 

En vedette (20)

Internal rate of return(IRR)
Internal rate of return(IRR)Internal rate of return(IRR)
Internal rate of return(IRR)
 
NPV v/s IRR
NPV v/s IRRNPV v/s IRR
NPV v/s IRR
 
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
 
Joint stock company
Joint stock companyJoint stock company
Joint stock company
 
Commerce quiz, joint stock company and general
Commerce quiz, joint stock company and generalCommerce quiz, joint stock company and general
Commerce quiz, joint stock company and general
 
Example Project: Strategic Project Selection and Accelerated Development by J...
Example Project: Strategic Project Selection and Accelerated Development by J...Example Project: Strategic Project Selection and Accelerated Development by J...
Example Project: Strategic Project Selection and Accelerated Development by J...
 
Joint Stock Company
Joint Stock CompanyJoint Stock Company
Joint Stock Company
 
Joint stock company2
Joint stock company2Joint stock company2
Joint stock company2
 
Joint stock company
Joint stock companyJoint stock company
Joint stock company
 
Negotiation Strategies for Project Managers
Negotiation Strategies for Project ManagersNegotiation Strategies for Project Managers
Negotiation Strategies for Project Managers
 
Joint Stock Company
Joint Stock CompanyJoint Stock Company
Joint Stock Company
 
Joint stock company
Joint stock companyJoint stock company
Joint stock company
 
The Mathematics Behind Project Management
The Mathematics Behind Project ManagementThe Mathematics Behind Project Management
The Mathematics Behind Project Management
 
Difference between Sole Proprietorship, Partnership & Joint Stock Company
Difference between Sole Proprietorship, Partnership & Joint Stock CompanyDifference between Sole Proprietorship, Partnership & Joint Stock Company
Difference between Sole Proprietorship, Partnership & Joint Stock Company
 
Relationship between IRR & NPV
Relationship between IRR & NPVRelationship between IRR & NPV
Relationship between IRR & NPV
 
Joint stock company
Joint stock companyJoint stock company
Joint stock company
 
Joint stock company
Joint stock companyJoint stock company
Joint stock company
 
Joint stock company
Joint stock companyJoint stock company
Joint stock company
 
Why do people share on social media? Global survey results
Why do people share on social media? Global survey resultsWhy do people share on social media? Global survey results
Why do people share on social media? Global survey results
 
Net Present Value - NPV
Net Present Value - NPVNet Present Value - NPV
Net Present Value - NPV
 

Similaire à iZenBridge's PMP® Math Series: Project Selection : PV , NPV, IRR, BCR and Payback Period

Similaire à iZenBridge's PMP® Math Series: Project Selection : PV , NPV, IRR, BCR and Payback Period (20)

Chapter 9 q&p
Chapter 9 q&pChapter 9 q&p
Chapter 9 q&p
 
LECTURE 4 (2).pptx
LECTURE 4 (2).pptxLECTURE 4 (2).pptx
LECTURE 4 (2).pptx
 
case study in corporate finance npv irr arr
case study in corporate finance npv irr arrcase study in corporate finance npv irr arr
case study in corporate finance npv irr arr
 
Financial concepts
Financial conceptsFinancial concepts
Financial concepts
 
Sfm
SfmSfm
Sfm
 
Finalize Updated 1200hrs - 03.09.2016 - Group 8 Presentation
Finalize Updated 1200hrs - 03.09.2016 - Group 8 PresentationFinalize Updated 1200hrs - 03.09.2016 - Group 8 Presentation
Finalize Updated 1200hrs - 03.09.2016 - Group 8 Presentation
 
Project Evaluation Report
Project Evaluation ReportProject Evaluation Report
Project Evaluation Report
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Chapter8 investmentcriteria
Chapter8 investmentcriteriaChapter8 investmentcriteria
Chapter8 investmentcriteria
 
Cfa corporate finance chapter2
Cfa corporate finance chapter2Cfa corporate finance chapter2
Cfa corporate finance chapter2
 
Project management
Project managementProject management
Project management
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
MBA fin mgt Lecture 5 inv appraisal.pptx
MBA fin mgt Lecture 5 inv appraisal.pptxMBA fin mgt Lecture 5 inv appraisal.pptx
MBA fin mgt Lecture 5 inv appraisal.pptx
 
Cap budget
Cap budgetCap budget
Cap budget
 
case study-capital budgeting
case study-capital budgetingcase study-capital budgeting
case study-capital budgeting
 
Time Value of Money
Time Value of MoneyTime Value of Money
Time Value of Money
 
Capital Investment Analysis
Capital Investment AnalysisCapital Investment Analysis
Capital Investment Analysis
 
Teori investasi
Teori investasiTeori investasi
Teori investasi
 
Teori investasi
Teori investasiTeori investasi
Teori investasi
 
Cb-1.pptx
Cb-1.pptxCb-1.pptx
Cb-1.pptx
 

Plus de Saket Bansal

Improving Collaboration by Awareness of Mind Games
Improving Collaboration by Awareness of  Mind GamesImproving Collaboration by Awareness of  Mind Games
Improving Collaboration by Awareness of Mind GamesSaket Bansal
 
Emotional Intelligence: From Theory to Practice
Emotional Intelligence: From Theory to PracticeEmotional Intelligence: From Theory to Practice
Emotional Intelligence: From Theory to PracticeSaket Bansal
 
Webinar on Agile and PMBOK® Guide Sixth Edition
Webinar on Agile and PMBOK® Guide Sixth EditionWebinar on Agile and PMBOK® Guide Sixth Edition
Webinar on Agile and PMBOK® Guide Sixth EditionSaket Bansal
 
Webinar on Leader As Coach
Webinar on Leader As Coach Webinar on Leader As Coach
Webinar on Leader As Coach Saket Bansal
 
Workshop on Test Driven Development (TDD) Noida
Workshop on Test Driven Development (TDD) NoidaWorkshop on Test Driven Development (TDD) Noida
Workshop on Test Driven Development (TDD) NoidaSaket Bansal
 
Webinar On Collect Requirement - iZenBridge
Webinar On Collect Requirement - iZenBridgeWebinar On Collect Requirement - iZenBridge
Webinar On Collect Requirement - iZenBridgeSaket Bansal
 
Webinar on Requirement Prioritization Process - iZenBridge
Webinar on Requirement Prioritization Process - iZenBridgeWebinar on Requirement Prioritization Process - iZenBridge
Webinar on Requirement Prioritization Process - iZenBridgeSaket Bansal
 
Webinar on Agile Metrics
Webinar on Agile Metrics Webinar on Agile Metrics
Webinar on Agile Metrics Saket Bansal
 
Lean India Summit : From Productivity to Profitability
Lean India Summit : From Productivity to Profitability Lean India Summit : From Productivity to Profitability
Lean India Summit : From Productivity to Profitability Saket Bansal
 
Webinar On Scaled Agile Framework (SAFe) | iZenBridge
Webinar On Scaled Agile Framework (SAFe) | iZenBridgeWebinar On Scaled Agile Framework (SAFe) | iZenBridge
Webinar On Scaled Agile Framework (SAFe) | iZenBridgeSaket Bansal
 
PMP : Precedence Diagram Method : Relationship Types | iZenBridge
PMP : Precedence Diagram Method : Relationship Types | iZenBridgePMP : Precedence Diagram Method : Relationship Types | iZenBridge
PMP : Precedence Diagram Method : Relationship Types | iZenBridgeSaket Bansal
 
Agile NCR : Starting your business in a lean way
Agile NCR : Starting your business in a lean wayAgile NCR : Starting your business in a lean way
Agile NCR : Starting your business in a lean waySaket Bansal
 
Webinar on Agile Estimation : iZenBridge
Webinar on Agile Estimation : iZenBridgeWebinar on Agile Estimation : iZenBridge
Webinar on Agile Estimation : iZenBridgeSaket Bansal
 
Introduction of Project Management
Introduction of Project ManagementIntroduction of Project Management
Introduction of Project ManagementSaket Bansal
 
Lean , Pull System & Kanban |iZenBridge
Lean , Pull System & Kanban |iZenBridgeLean , Pull System & Kanban |iZenBridge
Lean , Pull System & Kanban |iZenBridgeSaket Bansal
 
Plan Risk Responses : PMP : Project Risk Management
Plan Risk Responses : PMP : Project Risk ManagementPlan Risk Responses : PMP : Project Risk Management
Plan Risk Responses : PMP : Project Risk ManagementSaket Bansal
 
Risk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk ManagementRisk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk ManagementSaket Bansal
 
Agile Beyond Rituals | Presented at Agile Noida
Agile Beyond Rituals | Presented at Agile Noida Agile Beyond Rituals | Presented at Agile Noida
Agile Beyond Rituals | Presented at Agile Noida Saket Bansal
 
Procurement Contract Types | PMP | iZenBridge - Webinar
Procurement Contract Types | PMP | iZenBridge - Webinar Procurement Contract Types | PMP | iZenBridge - Webinar
Procurement Contract Types | PMP | iZenBridge - Webinar Saket Bansal
 
Agile Metric | Velocity | PMI ACP | IZenBridge
Agile Metric | Velocity | PMI ACP | IZenBridgeAgile Metric | Velocity | PMI ACP | IZenBridge
Agile Metric | Velocity | PMI ACP | IZenBridgeSaket Bansal
 

Plus de Saket Bansal (20)

Improving Collaboration by Awareness of Mind Games
Improving Collaboration by Awareness of  Mind GamesImproving Collaboration by Awareness of  Mind Games
Improving Collaboration by Awareness of Mind Games
 
Emotional Intelligence: From Theory to Practice
Emotional Intelligence: From Theory to PracticeEmotional Intelligence: From Theory to Practice
Emotional Intelligence: From Theory to Practice
 
Webinar on Agile and PMBOK® Guide Sixth Edition
Webinar on Agile and PMBOK® Guide Sixth EditionWebinar on Agile and PMBOK® Guide Sixth Edition
Webinar on Agile and PMBOK® Guide Sixth Edition
 
Webinar on Leader As Coach
Webinar on Leader As Coach Webinar on Leader As Coach
Webinar on Leader As Coach
 
Workshop on Test Driven Development (TDD) Noida
Workshop on Test Driven Development (TDD) NoidaWorkshop on Test Driven Development (TDD) Noida
Workshop on Test Driven Development (TDD) Noida
 
Webinar On Collect Requirement - iZenBridge
Webinar On Collect Requirement - iZenBridgeWebinar On Collect Requirement - iZenBridge
Webinar On Collect Requirement - iZenBridge
 
Webinar on Requirement Prioritization Process - iZenBridge
Webinar on Requirement Prioritization Process - iZenBridgeWebinar on Requirement Prioritization Process - iZenBridge
Webinar on Requirement Prioritization Process - iZenBridge
 
Webinar on Agile Metrics
Webinar on Agile Metrics Webinar on Agile Metrics
Webinar on Agile Metrics
 
Lean India Summit : From Productivity to Profitability
Lean India Summit : From Productivity to Profitability Lean India Summit : From Productivity to Profitability
Lean India Summit : From Productivity to Profitability
 
Webinar On Scaled Agile Framework (SAFe) | iZenBridge
Webinar On Scaled Agile Framework (SAFe) | iZenBridgeWebinar On Scaled Agile Framework (SAFe) | iZenBridge
Webinar On Scaled Agile Framework (SAFe) | iZenBridge
 
PMP : Precedence Diagram Method : Relationship Types | iZenBridge
PMP : Precedence Diagram Method : Relationship Types | iZenBridgePMP : Precedence Diagram Method : Relationship Types | iZenBridge
PMP : Precedence Diagram Method : Relationship Types | iZenBridge
 
Agile NCR : Starting your business in a lean way
Agile NCR : Starting your business in a lean wayAgile NCR : Starting your business in a lean way
Agile NCR : Starting your business in a lean way
 
Webinar on Agile Estimation : iZenBridge
Webinar on Agile Estimation : iZenBridgeWebinar on Agile Estimation : iZenBridge
Webinar on Agile Estimation : iZenBridge
 
Introduction of Project Management
Introduction of Project ManagementIntroduction of Project Management
Introduction of Project Management
 
Lean , Pull System & Kanban |iZenBridge
Lean , Pull System & Kanban |iZenBridgeLean , Pull System & Kanban |iZenBridge
Lean , Pull System & Kanban |iZenBridge
 
Plan Risk Responses : PMP : Project Risk Management
Plan Risk Responses : PMP : Project Risk ManagementPlan Risk Responses : PMP : Project Risk Management
Plan Risk Responses : PMP : Project Risk Management
 
Risk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk ManagementRisk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk Management
 
Agile Beyond Rituals | Presented at Agile Noida
Agile Beyond Rituals | Presented at Agile Noida Agile Beyond Rituals | Presented at Agile Noida
Agile Beyond Rituals | Presented at Agile Noida
 
Procurement Contract Types | PMP | iZenBridge - Webinar
Procurement Contract Types | PMP | iZenBridge - Webinar Procurement Contract Types | PMP | iZenBridge - Webinar
Procurement Contract Types | PMP | iZenBridge - Webinar
 
Agile Metric | Velocity | PMI ACP | IZenBridge
Agile Metric | Velocity | PMI ACP | IZenBridgeAgile Metric | Velocity | PMI ACP | IZenBridge
Agile Metric | Velocity | PMI ACP | IZenBridge
 

Dernier

Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docxPoojaSen20
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingTeacherCyreneCayanan
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxAreebaZafar22
 
An Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdfAn Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdfSanaAli374401
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Disha Kariya
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.MateoGardella
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxnegromaestrong
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Shubhangi Sonawane
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.christianmathematics
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...KokoStevan
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxVishalSingh1417
 

Dernier (20)

Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
An Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdfAn Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdf
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 

iZenBridge's PMP® Math Series: Project Selection : PV , NPV, IRR, BCR and Payback Period

  • 1. PMP® Math Series Economic Model PMP is a registered trademark of the Project Management Institute, Inc. © 2013 iZenBridge | CONFIDENTIAL
  • 2. Present Value Net Present Value Internal Rate of Return Benefit Cost Ratio Payback Period © 2013 iZenBridge | CONFIDENTIAL
  • 3. The time value of money. The money you get in 5 years isn’t worth as money you get today © 2013 iZenBridge | CONFIDENTIAL
  • 4. Present Value © 2013 iZenBridge | CONFIDENTIAL
  • 5. Present Value • Value today of the future cash flow • Present Value = FV / (1 + i)^ n • i = Discount rate • n = Period • FV = Future Cash Inflow/ Outflow Now Year 2 Year 1 © 2013 iZenBridge | CONFIDENTIAL Year 3
  • 6. Present Value Year 2 4000 USD Now Year 1 • • • • • Discount Rate = 10% PV = 4000 / (1+10/100) ^2 PV = 4000/ (1.1) ^2 PV = 4000 / 1.21 PV = 3305 • It mean 3305 USD earned today is equals to 4000 USD earned after two year © 2013 iZenBridge | CONFIDENTIAL
  • 7. Which Investment Option is Better ? Option A : Returns: 4000 USD after 2 years Option B: Returns: 3500 USD after 1 years Discount Rate = 10% per annum PV = 4000/(1.1) ^2 = 3305 USD PV = 3500/(1.1) = 3181 USD © 2013 iZenBridge | CONFIDENTIAL
  • 8. Usages of Present Value (PV) • Used as a base for calculating the Net Present Value (NPV) • Simple investment decisions can be made using this technique • Higher the PV the better the investment © 2013 iZenBridge | CONFIDENTIAL
  • 9. Net Present Value (NPV) © 2013 iZenBridge | CONFIDENTIAL
  • 10. Net Present Value (NPV) • NPV is a measure of how much money a project can be expected to return (in today’s present value). • It’s a Sum of Inflow and outflow in present value term (mean discounted based on duration) Now FV 2 (Year 2) FV 1 (Year 1) © 2013 iZenBridge | CONFIDENTIAL
  • 11. Net Present Value NPV = Sum (PV) = Sum (FV / (1 + i)^ n) i = Discount rate n = Period FV = Future Cash Inflow (+) / Outflow (-) © 2013 iZenBridge | CONFIDENTIAL
  • 12. Net Present Value Outflow 1000 USD (Now) Inflow 4000 USD (Year 2) Outflow 1000 USD (Year 1) • Discount Rate = 10% • NPV = -1000-1000 /((1+10/100) ^1) • + 4000/((1+10/100)^2) • = -1000 – 909 +3306 • = 1397 (This Project returns 1397 USD in present value term) © 2013 iZenBridge | CONFIDENTIAL
  • 13. Which Project to Select? • Project A has a duration of 4 years and an NPV of $40,000, • Project B has a duration of 3 years and an NPV of $45,000, • Project C has a duration of 6 years and an NPV of $62,000 Which project will you select? Go with Project C, Time value of money already considered in NPV so years doesn’t matter © 2013 iZenBridge | CONFIDENTIAL
  • 14. Usages of Net Present Value (NPV) • • • • • One of the frequently used tools for project selection Take in account inflow and outflow of cash Easy to calculate A negative value indicates that we are loosing money Higher the NPV the better the project © 2013 iZenBridge | CONFIDENTIAL
  • 15. Internal Rate of Return (IRR) © 2013 iZenBridge | CONFIDENTIAL
  • 16. Internal Rate of Return (IRR) • IRR is a measure of how quickly the money invested in a project will increase in value. It’s a rate of return which calculate based on the inflow and outflow of the project. © 2013 iZenBridge | CONFIDENTIAL
  • 17. Internal Rate of Return (IRR) • The rule is same like NPV, the difference is, now we need to compute the rate (i) which equalizes the cash inflow and outflow 0 = Sum (FV / (1 + i) ^ n) i = IRR this is what we calculate n = period © 2013 iZenBridge | CONFIDENTIAL
  • 18. Internal Rate Return (IRR) Outflow 1000 USD (Now) Inflow 4000 USD (Year 2) Outflow 1000 USD (Year 1) • 0 = -1000-1000 /((1+i/100) ^1) + 4000/((1+i/100) ^2) • If we put i = 56, it makes the equation balance, so in this case IRR = 56% © 2013 iZenBridge | CONFIDENTIAL
  • 19. Internal Rate of Return (IRR) • Which Project you will select? Project Name IRR Investment Gold 6% 4,500,000 Silver 5.8% 1,700,000 Platinum 5.4 % 2,000,000 Copper 3% 1,000,000 © 2013 iZenBridge | CONFIDENTIAL
  • 20. Usages of Internal Rate of Return (IRR) • • • • Frequently used in Project selection It does not require assumption of discount rate Gives the result in % term rather than absolute Higher the IRR the better the project © 2013 iZenBridge | CONFIDENTIAL
  • 21. NPV vs IRR NPV represents the project benefit in absolute term like 100,000 USD IRR represents the value in proportion like 10%, 56% We can get contradictory recommendations from NPV and IRR, but in exam you do not get such questions © 2013 iZenBridge | CONFIDENTIAL
  • 22. Benefit Cost Ratio © 2013 iZenBridge | CONFIDENTIAL
  • 23. Benefit Cost Ratio • Money project going to make versus its cost. • Benefit/Cost OR Revenue/cost • Remember : Revenue is not equals to Profit © 2013 iZenBridge | CONFIDENTIAL
  • 24. Benefit Cost Ratio (BCR) • Greater Benefit<->Greater Ratio <-> Better project © 2013 iZenBridge | CONFIDENTIAL
  • 25. Benefit Cost Ratio (BCR) • Which of the following projects do you select? • A) Project Gold with a BCR of 0.9 • B) Project Silver with a CBR of 0.9 and cost of $100,000 • C) Project Diamond with a cost of $100,000 and benefits of $110,000 • D) Project Platinum with a BCR of 1.2 a) 0.9 b) BCR = 1/0.9 = 1.11 c) 11/10 = 1.1 d) 1.2 • Answer: D © 2013 iZenBridge | CONFIDENTIAL
  • 26. Usages of Benefit Cost Ratio • • • • • Ratio helps in visualizing the relative value May calculate considering Time Value of Money Simple to calculate and explain Ratio less than 1 indicate we are losing money Higher the value, the better it is. © 2013 iZenBridge | CONFIDENTIAL
  • 27. Payback Period © 2013 iZenBridge | CONFIDENTIAL
  • 28. Payback Period • Time required to get originally invested amount back • Smaller is better . Earlier we get money, better it is © 2013 iZenBridge | CONFIDENTIAL
  • 29. Payback Period • Project A requires investment of $500,000. The project is expected to generate $25K per quarter for the first year and $100K per quarter after that. What is the payback period? By when I get 500,000 Back? First Year = 25K + 25K + 25K + 25K = 100K (still need 400K) Second Year = 100K + 100K+100K+ 100K = 400K (Done) © 2013 iZenBridge | CONFIDENTIAL
  • 30. Usages of Payback Period • • • • Helps in looking the investment in time dimension The sooner we get our money back is better Usually calculated without considering the time value of money One can calculate discounted payback period © 2013 iZenBridge | CONFIDENTIAL
  • 31. Present Value Net Present Value Higher is Better Internal Rate of Return Higher is Better Benefit Cost Ratio Higher is Better Payback Period Exam Tip Higher is Better Shorter is Better © 2013 iZenBridge | CONFIDENTIAL
  • 32. Stay Connected Contact Us Saket.Bansal@iZenBridge.com www.iZenBridge.com forum.izenbridge.com Join Us @ Linkedin: www.linkedin.com/company/izenbridge-consultancy-private-limited Facebook: https://www.facebook.com/izenbridge Google+: https://plus.google.com/+Izenbridge1 © 2013 iZenBridge | CONFIDENTIAL