Energy Crisis in Bangladesh
   Short and Long Term Solutions




             April 30, 2009

       Compiled by Shawkat Haider
Electricity Generation Worldwide




                                           Current production costs :
                                           1.76 cents per kWh for nuclear,
                                           2.47 cents for coal,
                                           6.78 cents for natural gas and
                                           10.26 cents for petroleum.

Coal accounts for 39% of global energy
                                                  World Nuclear Association
                                                  IAEA.
Electricity Generation in Bangladesh


Peak demand is catered by:                            Demand from:
Natural gas     85%
                                                      DESA, DESCO 1800MW
Liquid fuel     6.76%
                                                      REB         2200MW
Coal            5.41%
                                                      PDB itself  1500MW
Hydropower      2.45%



    1 TCF Coal (37MT) can produce 14000-94000 MW
    1 TCF Gas can produce 22000 MW

    3.5 barrels of oil = 17000 cubic feet gas = 1780 pound coal
                 (in terms of energy production)


                   Coal Mining Challenges in Bangladesh Khondkar Abdus Saleque, energybangla, April 2009
                   Solution lies in gas supply, Sharier Khan, The Daily Star
                   Dr. Khalequzzaman, The Daily Star
                   World Nuclear Association
Energy Sector Snapshots

TOTAL INSTALLED CAPACITY                      5453 MW (105 Unit)                 December - 2008
BPDB                                          3812 MW (59 Unit)                  December - 2008
IPP                                           1330 MW (39 Unit)                  December - 2008
SIPP & Rental                                   311 MW (7 Unit)                  December - 2008
Present generation capacity                         4931 MW                      December - 2008
Current demand                                      5500 MW                          April- 2009
Average generation                               3700-3800 MW                        April- 2009
Maximum generation in history                      4146.9 MW                          April-2009
Load shedding                                    1000-1500 MW                         April-2009
Access to electricity                                  45%                            FY- 2008
Per capita generation                                149 kWh                          FY- 2008

Distribution lines (33 KV & below)             47,479 Route KM                         FY-2007

                                          Bangladesh power development board, BPDB; Power Cell, Energybangla
Power Sector Structure in Bangladesh
Gas Sector Scenario in Bangladesh


Total recoverable gas                   : 21 TCF
(proven and probable)
Reserve remaining                        : 13 TCF

National demand of natural gas : 2200 MMCFD
Production capacity            : 1880 MMCFD

Power sector requirement                 : 921 MMCFD
Power sector gets                        : 800 MMCFD




              PetroBangla
              Coal Mining Challenges in Bangladesh, Khondkar Abdus Saleque, Energybangla
GAS PRODUCTON CAPACITY 2009
                                                        Capacity

Company                  Field        Producing Wells   (mmscfd)

 1.BGFCL      TITAS                         14            405

              BAKHRABAD                     4              34

              HABIGANJ                      9             240
                                                                        Category Wise Gas
              NARSHINGDI                    2              35

                                                                        Consumption (2007)
              MEGHNA                        1              0

                      Sub Total             30            714

 2.SGFL       SYLHET                        1              2
                                                                        Power             44%
              KAILASHTILA                   6              97
                                                                        Fertilizer        13%
              RASHIDPUR                     5              53

                                                                        Captive Power     13%
              BEANIBAZAR                    2              18

                                                                        Industrial        16%
                      Sub Total             14            170

 3.BAPEX      SALDANADI                     2              11
                                                                        Domestic          11%
              FENCHUGANJ                    2              32
                                                                        Others             3%
                      Sub Total             4              43

          SUBTOTAL (1+2+3)                  48            927

CAIRN         SANGU                         6              35

                                                                                        Titas Gas, Petrobangla
              JALALABAD                     4             230

              MOULOVIBAZAR                  4              75

CHEVRON       BIBIYANA                      12            500

NIKO          FENI                          3              3

TULLOW        BANGURA                       2             100

                                            31            943
             Sub Total
               TOTAL                        79            1870

                                                          PetroBangla
Coal Sector Scenario in Bangladesh

                     The total coal reserves in 5 coal fields
                                         =
                             2.9 billion metric tons
                                         =
                      energy equivalent to 67 TCF of gas



Only Baropukuria Coal Mine is operational from where 1.73 mill MT of coal has
        been extracted up to December 2008 for 250MW power plant

Place/ Field (Discovery)                Depth (Meter)                 Proven Reserve (Mill Ton)
Barapukuria, Dinajpur (1985)            119-506                       390
Khalashpeer, Rangpur (1995)             257-483                       143 (GSB), 685 (Hosaf)
Phulbari, Dinajpur (1997)               150-240                       572
Jamalganj, Jaipurhat (1965)             900-1000                      1050
Dighirpar, Dinajpur (1995)              327                           200 (partly evaluated)
                                                                                                  Petrobangla

                 Coal Mining Challenges in Bangladesh, Khondkar Abdus Saleque, April 26, 2009, Energybangla.com
Power Plant Status in Bangladesh

Years in operation            No. of power                 Capacity (MW)
                              plants

40 +                          7                            140
31 - 40                       6                            318
21 – 30                       26                           1399
11 - 20                       10                           1113
01 - 10                       50                           2483
                                                           5453

Power Crisis: Issues and Challenges Md. Mizanur Rahman, March 26, 2009, Energybangla
Causes of Power Crisis


                   •     The demand for around 5,500MW of electricity is not
                         met by an avg supply of only 3,800MW.

                   •     High gas dependence. Many power plants are idle
                         due to shortage of gas supply and poor
                         maintenance.

                   •     An inefficient transmission and distribution system
                         operated by state owned companies are the main
                         factor behind huge system loss (15-20%).

                   •     Unprecedented delay in finalizing a coal policy. We
                         have a probable coal reserve of 3.3 billion tones,
                         which is around 5 times higher than our current
                         proven gas reserve in terms of its heating value.

                   •     A lack of transparency in power generation
                         procurement and tendering in the past. Highly
                         inefficient decision making process



Maximizing Growth for Bangladesh: A Private Sector Vision, Ifty Islam, Asian Tiger Capital Partners
Short Term Solutions

• Shutting down of all the government owned urea plants. This the only immediate source of
additional gas to be used for power generation. Most of these fertilizer factories use old fuel
inefficient process which already have outlived their effective economic life.

• Going for long term agreements to import urea right now as international price of urea is low.
The availability of urea must be assured but the price should be appropriate; a subsidy is
possible but undesirable. At least the subsidy should be linked to the price of rice.

• More Rental Power Plants need to be installed to overcome the short term power crisis.

• Reducing system loss in the power sector should be a priority as a reduction of 1% system
loss can save around 45 MW of power. The government should implement the merchant
power policy immediately

• The government can set up some small coal fired power plants and can import coal from
India on a temporary basis before developing our own coal mines

• Several large barge mounted power plants can be contracted on short term basis which can
supply additional 600 MW by the end of the year. This will ease the power crisis for a few
years while other fuel sources are developed and the required power plants constructed

                      Solving the energy crisis Salman F Rahman and Forrest Cookson
                      Maximizing Growth for Bangladesh: A Private Sector Vision, Ifty Islam, Asian Tiger Capital Partners
                      Power Crisis: Issues and Challenges Md. Mizanur Rahman, Energybangla.com
                      Bangladesh Power System Master Plan Review, Engr Khondkar Abdus Saleque, Feb 2009, Enerybangla.com
Short Term Solutions

• Captive power generation by the private sector is around 1800-2000 MW; 20-25% of this
capacity remains unutilized which can be added to the national gridline. Provide incentive
to the standby captive generators to run their machine without taking power from grid.

The improvement of the gas pipelines and installation of compressors to increase pipeline
pressure - should be implemented immediately.

• Daylight energy saving. Changing the office timetable to 8 am - 2 pm can save more
electricity for using in the evening peak hours. 350 MW at Dhaka and Chittagong can be
saved daily

• Using energy efficient appliances and immediate removal of taxes on them

• Importing Liquefied Natural Gas (LNG) from gas exporting countries like Indonesia, Qatar
to meet urgent need

• Nation-wide power conservation awareness program




                   Solving the energy crisis Salman F Rahman and Forrest Cookson
                   Maximizing Growth for Bangladesh: A Private Sector Vision, Ifty Islam, Asian Tiger Capital Partners
                   Power Crisis: Issues and Challenges Md. Mizanur Rahman, Energybangla.com
                   Bangladesh Power System Master Plan Review, Engr Khondkar Abdus Saleque, Feb 2009, Enerybangla.com
Mid to Long Term Solution

• Accelerate the exploration for gas. The recoverable proven remaining reserve of gas is
will start depleting after 2012. The maritime boundary dispute with India and Myanmar is a
major barrier to offshore gas exploration, and should be resolved as soon as possible.

• Petrobangla and EMRD must do everything possible to support Bapex to make it a self
reliant exploration company.

• Install new urea plants that are more gas efficient. As coal fired power plants come on
line in five years the gas can be sold to the urea factories enabling imports of urea to be
curtailed.

• Fast-track the development of Phulbari and other coal deposits and simultaneously build
large-scale coal-fired power stations. Gradually remove coal imports (currently about 5
mill MT) and supply ultimately 18 MMT to the power plants [enough for 6000 MWs].
Contract for 3 coal fired power plants each for 1000 MWs in about 4-5 years. When these
plants are available gas is switched to new efficient urea plants and peaking plants for the
power sector and for direct industrial use.

• Public private partnership should be highly encouraged. If needed, energy bond or levies
should be charged to raise funds.

                   Solving the energy crisis Salman F Rahman and Forrest Cookson
                   Maximizing Growth for Bangladesh: A Private Sector Vision, Ifty Islam, Asian Tiger Capital Partners
                   Power Crisis: Issues and Challenges Md. Mizanur Rahman, Energybangla.com
                   Bangladesh Power System Master Plan Review, Engr Khondkar Abdus Saleque, Feb 2009, Enerybangla.com
Mid to Long Term Solution

• Government must encourage expansion of Solar, wind and bio fuel energy
generation. Efforts to use solar power on tall buildings, factories, rural areas
should be promoted with low cost loans while removing taxes on solar
equipment. Full potential of mini micro hydro generation must also be explored.
Energy from solid municipal waste in major cities can be possibility also.

• Nuclear energy is a long term solution with huge cost involvement of billion
dollar per 1000 MW plant, but essentially this would become a vital source with
highest durability and low unit cost of production.

• Many power plants set up in Ashuganj, Ghorashal, Shajibazar have outlived
their effective economic life. Further investment in those will be waste of money
and efforts. There has been considerable drainage of national resources in
maintenance of some plants. These can be replaced with fuel efficient modern
plants.

• A more efficient and faster procurement and tendering process should be
adopted for quicker implementation of any project.


             Solving the energy crisis Salman F Rahman and Forrest Cookson
             Maximizing Growth for Bangladesh: A Private Sector Vision, Ifty Islam, Asian Tiger Capital Partners
             Power Crisis: Issues and Challenges Md. Mizanur Rahman, Energybangla.com
             Bangladesh Power System Master Plan Review, Engr Khondkar Abdus Saleque, Feb 2009, Enerybangla.com

Contenu connexe

Tendances

Power Sector In Bangladesh
Power Sector In BangladeshPower Sector In Bangladesh
Power Sector In Bangladesh
Sayanton Vhaduri
 
Sustainable development methodology
Sustainable development methodologySustainable development methodology
Sustainable development methodology
Gregory Borne
 
ENERGY CRISIS
ENERGY CRISISENERGY CRISIS
ENERGY CRISIS
SVCE
 
Power Generation In Pakistan
Power Generation In PakistanPower Generation In Pakistan
Power Generation In Pakistan
Imad Baig
 
ppt on cement industry in india
ppt on cement industry in indiappt on cement industry in india
ppt on cement industry in india
js slides
 
ENERGY SCENARIO IN PAKISTAN.Ali Raza
ENERGY SCENARIO IN PAKISTAN.Ali RazaENERGY SCENARIO IN PAKISTAN.Ali Raza
ENERGY SCENARIO IN PAKISTAN.Ali Raza
Ali Raza
 

Tendances (20)

MHPS(DVC) PROJECT REPORT
MHPS(DVC) PROJECT REPORTMHPS(DVC) PROJECT REPORT
MHPS(DVC) PROJECT REPORT
 
Power Sector In Bangladesh
Power Sector In BangladeshPower Sector In Bangladesh
Power Sector In Bangladesh
 
Sustainable development methodology
Sustainable development methodologySustainable development methodology
Sustainable development methodology
 
Coal Mining Pakistan
Coal Mining PakistanCoal Mining Pakistan
Coal Mining Pakistan
 
ENERGY CRISIS
ENERGY CRISISENERGY CRISIS
ENERGY CRISIS
 
Renewable energy
Renewable energyRenewable energy
Renewable energy
 
Nuclear power-plant-in-bangladesh
Nuclear power-plant-in-bangladeshNuclear power-plant-in-bangladesh
Nuclear power-plant-in-bangladesh
 
Ganga pollution
Ganga pollutionGanga pollution
Ganga pollution
 
Power Generation In Pakistan
Power Generation In PakistanPower Generation In Pakistan
Power Generation In Pakistan
 
Coal Based Power Plants in India
Coal Based Power Plants in IndiaCoal Based Power Plants in India
Coal Based Power Plants in India
 
ppt on cement industry in india
ppt on cement industry in indiappt on cement industry in india
ppt on cement industry in india
 
Bangladesh studies presentation slide
Bangladesh studies presentation slideBangladesh studies presentation slide
Bangladesh studies presentation slide
 
Rampal power plant
Rampal power plantRampal power plant
Rampal power plant
 
Industrial training report- Visakhapatnam Steel Plant.
Industrial training report- Visakhapatnam Steel Plant. Industrial training report- Visakhapatnam Steel Plant.
Industrial training report- Visakhapatnam Steel Plant.
 
Renewable energy-in-bangladesh
Renewable energy-in-bangladeshRenewable energy-in-bangladesh
Renewable energy-in-bangladesh
 
Renewable Energy & Overview in Bangladesh
Renewable Energy & Overview in BangladeshRenewable Energy & Overview in Bangladesh
Renewable Energy & Overview in Bangladesh
 
ENERGY SCENARIO IN PAKISTAN.Ali Raza
ENERGY SCENARIO IN PAKISTAN.Ali RazaENERGY SCENARIO IN PAKISTAN.Ali Raza
ENERGY SCENARIO IN PAKISTAN.Ali Raza
 
The mineral resources of bangladesh part 1
The mineral resources of bangladesh part 1 The mineral resources of bangladesh part 1
The mineral resources of bangladesh part 1
 
Role of energy in sustainable development goals
Role of energy in sustainable development goalsRole of energy in sustainable development goals
Role of energy in sustainable development goals
 
Rooppur Atomic Power Plant, Bangladesh.
Rooppur Atomic Power Plant, Bangladesh.Rooppur Atomic Power Plant, Bangladesh.
Rooppur Atomic Power Plant, Bangladesh.
 

En vedette

Production of Industrial Enzymes
Production of Industrial EnzymesProduction of Industrial Enzymes
Production of Industrial Enzymes
Ajjay Kumar Gupta
 
Extraction, Purification and Production of Enzymes (Biotechnology)
Extraction, Purification and Production of Enzymes (Biotechnology) Extraction, Purification and Production of Enzymes (Biotechnology)
Extraction, Purification and Production of Enzymes (Biotechnology)
Ajjay Kumar Gupta
 

En vedette (7)

Production of Industrial Enzymes
Production of Industrial EnzymesProduction of Industrial Enzymes
Production of Industrial Enzymes
 
Leather & Tannery Industry in Bangladesh.
Leather & Tannery Industry in Bangladesh.Leather & Tannery Industry in Bangladesh.
Leather & Tannery Industry in Bangladesh.
 
Industrial enzymes for sustainable bio-economy: Large scale production and ap...
Industrial enzymes for sustainable bio-economy: Large scale production and ap...Industrial enzymes for sustainable bio-economy: Large scale production and ap...
Industrial enzymes for sustainable bio-economy: Large scale production and ap...
 
Extraction, Purification and Production of Enzymes (Biotechnology)
Extraction, Purification and Production of Enzymes (Biotechnology) Extraction, Purification and Production of Enzymes (Biotechnology)
Extraction, Purification and Production of Enzymes (Biotechnology)
 
Trade unions in bangladesh and its impact
Trade unions in bangladesh and its impactTrade unions in bangladesh and its impact
Trade unions in bangladesh and its impact
 
Scope and importance of biotechnology
Scope and importance of biotechnologyScope and importance of biotechnology
Scope and importance of biotechnology
 
Production of Enzymes
Production of Enzymes Production of Enzymes
Production of Enzymes
 

Similaire à Bangladesh Energy Crisis Solutions

Nuclear power corporation of india limited (npcil (2)
Nuclear power corporation of india limited (npcil (2)Nuclear power corporation of india limited (npcil (2)
Nuclear power corporation of india limited (npcil (2)
Saurav Singh
 
Indonesiacoal indutry outlook_english
Indonesiacoal indutry outlook_englishIndonesiacoal indutry outlook_english
Indonesiacoal indutry outlook_english
sunapa
 
New Energy Conference-Mohammad Abu Zarour from NEPCO
New Energy Conference-Mohammad Abu Zarour from NEPCONew Energy Conference-Mohammad Abu Zarour from NEPCO
New Energy Conference-Mohammad Abu Zarour from NEPCO
EDAMA
 
1.2 power plant module2 batch3
1.2 power plant module2 batch31.2 power plant module2 batch3
1.2 power plant module2 batch3
daisydhei
 
TURKISH POWER SYSTEM AND RENEWABLE ENERGY IN TURKEY
TURKISH POWER SYSTEM AND RENEWABLE ENERGY IN TURKEYTURKISH POWER SYSTEM AND RENEWABLE ENERGY IN TURKEY
TURKISH POWER SYSTEM AND RENEWABLE ENERGY IN TURKEY
Suat Furkan ISIK
 
Lowering threats in sustainable development using nuclear energy
Lowering threats in sustainable development using nuclear energy Lowering threats in sustainable development using nuclear energy
Lowering threats in sustainable development using nuclear energy
anil_kakodkar
 
xcel energy
xcel energy   xcel energy
xcel energy
finance26
 
xcel energy
xcel energy   xcel energy
xcel energy
finance26
 
xcel energy
xcel energy  xcel energy
xcel energy
finance26
 
Pakistan wind-power- arif alauddin
Pakistan wind-power- arif alauddinPakistan wind-power- arif alauddin
Pakistan wind-power- arif alauddin
IPPAI
 

Similaire à Bangladesh Energy Crisis Solutions (20)

Nuclear power corporation of india limited (npcil (2)
Nuclear power corporation of india limited (npcil (2)Nuclear power corporation of india limited (npcil (2)
Nuclear power corporation of india limited (npcil (2)
 
Gas for Power Generation or for Industry - A case for Pakistan
Gas for Power Generation or for Industry - A case for PakistanGas for Power Generation or for Industry - A case for Pakistan
Gas for Power Generation or for Industry - A case for Pakistan
 
M.Sc thesis Presentation
M.Sc thesis PresentationM.Sc thesis Presentation
M.Sc thesis Presentation
 
Syria
SyriaSyria
Syria
 
Indonesiacoal indutry outlook_english
Indonesiacoal indutry outlook_englishIndonesiacoal indutry outlook_english
Indonesiacoal indutry outlook_english
 
New Energy Conference-Mohammad Abu Zarour from NEPCO
New Energy Conference-Mohammad Abu Zarour from NEPCONew Energy Conference-Mohammad Abu Zarour from NEPCO
New Energy Conference-Mohammad Abu Zarour from NEPCO
 
1.2 power plant module2 batch3
1.2 power plant module2 batch31.2 power plant module2 batch3
1.2 power plant module2 batch3
 
Bangladesh Country Presentation.pdf
Bangladesh Country Presentation.pdfBangladesh Country Presentation.pdf
Bangladesh Country Presentation.pdf
 
TURKISH POWER SYSTEM AND RENEWABLE ENERGY IN TURKEY
TURKISH POWER SYSTEM AND RENEWABLE ENERGY IN TURKEYTURKISH POWER SYSTEM AND RENEWABLE ENERGY IN TURKEY
TURKISH POWER SYSTEM AND RENEWABLE ENERGY IN TURKEY
 
Where will CSP plants be built? Incentives, RPS requirements, and Project Eco...
Where will CSP plants be built? Incentives, RPS requirements, and Project Eco...Where will CSP plants be built? Incentives, RPS requirements, and Project Eco...
Where will CSP plants be built? Incentives, RPS requirements, and Project Eco...
 
AREVA, business & strategy overview - January 2009 - Appendix 1 to 6
AREVA, business & strategy overview - January 2009 - Appendix 1 to 6AREVA, business & strategy overview - January 2009 - Appendix 1 to 6
AREVA, business & strategy overview - January 2009 - Appendix 1 to 6
 
Lowering threats in sustainable development using nuclear energy
Lowering threats in sustainable development using nuclear energy Lowering threats in sustainable development using nuclear energy
Lowering threats in sustainable development using nuclear energy
 
Exe mba ee-nuclear energy_sarjeevan
Exe mba ee-nuclear energy_sarjeevanExe mba ee-nuclear energy_sarjeevan
Exe mba ee-nuclear energy_sarjeevan
 
xcel energy
xcel energy   xcel energy
xcel energy
 
xcel energy
xcel energy   xcel energy
xcel energy
 
xcel energy
xcel energy  xcel energy
xcel energy
 
Chp Job Reference(1009)
Chp Job Reference(1009)Chp Job Reference(1009)
Chp Job Reference(1009)
 
CCS Assessment in the Philippines - Carlo Arcilla and Raymond Tan
CCS Assessment in the Philippines - Carlo Arcilla and Raymond TanCCS Assessment in the Philippines - Carlo Arcilla and Raymond Tan
CCS Assessment in the Philippines - Carlo Arcilla and Raymond Tan
 
Indonesia Emergency Response
Indonesia Emergency ResponseIndonesia Emergency Response
Indonesia Emergency Response
 
Pakistan wind-power- arif alauddin
Pakistan wind-power- arif alauddinPakistan wind-power- arif alauddin
Pakistan wind-power- arif alauddin
 

Dernier

Dernier (20)

HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptx
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
latest AZ-104 Exam Questions and Answers
latest AZ-104 Exam Questions and Answerslatest AZ-104 Exam Questions and Answers
latest AZ-104 Exam Questions and Answers
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx
 
Tatlong Kwento ni Lola basyang-1.pdf arts
Tatlong Kwento ni Lola basyang-1.pdf artsTatlong Kwento ni Lola basyang-1.pdf arts
Tatlong Kwento ni Lola basyang-1.pdf arts
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 

Bangladesh Energy Crisis Solutions

  • 1. Energy Crisis in Bangladesh Short and Long Term Solutions April 30, 2009 Compiled by Shawkat Haider
  • 2. Electricity Generation Worldwide Current production costs : 1.76 cents per kWh for nuclear, 2.47 cents for coal, 6.78 cents for natural gas and 10.26 cents for petroleum. Coal accounts for 39% of global energy World Nuclear Association IAEA.
  • 3. Electricity Generation in Bangladesh Peak demand is catered by: Demand from: Natural gas 85% DESA, DESCO 1800MW Liquid fuel 6.76% REB 2200MW Coal 5.41% PDB itself 1500MW Hydropower 2.45% 1 TCF Coal (37MT) can produce 14000-94000 MW 1 TCF Gas can produce 22000 MW 3.5 barrels of oil = 17000 cubic feet gas = 1780 pound coal (in terms of energy production) Coal Mining Challenges in Bangladesh Khondkar Abdus Saleque, energybangla, April 2009 Solution lies in gas supply, Sharier Khan, The Daily Star Dr. Khalequzzaman, The Daily Star World Nuclear Association
  • 4. Energy Sector Snapshots TOTAL INSTALLED CAPACITY 5453 MW (105 Unit) December - 2008 BPDB 3812 MW (59 Unit) December - 2008 IPP 1330 MW (39 Unit) December - 2008 SIPP & Rental 311 MW (7 Unit) December - 2008 Present generation capacity 4931 MW December - 2008 Current demand 5500 MW April- 2009 Average generation 3700-3800 MW April- 2009 Maximum generation in history 4146.9 MW April-2009 Load shedding 1000-1500 MW April-2009 Access to electricity 45% FY- 2008 Per capita generation 149 kWh FY- 2008 Distribution lines (33 KV & below) 47,479 Route KM FY-2007 Bangladesh power development board, BPDB; Power Cell, Energybangla
  • 5. Power Sector Structure in Bangladesh
  • 6. Gas Sector Scenario in Bangladesh Total recoverable gas : 21 TCF (proven and probable) Reserve remaining : 13 TCF National demand of natural gas : 2200 MMCFD Production capacity : 1880 MMCFD Power sector requirement : 921 MMCFD Power sector gets : 800 MMCFD PetroBangla Coal Mining Challenges in Bangladesh, Khondkar Abdus Saleque, Energybangla
  • 7. GAS PRODUCTON CAPACITY 2009 Capacity Company Field Producing Wells (mmscfd) 1.BGFCL TITAS 14 405 BAKHRABAD 4 34 HABIGANJ 9 240 Category Wise Gas NARSHINGDI 2 35 Consumption (2007) MEGHNA 1 0 Sub Total 30 714 2.SGFL SYLHET 1 2 Power 44% KAILASHTILA 6 97 Fertilizer 13% RASHIDPUR 5 53 Captive Power 13% BEANIBAZAR 2 18 Industrial 16% Sub Total 14 170 3.BAPEX SALDANADI 2 11 Domestic 11% FENCHUGANJ 2 32 Others 3% Sub Total 4 43 SUBTOTAL (1+2+3) 48 927 CAIRN SANGU 6 35 Titas Gas, Petrobangla JALALABAD 4 230 MOULOVIBAZAR 4 75 CHEVRON BIBIYANA 12 500 NIKO FENI 3 3 TULLOW BANGURA 2 100 31 943 Sub Total TOTAL 79 1870 PetroBangla
  • 8. Coal Sector Scenario in Bangladesh The total coal reserves in 5 coal fields = 2.9 billion metric tons = energy equivalent to 67 TCF of gas Only Baropukuria Coal Mine is operational from where 1.73 mill MT of coal has been extracted up to December 2008 for 250MW power plant Place/ Field (Discovery) Depth (Meter) Proven Reserve (Mill Ton) Barapukuria, Dinajpur (1985) 119-506 390 Khalashpeer, Rangpur (1995) 257-483 143 (GSB), 685 (Hosaf) Phulbari, Dinajpur (1997) 150-240 572 Jamalganj, Jaipurhat (1965) 900-1000 1050 Dighirpar, Dinajpur (1995) 327 200 (partly evaluated) Petrobangla Coal Mining Challenges in Bangladesh, Khondkar Abdus Saleque, April 26, 2009, Energybangla.com
  • 9. Power Plant Status in Bangladesh Years in operation No. of power Capacity (MW) plants 40 + 7 140 31 - 40 6 318 21 – 30 26 1399 11 - 20 10 1113 01 - 10 50 2483 5453 Power Crisis: Issues and Challenges Md. Mizanur Rahman, March 26, 2009, Energybangla
  • 10. Causes of Power Crisis • The demand for around 5,500MW of electricity is not met by an avg supply of only 3,800MW. • High gas dependence. Many power plants are idle due to shortage of gas supply and poor maintenance. • An inefficient transmission and distribution system operated by state owned companies are the main factor behind huge system loss (15-20%). • Unprecedented delay in finalizing a coal policy. We have a probable coal reserve of 3.3 billion tones, which is around 5 times higher than our current proven gas reserve in terms of its heating value. • A lack of transparency in power generation procurement and tendering in the past. Highly inefficient decision making process Maximizing Growth for Bangladesh: A Private Sector Vision, Ifty Islam, Asian Tiger Capital Partners
  • 11. Short Term Solutions • Shutting down of all the government owned urea plants. This the only immediate source of additional gas to be used for power generation. Most of these fertilizer factories use old fuel inefficient process which already have outlived their effective economic life. • Going for long term agreements to import urea right now as international price of urea is low. The availability of urea must be assured but the price should be appropriate; a subsidy is possible but undesirable. At least the subsidy should be linked to the price of rice. • More Rental Power Plants need to be installed to overcome the short term power crisis. • Reducing system loss in the power sector should be a priority as a reduction of 1% system loss can save around 45 MW of power. The government should implement the merchant power policy immediately • The government can set up some small coal fired power plants and can import coal from India on a temporary basis before developing our own coal mines • Several large barge mounted power plants can be contracted on short term basis which can supply additional 600 MW by the end of the year. This will ease the power crisis for a few years while other fuel sources are developed and the required power plants constructed Solving the energy crisis Salman F Rahman and Forrest Cookson Maximizing Growth for Bangladesh: A Private Sector Vision, Ifty Islam, Asian Tiger Capital Partners Power Crisis: Issues and Challenges Md. Mizanur Rahman, Energybangla.com Bangladesh Power System Master Plan Review, Engr Khondkar Abdus Saleque, Feb 2009, Enerybangla.com
  • 12. Short Term Solutions • Captive power generation by the private sector is around 1800-2000 MW; 20-25% of this capacity remains unutilized which can be added to the national gridline. Provide incentive to the standby captive generators to run their machine without taking power from grid. The improvement of the gas pipelines and installation of compressors to increase pipeline pressure - should be implemented immediately. • Daylight energy saving. Changing the office timetable to 8 am - 2 pm can save more electricity for using in the evening peak hours. 350 MW at Dhaka and Chittagong can be saved daily • Using energy efficient appliances and immediate removal of taxes on them • Importing Liquefied Natural Gas (LNG) from gas exporting countries like Indonesia, Qatar to meet urgent need • Nation-wide power conservation awareness program Solving the energy crisis Salman F Rahman and Forrest Cookson Maximizing Growth for Bangladesh: A Private Sector Vision, Ifty Islam, Asian Tiger Capital Partners Power Crisis: Issues and Challenges Md. Mizanur Rahman, Energybangla.com Bangladesh Power System Master Plan Review, Engr Khondkar Abdus Saleque, Feb 2009, Enerybangla.com
  • 13. Mid to Long Term Solution • Accelerate the exploration for gas. The recoverable proven remaining reserve of gas is will start depleting after 2012. The maritime boundary dispute with India and Myanmar is a major barrier to offshore gas exploration, and should be resolved as soon as possible. • Petrobangla and EMRD must do everything possible to support Bapex to make it a self reliant exploration company. • Install new urea plants that are more gas efficient. As coal fired power plants come on line in five years the gas can be sold to the urea factories enabling imports of urea to be curtailed. • Fast-track the development of Phulbari and other coal deposits and simultaneously build large-scale coal-fired power stations. Gradually remove coal imports (currently about 5 mill MT) and supply ultimately 18 MMT to the power plants [enough for 6000 MWs]. Contract for 3 coal fired power plants each for 1000 MWs in about 4-5 years. When these plants are available gas is switched to new efficient urea plants and peaking plants for the power sector and for direct industrial use. • Public private partnership should be highly encouraged. If needed, energy bond or levies should be charged to raise funds. Solving the energy crisis Salman F Rahman and Forrest Cookson Maximizing Growth for Bangladesh: A Private Sector Vision, Ifty Islam, Asian Tiger Capital Partners Power Crisis: Issues and Challenges Md. Mizanur Rahman, Energybangla.com Bangladesh Power System Master Plan Review, Engr Khondkar Abdus Saleque, Feb 2009, Enerybangla.com
  • 14. Mid to Long Term Solution • Government must encourage expansion of Solar, wind and bio fuel energy generation. Efforts to use solar power on tall buildings, factories, rural areas should be promoted with low cost loans while removing taxes on solar equipment. Full potential of mini micro hydro generation must also be explored. Energy from solid municipal waste in major cities can be possibility also. • Nuclear energy is a long term solution with huge cost involvement of billion dollar per 1000 MW plant, but essentially this would become a vital source with highest durability and low unit cost of production. • Many power plants set up in Ashuganj, Ghorashal, Shajibazar have outlived their effective economic life. Further investment in those will be waste of money and efforts. There has been considerable drainage of national resources in maintenance of some plants. These can be replaced with fuel efficient modern plants. • A more efficient and faster procurement and tendering process should be adopted for quicker implementation of any project. Solving the energy crisis Salman F Rahman and Forrest Cookson Maximizing Growth for Bangladesh: A Private Sector Vision, Ifty Islam, Asian Tiger Capital Partners Power Crisis: Issues and Challenges Md. Mizanur Rahman, Energybangla.com Bangladesh Power System Master Plan Review, Engr Khondkar Abdus Saleque, Feb 2009, Enerybangla.com