NATIONAL BUILDING CODE OF
INDIA– 2005
HISTORY
AND
OVERVIEW
VINAY KUMAR GUPTA
DYCE/G/N.RAILWAY
After the third Five Year Plan, the Planning Commission decided
that the whole gamut of operations involved in construction, such
as administrative, organizational, financial and technical aspects,
be studied in depth.
For this study a panel of experts was appointed in 1965 and its
recommendations are found in the
‘Report on Economies in Construction Cost’
published in 1968.
It revealed that some of the prevailing methods of construction
were outmoded; some designs were over burdened with safety
factors; building bylaws of municipal bodies were outdated etc.
etc.
These studies resulted in a recommendation that a
NATIONAL BUILDING CODE
be prepared
to unify the building regulations
throughout the country.
The than
Indian Standard Institute
(Now Bureau of Indian Standards)
was entrusted by the planning commission with the
preparation of the
National Building Code.
Guidance committee for the
preparation of the code was
set up in 1967
The first version of the
NATIONAL BUILDING CODE
was published in 1970
Since the publication in 1970 version of the
NATIONAL BUILDING CODE
a large number of comments and useful suggestions
for modifications and additions to different parts and
sections of the code were received.
The revised version of
NATIONAL BUILDING CODE of India
was therefore, brought out
in 1983
Based on the changes effected in the:
•Steel Code,
•Masonry Code
•Loading Codes
•As also in order to update Fire
Protection Requirements,
three voluminous amendments were brought out to
the 1983 version of the Code,
Two in 1987 and the third in 1997.
In the last about two decades since the publication of
the 1983 version of the Code,
substantial further experience had been gained in the
areas of the
•building planning,
•designing and
•construction.
Intensive efforts involving wide consultative process
have resulted in finalisation and publication of the
NATIONAL BUILDING CODE OF INDIA – 2005
reflecting the state-of-the-art and contemporary
applicable international practices.
The revised
NATIONAL BUILDING
CODE OF INDIA – 2005
was formally released on
16th
September 2005
at New Delhi
CONTENTS OF NBC 2005
• PART 0 INTEGRATED APPROACH – PREREQUISITE FOR
APPLYING PROVISION OF THE CODE
• PART 1 DEFINITIONS
• PART 2 ADMINISTRATION
• PART 3 DEVELOPMENT CONTROL RULES AND GENERAL
BUILDING REQUIREMENTS
• PART 4 FIRE AND LIFE SAFETY
• PART 5 BUILDING MATERIALS
• PART 6 STRUCTURAL DESIGN
• PART 7 CONSTRUCTIONAL PRACTICES AND SAFETY
• PART 8 BUILDING SERVICES
• PART 9 PLUMBING SERVICES
• PART 10 LANDSCAPING, SIGNS AND OUTDOOR DISPLAY
STRUCTURES
Part 0: Integrated Approach
Prerequisite for Applying
Provisions of the Code
This part covers guidelines to be
followed for judicious implementation of
the provisions of various parts/sections
of the Code.
PART 1 : DEFINITIONS
It lists the terms appearing in all the
parts/sections of the National Building Code
of India. However, some common definitions
are reproduced in this part also.
PART 2:
ADMINISTRATION
It covers the administrative aspects of the
Code, such as applicability of the Code,
organization of building department for
enforcement of the Code, procedure for
obtaining development and building
permits, and responsibility of the owner
and all professionals involved in the
planning, design and construction of the
building.
PART 3:
DEVELOPMENT CONTROL
RULES AND GENERAL
BUILDING REQUIREMENTS
It covers the development control rules and
general building requirements for proper
planning and design at the layout and
building level to ensure health safety, public
safety and desired quality of life.
Provides provisions for covered area, plinth
area, FAR, amenities, land use classification,
height/ size of rooms, kitchens etc. etc.
PART 4 : FIRE AND LIFE
SAFETY
It covers the requirements for fire prevention, life safety
in relation to fire, and fire protection of buildings. The
code specifies planning and construction features and fire
protection features for all occupancies that are necessary
to minimize danger to life and property.
The code cagorises the buildings as follows:
Group A - Residential Group B - Educational
Group C - Institutional Group D - Assembly
Group E - Business Group F - Mercantile
Group G - Industrial Group H - Storage
Group J - Hazardous
PART 5: BUILDING
MATERIALS
It covers the requirements of building
materials and components, and criteria
for accepting new or alternative building
materials and components.
29 Materials/ components which have been covered in
this part are:
1. Aluminum & other light
materials & their alloys
2. Bitumen & Tar products
3. Builders hardwares
4. Building chemicals
5. Building lime and products
6. Burnt clay products
7. Cement & concrete (i/c
reinforcement)
8. Composite matrix products
9. Conductors & cables
10. Doors/windows & ventilators
11. Electrical wiring & accessories
12. Fillers, stoppers & putties
13. Floor coverings, roofings &
other finishes
14. Glass
15. Gypsum based materials
16. Lignocellulosic building
materials (timber bamboos etc.)
17. Paints & allied products
18. Polymers, plastics etc.
19. Sanitary appliances & water
fittings
20. Soil based blocks
21. Steel & its alloys
22. Stones.
23. Structural sections
24. Thermal insulation materials
25. Threaded fasteners & rivets
26. Unit weight of building
materials
27. Water proofing & damp
proofing materials
28. Welding electrodes & wires
29. Wire ropes & wire products
PART 6 : STRUCTURAL
DESIGN
This part through its seven sections provides
for structural adequacy of buildings to deal
with both internal and external environment,
and provide guidance to engineers/ structural
engineers for varied usage of material/
technology types for building design.
Part 6 : Section 1 : Loads, Forces
and Effects
It covers basic design loads to be assumed in
the design of buildings. The live loads, wind
loads, seismic loads, snow loads and other
loads, which are specified herein, are
minimum working loads which should be
taken into consideration for purposes of
design.
Part 6 : Section 2 :
Soils and Foundations
It covers structural design (principles) of all
building foundations such as raft, pile and
other foundation systems to ensure safety and
serviceability without exceeding the
permissible stresses of the materials of
foundations and the bearing capacity of the
supporting soil.
Part 6 : Section 3A : Timber
It covers the use of structural timber in
structures or elements of structures
connected together by fasteners/
fastening techniques.
Part 6 : Section 3B : Bamboo
It covers the use of bamboo for constructional
purposes in structures or elements of the structure,
ensuring quality and effectiveness of design and
construction using bamboo. It covers minimum
strength data, dimensional and grading
requirements, seasoning, preservative treatment,
design and jointing techniques with bamboo which
would facilitate scientific application and long-term
performance of structures. It also covers guidelines
so as to ensure proper procurement, storage,
precautions and design limitations on bamboo.
Part 6 : Section 4 :
Masonry
It covers the structural design aspects of
unreinforced load bearing and non-load
bearing walls, constructed using various bricks,
stones and blocks permitted in accordance with
this section. This, however, also covers
provisions for design of reinforced brick and
reinforced brick concrete floors and roofs.
Part 6 : Section 5A :
Plain and
Reinforced Concrete
It covers the general structural use of
plain and reinforced concrete.
Part 6 : Section 5B :
Prestressed Concrete
It covers the general structural use of
prestressed concrete. It covers both work
carried out on site and the manufacture of
precast prestressed concrete units.
Part 6 : Section 6 :
Steel
It covers the use of structural steel in
general building construction including
the use of hot rolled steel sections and
steel tubes.
Part 6 : Section 7 :
Prefabrication and Systems
Building
Though desirable for large scale building activities, has
yet to take a firm hold in the country.
Includes a few recommendations on the need to avoid
‘progressive collapse’ of the structures.
Part 6 : Section 7A :
Prefabricated Concrete:
Part 6 : Section 7B :
Systems Building and mixed/
Composite Construction
It covers recommendations regarding
modular planning, component sizes,
joints, manufacture, storage, transport
and erection of prefabricated elements
for use in buildings and such related
requirements for mixed/composite
construction.
PART 7 : CONSTRUCTIONAL
PRACTICES AND SAFETY
It covers the constructional practices in
buildings; storage, stacking and handling of
materials and safety of personnel during
construction operations for all elements of a
building and demolition of buildings. The
objective can be best achieved through proper
coordination and working by the project
management and construction management
teams.
PART 8 : BUILDING
SERVICES
This part through its five elaborate
sections on utilities provides detailed
guidance to concerned professionals/
utility engineers for meeting necessary
functional requirements in buildings.
Part 8 : Section 1 :
Lighting and Ventilation
It covers requirements and methods for
lighting and ventilation of buildings.
PART 8 : Section 2 : Electrical
and Allied Installations
It covers the essential requirements for
electrical installations in buildings to
ensure efficient use of electricity
including safety from fire and shock.
This section also includes general
requirements relating to lightning
protection of buildings.
PART 8 : Section 3 : Air
conditioning, Heating and
Mechanical Ventilation
This section covers the design,
construction and installation of air
conditioning and heating systems and
equipment installed in buildings for the
purpose of providing and maintaining
conditions of air temperature, humidity,
purity and distribution suitable for the
use and occupancy of the space.
PART 8 : Section 4 :
Acoustics, Sound Insulation
and Noise Control
It covers requirements and guidelines
regarding planning against noise,
acceptable noise levels and the
requirements for sound insulation in
buildings with different occupancies. 2
PART 8 : Section 5 :
Installation of Lifts and
Escalators
It covers the essential requirements for the
installation, operation, maintenance and also
inspection of lifts (passenger lifts, goods lifts,
hospital lifts, service lifts and dumb-waiter
lifts) and escalators so as to ensure safe and
satisfactory performance.
PART 9 : PLUMBING
SERVICES
This part through its two sections gives
detailed guidance to concerned professionals/
plumbing engineers with regard to plumbing
and other related requirements in buildings.
PART 9 : Section 1 : Water
Supply, Drainage and Sanitation
(including Solid Waste Management)
It covers the basic requirements of water supply
for residential, business and other types of
buildings, including traffic terminal stations. This
section also deals with general requirements of
plumbing connected to public water supply and
design of water supply systems.
Provisions on Rain Water Harvesting have also
been included
PART 9 : Section 1 : Water
Supply, Drainage and Sanitation
(including Solid Waste
Management)
It also covers the design, layout, construction and
maintenance of drains for foul water, surface water
and subsoil water and sewage; together with all
ancillary works, such as connections, manholes and
inspection chambers used within the building and from
building to the connection to a public sewer, private
sewer, individual sewage-disposal system, cess-pool, or
to other approved point of disposal/ treatment work. It
further includes the provisions on solid waste
management.
PART 9 : Section 2 : Gas
Supply
It covers the requirements regarding the
safety of persons and property for all
piping uses and for all types of gases
used for fuel or lighting purposes in
buildings.
PART 10 : Section 1 :
Landscape Planning and
Design
It covers requirements of landscape
planning and design with the view to
promoting quality of outdoor built
environment and protection of land and
its resources.
PART 10 : Section 2 :
Signs and Outdoor Display
Structures
It covers the requirements with regard to
public safety, structural safety and fire
safety of all signs (advertisements) and
outdoor display structures including the
overall aesthetical aspects of imposition of
signs and outdoor display structures in the
outdoor built environment.
Few more terminologies related to signages
and explanatory figures have been added.
Salient Features of NBC – 2005
1. Inclusion of a complete philosophy and direction for
successfully accomplishing the building projects through
integrated multidisciplinary approach right from conceptual
stage through planning, designing, construction, operation and
maintenance stages.
2. A series of reforms in building permit process.
3. Provision for ensuring safety of buildings against natural
disaster& certification of structural sufficiency by engineer &
structural engineer.
4. Permission of two stage permit for high rise residential and
special buildings.
5. Provision for periodic renewal certificate of occupied buildings
from structural, fire, electrical, health safety point of view
6. Provision for empowering engineers/architects for sanctioning
plans for residential buildings up to 500 sqm.
Salient Features of NBC – 2005
(Contd..)
• Revision of parking requirements for metro & mega cities.
(mega cities are metros with population more than 50 lacs)
• Up gradation of special requirements for low income housing for
urban areas.
• Inclusion of special requirements for low income housing for
rural habitat planning.
• Inclusion of guidelines for development planning for hilly areas.
• Revisions of the provisions for building and facilities for
physically challenged
• Fire safety norms completely revamped through detailed
provisions on fire prevention, life safety and fire protection
• Inclusion of new categories of starred hotels, heritage structures
& archeological monuments for fire safety provisions
• Substitution of halon based fire extinguishers/fire fighting
system
Salient Features of NBC – 2005
(Contd..)
• Promotion to new/innovative building materials/technologies
• Inclusion of latest provisions for earthquake resistant design &
construction
• Inclusion of details on multi-disaster prone districts
• Inclusion of new chapter on design & construction using
bamboos
• Chapter on pre-fabricated & composite construction for speedier
construction
• Up gradation of provision of safety in construction.
• Complete revision of provision on building & plumbing services
in line with applicable international practices.
• Provision on Rain Water Harvesting
• Inclusion of new chapter to cover landscaping needs.
A few points which were not clarified during the workshop on
NATIONAL BUILDING CODE OF INDIA– 2005 held at
Mumbai on 26 & 27th
October’2006:
•In this age of terrorism security is given more importance than
safety. Code is silent on this . In the name of security we are
playing with safety esp. in most important buildings which are
prone to terrorism
•Code is silent about ground water management. During
construction of basements of buildings dewatering continues,
sometimes for years together.
•Part 2 of the code empowers Engineers/Architects for for
sanctioning residential buildings up to 500 Sqm area. Are the
local bodies going to accept it?
National building codes 2005 history overview

Contenu connexe

Tendances

Building service final pdf
Building service final pdfBuilding service final pdf
Building service final pdf
杉 江紫
 

Tendances (20)

Cbri
CbriCbri
Cbri
 
Auditorium Literature Study & Design Considerations
Auditorium Literature Study & Design ConsiderationsAuditorium Literature Study & Design Considerations
Auditorium Literature Study & Design Considerations
 
NBC summary part 1 ,2
NBC summary part 1 ,2NBC summary part 1 ,2
NBC summary part 1 ,2
 
building services- II Lighting
building services- II Lightingbuilding services- II Lighting
building services- II Lighting
 
Building service final pdf
Building service final pdfBuilding service final pdf
Building service final pdf
 
HOT AND DRY CLIMATE -CASE STUDY
HOT AND DRY CLIMATE -CASE STUDYHOT AND DRY CLIMATE -CASE STUDY
HOT AND DRY CLIMATE -CASE STUDY
 
Building services
Building servicesBuilding services
Building services
 
Architectural acoustics
Architectural acousticsArchitectural acoustics
Architectural acoustics
 
NBC NORMS FOR HVAC SYSTEMS
NBC NORMS FOR HVAC SYSTEMSNBC NORMS FOR HVAC SYSTEMS
NBC NORMS FOR HVAC SYSTEMS
 
Waffle or ribbed slab
Waffle or ribbed slabWaffle or ribbed slab
Waffle or ribbed slab
 
Folded plates
Folded platesFolded plates
Folded plates
 
Architectural acoustic notes
Architectural acoustic notesArchitectural acoustic notes
Architectural acoustic notes
 
Curtain wall
Curtain wallCurtain wall
Curtain wall
 
National Building Code : Building Services
National Building Code : Building ServicesNational Building Code : Building Services
National Building Code : Building Services
 
Services in High Rise Building
Services in High Rise Building  Services in High Rise Building
Services in High Rise Building
 
Basement construction report
Basement construction reportBasement construction report
Basement construction report
 
Builiding Byes laws
Builiding Byes laws Builiding Byes laws
Builiding Byes laws
 
Fire safety as per National Building Code-2016
Fire safety as per National Building Code-2016Fire safety as per National Building Code-2016
Fire safety as per National Building Code-2016
 
Fire fighting system in buildings
Fire fighting system  in buildingsFire fighting system  in buildings
Fire fighting system in buildings
 
Lifts
LiftsLifts
Lifts
 

En vedette (13)

National building code for residential apartments in india
National building code for residential apartments in indiaNational building code for residential apartments in india
National building code for residential apartments in india
 
Final Folio Template
Final Folio TemplateFinal Folio Template
Final Folio Template
 
Lab safety good ppt
Lab safety   good pptLab safety   good ppt
Lab safety good ppt
 
FIRE NORMS AND INDIAN HABITAT CENTRE CASE STUDY
FIRE NORMS AND INDIAN HABITAT CENTRE CASE STUDYFIRE NORMS AND INDIAN HABITAT CENTRE CASE STUDY
FIRE NORMS AND INDIAN HABITAT CENTRE CASE STUDY
 
2.01 environmental safety
2.01 environmental safety2.01 environmental safety
2.01 environmental safety
 
Safety Symbols
Safety SymbolsSafety Symbols
Safety Symbols
 
commentry on nbc part 4
commentry on nbc part 4commentry on nbc part 4
commentry on nbc part 4
 
Fundamentals of Environmental Health and Safety
Fundamentals of Environmental Health and SafetyFundamentals of Environmental Health and Safety
Fundamentals of Environmental Health and Safety
 
National Building Code 2005
National Building Code 2005National Building Code 2005
National Building Code 2005
 
Lab Safety
Lab SafetyLab Safety
Lab Safety
 
Lab+safety+rules+ppt
Lab+safety+rules+pptLab+safety+rules+ppt
Lab+safety+rules+ppt
 
Fire Safety Management
Fire Safety ManagementFire Safety Management
Fire Safety Management
 
Iso 14000
Iso 14000Iso 14000
Iso 14000
 

Similaire à National building codes 2005 history overview

Comparision of Design Codes ACI 318-11, IS 456 2000 and Eurocode II
Comparision of Design Codes ACI 318-11, IS 456 2000 and Eurocode IIComparision of Design Codes ACI 318-11, IS 456 2000 and Eurocode II
Comparision of Design Codes ACI 318-11, IS 456 2000 and Eurocode II
ijtsrd
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System
마 이환
 
EXPLORING THE NATIONAL BUILDING CODE- text of paper 2012 (1)
EXPLORING THE NATIONAL BUILDING CODE- text of paper 2012 (1)EXPLORING THE NATIONAL BUILDING CODE- text of paper 2012 (1)
EXPLORING THE NATIONAL BUILDING CODE- text of paper 2012 (1)
Abass Adeolu Ologbenla. CPM
 
Building Technology : Industrialize Building Technology
Building Technology : Industrialize Building TechnologyBuilding Technology : Industrialize Building Technology
Building Technology : Industrialize Building Technology
Quinn Liew
 
Book let-Guide-for-Using-NBC-2016 hand book for users.pdf
Book let-Guide-for-Using-NBC-2016 hand book for users.pdfBook let-Guide-for-Using-NBC-2016 hand book for users.pdf
Book let-Guide-for-Using-NBC-2016 hand book for users.pdf
aeekhsdrpsubdnhvr
 

Similaire à National building codes 2005 history overview (20)

Comparative Study of Codal Provisions for Pre-Engineered Buildings
Comparative Study of  Codal Provisions for Pre-Engineered BuildingsComparative Study of  Codal Provisions for Pre-Engineered Buildings
Comparative Study of Codal Provisions for Pre-Engineered Buildings
 
Irjet v4 i7530
Irjet v4 i7530Irjet v4 i7530
Irjet v4 i7530
 
Comparision of Design Codes ACI 318-11, IS 456 2000 and Eurocode II
Comparision of Design Codes ACI 318-11, IS 456 2000 and Eurocode IIComparision of Design Codes ACI 318-11, IS 456 2000 and Eurocode II
Comparision of Design Codes ACI 318-11, IS 456 2000 and Eurocode II
 
National building code
National building codeNational building code
National building code
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System
 
IRJET- U-Boot Technology
IRJET-  	  U-Boot TechnologyIRJET-  	  U-Boot Technology
IRJET- U-Boot Technology
 
EXPLORING THE NATIONAL BUILDING CODE- text of paper 2012 (1)
EXPLORING THE NATIONAL BUILDING CODE- text of paper 2012 (1)EXPLORING THE NATIONAL BUILDING CODE- text of paper 2012 (1)
EXPLORING THE NATIONAL BUILDING CODE- text of paper 2012 (1)
 
Summary of NBC 2016
Summary of NBC 2016Summary of NBC 2016
Summary of NBC 2016
 
Provisions of NBC.pptx
Provisions of NBC.pptxProvisions of NBC.pptx
Provisions of NBC.pptx
 
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
 
Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)
 
Building Technology : Industrialize Building Technology
Building Technology : Industrialize Building TechnologyBuilding Technology : Industrialize Building Technology
Building Technology : Industrialize Building Technology
 
Building Technology Project 1 Report
Building Technology Project 1 ReportBuilding Technology Project 1 Report
Building Technology Project 1 Report
 
Btech report
Btech reportBtech report
Btech report
 
Efficient Design for Multi-story Building Using Pre-Fabricated Steel Structur...
Efficient Design for Multi-story Building Using Pre-Fabricated Steel Structur...Efficient Design for Multi-story Building Using Pre-Fabricated Steel Structur...
Efficient Design for Multi-story Building Using Pre-Fabricated Steel Structur...
 
Inception Report
Inception ReportInception Report
Inception Report
 
2572
25722572
2572
 
SUMMER TRAINING REPORT BY VIJAY VERMA
SUMMER TRAINING REPORT BY VIJAY VERMASUMMER TRAINING REPORT BY VIJAY VERMA
SUMMER TRAINING REPORT BY VIJAY VERMA
 
Steel building Graded Unit Civil Engineering Project HND Project Glasgow Kel...
Steel building Graded Unit  Civil Engineering Project HND Project Glasgow Kel...Steel building Graded Unit  Civil Engineering Project HND Project Glasgow Kel...
Steel building Graded Unit Civil Engineering Project HND Project Glasgow Kel...
 
Book let-Guide-for-Using-NBC-2016 hand book for users.pdf
Book let-Guide-for-Using-NBC-2016 hand book for users.pdfBook let-Guide-for-Using-NBC-2016 hand book for users.pdf
Book let-Guide-for-Using-NBC-2016 hand book for users.pdf
 

Plus de Shourya Puri

Plus de Shourya Puri (20)

Smo(social media optimisation)
Smo(social media optimisation)Smo(social media optimisation)
Smo(social media optimisation)
 
SMO (social media optimization)
SMO (social media optimization)SMO (social media optimization)
SMO (social media optimization)
 
Seo digital marketing
Seo digital marketingSeo digital marketing
Seo digital marketing
 
report of dance, drama and music academy and auditorium
report of dance, drama and music academy and auditoriumreport of dance, drama and music academy and auditorium
report of dance, drama and music academy and auditorium
 
Synopsis Of cultural complex
Synopsis Of cultural complexSynopsis Of cultural complex
Synopsis Of cultural complex
 
Wildcraft marketing
Wildcraft marketingWildcraft marketing
Wildcraft marketing
 
Wagah border
Wagah border Wagah border
Wagah border
 
Tender calling procedure
Tender calling procedureTender calling procedure
Tender calling procedure
 
History of jammu & kashmir
History  of jammu & kashmirHistory  of jammu & kashmir
History of jammu & kashmir
 
Town plan auroville
Town plan aurovilleTown plan auroville
Town plan auroville
 
Hybrid trusses
Hybrid trussesHybrid trusses
Hybrid trusses
 
Xeriscaping landscape and bioswale
Xeriscaping  landscape and bioswaleXeriscaping  landscape and bioswale
Xeriscaping landscape and bioswale
 
Glass Report
Glass ReportGlass Report
Glass Report
 
Fiberglass
FiberglassFiberglass
Fiberglass
 
MODERN CONSTRUCTION METHODS
MODERN CONSTRUCTION METHODSMODERN CONSTRUCTION METHODS
MODERN CONSTRUCTION METHODS
 
Sustainable Waste Management
Sustainable Waste ManagementSustainable Waste Management
Sustainable Waste Management
 
Improve communication skills
Improve communication skillsImprove communication skills
Improve communication skills
 
Office case study
Office case studyOffice case study
Office case study
 
SITE VISIT ARCHITECTRE
SITE VISIT ARCHITECTRE  SITE VISIT ARCHITECTRE
SITE VISIT ARCHITECTRE
 
Convention hall interior acoustics
Convention hall  interior acoustics Convention hall  interior acoustics
Convention hall interior acoustics
 

Dernier

Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
kauryashika82
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
QucHHunhnh
 

Dernier (20)

Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesEnergy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 

National building codes 2005 history overview

  • 1. NATIONAL BUILDING CODE OF INDIA– 2005 HISTORY AND OVERVIEW VINAY KUMAR GUPTA DYCE/G/N.RAILWAY
  • 2. After the third Five Year Plan, the Planning Commission decided that the whole gamut of operations involved in construction, such as administrative, organizational, financial and technical aspects, be studied in depth. For this study a panel of experts was appointed in 1965 and its recommendations are found in the ‘Report on Economies in Construction Cost’ published in 1968.
  • 3. It revealed that some of the prevailing methods of construction were outmoded; some designs were over burdened with safety factors; building bylaws of municipal bodies were outdated etc. etc. These studies resulted in a recommendation that a NATIONAL BUILDING CODE be prepared to unify the building regulations throughout the country.
  • 4. The than Indian Standard Institute (Now Bureau of Indian Standards) was entrusted by the planning commission with the preparation of the National Building Code. Guidance committee for the preparation of the code was set up in 1967
  • 5. The first version of the NATIONAL BUILDING CODE was published in 1970 Since the publication in 1970 version of the NATIONAL BUILDING CODE a large number of comments and useful suggestions for modifications and additions to different parts and sections of the code were received.
  • 6. The revised version of NATIONAL BUILDING CODE of India was therefore, brought out in 1983 Based on the changes effected in the: •Steel Code, •Masonry Code •Loading Codes •As also in order to update Fire Protection Requirements, three voluminous amendments were brought out to the 1983 version of the Code, Two in 1987 and the third in 1997.
  • 7. In the last about two decades since the publication of the 1983 version of the Code, substantial further experience had been gained in the areas of the •building planning, •designing and •construction. Intensive efforts involving wide consultative process have resulted in finalisation and publication of the NATIONAL BUILDING CODE OF INDIA – 2005 reflecting the state-of-the-art and contemporary applicable international practices.
  • 8. The revised NATIONAL BUILDING CODE OF INDIA – 2005 was formally released on 16th September 2005 at New Delhi
  • 9. CONTENTS OF NBC 2005 • PART 0 INTEGRATED APPROACH – PREREQUISITE FOR APPLYING PROVISION OF THE CODE • PART 1 DEFINITIONS • PART 2 ADMINISTRATION • PART 3 DEVELOPMENT CONTROL RULES AND GENERAL BUILDING REQUIREMENTS • PART 4 FIRE AND LIFE SAFETY • PART 5 BUILDING MATERIALS • PART 6 STRUCTURAL DESIGN • PART 7 CONSTRUCTIONAL PRACTICES AND SAFETY • PART 8 BUILDING SERVICES • PART 9 PLUMBING SERVICES • PART 10 LANDSCAPING, SIGNS AND OUTDOOR DISPLAY STRUCTURES
  • 10. Part 0: Integrated Approach Prerequisite for Applying Provisions of the Code This part covers guidelines to be followed for judicious implementation of the provisions of various parts/sections of the Code.
  • 11. PART 1 : DEFINITIONS It lists the terms appearing in all the parts/sections of the National Building Code of India. However, some common definitions are reproduced in this part also.
  • 12. PART 2: ADMINISTRATION It covers the administrative aspects of the Code, such as applicability of the Code, organization of building department for enforcement of the Code, procedure for obtaining development and building permits, and responsibility of the owner and all professionals involved in the planning, design and construction of the building.
  • 13. PART 3: DEVELOPMENT CONTROL RULES AND GENERAL BUILDING REQUIREMENTS It covers the development control rules and general building requirements for proper planning and design at the layout and building level to ensure health safety, public safety and desired quality of life. Provides provisions for covered area, plinth area, FAR, amenities, land use classification, height/ size of rooms, kitchens etc. etc.
  • 14. PART 4 : FIRE AND LIFE SAFETY It covers the requirements for fire prevention, life safety in relation to fire, and fire protection of buildings. The code specifies planning and construction features and fire protection features for all occupancies that are necessary to minimize danger to life and property. The code cagorises the buildings as follows: Group A - Residential Group B - Educational Group C - Institutional Group D - Assembly Group E - Business Group F - Mercantile Group G - Industrial Group H - Storage Group J - Hazardous
  • 15. PART 5: BUILDING MATERIALS It covers the requirements of building materials and components, and criteria for accepting new or alternative building materials and components.
  • 16. 29 Materials/ components which have been covered in this part are: 1. Aluminum & other light materials & their alloys 2. Bitumen & Tar products 3. Builders hardwares 4. Building chemicals 5. Building lime and products 6. Burnt clay products 7. Cement & concrete (i/c reinforcement) 8. Composite matrix products 9. Conductors & cables 10. Doors/windows & ventilators 11. Electrical wiring & accessories 12. Fillers, stoppers & putties 13. Floor coverings, roofings & other finishes 14. Glass 15. Gypsum based materials 16. Lignocellulosic building materials (timber bamboos etc.) 17. Paints & allied products 18. Polymers, plastics etc. 19. Sanitary appliances & water fittings 20. Soil based blocks 21. Steel & its alloys 22. Stones. 23. Structural sections 24. Thermal insulation materials 25. Threaded fasteners & rivets 26. Unit weight of building materials 27. Water proofing & damp proofing materials 28. Welding electrodes & wires 29. Wire ropes & wire products
  • 17. PART 6 : STRUCTURAL DESIGN This part through its seven sections provides for structural adequacy of buildings to deal with both internal and external environment, and provide guidance to engineers/ structural engineers for varied usage of material/ technology types for building design.
  • 18. Part 6 : Section 1 : Loads, Forces and Effects It covers basic design loads to be assumed in the design of buildings. The live loads, wind loads, seismic loads, snow loads and other loads, which are specified herein, are minimum working loads which should be taken into consideration for purposes of design.
  • 19. Part 6 : Section 2 : Soils and Foundations It covers structural design (principles) of all building foundations such as raft, pile and other foundation systems to ensure safety and serviceability without exceeding the permissible stresses of the materials of foundations and the bearing capacity of the supporting soil.
  • 20. Part 6 : Section 3A : Timber It covers the use of structural timber in structures or elements of structures connected together by fasteners/ fastening techniques.
  • 21. Part 6 : Section 3B : Bamboo It covers the use of bamboo for constructional purposes in structures or elements of the structure, ensuring quality and effectiveness of design and construction using bamboo. It covers minimum strength data, dimensional and grading requirements, seasoning, preservative treatment, design and jointing techniques with bamboo which would facilitate scientific application and long-term performance of structures. It also covers guidelines so as to ensure proper procurement, storage, precautions and design limitations on bamboo.
  • 22. Part 6 : Section 4 : Masonry It covers the structural design aspects of unreinforced load bearing and non-load bearing walls, constructed using various bricks, stones and blocks permitted in accordance with this section. This, however, also covers provisions for design of reinforced brick and reinforced brick concrete floors and roofs.
  • 23. Part 6 : Section 5A : Plain and Reinforced Concrete It covers the general structural use of plain and reinforced concrete.
  • 24. Part 6 : Section 5B : Prestressed Concrete It covers the general structural use of prestressed concrete. It covers both work carried out on site and the manufacture of precast prestressed concrete units.
  • 25. Part 6 : Section 6 : Steel It covers the use of structural steel in general building construction including the use of hot rolled steel sections and steel tubes.
  • 26. Part 6 : Section 7 : Prefabrication and Systems Building
  • 27. Though desirable for large scale building activities, has yet to take a firm hold in the country. Includes a few recommendations on the need to avoid ‘progressive collapse’ of the structures. Part 6 : Section 7A : Prefabricated Concrete:
  • 28. Part 6 : Section 7B : Systems Building and mixed/ Composite Construction It covers recommendations regarding modular planning, component sizes, joints, manufacture, storage, transport and erection of prefabricated elements for use in buildings and such related requirements for mixed/composite construction.
  • 29. PART 7 : CONSTRUCTIONAL PRACTICES AND SAFETY It covers the constructional practices in buildings; storage, stacking and handling of materials and safety of personnel during construction operations for all elements of a building and demolition of buildings. The objective can be best achieved through proper coordination and working by the project management and construction management teams.
  • 30. PART 8 : BUILDING SERVICES This part through its five elaborate sections on utilities provides detailed guidance to concerned professionals/ utility engineers for meeting necessary functional requirements in buildings.
  • 31. Part 8 : Section 1 : Lighting and Ventilation It covers requirements and methods for lighting and ventilation of buildings.
  • 32. PART 8 : Section 2 : Electrical and Allied Installations It covers the essential requirements for electrical installations in buildings to ensure efficient use of electricity including safety from fire and shock. This section also includes general requirements relating to lightning protection of buildings.
  • 33. PART 8 : Section 3 : Air conditioning, Heating and Mechanical Ventilation This section covers the design, construction and installation of air conditioning and heating systems and equipment installed in buildings for the purpose of providing and maintaining conditions of air temperature, humidity, purity and distribution suitable for the use and occupancy of the space.
  • 34. PART 8 : Section 4 : Acoustics, Sound Insulation and Noise Control It covers requirements and guidelines regarding planning against noise, acceptable noise levels and the requirements for sound insulation in buildings with different occupancies. 2
  • 35. PART 8 : Section 5 : Installation of Lifts and Escalators It covers the essential requirements for the installation, operation, maintenance and also inspection of lifts (passenger lifts, goods lifts, hospital lifts, service lifts and dumb-waiter lifts) and escalators so as to ensure safe and satisfactory performance.
  • 36. PART 9 : PLUMBING SERVICES This part through its two sections gives detailed guidance to concerned professionals/ plumbing engineers with regard to plumbing and other related requirements in buildings.
  • 37. PART 9 : Section 1 : Water Supply, Drainage and Sanitation (including Solid Waste Management) It covers the basic requirements of water supply for residential, business and other types of buildings, including traffic terminal stations. This section also deals with general requirements of plumbing connected to public water supply and design of water supply systems. Provisions on Rain Water Harvesting have also been included
  • 38. PART 9 : Section 1 : Water Supply, Drainage and Sanitation (including Solid Waste Management) It also covers the design, layout, construction and maintenance of drains for foul water, surface water and subsoil water and sewage; together with all ancillary works, such as connections, manholes and inspection chambers used within the building and from building to the connection to a public sewer, private sewer, individual sewage-disposal system, cess-pool, or to other approved point of disposal/ treatment work. It further includes the provisions on solid waste management.
  • 39. PART 9 : Section 2 : Gas Supply It covers the requirements regarding the safety of persons and property for all piping uses and for all types of gases used for fuel or lighting purposes in buildings.
  • 40. PART 10 : Section 1 : Landscape Planning and Design It covers requirements of landscape planning and design with the view to promoting quality of outdoor built environment and protection of land and its resources.
  • 41. PART 10 : Section 2 : Signs and Outdoor Display Structures It covers the requirements with regard to public safety, structural safety and fire safety of all signs (advertisements) and outdoor display structures including the overall aesthetical aspects of imposition of signs and outdoor display structures in the outdoor built environment. Few more terminologies related to signages and explanatory figures have been added.
  • 42. Salient Features of NBC – 2005 1. Inclusion of a complete philosophy and direction for successfully accomplishing the building projects through integrated multidisciplinary approach right from conceptual stage through planning, designing, construction, operation and maintenance stages. 2. A series of reforms in building permit process. 3. Provision for ensuring safety of buildings against natural disaster& certification of structural sufficiency by engineer & structural engineer. 4. Permission of two stage permit for high rise residential and special buildings. 5. Provision for periodic renewal certificate of occupied buildings from structural, fire, electrical, health safety point of view 6. Provision for empowering engineers/architects for sanctioning plans for residential buildings up to 500 sqm.
  • 43. Salient Features of NBC – 2005 (Contd..) • Revision of parking requirements for metro & mega cities. (mega cities are metros with population more than 50 lacs) • Up gradation of special requirements for low income housing for urban areas. • Inclusion of special requirements for low income housing for rural habitat planning. • Inclusion of guidelines for development planning for hilly areas. • Revisions of the provisions for building and facilities for physically challenged • Fire safety norms completely revamped through detailed provisions on fire prevention, life safety and fire protection • Inclusion of new categories of starred hotels, heritage structures & archeological monuments for fire safety provisions • Substitution of halon based fire extinguishers/fire fighting system
  • 44. Salient Features of NBC – 2005 (Contd..) • Promotion to new/innovative building materials/technologies • Inclusion of latest provisions for earthquake resistant design & construction • Inclusion of details on multi-disaster prone districts • Inclusion of new chapter on design & construction using bamboos • Chapter on pre-fabricated & composite construction for speedier construction • Up gradation of provision of safety in construction. • Complete revision of provision on building & plumbing services in line with applicable international practices. • Provision on Rain Water Harvesting • Inclusion of new chapter to cover landscaping needs.
  • 45. A few points which were not clarified during the workshop on NATIONAL BUILDING CODE OF INDIA– 2005 held at Mumbai on 26 & 27th October’2006: •In this age of terrorism security is given more importance than safety. Code is silent on this . In the name of security we are playing with safety esp. in most important buildings which are prone to terrorism •Code is silent about ground water management. During construction of basements of buildings dewatering continues, sometimes for years together. •Part 2 of the code empowers Engineers/Architects for for sanctioning residential buildings up to 500 Sqm area. Are the local bodies going to accept it?