Assignment
DRIVE SRING 2016
PROGRAM MBADS (SEM 3/SEM 5)MBAFLEX/ MBA (SEM 3)PGDPMN(SEM 1)
SUBJECT CODE & NAME PM0011 – PROJECT PLANNING ANDSCHEDULING
BK ID B1937
CREDIT & MARKS 4 CREDITS & 60 MARKS
Question. 1. Write short notes on:
Hierarchy of organisational objectives
Answer:Hierarchy of Objectives:The hierarchy of objectives is a tool that helps analyze and
communicate the project objectives. It organizes these objectives into different levels of a hierarchy or
tree. Different organizations use different names for the various levels and the types of objectives at
each level,butotherwisethere isagreatdeal of similarityinapproach.
Thisapproach organizesobjectivesintothreebroadlevels:
 Policy
Porter model a tool for identifying investment opportunities
Answer:Michael Porter’s Five Forces is a model used to explore the environment in which a product or
companyoperatestogenerate competitive advantage.
Michael Porter (Harvard Business School Management Researcher) designed various vital frameworks
for developinganorganization’s
Design phase of project management life cycle
Answer:Up to now, the project team and the client have focused on high-level questions regarding the
project. These start with simple questions like "why is this solution important?," "what is the business
value?" and "what are we going to deliver?" In the Design Phase, these questions are taken to a lower
level of detail,andyoustart to askthe "how"questions.The bigone is"how will we buildthissolution?"
At this point, the project team should have a complete set of requirements to work from, a set of
direction-setting strategies and a Conceptual Systems Design. The design process comes next. Even if
the projectwas small andthe requirementswere
Question.2 Budget Estimation of ABC Company Ltd.
ABC Company Ltd., established in 1985, is engaged in the manufacturing of leather accessories. Over
the years, the company, which started out as a local firm,has made its mark as an international
corporation. However,the company is still working as a traditional set up.
The high quality and durability of products have increased the demand of the products in the market.
As the production of the organisation is being increased to meet the demand, the traditional set up is
creating hurdlesin the production process.
Organisation conflicts have arisen among the team members because of the unorganised hierarchical
structure of the company, which is affecting the output of the organisation. Now that the
management has decided to expand the business and opened up branches abroad, the company is
facing two more problems. The first problem is in budgeting as the company is unfamiliar with
international market conditions, strategy, and business policy while the second problem is conflicts at
the time of team formation due to lack ofexperience ofand exposure to multinational work
culture,which has further affectedthe output of the company.
The company can estimate the budget through two methods,the bottom - up approach
and the top - down approach. The bottom -up approach is generally followed by the MNCs as it is
more accurate and reliable.
Mr.Parag has been appointed as the country head of the company and he has also been assigned the
responsibilityofincorporatingthe advanced projectset up in the organisation.
Questions:
Which project estimation approach should be used by the company
and why?
Bottom-up estimating(alsocalleddetail or resource-drivenestimating)
Bottom-up estimating is an extremely helpful technique in project management as it allows for the
ability to get a more refined estimate of a particular component of work. In bottom-up estimating, each
task is broken down into smaller components. Then, individual estimates are developed to determine
what specifically is needed to meet the requirements of each of these smaller components of the work.
The estimates for the smaller individual components are then aggregated to develop a larger estimate
for the entire taskas a whole.Indoing
Question.2. What type of project organisation structure should be
used by the company and why?
This is one of the main benefits of projectized organized structure, as they are adaptive and learn from
theirownas well asfromothers’experiences.
In projectized organizations, most of the resources are utilized in the project work. Projectized
organizations are only interested in the project work which they get from external clients. Usually they
have some small departmentssuchasAdmin,
Question.3 What is the importance of operational feasibility? Explain
the factors that affect operational feasibility.
Answer:A feasibility study aims to objectively and rationally uncover the strengths and weaknesses of an
existing business or proposed venture, opportunities and threats present in the environment, the
resources required to carry through, and ultimately the prospects for success. In its simplest terms, the
twocriteriato judge feasibilityare costrequiredandvalue tobe attained.
A well-designed feasibility study should provide a historical background of the business or project, a
descriptionof the productor service,
Question.4. Write short notes on:
Crashing
Answer:It is the process by which duration of project is reduced by INCREASING the amount of
RESOURCES allocated. It is important to note that crashing is done only to CRITICAL activities. This can
be achievedbyanyof the followingapproaches:
1) Addressing productivity issues of the current resources and making them more efficient. This can be
done bytakingbettercare of resourcesava
Precedence diagramming method
Answer:The precedence diagram method (PDM) is a tool for scheduling activities in a project plan. It is a
method of constructing a project schedule network diagram that uses boxes, referred to as nodes, to
represent activities and connects them with arrows that show the dependencies. It is also called the
activity-on-node(AON) method.
 Critical tasks,
Resource allocation
Answer:Resource allocation is the assignment of available resources to various uses. In the context of an
entire economy, resources can be allocated by various means, such as markets or central planning. In
project management, resource allocation or resource managementis the scheduling of activities and the
resources required by those activities while taking into consideration both the resource availability and
the projecttime.
In economics,the areaof public
Scope creep
Answer:Scope creep (also called requirement creep, function creep and feature creep) in project
management refers to uncontrolled changes or continuous growth in a project’s scope. This can occur
when the scope of a project is not properly defined, documented, or controlled. It is generally
consideredharmful.
Question.5 What do you understand by cost of quality? Elaborate on
various types of costs of quality associated with a project.
Answer:In process improvement efforts, quality costs or cost of quality is a means to quantify the total
cost of quality-relatedefforts and deficiencies. It was first described by Armand V. Feigenbaum in a 1956
Harvard BusinessReviewarticle.
Prior to its introduction, the general perception was that higher quality requires higher costs, either by
buying better materials or machines or by hiring more labor. Furthermore, while cost accounting had
evolved to categorize financial transactions into revenues, expenses, and changes in shareholder equity,
it had not attempted to categorize costs relevant to quality, which is especially important given that
mostpeople involvedinmanufacturingneverset
QUESTION 6. What do you understand by project scope? What are the
various components ofproject scope? What is scope creep? Explain
various reasons for scope creep.
Answer: Scope creep can mean many things depending upon context so it is probably best that I start by
explaining my definition. For the purposes of this article, scope creep is the process by which a project
growsbeyonditsoriginallyanticipatedsize.
I’d be willing to bet that most people who read that sentence are likely to conjure up images of
unscrupulous clients seeking to take advantage of well-meaning service providers, but scope creep is
more oftendownto misunderstandingthananythingelse.
Dear students get fully solved assignments
Send your semester & Specialization name to our mail id :
help.mbaassignments@gmail.com
or
call us at : 08263069601

Contenu connexe

Tendances

Conducting a Business Simulation
Conducting a Business SimulationConducting a Business Simulation
Conducting a Business SimulationScottMadden, Inc.
 
Day 2 1135 - 1220 - pearl 2 - karthik parvathi
Day 2   1135 - 1220 - pearl 2 - karthik parvathiDay 2   1135 - 1220 - pearl 2 - karthik parvathi
Day 2 1135 - 1220 - pearl 2 - karthik parvathiPMI2011
 
John osteenb rajagopalansubramanian
John osteenb rajagopalansubramanianJohn osteenb rajagopalansubramanian
John osteenb rajagopalansubramanianPMI2011
 
The Government’s new Project Delivery Capability Framework webinar, Question ...
The Government’s new Project Delivery Capability Framework webinar, Question ...The Government’s new Project Delivery Capability Framework webinar, Question ...
The Government’s new Project Delivery Capability Framework webinar, Question ...Association for Project Management
 
Business Planning for Success - 5 Essential Steps
Business Planning for Success - 5 Essential StepsBusiness Planning for Success - 5 Essential Steps
Business Planning for Success - 5 Essential StepsWalter Adamson
 
Balanced Scorecard
Balanced ScorecardBalanced Scorecard
Balanced ScorecardRicky Tanna
 
Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...
Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...
Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...TURKI , PMP
 
Execution of Strategic Plan
Execution of Strategic PlanExecution of Strategic Plan
Execution of Strategic Plancandice_chow
 
Business planning & policy management
Business planning & policy managementBusiness planning & policy management
Business planning & policy managementsmumbahelp
 
Final Afternoon
Final AfternoonFinal Afternoon
Final Afternoonchandan005
 
Chapter 4 benchmarking (1)
Chapter   4 benchmarking (1)Chapter   4 benchmarking (1)
Chapter 4 benchmarking (1)Abhinav Anand
 
Strategic Planning And Budgeting Part 1: Business Model and Strategy
Strategic Planning And Budgeting Part 1: Business Model and StrategyStrategic Planning And Budgeting Part 1: Business Model and Strategy
Strategic Planning And Budgeting Part 1: Business Model and StrategyKenny Ong
 
Business Math Chapter 7
Business Math Chapter 7Business Math Chapter 7
Business Math Chapter 7Nazrin Nazdri
 
Introduction to project, program & portfolio management
Introduction to project, program & portfolio managementIntroduction to project, program & portfolio management
Introduction to project, program & portfolio managementray_davis
 
Philippines Airlines balance scorecard
Philippines Airlines balance scorecardPhilippines Airlines balance scorecard
Philippines Airlines balance scorecardJesse Eman
 
Strategy Maps: Innovation Process - A Book by Robert S Kaplan & David P Norton
Strategy Maps: Innovation Process - A Book by Robert S Kaplan & David P NortonStrategy Maps: Innovation Process - A Book by Robert S Kaplan & David P Norton
Strategy Maps: Innovation Process - A Book by Robert S Kaplan & David P NortonEndro Catur
 

Tendances (19)

Conducting a Business Simulation
Conducting a Business SimulationConducting a Business Simulation
Conducting a Business Simulation
 
Final Paper
Final PaperFinal Paper
Final Paper
 
Day 2 1135 - 1220 - pearl 2 - karthik parvathi
Day 2   1135 - 1220 - pearl 2 - karthik parvathiDay 2   1135 - 1220 - pearl 2 - karthik parvathi
Day 2 1135 - 1220 - pearl 2 - karthik parvathi
 
John osteenb rajagopalansubramanian
John osteenb rajagopalansubramanianJohn osteenb rajagopalansubramanian
John osteenb rajagopalansubramanian
 
The Government’s new Project Delivery Capability Framework webinar, Question ...
The Government’s new Project Delivery Capability Framework webinar, Question ...The Government’s new Project Delivery Capability Framework webinar, Question ...
The Government’s new Project Delivery Capability Framework webinar, Question ...
 
Business Planning for Success - 5 Essential Steps
Business Planning for Success - 5 Essential StepsBusiness Planning for Success - 5 Essential Steps
Business Planning for Success - 5 Essential Steps
 
Balanced Scorecard
Balanced ScorecardBalanced Scorecard
Balanced Scorecard
 
Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...
Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...
Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...
 
Benchmarking
BenchmarkingBenchmarking
Benchmarking
 
Execution of Strategic Plan
Execution of Strategic PlanExecution of Strategic Plan
Execution of Strategic Plan
 
Business planning & policy management
Business planning & policy managementBusiness planning & policy management
Business planning & policy management
 
Final Afternoon
Final AfternoonFinal Afternoon
Final Afternoon
 
Sheri Ann lowe
Sheri Ann loweSheri Ann lowe
Sheri Ann lowe
 
Chapter 4 benchmarking (1)
Chapter   4 benchmarking (1)Chapter   4 benchmarking (1)
Chapter 4 benchmarking (1)
 
Strategic Planning And Budgeting Part 1: Business Model and Strategy
Strategic Planning And Budgeting Part 1: Business Model and StrategyStrategic Planning And Budgeting Part 1: Business Model and Strategy
Strategic Planning And Budgeting Part 1: Business Model and Strategy
 
Business Math Chapter 7
Business Math Chapter 7Business Math Chapter 7
Business Math Chapter 7
 
Introduction to project, program & portfolio management
Introduction to project, program & portfolio managementIntroduction to project, program & portfolio management
Introduction to project, program & portfolio management
 
Philippines Airlines balance scorecard
Philippines Airlines balance scorecardPhilippines Airlines balance scorecard
Philippines Airlines balance scorecard
 
Strategy Maps: Innovation Process - A Book by Robert S Kaplan & David P Norton
Strategy Maps: Innovation Process - A Book by Robert S Kaplan & David P NortonStrategy Maps: Innovation Process - A Book by Robert S Kaplan & David P Norton
Strategy Maps: Innovation Process - A Book by Robert S Kaplan & David P Norton
 

Similaire à Pm0011 project planning and scheduling

Pm0010 – interduction to project management
Pm0010 – interduction to project managementPm0010 – interduction to project management
Pm0010 – interduction to project managementsmumbahelp
 
Pearson HND BTEC Level 5 HNDManaging a Successful Business Pr.docx
Pearson HND BTEC Level 5 HNDManaging a Successful Business Pr.docxPearson HND BTEC Level 5 HNDManaging a Successful Business Pr.docx
Pearson HND BTEC Level 5 HNDManaging a Successful Business Pr.docxAASTHA76
 
Om0017 advanced production planning and control
Om0017   advanced production planning and controlOm0017   advanced production planning and control
Om0017 advanced production planning and controlStudy Stuff
 
Pm0011 project planning and scheduling
Pm0011 project planning and schedulingPm0011 project planning and scheduling
Pm0011 project planning and schedulingconsult4solutions
 
Pm0011 project planning and scheduling
Pm0011 project planning and schedulingPm0011 project planning and scheduling
Pm0011 project planning and schedulingconsult4solutions
 
Om0017 advanced production planning and control
Om0017   advanced production planning and controlOm0017   advanced production planning and control
Om0017 advanced production planning and controlsmumbahelp
 
Pm0011 project planning and scheduling
Pm0011  project planning and schedulingPm0011  project planning and scheduling
Pm0011 project planning and schedulingsmumbahelp
 
Om0017 advanced production planning and control
Om0017   advanced production planning and controlOm0017   advanced production planning and control
Om0017 advanced production planning and controlsmumbahelp
 
Ms 05 management of machines and materials
Ms 05 management of machines and materialsMs 05 management of machines and materials
Ms 05 management of machines and materialssmumbahelp
 
Project management 3rd sem - smu mba solved assignments
Project management  3rd   sem - smu mba solved assignmentsProject management  3rd   sem - smu mba solved assignments
Project management 3rd sem - smu mba solved assignmentssmumbahelp
 
Pm0011 project planning and scheduling
Pm0011  project planning and schedulingPm0011  project planning and scheduling
Pm0011 project planning and schedulingsmumbahelp
 
Pm0011 project planning and scheduling
Pm0011  project planning and schedulingPm0011  project planning and scheduling
Pm0011 project planning and schedulingStudy Stuff
 
Pm0015 quantitative methods in project management
Pm0015  quantitative methods in project managementPm0015  quantitative methods in project management
Pm0015 quantitative methods in project managementsmumbahelp
 
Pm0011 project planning and scheduling
Pm0011  project planning and schedulingPm0011  project planning and scheduling
Pm0011 project planning and schedulingsmumbahelp
 
How to Build a Business Case for ERP Replatforming
How to Build a Business Case for ERP ReplatformingHow to Build a Business Case for ERP Replatforming
How to Build a Business Case for ERP ReplatformingBlytheco
 
BUSN350Week 3 Business Problem and RequirementsBusiness.docx
BUSN350Week 3 Business Problem and RequirementsBusiness.docxBUSN350Week 3 Business Problem and RequirementsBusiness.docx
BUSN350Week 3 Business Problem and RequirementsBusiness.docxhumphrieskalyn
 
Ml0018 project management in retail
Ml0018  project management in retailMl0018  project management in retail
Ml0018 project management in retailsmumbahelp
 
Project Management MethodologiesPPMP20009Week 10 LectureDr.docx
Project Management MethodologiesPPMP20009Week 10 LectureDr.docxProject Management MethodologiesPPMP20009Week 10 LectureDr.docx
Project Management MethodologiesPPMP20009Week 10 LectureDr.docxbriancrawford30935
 
Smu mba sem 3 pm spring 2016 assignments
Smu mba sem 3 pm spring 2016 assignmentsSmu mba sem 3 pm spring 2016 assignments
Smu mba sem 3 pm spring 2016 assignmentssolved_assignments
 

Similaire à Pm0011 project planning and scheduling (20)

Pm0010 – interduction to project management
Pm0010 – interduction to project managementPm0010 – interduction to project management
Pm0010 – interduction to project management
 
Pearson HND BTEC Level 5 HNDManaging a Successful Business Pr.docx
Pearson HND BTEC Level 5 HNDManaging a Successful Business Pr.docxPearson HND BTEC Level 5 HNDManaging a Successful Business Pr.docx
Pearson HND BTEC Level 5 HNDManaging a Successful Business Pr.docx
 
Om0017 advanced production planning and control
Om0017   advanced production planning and controlOm0017   advanced production planning and control
Om0017 advanced production planning and control
 
Pm0011 project planning and scheduling
Pm0011 project planning and schedulingPm0011 project planning and scheduling
Pm0011 project planning and scheduling
 
Pm0011 project planning and scheduling
Pm0011 project planning and schedulingPm0011 project planning and scheduling
Pm0011 project planning and scheduling
 
Om0017 advanced production planning and control
Om0017   advanced production planning and controlOm0017   advanced production planning and control
Om0017 advanced production planning and control
 
Pm0011 project planning and scheduling
Pm0011  project planning and schedulingPm0011  project planning and scheduling
Pm0011 project planning and scheduling
 
Om0017 advanced production planning and control
Om0017   advanced production planning and controlOm0017   advanced production planning and control
Om0017 advanced production planning and control
 
Ms 05 management of machines and materials
Ms 05 management of machines and materialsMs 05 management of machines and materials
Ms 05 management of machines and materials
 
Project management 3rd sem - smu mba solved assignments
Project management  3rd   sem - smu mba solved assignmentsProject management  3rd   sem - smu mba solved assignments
Project management 3rd sem - smu mba solved assignments
 
Pm0011 project planning and scheduling
Pm0011  project planning and schedulingPm0011  project planning and scheduling
Pm0011 project planning and scheduling
 
Pm0011 project planning and scheduling
Pm0011  project planning and schedulingPm0011  project planning and scheduling
Pm0011 project planning and scheduling
 
Pm0015 quantitative methods in project management
Pm0015  quantitative methods in project managementPm0015  quantitative methods in project management
Pm0015 quantitative methods in project management
 
Pm0011 project planning and scheduling
Pm0011  project planning and schedulingPm0011  project planning and scheduling
Pm0011 project planning and scheduling
 
How to Build a Business Case for ERP Replatforming
How to Build a Business Case for ERP ReplatformingHow to Build a Business Case for ERP Replatforming
How to Build a Business Case for ERP Replatforming
 
Chap 2 Organization Strategy
Chap 2 Organization StrategyChap 2 Organization Strategy
Chap 2 Organization Strategy
 
BUSN350Week 3 Business Problem and RequirementsBusiness.docx
BUSN350Week 3 Business Problem and RequirementsBusiness.docxBUSN350Week 3 Business Problem and RequirementsBusiness.docx
BUSN350Week 3 Business Problem and RequirementsBusiness.docx
 
Ml0018 project management in retail
Ml0018  project management in retailMl0018  project management in retail
Ml0018 project management in retail
 
Project Management MethodologiesPPMP20009Week 10 LectureDr.docx
Project Management MethodologiesPPMP20009Week 10 LectureDr.docxProject Management MethodologiesPPMP20009Week 10 LectureDr.docx
Project Management MethodologiesPPMP20009Week 10 LectureDr.docx
 
Smu mba sem 3 pm spring 2016 assignments
Smu mba sem 3 pm spring 2016 assignmentsSmu mba sem 3 pm spring 2016 assignments
Smu mba sem 3 pm spring 2016 assignments
 

Dernier

Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...christianmathematics
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxVishalSingh1417
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...KokoStevan
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
An Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdfAn Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdfSanaAli374401
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingTeacherCyreneCayanan
 

Dernier (20)

Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
An Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdfAn Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdf
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 

Pm0011 project planning and scheduling

  • 1. Dear students get fully solved assignments Send your semester & Specialization name to our mail id : help.mbaassignments@gmail.com or call us at : 08263069601 Assignment DRIVE SRING 2016 PROGRAM MBADS (SEM 3/SEM 5)MBAFLEX/ MBA (SEM 3)PGDPMN(SEM 1) SUBJECT CODE & NAME PM0011 – PROJECT PLANNING ANDSCHEDULING BK ID B1937 CREDIT & MARKS 4 CREDITS & 60 MARKS Question. 1. Write short notes on: Hierarchy of organisational objectives Answer:Hierarchy of Objectives:The hierarchy of objectives is a tool that helps analyze and communicate the project objectives. It organizes these objectives into different levels of a hierarchy or tree. Different organizations use different names for the various levels and the types of objectives at each level,butotherwisethere isagreatdeal of similarityinapproach. Thisapproach organizesobjectivesintothreebroadlevels:  Policy Porter model a tool for identifying investment opportunities Answer:Michael Porter’s Five Forces is a model used to explore the environment in which a product or companyoperatestogenerate competitive advantage.
  • 2. Michael Porter (Harvard Business School Management Researcher) designed various vital frameworks for developinganorganization’s Design phase of project management life cycle Answer:Up to now, the project team and the client have focused on high-level questions regarding the project. These start with simple questions like "why is this solution important?," "what is the business value?" and "what are we going to deliver?" In the Design Phase, these questions are taken to a lower level of detail,andyoustart to askthe "how"questions.The bigone is"how will we buildthissolution?" At this point, the project team should have a complete set of requirements to work from, a set of direction-setting strategies and a Conceptual Systems Design. The design process comes next. Even if the projectwas small andthe requirementswere Question.2 Budget Estimation of ABC Company Ltd. ABC Company Ltd., established in 1985, is engaged in the manufacturing of leather accessories. Over the years, the company, which started out as a local firm,has made its mark as an international corporation. However,the company is still working as a traditional set up. The high quality and durability of products have increased the demand of the products in the market. As the production of the organisation is being increased to meet the demand, the traditional set up is creating hurdlesin the production process. Organisation conflicts have arisen among the team members because of the unorganised hierarchical structure of the company, which is affecting the output of the organisation. Now that the management has decided to expand the business and opened up branches abroad, the company is facing two more problems. The first problem is in budgeting as the company is unfamiliar with international market conditions, strategy, and business policy while the second problem is conflicts at the time of team formation due to lack ofexperience ofand exposure to multinational work culture,which has further affectedthe output of the company. The company can estimate the budget through two methods,the bottom - up approach and the top - down approach. The bottom -up approach is generally followed by the MNCs as it is more accurate and reliable. Mr.Parag has been appointed as the country head of the company and he has also been assigned the responsibilityofincorporatingthe advanced projectset up in the organisation. Questions: Which project estimation approach should be used by the company and why? Bottom-up estimating(alsocalleddetail or resource-drivenestimating)
  • 3. Bottom-up estimating is an extremely helpful technique in project management as it allows for the ability to get a more refined estimate of a particular component of work. In bottom-up estimating, each task is broken down into smaller components. Then, individual estimates are developed to determine what specifically is needed to meet the requirements of each of these smaller components of the work. The estimates for the smaller individual components are then aggregated to develop a larger estimate for the entire taskas a whole.Indoing Question.2. What type of project organisation structure should be used by the company and why? This is one of the main benefits of projectized organized structure, as they are adaptive and learn from theirownas well asfromothers’experiences. In projectized organizations, most of the resources are utilized in the project work. Projectized organizations are only interested in the project work which they get from external clients. Usually they have some small departmentssuchasAdmin, Question.3 What is the importance of operational feasibility? Explain the factors that affect operational feasibility. Answer:A feasibility study aims to objectively and rationally uncover the strengths and weaknesses of an existing business or proposed venture, opportunities and threats present in the environment, the resources required to carry through, and ultimately the prospects for success. In its simplest terms, the twocriteriato judge feasibilityare costrequiredandvalue tobe attained. A well-designed feasibility study should provide a historical background of the business or project, a descriptionof the productor service, Question.4. Write short notes on: Crashing Answer:It is the process by which duration of project is reduced by INCREASING the amount of RESOURCES allocated. It is important to note that crashing is done only to CRITICAL activities. This can be achievedbyanyof the followingapproaches: 1) Addressing productivity issues of the current resources and making them more efficient. This can be done bytakingbettercare of resourcesava
  • 4. Precedence diagramming method Answer:The precedence diagram method (PDM) is a tool for scheduling activities in a project plan. It is a method of constructing a project schedule network diagram that uses boxes, referred to as nodes, to represent activities and connects them with arrows that show the dependencies. It is also called the activity-on-node(AON) method.  Critical tasks, Resource allocation Answer:Resource allocation is the assignment of available resources to various uses. In the context of an entire economy, resources can be allocated by various means, such as markets or central planning. In project management, resource allocation or resource managementis the scheduling of activities and the resources required by those activities while taking into consideration both the resource availability and the projecttime. In economics,the areaof public Scope creep Answer:Scope creep (also called requirement creep, function creep and feature creep) in project management refers to uncontrolled changes or continuous growth in a project’s scope. This can occur when the scope of a project is not properly defined, documented, or controlled. It is generally consideredharmful. Question.5 What do you understand by cost of quality? Elaborate on various types of costs of quality associated with a project. Answer:In process improvement efforts, quality costs or cost of quality is a means to quantify the total cost of quality-relatedefforts and deficiencies. It was first described by Armand V. Feigenbaum in a 1956 Harvard BusinessReviewarticle.
  • 5. Prior to its introduction, the general perception was that higher quality requires higher costs, either by buying better materials or machines or by hiring more labor. Furthermore, while cost accounting had evolved to categorize financial transactions into revenues, expenses, and changes in shareholder equity, it had not attempted to categorize costs relevant to quality, which is especially important given that mostpeople involvedinmanufacturingneverset QUESTION 6. What do you understand by project scope? What are the various components ofproject scope? What is scope creep? Explain various reasons for scope creep. Answer: Scope creep can mean many things depending upon context so it is probably best that I start by explaining my definition. For the purposes of this article, scope creep is the process by which a project growsbeyonditsoriginallyanticipatedsize. I’d be willing to bet that most people who read that sentence are likely to conjure up images of unscrupulous clients seeking to take advantage of well-meaning service providers, but scope creep is more oftendownto misunderstandingthananythingelse. Dear students get fully solved assignments Send your semester & Specialization name to our mail id : help.mbaassignments@gmail.com or call us at : 08263069601