Tim Bryce THE 99% COMPLETE
SYNDROME
It is an undocumented fact that the last 1% of
anything takes longer than the other 99%.
There are plenty of examples to support this
argument, perhaps none quite as visible as the
progress bars we see on computers. You
know, those little bars telling you how you are
progressing in the installation of software or
the execution of a program. More often than
not, such progress bars seem to race through
the first 99% like a blazing track star, yet when
we get to that last 1% it seems to slow down to
a snail's pace.
I have also witnessed this same phenomenon
in project management situations. As we were
building our office in Florida our contractor
proudly proclaimed he was 99% complete and
we should prepare ourselves to move in.
Interestingly, that last 1% dragged on for days,
weeks, and even a few months, thereby
delaying inspections and prohibiting our move.
In the Information Technology field, it is
difficult to get a realistic picture of how much
work remains on a project. Programmers love
to announce they are 99% complete in writing
their programs, but somehow that last 1%
never seems to come to conclusion. Either
something was wrong in the design of their
software they hadn't anticipated, something
had changed, or gremlins had compounded
their best efforts. Regardless, the project never
ends.
This phenomenon is related to our perspective
on work, specifically, "Is the glass half empty
or half filled?" Instead of focusing on the work
completed, people should be more concerned
with the amount of effort remaining. For
example, instead of asking about percentages,
workers should be constantly evaluating the
amount of effort required to complete
remaining tasks in hours. Only after this is
known should we consider the application of
percentages, not before. Unfortunately, that is
not the mindset in most project environments.
Instead, people tend to consider the amount of
work expended against the original estimate,
not the remaining effort. This is certainly not a
realistic or reliable way of reporting progress.
It is pure fantasy.
Surprisingly, there are still quite a few project
management packages allowing people to post
percentages as opposed to automatically
calculating it based on the estimate of hours
remaining on project tasks which is simply
ludicrous.
So, next time you hear someone claim they are
99% complete with something, it means they still
have a long way to go and the person hasn't got a
clue when it will be completed, but it's
close...maybe. Ask yourself this, when was the last
time you saw the final two minutes of a football
game finish within 120 seconds? I've never seen it
either.
"The last 1% of a project can take as long as the
first 99%." - Bryce's Law
Keep the Faith!

Contenu connexe

Tendances

Synchronization - Election Algorithms
Synchronization  - Election AlgorithmsSynchronization  - Election Algorithms
Synchronization - Election Algorithms
OsaMa Hasan
 
Assignment problem branch and bound.pptx
Assignment problem branch and bound.pptxAssignment problem branch and bound.pptx
Assignment problem branch and bound.pptx
KrishnaVardhan50
 

Tendances (20)

Socket Programming
Socket ProgrammingSocket Programming
Socket Programming
 
Divide&Conquer & Dynamic Programming
Divide&Conquer & Dynamic ProgrammingDivide&Conquer & Dynamic Programming
Divide&Conquer & Dynamic Programming
 
Replication in Distributed Systems
Replication in Distributed SystemsReplication in Distributed Systems
Replication in Distributed Systems
 
Spm unit 3
Spm unit 3Spm unit 3
Spm unit 3
 
Software engineering project(srs)!!
Software engineering project(srs)!!Software engineering project(srs)!!
Software engineering project(srs)!!
 
Recursive Descent Parsing
Recursive Descent Parsing  Recursive Descent Parsing
Recursive Descent Parsing
 
Voice based email for blinds
Voice based email for blindsVoice based email for blinds
Voice based email for blinds
 
Synchronization - Election Algorithms
Synchronization  - Election AlgorithmsSynchronization  - Election Algorithms
Synchronization - Election Algorithms
 
Employee management system uml
Employee management system umlEmployee management system uml
Employee management system uml
 
Code optimization in compiler design
Code optimization in compiler designCode optimization in compiler design
Code optimization in compiler design
 
NLP_KASHK:Minimum Edit Distance
NLP_KASHK:Minimum Edit DistanceNLP_KASHK:Minimum Edit Distance
NLP_KASHK:Minimum Edit Distance
 
Assignment problem branch and bound.pptx
Assignment problem branch and bound.pptxAssignment problem branch and bound.pptx
Assignment problem branch and bound.pptx
 
Decision properties of reular languages
Decision properties of reular languagesDecision properties of reular languages
Decision properties of reular languages
 
Postfix Notation | Compiler design
Postfix Notation | Compiler designPostfix Notation | Compiler design
Postfix Notation | Compiler design
 
Phases of Compiler
Phases of CompilerPhases of Compiler
Phases of Compiler
 
Railway booking & management system
Railway booking & management systemRailway booking & management system
Railway booking & management system
 
Network security - OSI Security Architecture
Network security - OSI Security ArchitectureNetwork security - OSI Security Architecture
Network security - OSI Security Architecture
 
Weather Now
Weather NowWeather Now
Weather Now
 
Digital Forensics
Digital ForensicsDigital Forensics
Digital Forensics
 
Macro Processor
Macro ProcessorMacro Processor
Macro Processor
 

Similaire à 99 % syndrome

Paper mythical manmonth
Paper   mythical manmonthPaper   mythical manmonth
Paper mythical manmonth
Vu Hung Nguyen
 
Project portfolio management and what it means for your company
Project portfolio management and what it means for your companyProject portfolio management and what it means for your company
Project portfolio management and what it means for your company
williamsjohnseoexperts
 
How to Achieve Per-Project Profitability
How to Achieve Per-Project ProfitabilityHow to Achieve Per-Project Profitability
How to Achieve Per-Project Profitability
williamsjohnseoexperts
 
Pre production techniques - resubmission
Pre production techniques - resubmissionPre production techniques - resubmission
Pre production techniques - resubmission
RichardBurnn
 
Leesman Review Issue Leesman Review Issue 17
Leesman Review Issue Leesman Review Issue 17Leesman Review Issue Leesman Review Issue 17
Leesman Review Issue Leesman Review Issue 17
Paige Hodsman
 

Similaire à 99 % syndrome (20)

10 key points why a project fails
10 key points why a project fails10 key points why a project fails
10 key points why a project fails
 
Unseen
UnseenUnseen
Unseen
 
Paper mythical manmonth
Paper   mythical manmonthPaper   mythical manmonth
Paper mythical manmonth
 
Critical chain-concepts
Critical chain-conceptsCritical chain-concepts
Critical chain-concepts
 
Increasing The Probability Of Success For Your Project
Increasing The Probability Of Success For Your ProjectIncreasing The Probability Of Success For Your Project
Increasing The Probability Of Success For Your Project
 
Agile Coach Retreat @ Seedbox in Montreal - Sept. 7, 2013
Agile Coach Retreat @ Seedbox in Montreal - Sept. 7, 2013Agile Coach Retreat @ Seedbox in Montreal - Sept. 7, 2013
Agile Coach Retreat @ Seedbox in Montreal - Sept. 7, 2013
 
The Future of Project Management
The Future of Project ManagementThe Future of Project Management
The Future of Project Management
 
Tpma focus issue 13 (3 q2013)(1)
Tpma focus   issue 13 (3 q2013)(1)Tpma focus   issue 13 (3 q2013)(1)
Tpma focus issue 13 (3 q2013)(1)
 
201207 Tech Decisions: 5 Keys to Fast Successful New Deployments.pdf
201207 Tech Decisions: 5 Keys to Fast Successful New Deployments.pdf201207 Tech Decisions: 5 Keys to Fast Successful New Deployments.pdf
201207 Tech Decisions: 5 Keys to Fast Successful New Deployments.pdf
 
Working from Home - Should You Offer It?
Working from Home - Should You Offer It?Working from Home - Should You Offer It?
Working from Home - Should You Offer It?
 
Untitled
UntitledUntitled
Untitled
 
Project portfolio management and what it means for your company
Project portfolio management and what it means for your companyProject portfolio management and what it means for your company
Project portfolio management and what it means for your company
 
Full-Stack Agile - What's your Cycle Time?
Full-Stack Agile - What's your Cycle Time? Full-Stack Agile - What's your Cycle Time?
Full-Stack Agile - What's your Cycle Time?
 
Wait A Moment? How High Workload Kills Efficiency! - Roman Pickl
Wait A Moment? How High Workload Kills Efficiency! - Roman PicklWait A Moment? How High Workload Kills Efficiency! - Roman Pickl
Wait A Moment? How High Workload Kills Efficiency! - Roman Pickl
 
How to Achieve Per-Project Profitability
How to Achieve Per-Project ProfitabilityHow to Achieve Per-Project Profitability
How to Achieve Per-Project Profitability
 
Pre production techniques - resubmission
Pre production techniques - resubmissionPre production techniques - resubmission
Pre production techniques - resubmission
 
Software development project management
Software development project managementSoftware development project management
Software development project management
 
How to stay focused with task management software
How to stay focused with task management softwareHow to stay focused with task management software
How to stay focused with task management software
 
Leesman Review Issue Leesman Review Issue 17
Leesman Review Issue Leesman Review Issue 17Leesman Review Issue Leesman Review Issue 17
Leesman Review Issue Leesman Review Issue 17
 
Recession Survival Toolkit: Business Software to Stay Afloat
Recession Survival Toolkit: Business Software to Stay AfloatRecession Survival Toolkit: Business Software to Stay Afloat
Recession Survival Toolkit: Business Software to Stay Afloat
 

Plus de Sumit Malhotra (20)

Types of retailing done
Types of retailing doneTypes of retailing done
Types of retailing done
 
Retail communications done
Retail communications doneRetail communications done
Retail communications done
 
Retail
RetailRetail
Retail
 
Retail buying behaviour
Retail buying behaviourRetail buying behaviour
Retail buying behaviour
 
Merchandising
MerchandisingMerchandising
Merchandising
 
What does retailer do
What does retailer doWhat does retailer do
What does retailer do
 
Banking tools
Banking toolsBanking tools
Banking tools
 
Introduction to indian banking
Introduction to indian bankingIntroduction to indian banking
Introduction to indian banking
 
Debt recovery
Debt recoveryDebt recovery
Debt recovery
 
Bank
BankBank
Bank
 
Tata case
Tata caseTata case
Tata case
 
Project cycle
Project cycleProject cycle
Project cycle
 
Intro to ventures
Intro to venturesIntro to ventures
Intro to ventures
 
Dmaic model
Dmaic modelDmaic model
Dmaic model
 
Resistant to change 2 copy (1)
Resistant to change 2   copy (1)Resistant to change 2   copy (1)
Resistant to change 2 copy (1)
 
Location decision
Location decisionLocation decision
Location decision
 
Jit and lean operations
Jit and lean operationsJit and lean operations
Jit and lean operations
 
Introduction to pom
Introduction to pomIntroduction to pom
Introduction to pom
 
Product design
Product designProduct design
Product design
 
Viral
ViralViral
Viral
 

Dernier

Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Krashi Coaching
 

Dernier (20)

SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024
 

99 % syndrome

  • 1. http://project-management.alltop.com/ Tim Bryce THE 99% COMPLETE SYNDROME It is an undocumented fact that the last 1% of anything takes longer than the other 99%. There are plenty of examples to support this argument, perhaps none quite as visible as the progress bars we see on computers. You know, those little bars telling you how you are progressing in the installation of software or the execution of a program. More often than not, such progress bars seem to race through the first 99% like a blazing track star, yet when we get to that last 1% it seems to slow down to a snail's pace. I have also witnessed this same phenomenon in project management situations. As we were building our office in Florida our contractor proudly proclaimed he was 99% complete and we should prepare ourselves to move in. Interestingly, that last 1% dragged on for days, weeks, and even a few months, thereby delaying inspections and prohibiting our move.
  • 2. In the Information Technology field, it is difficult to get a realistic picture of how much work remains on a project. Programmers love to announce they are 99% complete in writing their programs, but somehow that last 1% never seems to come to conclusion. Either something was wrong in the design of their software they hadn't anticipated, something had changed, or gremlins had compounded their best efforts. Regardless, the project never ends. This phenomenon is related to our perspective on work, specifically, "Is the glass half empty or half filled?" Instead of focusing on the work completed, people should be more concerned with the amount of effort remaining. For example, instead of asking about percentages, workers should be constantly evaluating the amount of effort required to complete remaining tasks in hours. Only after this is known should we consider the application of percentages, not before. Unfortunately, that is not the mindset in most project environments. Instead, people tend to consider the amount of work expended against the original estimate, not the remaining effort. This is certainly not a realistic or reliable way of reporting progress. It is pure fantasy.
  • 3. Surprisingly, there are still quite a few project management packages allowing people to post percentages as opposed to automatically calculating it based on the estimate of hours remaining on project tasks which is simply ludicrous. So, next time you hear someone claim they are 99% complete with something, it means they still have a long way to go and the person hasn't got a clue when it will be completed, but it's close...maybe. Ask yourself this, when was the last time you saw the final two minutes of a football game finish within 120 seconds? I've never seen it either. "The last 1% of a project can take as long as the first 99%." - Bryce's Law Keep the Faith!