1. Claudio G. Casati
PIANIFICAZIONE PROGETTI
PROJECT PLANNING
Parte 4 di 4
Logica di progetto, Diagramma di Gantt, Project Baseline
Gennaio 2011
2. Metodologie
PMI PMBOK - Project Management Body of
Knowledge
Internationally recognised standard
Application of knowledge, skills, tools & techniques,
processes
IPMA Competence Baseline – ICB
the world’s leading certification program
a major role in the promotion and progress of project
management
PRINCE 2 - PRoject IN a Controlled
Environment 2nd edition (UK Gov.)
• International best practice in project management
• Process based project management methodology
2
3. Contenuti
Network - Logica di progetto
Diagramma di Gantt
Project Baseline
Metodologia di riferimento PMI PMBOK Guide
3
4. The Essence of PMBOK® Guide
5 Project Management Process Groups
Monitoring and
Initiating Planning Executing Controlling Closing
Process Group Process Group Process Group Process Group Process Group
9 Knowledge Areas Processes
Project Integration Project Scope Project Time Project Cost Project Quality
Management Management Management Management Management
Project Human Project Project
Project Risk
Resource Communications Procurement
Management
Management Management Management
4
5. Citazione
Vengono utilizzati materiali tratti dai corsi:
MIT OpenCourseWare | Sloan School of Management |
ESD.36J/1.432J System & Project Management, Fall 2003 |
1.040/1.401J/ESD.018J Project Management, Spring 2004 |
Prof. Prof. Olivier de Weck, Prof. Steven Eppinger, Prof. James Lyneis,
course materials for ESD.36J/1.432J System & Project Management,
Fall 2003, MIT OpenCourseWare (http://ocw.mit.edu), Massachusetts
Institute of Technology. Downloaded on 29 October 2005.
Dr. Nathaniel Osgood, course materials for 1.040/1.401J/ESD.018J
Project Management, Spring 2004, MIT OpenCourseWare
(http://ocw.mit.edu), Massachusetts Institute of Technology.
Downloaded on 29 October 2005.
5
7. Pianificazione Progetto
1 : WBS - Cosa si deve fare ? 2 : OBS Struttura di Progetto
1
3 : RAM – Assegnazione responsabilità
1.1 1.2 1.3
WBS - Cena di gala
1.1.1 1.1.2 1.1.3 1.2.1 1.2.2 1.2.3 1.2.4 1.3.1 1.3.2
Organizzazione Acquisti Preparazione
Inviti Scelta sala Scelta menù Personale Cibi Bevande Vettovaglie Fiori Sala Cucina Cottura Servizio
4 : Network – Logica di progetto Resp. Progetto
Dott. Galante
Segreteria
Sig.a Salvi
Ufficio P.R.
D.ssa Paoli
Squadra Cucina
1° Chef
Ufficio Servizi
Sig. Ulivi
Impresa di Trasporto
Squadra Camerieri
BASELINE
5 : Diagramma di Gantt 6 : Piano delle risorse 7 : Piano dei costi
Attività 1
Attività 2
Attività 3
Attività 4
Attività 5
7
8. Project Network
A project network is a graph (flow chart) depicting
the sequence in which a project's terminal elements
are to be completed by showing terminal elements
and their Product Breakdown Structure show the
"part-whole" relations. In contrast, the Project
Network shows the "before-after" relations.
The most popular form of project network is activity
on node, the other one is activity on arrow.
The condition for a valid project network is that it
doesn't contain any circular references.
8
9. Predecessor Table & DSM
The activity network diagram technique emerged as the
Program Evaluation Research Technique (PERT) and as
the Critical Path Method (CPM) in the 1950s. There are
several ways to represent the output of the PERT/CPM
process.
Project dependencies can also be depicted by a
Predecessor Table.
An alternative way of showing and analyzing the
sequence of project work is DSM * (Design Structure
Matrix).
* MIT OCW: ESD.36J / 1.432J System and Project
Management
9
10. Logic network and Planning
The logic network, also refereed to as precedence
diagraming, is the basic management tool for
controlling, monitoring, and distributing all resources
that are directly related to time.
The logic network at the planning stage is a pure
dependency diagram. All activities are drawn in the
order in which they must be accomplished without
regard to particular construction preference.
One of the major uses of the logic network during
the planning stage is to indicate all activities that must
be accomplished to complete a particular project.
As a general rule, an activity should be created for
any function that consumes or uses direct labor
resources.
10
11. Costruzione Box:
Network Diagram
Scelta
modello (1g)
Acquisto Costruzione Controllo
Materiali (1g) Base (3g) Gettata (2g)
Preparazione Assemblaggio
Legno (2g) (3g)
Collaudo
Box (1g)
11
12. Costruzione Box:
Predecessor Table
Durata
# Attività Predecessore
in giorni
1 Inizio Progetto Box 0
2 Scelta modello Box 1 1
3 Acquisto Materiali 1 2
4 Costruzione Base 3 3
5 Controllo Gettata 2 4
6 Preparazione Legno 2 3
7 Assemblaggio 3 5, 6
8 Collaudo Box 1 7
9 Fine Progetto Box 0 8
12
14. Pianificazione Progetto
1 : WBS - Cosa si deve fare ? 2 : OBS Struttura di Progetto
1
3 : RAM – Assegnazione responsabilità
1.1 1.2 1.3
WBS - Cena di gala
1.1.1 1.1.2 1.1.3 1.2.1 1.2.2 1.2.3 1.2.4 1.3.1 1.3.2
Organizzazione Acquisti Preparazione
Inviti Scelta sala Scelta menù Personale Cibi Bevande Vettovaglie Fiori Sala Cucina Cottura Servizio
4 : Network – Logica di progetto Resp. Progetto
Dott. Galante
Segreteria
Sig.a Salvi
Ufficio P.R.
D.ssa Paoli
Squadra Cucina
1° Chef
Ufficio Servizi
Sig. Ulivi
Impresa di Trasporto
Squadra Camerieri
BASELINE
5 : Diagramma di Gantt 6 : Piano delle risorse 7 : Piano dei costi
Attività 1
Attività 2
Attività 3
Attività 4
Attività 5
14
15. Diagramma di Gantt
Periodo
Attuale
Attività Gen Feb Mar Apr Mag Giu Lug Ago
Inizio Progetto
Attività 1
Attività 2
Attività 3
Attività 4
P&C Progetto
Fine Progetto
15
17. Diagramma di Gantt
A popular bar chart that aims to show the timing of tasks or
activities as they occur across time.
Although the Gantt chart did
not initially show the relation-
ships between activities, this
has become more common in
current use as both timing and
interdependencies between
tasks can be identified.
17
18. Pianificazione Pietre Miliari
Pietre Inizio
miliari Progetto
Milestone
A key event during the
life of a project, usually
completing project
deliverables or other
noteworthy achievement.
Obiettivo
Progetto
18
20. Relazione tra attività
Per avere la massima rispondenza con la modellazione
dei processi le relazioni di interdipendenza temporali
sono:
Le relazioni sono ulteriormente modificabili con
l’introduzione di ritardi, o anticipi, rispetto al
predecessore.
20
21. Costruzione Box:
WBS
Costruzione Box
PM
Scelta Acquisto Preparaz Preparaz Assem-
Collaudo
Modello Materiali Base Legno blaggio
Costruz Controllo
Base Gettata
21
22. Costruzione Box: Grafo di
Progetto - Network Diagram
Scelta
modello (1g)
Acquisto Costruzione Controllo
Materiali (1g) Base (3g) Gettata (2g)
Preparazione Assemblaggio
Legno (2g) (3g)
Collaudo
Box (1g)
22
23. Percorso critico/
Critical Path
The critical path is the sequence of activities that must be
completed on time for the entire project to be completed
on schedule.
It is the longest duration path through the workplan.
If an activity on the critical path is delayed by one day, the
entire project will be delayed by one day unless another
activity on the critical path can be finished a day earlier
than planned.
23
24. Costruzione Box:
Cammino Critico
Scelta
modello (1g)
Acquisto Costruzione Controllo
Materiali (1g) Base (3g) Gettata (2g)
Preparazione Assemblaggio
Legno (2g) (3g)
Collaudo
Box (1g)
24
27. Project Baseline
A baseline is an approved configuration item, for
example a project plan that has been signed off for
execution.
The baseline records the schedule, the planned
resources, the planned costs, and technical requirements
against which a project is measured. Data including:
Tasks: Duration, Start and Finish dates, work,
timephased work, cost and timephased cost.
Resources: Work, timephased work, cost, timephased
cost, budget work, timephased budget work, budget
cost and timephased budget cost.
27