SlideShare une entreprise Scribd logo
1  sur  25
1
PREPARED BY : ASST. PROF. VATSAL D. PATEL
MAHATMA GANDHI INSTITUTE OF
TECHNICAL EDUCATION &
RESEARCH CENTRE, NAVSARI.
Cofferdams are temporary enclosures to keep out water and soil so as to permit
dewatering and construction of the permanent facility (structure) in the dry.
A Coffer Dam is a temporary structure designed tokeep water and /or soil out of
the excavation in which a bridge pier or other structure is built.
Meaning of Coffer Dam : Coffer = Box
Totake up the Foundation works in the Marine Region, it is necessary to
obstruct the water flow by means of Coffer Dam.
To retain Soil & Water
Can be used as either Temporary or Permanent
Main purpose is to provide dry working area for workers
It is constructed to facilitate pile driving operations.
It is used to place grillage as well as the raft foundations
It is used ,when the foundations for piers and abutments of a bridge,
dams, locks, etc. are to be constructed.
Some times it is also provided to store water temporarily.
Cofferdams can be used in all the sectors as explained below.
Civil Engineering: Underground Car Parking, Foundation, Basement Construction
Transport Engineering: Bridge Pier, Support Walls, Ramps, Ground Water
Retention, Tunnel Work etc.
Water Engineering: Weirs, Culverts, Flood Protection Walls, Scour Protection
Walls, Securing Embankment etc
Port Construction: Dock Works, Jetty Works etc.
1. Low heads of water – earth fill cofferdams
2. Narrow Excavations – single wall sheet pile cofferdams otherwise double
wall cofferdams or cellular sheet piling are suitable for wide excavations
3. The materials available at site of work for construction
4. The possibility of overtopping by floods, tides, etc. and sliding – rock filled crib
cofferdams.
5. The nature of bed on which the cofferdam is to rest – deep deposits of soft clay,
A heavy earth filled crib or cellular cofferdam could not be suitable but single
wall sheet pile would be required in these conditions.
6. The nature of velocity of flow, i.e. water flowing with slow current or with swift
current
7. The chances of bed erosion due to reduction of water way caused by the
construction of a cofferdam.
8. The facilities available for the transport of equipment and material required for
the construction of a cofferdam.
1. Earth fill cofferdams - mainly for low level water
2. Sand Bag Coffer Dam – to divert coarse of water
3. Rock fill cofferdams
4. Timber Crib or rock filled crib cofferdams - Construction on land and than
floated into place, which is also known as Gravity Dam
5. Braced / Sheet Pile Coffer Dam- Consisting of Sheet Piles, mainly used in shallow
water depth
(i). Single wall coffer dams (ii). Double wall coffer
dams (iii). Cellular cofferdams
6. Movable or suspended cofferdams
Suitable for rivers or streams having shallow depth of water, about 120 to 150 cm,
with low velocity of flow
 It is the simplest type of cofferdam.
 Free board – 60 to 90cm
 Top width of earth dyke – onemeter
 Suitable side slope should be provided
 Provided suitabledrain
 Its depends on soil availability and siteconditions.
 Dry conditions – clay embankmentprovided
 Wet condition – sand materialssuitable
The construction of rock fill cofferdams is similar to earth fill dams
 It can be constructed with steeper slopes
 Water depths – 3m.
 In case of high heads of water , this can be achieved by a clay or concrete care
wall
 Impervious layer provided(concrete or clay core wall or sheet pile ) for reducing
entry of seepage
It consists of timber cribs made from logs ofwood
 Constructed on land and floated intoplace
 It consists of a unit or a cell open at the bottom and having the framework of
horizontal timber members.
 Hollow space thus formed are then filled with rock or gravel
 Depth of water – 10 to 20m
 Used for wide excavation and rocky river bottoms
1. Single wall cofferdams
-it used in places, where the area to be enclosed is very
small
-depth of water is more = 4.5 to 6 m
- A single row of sheet piles is provided on the whole length of the cofferdam
- Guide piles, Wales and struts (wood)
- guide piles are first driven deep in the river bed and spacing between
them 1.8 to 3.0 m
- The sand bags are stacked on the inside and outside faces
of the sheet to increase the stability of cofferdam
2. Double wall cofferdams
- when the area to be enclosed is large it is necessary to provide double wall
cofferdam
- The double wall cofferdams are of two types:
(i) Ohio – river type cofferdams
(ii) timber or steel sheeting cofferdams
3. Cellular Cofferdams
- The cellular cofferdams are mostly used for dewatering large areas , where the
depth of water may be 19 to 21 m.
-Mostly used the constuction of marine structures like Dams ,Locks etc.
- The two common shapes of the cellular cofferdam are:
(i) Circular type
(ii) Diaphragm type
CIRCULAR TYPE
DIAPHRAGM TYPE
Where there are numbers of repetition work in under water foundations ,such as in
the piers of multi span river bridges, it is economical to design the cofferdams to
be moved as a single unit from one foundation to another.
The design of a cofferdam depends on various factors such as:
(1)Hydrostatic head of Water
(2)Dimensions of the area to be covered by coffer dam
(3)Subsoil condition
(4)Fluctuations or of outside water level
(5)Possibility of erosion
(6)Presence of ice
(7)Floating logs (the stem of cut-down tree etc.)
 A purely theoretically designed cofferdam may fail for factors unaccounted in
its design.
Therefore ,become necessary to combine practical knowledge or experience with
the theoretical aspects in the design of a cofferdam.
For width and Depth of cofferdam : for H < 3 m, W = W
H > 3, W = 3 + ½*(H-3)
Where, W = Width of cofferdam in
metres
H = Height of water above river bed in metres
1.Driving of Guide Frame
2.Lowering of Sheet Pile
3. Driving of Sheet Pile
4.Horizontal Bracing (Waller & Strut arrangement) to withstand the load coming on
sheet piles from outside.
5.Excavation and Plug in Concrete to resist uplift pressure
6.Reinforcement and Concrete work of the Permanent Structure
Factors governing the Economic Height of Coffer Dam
1.Depth of Water
- Low depth => Earthen Dam
- High Depth => Sheet Pile Coffer Dam
2.Current and nature of flowering of Sheet Pile
- High Current => Sheet Pile Coffer Dam (Higher Seepage Control
Capacity)
- Low Current => Earthen or any other Dam (Less Seepage Control
Capacity)
3.Type and Period of Work
- Short Duration Work => Timber Dam
- Long Duration work => Sheet Pile Coffer Dam
4.High and Low Tide Level of Reservoir
- Sheet Pile must have top level slightly higher than that of the HTL. So
that even in extreme case water can not over top the coffer dam, to
achieve the dry working through out the season.
5. Scour Level of Reservoir
- Scour level can be considered as the bottom most layer of the loose soil of river
Bed Level.
- Up to Scour level there are chances of erosion due to the current of water. In
any Pile or Well foundation, the care to be taken that the founding level must be
below the scour water level
6. Type of Material to be used
- Structural Sheet pile is costly but can be reused at different projects.
(i) Diaphragm type
25

Contenu connexe

Tendances

Tendances (20)

Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
 
types of coffer dam
types of coffer dam types of coffer dam
types of coffer dam
 
Caissons
Caissons Caissons
Caissons
 
Arch and Buttress Dams
Arch and Buttress DamsArch and Buttress Dams
Arch and Buttress Dams
 
Well foundation ppt
Well foundation pptWell foundation ppt
Well foundation ppt
 
introduction to a bridge foundation
introduction to a bridge foundationintroduction to a bridge foundation
introduction to a bridge foundation
 
CABLE ANCHORING AND GROUTING / Diaphragm Walls
CABLE ANCHORING AND GROUTING / Diaphragm Walls CABLE ANCHORING AND GROUTING / Diaphragm Walls
CABLE ANCHORING AND GROUTING / Diaphragm Walls
 
Well foundation
Well foundationWell foundation
Well foundation
 
Gallery in Concrete Gravity Dam
Gallery in Concrete Gravity DamGallery in Concrete Gravity Dam
Gallery in Concrete Gravity Dam
 
Different types of pile
Different types of pile Different types of pile
Different types of pile
 
Bridge
BridgeBridge
Bridge
 
TYPES OF PILE FOUNDATION & APPLICATIONS
TYPES OF PILE FOUNDATION & APPLICATIONSTYPES OF PILE FOUNDATION & APPLICATIONS
TYPES OF PILE FOUNDATION & APPLICATIONS
 
Retaining wall
 Retaining wall  Retaining wall
Retaining wall
 
Formwork
FormworkFormwork
Formwork
 
Diversion Headworks
Diversion HeadworksDiversion Headworks
Diversion Headworks
 
Gravity Dam
Gravity DamGravity Dam
Gravity Dam
 
CANAL REGULATIONS
CANAL REGULATIONSCANAL REGULATIONS
CANAL REGULATIONS
 
Embankment lecture 1
Embankment lecture 1Embankment lecture 1
Embankment lecture 1
 
Force acting on gravity dam
Force acting on gravity damForce acting on gravity dam
Force acting on gravity dam
 
Diaphragm wall
Diaphragm wallDiaphragm wall
Diaphragm wall
 

Similaire à 4. COFFERDAM (ACE) 2160601 GTU

cofferdam-150424121052-conversion-gate01.pptx
cofferdam-150424121052-conversion-gate01.pptxcofferdam-150424121052-conversion-gate01.pptx
cofferdam-150424121052-conversion-gate01.pptx
ssuser23e4af
 

Similaire à 4. COFFERDAM (ACE) 2160601 GTU (20)

cofferdam-150424121052-conversion-gate01.pptx
cofferdam-150424121052-conversion-gate01.pptxcofferdam-150424121052-conversion-gate01.pptx
cofferdam-150424121052-conversion-gate01.pptx
 
BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)
 
Cofferdam_ppt.pptx
Cofferdam_ppt.pptxCofferdam_ppt.pptx
Cofferdam_ppt.pptx
 
Chapter 2 coffer-dam
Chapter 2 coffer-damChapter 2 coffer-dam
Chapter 2 coffer-dam
 
Reservoir Planning
Reservoir PlanningReservoir Planning
Reservoir Planning
 
Introduction to Dams.pptx
Introduction to Dams.pptxIntroduction to Dams.pptx
Introduction to Dams.pptx
 
Earthen dam
Earthen damEarthen dam
Earthen dam
 
Notes on introduction and design of caissons
Notes on introduction and design of caissonsNotes on introduction and design of caissons
Notes on introduction and design of caissons
 
Earthen dam
Earthen damEarthen dam
Earthen dam
 
Dams
DamsDams
Dams
 
Dams
DamsDams
Dams
 
OK
OKOK
OK
 
Lesson4
Lesson4Lesson4
Lesson4
 
First assignment group (2) presentation.pdf
First assignment group (2) presentation.pdfFirst assignment group (2) presentation.pdf
First assignment group (2) presentation.pdf
 
Earthen Dams
Earthen DamsEarthen Dams
Earthen Dams
 
underwater consruction VIII sem MMBC.pptx
underwater consruction VIII sem MMBC.pptxunderwater consruction VIII sem MMBC.pptx
underwater consruction VIII sem MMBC.pptx
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
 
Design consideration Of Earth Dams
Design consideration Of Earth DamsDesign consideration Of Earth Dams
Design consideration Of Earth Dams
 
Cofferdams_Advanced Construction Technology
Cofferdams_Advanced Construction TechnologyCofferdams_Advanced Construction Technology
Cofferdams_Advanced Construction Technology
 
Cofferdam
CofferdamCofferdam
Cofferdam
 

Plus de VATSAL PATEL

Plus de VATSAL PATEL (20)

5. AIR TRANSPORTATION (TRE) GTU 3150611
5. AIR TRANSPORTATION (TRE) GTU 31506115. AIR TRANSPORTATION (TRE) GTU 3150611
5. AIR TRANSPORTATION (TRE) GTU 3150611
 
3. RAIL TRANSPORTATION (TRE) GTU 3150611
3. RAIL TRANSPORTATION (TRE) GTU 31506113. RAIL TRANSPORTATION (TRE) GTU 3150611
3. RAIL TRANSPORTATION (TRE) GTU 3150611
 
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
 
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
 
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
 
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
 
2. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 31706232. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 3170623
 
4. WATER TRANSPORTATION (TRE) GTU 3150611
4. WATER TRANSPORTATION (TRE) GTU 31506114. WATER TRANSPORTATION (TRE) GTU 3150611
4. WATER TRANSPORTATION (TRE) GTU 3150611
 
8. IMPACT ANALYSIS (PHE) GTU 3170623
8. IMPACT ANALYSIS (PHE) GTU 31706238. IMPACT ANALYSIS (PHE) GTU 3170623
8. IMPACT ANALYSIS (PHE) GTU 3170623
 
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
 
7. SEAPORT MAINTENANCE (PHE) GTU 3170623
7. SEAPORT MAINTENANCE (PHE) GTU 31706237. SEAPORT MAINTENANCE (PHE) GTU 3170623
7. SEAPORT MAINTENANCE (PHE) GTU 3170623
 
6. NAVIGATIONAL AIDS (PHE) GTU 3170623
6. NAVIGATIONAL AIDS (PHE) GTU 31706236. NAVIGATIONAL AIDS (PHE) GTU 3170623
6. NAVIGATIONAL AIDS (PHE) GTU 3170623
 
5. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
5. PORT AMENITIES & OPERATIONS (PHE) GTU 31706235. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
5. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
 
4. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
4. HARBOUR INFRASTRUCTURES (PHE) GTU 31706234. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
4. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
 
3. NATURAL PHENOMENA (PHE) GTU 3170623
3. NATURAL PHENOMENA (PHE) GTU 31706233. NATURAL PHENOMENA (PHE) GTU 3170623
3. NATURAL PHENOMENA (PHE) GTU 3170623
 
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
 
1. INTRODUCTION TO WATER TRANSPORTATION (PHE) GTU 3170623
1. INTRODUCTION  TO WATER TRANSPORTATION (PHE) GTU 31706231. INTRODUCTION  TO WATER TRANSPORTATION (PHE) GTU 3170623
1. INTRODUCTION TO WATER TRANSPORTATION (PHE) GTU 3170623
 
2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU
2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU
2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU
 
1. INTRODUCTION (TRE) 3150611 GTU
1. INTRODUCTION (TRE) 3150611 GTU1. INTRODUCTION (TRE) 3150611 GTU
1. INTRODUCTION (TRE) 3150611 GTU
 
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU
 

Dernier

AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 

Dernier (20)

Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 

4. COFFERDAM (ACE) 2160601 GTU

  • 1. 1 PREPARED BY : ASST. PROF. VATSAL D. PATEL MAHATMA GANDHI INSTITUTE OF TECHNICAL EDUCATION & RESEARCH CENTRE, NAVSARI.
  • 2. Cofferdams are temporary enclosures to keep out water and soil so as to permit dewatering and construction of the permanent facility (structure) in the dry. A Coffer Dam is a temporary structure designed tokeep water and /or soil out of the excavation in which a bridge pier or other structure is built. Meaning of Coffer Dam : Coffer = Box Totake up the Foundation works in the Marine Region, it is necessary to obstruct the water flow by means of Coffer Dam.
  • 3. To retain Soil & Water Can be used as either Temporary or Permanent Main purpose is to provide dry working area for workers It is constructed to facilitate pile driving operations. It is used to place grillage as well as the raft foundations It is used ,when the foundations for piers and abutments of a bridge, dams, locks, etc. are to be constructed. Some times it is also provided to store water temporarily.
  • 4. Cofferdams can be used in all the sectors as explained below. Civil Engineering: Underground Car Parking, Foundation, Basement Construction Transport Engineering: Bridge Pier, Support Walls, Ramps, Ground Water Retention, Tunnel Work etc. Water Engineering: Weirs, Culverts, Flood Protection Walls, Scour Protection Walls, Securing Embankment etc Port Construction: Dock Works, Jetty Works etc.
  • 5. 1. Low heads of water – earth fill cofferdams 2. Narrow Excavations – single wall sheet pile cofferdams otherwise double wall cofferdams or cellular sheet piling are suitable for wide excavations 3. The materials available at site of work for construction 4. The possibility of overtopping by floods, tides, etc. and sliding – rock filled crib cofferdams. 5. The nature of bed on which the cofferdam is to rest – deep deposits of soft clay, A heavy earth filled crib or cellular cofferdam could not be suitable but single wall sheet pile would be required in these conditions. 6. The nature of velocity of flow, i.e. water flowing with slow current or with swift current 7. The chances of bed erosion due to reduction of water way caused by the construction of a cofferdam. 8. The facilities available for the transport of equipment and material required for the construction of a cofferdam.
  • 6. 1. Earth fill cofferdams - mainly for low level water 2. Sand Bag Coffer Dam – to divert coarse of water 3. Rock fill cofferdams 4. Timber Crib or rock filled crib cofferdams - Construction on land and than floated into place, which is also known as Gravity Dam 5. Braced / Sheet Pile Coffer Dam- Consisting of Sheet Piles, mainly used in shallow water depth (i). Single wall coffer dams (ii). Double wall coffer dams (iii). Cellular cofferdams 6. Movable or suspended cofferdams
  • 7. Suitable for rivers or streams having shallow depth of water, about 120 to 150 cm, with low velocity of flow  It is the simplest type of cofferdam.  Free board – 60 to 90cm  Top width of earth dyke – onemeter  Suitable side slope should be provided  Provided suitabledrain  Its depends on soil availability and siteconditions.  Dry conditions – clay embankmentprovided  Wet condition – sand materialssuitable
  • 8. The construction of rock fill cofferdams is similar to earth fill dams  It can be constructed with steeper slopes  Water depths – 3m.  In case of high heads of water , this can be achieved by a clay or concrete care wall  Impervious layer provided(concrete or clay core wall or sheet pile ) for reducing entry of seepage
  • 9. It consists of timber cribs made from logs ofwood  Constructed on land and floated intoplace  It consists of a unit or a cell open at the bottom and having the framework of horizontal timber members.  Hollow space thus formed are then filled with rock or gravel  Depth of water – 10 to 20m  Used for wide excavation and rocky river bottoms
  • 10. 1. Single wall cofferdams -it used in places, where the area to be enclosed is very small -depth of water is more = 4.5 to 6 m - A single row of sheet piles is provided on the whole length of the cofferdam - Guide piles, Wales and struts (wood) - guide piles are first driven deep in the river bed and spacing between them 1.8 to 3.0 m - The sand bags are stacked on the inside and outside faces of the sheet to increase the stability of cofferdam
  • 11.
  • 12. 2. Double wall cofferdams - when the area to be enclosed is large it is necessary to provide double wall cofferdam - The double wall cofferdams are of two types: (i) Ohio – river type cofferdams (ii) timber or steel sheeting cofferdams
  • 13. 3. Cellular Cofferdams - The cellular cofferdams are mostly used for dewatering large areas , where the depth of water may be 19 to 21 m. -Mostly used the constuction of marine structures like Dams ,Locks etc. - The two common shapes of the cellular cofferdam are: (i) Circular type (ii) Diaphragm type
  • 16. Where there are numbers of repetition work in under water foundations ,such as in the piers of multi span river bridges, it is economical to design the cofferdams to be moved as a single unit from one foundation to another.
  • 17. The design of a cofferdam depends on various factors such as: (1)Hydrostatic head of Water (2)Dimensions of the area to be covered by coffer dam (3)Subsoil condition (4)Fluctuations or of outside water level (5)Possibility of erosion (6)Presence of ice (7)Floating logs (the stem of cut-down tree etc.)
  • 18.  A purely theoretically designed cofferdam may fail for factors unaccounted in its design. Therefore ,become necessary to combine practical knowledge or experience with the theoretical aspects in the design of a cofferdam. For width and Depth of cofferdam : for H < 3 m, W = W H > 3, W = 3 + ½*(H-3) Where, W = Width of cofferdam in metres H = Height of water above river bed in metres
  • 19. 1.Driving of Guide Frame 2.Lowering of Sheet Pile 3. Driving of Sheet Pile 4.Horizontal Bracing (Waller & Strut arrangement) to withstand the load coming on sheet piles from outside. 5.Excavation and Plug in Concrete to resist uplift pressure 6.Reinforcement and Concrete work of the Permanent Structure
  • 20. Factors governing the Economic Height of Coffer Dam 1.Depth of Water - Low depth => Earthen Dam - High Depth => Sheet Pile Coffer Dam 2.Current and nature of flowering of Sheet Pile - High Current => Sheet Pile Coffer Dam (Higher Seepage Control Capacity) - Low Current => Earthen or any other Dam (Less Seepage Control Capacity) 3.Type and Period of Work - Short Duration Work => Timber Dam - Long Duration work => Sheet Pile Coffer Dam 4.High and Low Tide Level of Reservoir - Sheet Pile must have top level slightly higher than that of the HTL. So that even in extreme case water can not over top the coffer dam, to achieve the dry working through out the season.
  • 21. 5. Scour Level of Reservoir - Scour level can be considered as the bottom most layer of the loose soil of river Bed Level. - Up to Scour level there are chances of erosion due to the current of water. In any Pile or Well foundation, the care to be taken that the founding level must be below the scour water level 6. Type of Material to be used - Structural Sheet pile is costly but can be reused at different projects.
  • 22.
  • 23.
  • 25. 25