Manpower, equipment, and materials are 
important project resources that require 
management attention. 
The basic objective of resource planning and 
resource allocation is to supply and support 
the field operations. 
The term resource allocation is used in the 
case where required resources are assigned 
such that available resources are not 
exceeded. 
2
Resources are the means of production 
needed to complete a project. 
Most project managers would consider the 
big three resources that will require your 
attention to be: 
• Material 
• Labor 
• Equipment 
3
A. LABOUR 
a. In the limited resource allocation case, there 
are two assumptions: 
(1) There are a fixed number of crews available 
to perform the work and 
(2) The project may be delayed as a result of 
the limitation of crews. 
The objective of the resource allocation 
problem is to determine when the project will 
be completed. 
4
b. In the unlimited resource leveling case, there 
are two assumptions: 
(1) There are an unlimited number of crews 
available to perform the work and 
(2) The project may not be delayed. 
The objective of the resource leveling 
problem is to determine how to limit the 
fluctuation in crews required on the job. 
5
B. MATERIALS 
Materials, for projects with sufficient on-site 
storage, are delivered to the site and assumed 
to be available to workers as needed. 
A material-related concern for sites that have 
sufficient space is that of optimizing the position 
of materials on the site so that they require the 
least travel time from the lay-down yard to the 
work-face. 
6
C. EQUIPMENTS 
There are various types of equipment used on 
construction sites. 
Some of this equipment should be considered in 
the project plan, some need not be included. 
Workers, and their companies, are typically 
required to provide the small tools needed to 
complete their specific features of work. 
There are some types of equipment, however, that 
can affect the overall sequence and duration of the 
project. 
7
Resource allocation is used to assign the 
available resources in an economic way. 
It is part of resource management. 
In project management, resource allocation 
is the scheduling of activities and the 
resources required by those activities while 
taking into consideration both the resource 
availability and the project time. 
8
Resource planning cannot be accomplished 
without four essential resources necessary 
to accomplish the given scope of work: 
• MATERIAL 
• MAN POWER 
• MACHINARY 
• TIME 
9
Human resources for construction planning 
breaks down into three major categories as 
follows: 
• Home office personnel(Administrative 
Persons) 
• Construction personnel (field supervision 
and labor) 
• Construction subcontractors(Electrification, 
Plumbing, etc) 
10
The ideal form of a personnel loading curves 
is a trapezoid. 
The average personnel loading curve is a 
straight line. 
Actual practice loading curves take the 
shape of a bell curve 
11
12
The latter two result when the personnel 
loading curves occur earlier or later than 
planned on a project. 
Front loaded curve- the work started as early 
as possible. 
Normal loaded curve- the work started at 
normal time. 
Back loaded curve- the work started as late 
as possible. 
13
The "S" curve for the ideally loaded project has 
a gradual start and finish, which indicates 
smooth starting and finishing conditions. 
The forward loaded curve shows a rapid project 
start up and an even more gradual than normal 
phase out at the end. 
The backward-loaded project indicates a more 
relaxed start and a very steep finish slope on 
the "S" curve. 
14
15
16
Ensuring that the material resources for the 
project arrive on time involves these 
important planning areas: 
• Long-delivery equipment 
• Special materials and alloys 
• Common materials in short supply 
• Services and system requirements 
• Transportation systems 
17
Resource Limited: The project must be finished as 
soon as possible, but without exceeding some 
specific level of resource usage or some general 
resource constraint 
18
1. When the schedule demands more workers 
per day than are available or if we have 
workers standing around without jobs, we 
have a problem. 
2. When a new hire is trained, there is loss of 
productivity. So, if we can keep the trained 
people and reduce the number of new hires, 
we should be better off. 
19
. As we know, every project suffers from start-up 
problems of some sort. Superintendents and 
project managers are very busy trying to get 
everybody working in a productivity manner. 
Therefore, if we can start with a small crew and 
increase its size gradually, we will eliminate some 
of the start-up problems. 
. Most projects suffer from congestion around 
project completion time because of reduced work 
areas. Thus, if we can gradually reduce the crew 
size as we approach project completion, we can 
improve productivity by reducing congestion. 
20
The leveling procedure are as follows: 
• Scheduling all the critical jobs first. 
• Starting the non-critical jobs whenever there 
is a drop in scheduled man power upto the 
point where the peak is reached. 
• Starting the non-critical jobs whenever there 
is a drop so that no ups and downs occur in 
the resource profile. 
21
› Time Limited: The project must be finished by a 
certain time, using as few resources as possible. 
But it is time, not resource usage, that is critical 
22
Resource Histograms: 
• A bar chart showing the amount of time 
assigned to a resource for the time interval. 
• Resource availability is depicted as a line for 
comparison purposes. 
• Resources assigned more work than 
available hours are considered “over-allocated”. 
23
INTRODUCTION 
ERP is a business management software, 
usually a suite of integrated applications, that a 
company can use to store and manage data 
from every stage of business, including: 
Product planning, cost and development 
Manufacturing 
Marketing and sales 
Inventory management 
Shipping and payment 
24
ERP systems could be used in the construction 
industry for the following general purposes: 
1. To improve responsibilities in relation to 
customers. 
2. To strength supply chain partnerships. 
3. To enhance organizational flexibility. 
4. To improve decision-making capabilities. 
5. To reduce project completion time and cost. 
25
26
27
Without the proper resource allocation, one will 
pay the price for late job completions and cost 
overruns. 
The goal of resource leveling is to assign 
resources to project activities in a manner that 
will improve productivity and efficiency. 
During the last two decades, the construction 
industry has progressed in this trend of 
improving resource allocation it merely out of 
interest but as a means of survival in a more 
competitive world. 
28
29
30

Contenu connexe

Tendances

Ppm lecture 10 11 planning, process, types
Ppm lecture 10 11 planning, process, typesPpm lecture 10 11 planning, process, types
Ppm lecture 10 11 planning, process, types
Vishakha Agarwal
 
Introduction-to-project-management
Introduction-to-project-managementIntroduction-to-project-management
Introduction-to-project-management
Savaş Şakar
 

Tendances (20)

Equipment management
Equipment managementEquipment management
Equipment management
 
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
 
Project Planning
Project PlanningProject Planning
Project Planning
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Ppm lecture 10 11 planning, process, types
Ppm lecture 10 11 planning, process, typesPpm lecture 10 11 planning, process, types
Ppm lecture 10 11 planning, process, types
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 
Project planning and project work plan
Project planning and project work planProject planning and project work plan
Project planning and project work plan
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
Project Management
Project ManagementProject Management
Project Management
 
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
 
Project execution and implementation
Project execution and implementationProject execution and implementation
Project execution and implementation
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
 
Introduction-to-project-management
Introduction-to-project-managementIntroduction-to-project-management
Introduction-to-project-management
 
Productivity improvement in construction
Productivity  improvement in constructionProductivity  improvement in construction
Productivity improvement in construction
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.
 

Similaire à Resource planning and resource allocation

Scheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.pptScheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.ppt
TecnicoItca
 
Lecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptxLecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptx
TecnicoItca
 

Similaire à Resource planning and resource allocation (20)

Resource allocation and smoothing
Resource allocation and smoothingResource allocation and smoothing
Resource allocation and smoothing
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
PM-Chapter8-1.pptx
PM-Chapter8-1.pptxPM-Chapter8-1.pptx
PM-Chapter8-1.pptx
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
Chap008.ppt
Chap008.pptChap008.ppt
Chap008.ppt
 
Project time management
Project time managementProject time management
Project time management
 
Allocating resources
Allocating resourcesAllocating resources
Allocating resources
 
Scheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.pptScheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.ppt
 
PM Session 6
PM Session 6PM Session 6
PM Session 6
 
Project typed
Project typedProject typed
Project typed
 
Chapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.pptChapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.ppt
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Project Resource Management-Good one.ppt
Project Resource Management-Good one.pptProject Resource Management-Good one.ppt
Project Resource Management-Good one.ppt
 
Planning & Scheduling 222030008.pptx
Planning & Scheduling 222030008.pptxPlanning & Scheduling 222030008.pptx
Planning & Scheduling 222030008.pptx
 
Scheduling resources and costs is a crucial aspect of project management that...
Scheduling resources and costs is a crucial aspect of project management that...Scheduling resources and costs is a crucial aspect of project management that...
Scheduling resources and costs is a crucial aspect of project management that...
 
Lecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptxLecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptx
 
SPM Resource Management
SPM Resource ManagementSPM Resource Management
SPM Resource Management
 
SPM Resource Management
SPM Resource ManagementSPM Resource Management
SPM Resource Management
 
SPM Resource Management
SPM Resource ManagementSPM Resource Management
SPM Resource Management
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.ppt
 

Dernier

Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 

Dernier (20)

Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 

Resource planning and resource allocation

  • 1. Presented by : VENUMADHAV.R.YEMUL Guided by : MILIND.D.DARADE Roll No : 5073 1
  • 2. Manpower, equipment, and materials are important project resources that require management attention. The basic objective of resource planning and resource allocation is to supply and support the field operations. The term resource allocation is used in the case where required resources are assigned such that available resources are not exceeded. 2
  • 3. Resources are the means of production needed to complete a project. Most project managers would consider the big three resources that will require your attention to be: • Material • Labor • Equipment 3
  • 4. A. LABOUR a. In the limited resource allocation case, there are two assumptions: (1) There are a fixed number of crews available to perform the work and (2) The project may be delayed as a result of the limitation of crews. The objective of the resource allocation problem is to determine when the project will be completed. 4
  • 5. b. In the unlimited resource leveling case, there are two assumptions: (1) There are an unlimited number of crews available to perform the work and (2) The project may not be delayed. The objective of the resource leveling problem is to determine how to limit the fluctuation in crews required on the job. 5
  • 6. B. MATERIALS Materials, for projects with sufficient on-site storage, are delivered to the site and assumed to be available to workers as needed. A material-related concern for sites that have sufficient space is that of optimizing the position of materials on the site so that they require the least travel time from the lay-down yard to the work-face. 6
  • 7. C. EQUIPMENTS There are various types of equipment used on construction sites. Some of this equipment should be considered in the project plan, some need not be included. Workers, and their companies, are typically required to provide the small tools needed to complete their specific features of work. There are some types of equipment, however, that can affect the overall sequence and duration of the project. 7
  • 8. Resource allocation is used to assign the available resources in an economic way. It is part of resource management. In project management, resource allocation is the scheduling of activities and the resources required by those activities while taking into consideration both the resource availability and the project time. 8
  • 9. Resource planning cannot be accomplished without four essential resources necessary to accomplish the given scope of work: • MATERIAL • MAN POWER • MACHINARY • TIME 9
  • 10. Human resources for construction planning breaks down into three major categories as follows: • Home office personnel(Administrative Persons) • Construction personnel (field supervision and labor) • Construction subcontractors(Electrification, Plumbing, etc) 10
  • 11. The ideal form of a personnel loading curves is a trapezoid. The average personnel loading curve is a straight line. Actual practice loading curves take the shape of a bell curve 11
  • 12. 12
  • 13. The latter two result when the personnel loading curves occur earlier or later than planned on a project. Front loaded curve- the work started as early as possible. Normal loaded curve- the work started at normal time. Back loaded curve- the work started as late as possible. 13
  • 14. The "S" curve for the ideally loaded project has a gradual start and finish, which indicates smooth starting and finishing conditions. The forward loaded curve shows a rapid project start up and an even more gradual than normal phase out at the end. The backward-loaded project indicates a more relaxed start and a very steep finish slope on the "S" curve. 14
  • 15. 15
  • 16. 16
  • 17. Ensuring that the material resources for the project arrive on time involves these important planning areas: • Long-delivery equipment • Special materials and alloys • Common materials in short supply • Services and system requirements • Transportation systems 17
  • 18. Resource Limited: The project must be finished as soon as possible, but without exceeding some specific level of resource usage or some general resource constraint 18
  • 19. 1. When the schedule demands more workers per day than are available or if we have workers standing around without jobs, we have a problem. 2. When a new hire is trained, there is loss of productivity. So, if we can keep the trained people and reduce the number of new hires, we should be better off. 19
  • 20. . As we know, every project suffers from start-up problems of some sort. Superintendents and project managers are very busy trying to get everybody working in a productivity manner. Therefore, if we can start with a small crew and increase its size gradually, we will eliminate some of the start-up problems. . Most projects suffer from congestion around project completion time because of reduced work areas. Thus, if we can gradually reduce the crew size as we approach project completion, we can improve productivity by reducing congestion. 20
  • 21. The leveling procedure are as follows: • Scheduling all the critical jobs first. • Starting the non-critical jobs whenever there is a drop in scheduled man power upto the point where the peak is reached. • Starting the non-critical jobs whenever there is a drop so that no ups and downs occur in the resource profile. 21
  • 22. › Time Limited: The project must be finished by a certain time, using as few resources as possible. But it is time, not resource usage, that is critical 22
  • 23. Resource Histograms: • A bar chart showing the amount of time assigned to a resource for the time interval. • Resource availability is depicted as a line for comparison purposes. • Resources assigned more work than available hours are considered “over-allocated”. 23
  • 24. INTRODUCTION ERP is a business management software, usually a suite of integrated applications, that a company can use to store and manage data from every stage of business, including: Product planning, cost and development Manufacturing Marketing and sales Inventory management Shipping and payment 24
  • 25. ERP systems could be used in the construction industry for the following general purposes: 1. To improve responsibilities in relation to customers. 2. To strength supply chain partnerships. 3. To enhance organizational flexibility. 4. To improve decision-making capabilities. 5. To reduce project completion time and cost. 25
  • 26. 26
  • 27. 27
  • 28. Without the proper resource allocation, one will pay the price for late job completions and cost overruns. The goal of resource leveling is to assign resources to project activities in a manner that will improve productivity and efficiency. During the last two decades, the construction industry has progressed in this trend of improving resource allocation it merely out of interest but as a means of survival in a more competitive world. 28
  • 29. 29
  • 30. 30