RECOMMENDED PROCEDURE
FOR
CHEMICAL CLEANING OF BOILER WITH
EDTA (Ethylene Diamine Tetra Acetic Acid )

PROJECT: HINDALCO MAHAN ALUMINUM
6X150MW UNITS

BHEL Ref No. BHEL/TSX/
DOC.
NO.

REV.NO:
1

PS WR
BHARAT HEAVY ELECTRICALS LIMITED
POWER SECTOR –WESTERN REGION
Shree Mohini Complex,345 – Kingsway ,Nagpur – 440 031
BHEL Ref No: PW / TSX /HINDCO/
HINDALCO MAHAN Unit-1 61X150 MW
Plant area: BOILER

Page 2 of 24

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA

PROJECT

HINDALCO MAHAN ALUMINUM 6X150MW UNITS

PROCEDURE

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA

PURPOSE
DOCUMENT

FOR EXECUTION / INFORMATION

DOCUMENT

DOC.NO. BHEL/TSX

00

Santosh Kumar

Rev.No.

Prepared by

Niranjan Ray
Reviewed by

Approved by

Date

BHARAT HEAVY ELECTRICALS LIMITED
POWER SECTOR –WESTERN REGION
Shree Mohini Complex,345 – Kingsway ,Nagpur – 440 031

Signatures

HINDALCO MAHAN

BHEL
BHEL Ref No: PW / TSX /HINDCO/
HINDALCO MAHAN Unit-1 61X150 MW
Plant area: BOILER

Page 3 of 24

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA

1.0

PLANT DETAILS

2.0

OBJECTIVES

3.0

PROPOSALS

4.0

SERVICES REQUIRED

5.0

EMERGENCY PROVISIONS

6.0

EMERGENCY PROCEDURES

7.0

STATE OF THE PLANT

8.0

PROCESS PROCEDURE

9.0

COMPLETION CRITERIA

10.0

CHEMICAL CLEANING WASTE TREATMENT & DISPOSAL

11.0

APPENDICES
A) DRAWING
B) ANALYTICAL PROCEDURES
C) LOG SHEET FORMATS

Signatures

HINDALCO MAHAN

BHEL
BHEL Ref No: PW / TSX /HINDCO/
HINDALCO MAHAN Unit-1 61X150 MW
Plant area: BOILER

Page 4 of 24

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA
Sl. No
1.0

STATUS
PLANT DETAILS
The steam Generator is a natural circulation boiler with Plain
water wall tubes.
Boiler Design Data:
SH outlet Pressure
SH outlet Temperature
Feed Water Temperature (at eco inlet)
Maximum Continuous Rating
Water Holding Capacity
1. Water wall + Drum (full)
2. Economizer
3. Superheater
4. Reheater

2.0

- 149 Kg/cm 2
- 540 0C
- 250 0 C
- 510 t/h.
-115
-40
-65
-30

m3
m3
m3
m3

OBJECTIVE
The objective of this procedure is to chemically clean and
passivate the internal surfaces of the steam generating portion
(water touched surfaces) and heating surfaces (Economizer)
using specified chemicals employing a single step process. This
will render the above mentioned surfaces free of mill scale, and
other deposits and form uniform & smooth protective layer of
magnetite. With this protective layer, the generating surfaces are
rendered passive to generate adequate negative potential under
the operating pH to resist corrosion.

3.0

PROPOSAL

3.1

The objectives are achieved by carrying out the following
proposals.

3.2

By carrying out water rinsing to remove loose rust, debris, oil and
grease, if any, left in the Boiler.

3.3

Then, it is subjected to acid cleaning for the removal of patchy mill
scale and adherent rust.

Signatures

HINDALCO MAHAN

BHEL
BHEL Ref No: PW / TSX /HINDCO/
HINDALCO MAHAN Unit-1 61X150 MW
Plant area: BOILER

Page 5 of 24

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA
Sl. No

STATUS
The acid pickled surface is passivated for the formation of uniform
and adherent magnetite layer. Both chemical cleaning and
passivation process are completed in a single step.

4.0

SERVICES REQUIRED

4.1

Prior to the commencement of chemical cleaning, all the DM
water storage tanks should be kept full and the de-mineralizing
units kept in regenerated condition. Approximately, 300 m³ of DM
water will be consumed for the entire process. At any time of acid
cleaning, a minimum of two boiler volumes (app. 600 M3) of DM
water should be available in ready stock to facilitate rapid flushing
of the system in the event of chemistry upset.

4.2

All the required quantities of chemicals as given below should be
made available prior to the commencement of the process.
SPECIFICATION OF CHEMICALS & QUANTITY
NAME OF CHEMICALS

QTY/Each Boiler

1. Tri Sodium Phosphate
(Purity, as P2O5 :17.5% Min)
110 kgs
2. Disodium Hydrogen Phosphate
(99 % purity)
60 kgs
3. Ammoniated EDTA,
40% wt/wt as active EDTA
ammoniated solution pH=9.0 to 9.8)
(EDTA : Ethylene diamine tetra acetic acid- C10H16N2O8 )
Density : 1.18
15 tons
2. Ammonia solution (20% Min as NH3,
sp gr:0.91) as per IS 799 / 1990
600 Liters
3. Hydrazine Hydrate
(80% Min. conc). To IS 12086/1991
700 Litres
4. Bhelmax
250 kg
5. Bhelsol
250 Litres
4.3

Temporary drum water level gauge glass and (Tel-tale lamp
indication) at control room and low point drain area.

Signatures

HINDALCO MAHAN

BHEL
BHEL Ref No: PW / TSX /HINDCO/
HINDALCO MAHAN Unit-1 61X150 MW
Plant area: BOILER

Page 6 of 24

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA
Sl. No
4.4

HT / LT Supply to be available.

STATUS

4.5

Control supply to be available.

4.6

Instrument/service Air to be available.

4.7

Chemist/Express lab to be made available for testing during the
process.

4.8

Flood lights / telephones / walkie-talkie are available.

4.9

For effluent treatment, compressed air facility and suitable
perforated Carbon Steel / polythene tubing arrangement shall be
made available.

4.10

SAFETY EQUIPMENTS:
1. Gum boots (Various sizes)

6 Pairs

2. Rubber gloves

6 Pairs

3. Rubber or Polythene aprons

6 Nos.

4. Helmets

12 Nos.

5. Safety goggles plain glass

6 Nos.

6. Face mask (Transparent, plastic)

4 Nos.

7. First aid box (containing dilute ammonium hydroxide, 50% sodium
bicarbonate solution, eye lotion, bandages, tincture of iodine,
cotton, burnol etc)
5.0

EMERGENCY PROVISIONS

5.1

Flushing and washing water supplies
Ample supplies of rapid flushing and washing water supplies shall
be provided at all possible points of discharge, spillage or escape
of chemicals.

Signatures

HINDALCO MAHAN

BHEL
BHEL Ref No: PW / TSX /HINDCO/
HINDALCO MAHAN Unit-1 61X150 MW
Plant area: BOILER

Page 7 of 24

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA
Sl. No
5.2

5.3

STATUS
Adequate provisions shall be made for emergency treatment of
the eyes, comprising eye wash bottles, located conveniently to
places where discharge, spillage or escape of chemicals can
occur.
Safety shower shall be provided.

5.4

A suitable first aid treatment room with outside telephone facilities
shall be provided within a reasonable distance of the place where
chemicals are being used.

5.5

The protective clothing and apparatus required for
emergency use shall be made available near the acid
cleaning area.

5.6

FIRST AID TREATMENT

5.7

Splashes of the eye

5.7.1

Immediately flood the eye with water. To be effective the eyelids
must be opened. The eyelids should be pushed apart using the
thumb and index finger of the left hand. The casualty will probably
not be able to open the eye himself because of painful spasms.

5.7.2

If an eye wash bottle is used the jet should not be directed at the
front of the eye. It should be directed in from the side, so that flow
is over the surface of the eye.

5.7.3

Irrigation should be continued for 5 – 10 minutes after which the
casualty should be taken to the first aid room.

5.7.4

Irrigation should be continued in the first aid room. Remember
vision is saved by thorough irrigation; no other treatment can
prevent damage if this is omitted.

5.7.5

After thorough irrigation the eye should be covered with a pad; the
patient should be referred for medical opinion.

5.7.6

Irritation of the skin

Signatures

HINDALCO MAHAN

BHEL
BHEL Ref No: PW / TSX /HINDCO/
HINDALCO MAHAN Unit-1 61X150 MW
Plant area: BOILER

Page 8 of 24

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA
Sl. No
5.8

5.9

STATUS
If signs of skin irritation occur the persons should be removed
from contact and referred for medical opinion. In the event of the
splashing of the skin with chemicals the effected area should be
washed thoroughly avoiding spreading contamination to the face
and eyes.
GENERAL

5.9.1

Test area will be cordoned off and unauthorized persons entry
shall be prohibited. Suitable signboard shall be displayed.

5.9.2

Whenever any inspection is made during the cleaning process,
the location should be adequately ventilated.

5.10

SAFETY OF PLANT:
A)

If the light up after cleaning could not be done within 4
weeks after completion of cleaning, the system will be suitably
preserved.
B)
Temperature limitations specified for various steps should
not be exceeded.
6.0

EMERGENCY PROCEDURES:

6.1

The testing team should be aware of the operating procedures of
fire extinguishers to be used for quenching minor or major fires.

6.2

The testing team should be aware of the procedure to be followed
in case of accidents involving personnel injury.

6.3

In case of failure of running pump the stand by pump should be
started immediately without delay.

6.4

An operator posted at the pump area, should be instructed to stop
the pumps and properly isolate the system in the event of
emergency. All operators should be well conversant with the
emergency operating instructions.

7.0

STATE OF THE PLANT

Signatures

HINDALCO MAHAN

BHEL
BHEL Ref No: PW / TSX /HINDCO/
HINDALCO MAHAN Unit-1 61X150 MW
Plant area: BOILER

Page 9 of 24

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA
Sl. No
7.1
7.2

STATUS
Readiness of the following is to be ensured.
During the EDTA cleaning process, all the permanent boiler
instruments are isolated except providing a temporary pressure
gauge of 0 to 5.0 kg/cm2 in the drum for monitoring pressure in
the drum during EDTA cleaning.
Provisions should be made at the following locations for the
measurement of temperature.
A) Two locations in the drum (left & right) for the measurement of
boiler Water temperature. Long thermocouples of around 400
mm length shall be installed directly in the spare / unused stubs
in the drum.
B) Water wall metal temperature measurements as given below:
At AB elevation, 4 number thermocouples shall be installed on
corner water wall tubes (outside the furnace) and at CD
elevation 2 numbers thermocouples shall be installed in the
front and rear water wall (outside the furnace) at accessible
locations.
C).Two more thermocouples with pads one each at left and right
side of ECO coil shall be welded at suitable locations, inside the
boiler (or penthouse) to measure the metal temp in the gas
side.
(Total 6 Nos thermocouples will be used for measurement of
water wall tube metal temperature and 2 Nos for economizer
tube temperature)
Preening type temporary thermocouples are to be provided in the
temp measurement points on the water walls and economizer.
Provision has to be made for monitoring temperature in the
control room.

7.3

SAMPLING DURING PROCESS
To get representative samples of the process solution, sampling
points with sample coolers are to be provided at the following

Signatures

HINDALCO MAHAN

BHEL
BHEL Ref No: PW / TSX /HINDCO/
HINDALCO MAHAN Unit-1 61X150 MW
Plant area: BOILER

Page 10 of 24

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA
Sl. No

STATUS
locations:
A) Drum water sample to be drawn from CBD sampling cooler
and from a spare tapping point in water side through the
permanent saturated steam coolers.
B) Two numbers of sampling point is to be provided from bottom
ring header through hand-hole cover.

7.4

For rinsing, chemical cleaning and passivation processes,
essential control and instruments viz. protections, interlock,
alarms, measurement, annunciation etc. required for safe light-up
of boiler are made available, as per mutually agreed list between
M/S Hindalco Mahan and BHEL site.

7.5

All the related boiler auxiliaries are made ready and available for
boiler light up. This includes chemical dozing pumps, tanks, fans,
oil pumps etc. A checklist, containing minimum operational
requirements to be made ready prior to commencement of
Chemical cleaning is enclosed at 7.15.

7.6

Prior to the commencement of flushing/rinsing of the boiler,
detergent flushing of pre-boiler system is to be completed.

7.7

In the steam drum, primary separators and screen driers are
to be installed and secondary separators are not to be
installed. In the drum, the screen plates shall be retained.
orifices are not to be installed.

7.8

The flap in the eco recirculation line NRV can be removed for fast
filling and draining of economizer (optional). The eco recirculation
valve shall be kept open throughout the chemical cleaning
process. Economizer inlet valve shall be kept closed.

7.9

O&M instruction for the boiler and other auxiliaries are to be
available well in advance of the commencement of the cleaning
process.

7.10

All the safety measures discussed and implemented in advance
with suitable instruction/caution tags provided at strategic places/

Signatures

HINDALCO MAHAN

BHEL
BHEL Ref No: PW / TSX /HINDCO/
HINDALCO MAHAN Unit-1 61X150 MW
Plant area: BOILER

Page 11 of 24

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA
Sl. No

STATUS
equipment.

7.11

Boiler water wall test tube coupons are placed at two ends inside
the drum to see the effectiveness of the cleaning.

7.12

Proper effluent treatment arrangement is to be made available at
site.

7.13

All fabrication work to be completed as per scheme provided.

7.14

Inhibitor efficiency test shall be carried out at BHEL Trichy or at
inhibitor vendor’s works.

7.15

MINIMUM OPERATIONAL REQUIREMENTS.
1.

Ensure the commissioning of the following including
their protections, interlocks, measurements, alarms and
annunciations:-

ONE ID FAN,
ONE FD FAN,
ONE AIR PRE-HEATER,
LIGHT OIL FIRING SYSTEM,
FSSS,
SADC,
SCANNER AIR SYSTEM.
Measurements, alarms, annunciations pertaining to secondary
air flue gas, feed water, steam & boiler metal temp.
2. Ensure free expansion of the furnace and duct and provision
of expansion markers
3. Blow down system of boiler
4. Proper drainage system of boiler area
5. Air leak test of two passes of ESP
6. Mechanical readiness of two passes of ESP.
7. Adequate quantity of light oil & readiness of light oil handling
system.
8. Completion of pre-boiler system detergent flushing.
Signatures

HINDALCO MAHAN

BHEL
BHEL Ref No: PW / TSX /HINDCO/
HINDALCO MAHAN Unit-1 61X150 MW
Plant area: BOILER

Page 12 of 24

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA
Sl. No

STATUS
9.

Temporary sampling system along with the cooling
arrangement for collecting samples from the header drains.
10.
Water and steam systems readiness for operation
11.
Air and flue gas system readiness for operation
12.
Effluent treatment pit to hold approximately 600
m3 .
13.
Drainage line to effluent treatment is ready
14. Readiness of BFP and feed system (optional)
15. Drum water sampling system along with sample cooling
arrangement.
16.
DG set, DG switchgear, emergency switch gear and
availability of emergency supplies for:
 Scanner air fan.
 Emergency lighting.
17. UPS readiness.
18. Fire fighting system of concerned equipments
19. Equipment cooling water system shall be made ready.
20. Availability of adequate quantity of DM water.
21. Adequate capacity of instrument air and service air system
22. Availability of HP dozing system.
23. Availability of test coupons & their fixing arrangements.
24. Emergency operating instructions viz. AC power failure, DC.
Power failure, APH fire etc.
25. Adequate lighting in operating areas.
26. Public address system at all operating locations, including
telephone & walkie talkies at all working areas
27. Readiness of staircases, hand railings and platforms
28. Personal safety equipment.
29. Easy access and approaches to all the operating equipments.
30. SH metal temperature measurement shall be made ready for
continuous monitoring in the control room.
31. Data logging printer at control room shall be made available
to record the boiler parameters periodically.
32. Proper isolation of APH, which will not be taken into service,
will be insured. Alternately, the same be kept running.
8.0
8.1
8.1.1

PROCESS PROCEDURE
ALKALI FLUSHING:

Signatures

HINDALCO MAHAN

BHEL
BHEL Ref No: PW / TSX /HINDCO/
HINDALCO MAHAN Unit-1 61X150 MW
Plant area: BOILER

Page 13 of 24

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA
Sl. No

STATUS

8.1.2

The requisite quantities of (a) Tri-sodium Phosphate (TSP) & (b)
Di Sodium Hydrogen Phosphate to be added to the mixing tank
along with DM Water and the solution will be thoroughly mixed by
recirculation so that final solution in the Boiler contains 0.1 %
TSP and 0.05 % DSP. The solution will be injected into the boiler
through the bottom ring header drains and economizer drain
operating the chemical filling pump. Further DM water will be
taken in the boiler up to normal level.

8.1.3

Light up the boiler as per O&M instructions and gradually raise the
boiler water temperature to 130–140 deg C. Trip the boiler and
keep the fans running for cooling.
Drain the boiler at 90 0 C to the plant water disposal system, by
keeping open the drain valves fully (without any throttling). The
drain solution will be diluted with plenty of service water.

8.2
8.2.1

HOT WATER RINSING

8.2.2

Once the draining is completed, refill the boiler with DM water
Light up the boiler. Gradually raise the boiler water temperature to
130-1400 C. Trip the boiler and keep the fans running for cooling.

8.2.3

Drain the boiler in the hot condition to the plant’s water disposal
system by keeping open the drain valves fully (without throttling).
The pH and PO4 will be measured in the drain water. The pH and
PO4 are to be reduced to a level below 7.5 and 10 ppm
respectively

8.3
8.3.1

COLD WATER RINSING
Cold water rinses will be done by fill and dump method. During
these steps, draining will be done to the plant’s water disposal
system. pH will be monitored during draining of each cold water
rinse stage. The rinsing operation will be continued until the pH of
the drain water is almost equal to pH of inlet water used for

Signatures

HINDALCO MAHAN

BHEL
BHEL Ref No: PW / TSX /HINDCO/
HINDALCO MAHAN Unit-1 61X150 MW
Plant area: BOILER

Page 14 of 24

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA
Sl. No
8.3.2

STATUS
rinsing.
Flush all sampling and blow down lines. Check all temperature /
pressure measurements relevant to the process for monitoring at
UCB and ensure their reliability.
The following guide line should be followed besides O & M
instruction for boiler light up.
LIGHTING UP
Drum air vents SH air vents & start up Vents is to be opened
before lighting up the boiler.
Initiate boiler light up as per O & M instructions.
Drum level is to be monitored closely and controlled below normal
level by operating down comer blow down from UCB or draining
and filling the boiler at drain header. Drum level Temporary
indication shall be displayed at UCB and near drain header.

8.4
8.4.1

EDTA CLEANING & PASSIVATION.

8.4.2

In this process the mixture of chemical solutions containing EDTA,
inhibitor, ammonia (if required) and hydrazine in DM water is filled
in the boiler. Boiler is fired and the temperature raised to 140-145 0
C and held for 4 hours and subsequently cooled. The removal of
deposit constituents and subsequent Passivation of the metal
surfaces will occur during this single step.

8.4.3

The required quantity of ammoniated EDTA (40% wt / wt) solution
will be kept ready in the EDTA storage tank.

8.4.4

The inhibitors “BHEL MAX” & “BHELSOL”, Hydrazine hydrate and
ammonia for addition in the Chemical dissolving tank will also be
made available near the mixing tank.

8.4.5

All the Boiler Blow down valves are kept shut and drum vent
valves & start up vent open during boiler filling.

Signatures

HINDALCO MAHAN

BHEL
BHEL Ref No: PW / TSX /HINDCO/
HINDALCO MAHAN Unit-1 61X150 MW
Plant area: BOILER

Page 15 of 24

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA
Sl. No

8.4.6

STATUS
40 m3 of DM water will be drawn in the dissolving tank. The
temporary chemical fill pump will be started and system put into
recirculation. The required quantity of Ammoniated EDTA (40%
wt/wt) solution will be transferred from the EDTA storage tank to
the dissolving tank. The EDTA concentration in the dissolving tank
will be checked. Transferring the EDTA solution will be stopped,
when the EDTA concentration reaches around 3 + 1% by weight.
Required quantity of Hydrazine hydrate and inhibitors (BHEL Max
& BHEL Sol) will also be added. Recirculation will be done till all
the chemicals uniformly mixed up. With this one batch of EDTA
Chemical solution will be ready for filling into the boiler.
The quantities of various chemicals that are to be mixed per batch
of 40 m3 is given below:
1. EDTA ammoniated (40 % ) concentrate :
2. BHELMAX
:
3. BHELSOL
:
4. N2H4.H2O (80%)
:

8.4.7

3 to 4 m 3
60 kgs
60 litres
60 litres

Ammonia will be added if required to adjust the pH between 9.0 to
9.8. DM water will be used to make up to 40 m 3 .
This solution will be filled into the Boiler through LP drain header
Boiler fill line with the temporary chemical fill pump.
The cleaning solution is quite harmless w.r.t. corrosion and hence
there is no time limitation for filling the boiler and retaining the
solution inside the boiler.
Repeat the preparation of Chemical solution and batch filling as
explained in point no 8.4.5 till water level in the drum reaches the
center line of the gauge glass.
The composition of the filling solution shall be as below:

8.4.8
8.4.8.1

EDTA content
Hydrazine
pH

:
:
:

3 + 1% W/v
1000 ppm (min)
9.0 to 9.8

The boiler will be lighted up as per normal operating procedure
with minimum firing rate (say 2 oil guns in AB elevation)

Signatures

HINDALCO MAHAN

BHEL
BHEL Ref No: PW / TSX /HINDCO/
HINDALCO MAHAN Unit-1 61X150 MW
Plant area: BOILER

Page 16 of 24

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA
Sl. No

STATUS

8.4.8.2

The drum and super heater vents are to be closed when
steaming starts, say at 1 kg/cm 2 in the drum and keep open the
SH start up vent.

8.4.8.3

The drain valve in S.H. header –1 will be kept in crack opened
Condition.

8.4.8.4

Note the time at which the temperature of boiler water reaches
110 0C.

8.4.8.5

Continue raising the temperature of boiler water to a saturation
temperature of 140 0C.

8.4.8.6

Once the temperature of boiler water reaches 140 0C, control the
firing rate in such a way that the boiler water temperature is
maintained at 140 to 145 0C, for a min period of 4 hours. Then trip
the boiler.

8.4.8.7

Continue running the ID/FD fans to bring down the boiler water
temperature. In case it appears that the results of iron
concentration may not level out when temp is expected to be 110
0
C, ID/FD fans shall be stopped, suitably, during the cooling down
phase & boiler shall be boxed up and kept in this condition to
achieve the EDTA contact period of 8 hours with temperature
exceeding 110 0C.

8.4.8.8

Samples have to be taken every 30 minutes from the sampling
points at locations given as per 7.3, from the time when the
temperature in the system has reached 110 0C and analyzed for
pH, EDTA concentration, and Iron content.

8.4.8.9

After attaining the completion criteria of pickling process, as per
clause 8.5, the system shall be allowed to cool with the ID & FD
fans in operation (ID & FD fans are to be restarted, in case they
have been stopped to meet the completion criteria, to bring down
the boiler water temperature). Open the drum air vents when the
pressure reaches to 1 kg/cm2.
Boiler water temperature & Water Wall Metal temperature at the

Signatures

HINDALCO MAHAN

BHEL
BHEL Ref No: PW / TSX /HINDCO/
HINDALCO MAHAN Unit-1 61X150 MW
Plant area: BOILER

Page 17 of 24

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA
Sl. No
8.4.8.10

STATUS
locations indicated as per 7.2 are to be measured and logged.
When the temperature comes down to 95 0C, the system shall be
drained completely in hot condition to the effluent pit by opening
all the drain valves.

8.5
8.5.1

PROCESS COMPLETION CRITERIA

8.5.2

Cleaning process is to be continued till iron concentration in three
consecutive samples show equilibrium status.

8.5.3

When the iron concentration in the cleaning solution is constant, it
indicates that all the oxides have been dissolved. However, a
minimum EDTA contact period of 6 hours from the time of
attaining the required temperature (110 0C) shall be allowed.
If the iron concentration values do not level out and attain
equilibrium status, regardless of analytical results, the EDTA
contact period with temperature exceeding 110 0C shall not be
allowed for more than 8 hours (approx).

8.6
8.6.1

TREATED DM WATER RINSING:

8.6.2

Prepare a blended solution of ammonia & Hydrazine with
calculated quantities in the Dissolving tank in order to achieve a
solution pH 9.0 to 9.5 and hydrazine content 50 ppm in the DM
water being filled in the boiler. Steam heats the solution to a
temperature of 60 0C before admitting into the boiler.

8.6.3

Fill the boiler with the above treated DM water through low point
drains and economizer as practiced earlier, up to just above the
centre gauge glass.

8.6.4

Light up the boiler as per O&M instruction maintain drum level up
to 100 mm above NWL

8.6.5

Raise boiler water temperature up to 110 0C and then shut
down the boiler. Allow the boiler to cool down naturally.

Signatures

HINDALCO MAHAN

BHEL
BHEL Ref No: PW / TSX /HINDCO/
HINDALCO MAHAN Unit-1 61X150 MW
Plant area: BOILER

Page 18 of 24

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA
Sl. No

STATUS

8.6.6

When the boiler water temperature comes down to 95 0C, drain
the boiler to the effluent pit and allow the system for natural
aeration.

8.6.7

Open upper & lower drums for inspection. Manually clean the
drums if required.
Refit the drum internals and restore the boiler and prepare it for
regular operation for steam blowing, safety valve floating etc.

9.0
9.1

INSPECTION CRITERIA:

9.2

The test coupons placed at identified locations will be taken out.
All coupons shall be free of deposits and shall have uniform
coating of the protective layer.

9.3

The drum surface shall be visually inspected for uniform smooth
coating of protective layer.
The low point headers will be inspected and loose debris if any,
will be removed.

10.0
10.1

CHEMICAL CLEANING WASTE TREATMENT & DISPOSAL.

10.2

Treatment and disposal of the waste and effluents of the chemical
cleaning process shall comply with the requirements / stipulations
of state pollution control board norms.

10.3

Hot DM water flushing shall be drained into plant normal drain.
The organic spent EDTA chemical solution after the cleaning
process is drained into a pit. The pH of the effluent will be in the
range of 8.5 to 9.0 and hence no treatment for pH adjustment is
required as it would meet the pH requirement for disposal.
Typical relative composition of the process solution (Temp. 75 0C)
immediately after draining is given below:

Signatures

HINDALCO MAHAN

BHEL
BHEL Ref No: PW / TSX /HINDCO/
HINDALCO MAHAN Unit-1 61X150 MW
Plant area: BOILER

Page 19 of 24

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA
Sl. No
10.4

11.0
11.1
11.1.1
11.1.2

STATUS
1.
2.
3.
4.

EDTA <15 g/l
N2H4 <0.05 g/l
Fe
<10.0 g/l
Compressed air shall be used to destroy the residual Hydrazine &
organics and the effluent shall be disposed after aeration for 10
days, as per state pollution control board norms. Effluent will be
disposed to ash dyke in installments through existing ash slurry
system (The organic chemical is completely bio-degradable).
APPENDIX
NOTE (Refer Drawings attached)
Drains to be provided at lowest points of temporary piping.

11.1.3

All temporary connections to Boiler should be of radiographic
quality.

11.1.4

Service water supply should be available near the pump
operating areas.

11.1.5

Additional Check lists/Modifications in the lay-out, if found
necessary, to be made at site in consultation with site
Commissioning In-charge.

11.2

All the sampling points along with sample coolers and the
temperature measurement points with necessary thermocouples
shall be provided as indicated in 7.3 & 7.2 respectively.
TERMINATION CRITERIA AT A GLANCE

11.2.1
Termination Criteria for each step will be as follows:
(Ref.8.1,8.2,8.3)
Alkali Flushing, Hot water flushing & cold water rinses:
11.2.2

pH: < 7.5
PO4 < 10 ppm

(Ref. 8.4.)

11.2.2.1

Acid cleaning & Passivation:
Cleaning process is to be continued till iron concentration in three

Signatures

HINDALCO MAHAN

BHEL
BHEL Ref No: PW / TSX /HINDCO/
HINDALCO MAHAN Unit-1 61X150 MW
Plant area: BOILER

Page 20 of 24

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA
Sl. No
11.2.2.2

STATUS
consecutive samples show equilibrium status.

11.2.2.3

When the iron concentration in the cleaning solution is constant, it
indicates that all the oxides have been dissolved. However, a
minimum EDTA contact period of 6 hours from the time of
attaining the required temperature (110 0C) shall be allowed.

11.2.2.4

If the iron concentration values do not level out and attain
equilibrium status, regardless of analytical results, the EDTA
contact period with temperature exceeding 110 0C shall not be
allowed for more than 8 hours (approx).

11.2.3
(Ref 8.6)

Declare the completion of pickling process once the EDTA
strength and iron concentration level out and reach equilibrium.
Treated DM Water Rinsing:
Completion criteria will be with one treated DM water rinse.
Inspection criteria:
The test coupons placed at identified locations will be taken out.
All coupons shall be free of deposits and shall have uniform
coating of the protective layer.
The drum surface shall be visually inspected for uniform smooth
coating of protective layer.
Chemical Cleaning Waste Treatment & Disposal:
pH: 5.0 to 9.0
The effluent will be disposed after ten days of aeration as per
local Pollution control board norms.

Signatures

HINDALCO MAHAN

BHEL
BHEL Ref No: PW / TSX /HINDCO/
HINDALCO MAHAN Unit-1 61X150 MW
Plant area: BOILER

Page 21 of 24

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA

LOG SHEET
PROJECT

: HINDALCO MAHAN 6X150MW UNITS

DATE: 18/01/2012

UNIT NO. : 1
ACTIVITY:

EDTA ACID CLEANING AND PASSIVATION

I.
ADDITION OF CHEMICALS:
____________________________________________________________________
Sl. No. DATE TIME
NAME OF CHEMICAL ADDED
QUANTITY

_____________________________________________________________________
II.
ANALYTICAL DATA:
_____________
_________________________________________________
Sl. DATE TIME SAMPLE POINT
TOTAL EDTA IRON pH
No.
HRS.
%
PPM
1.
2.
3.
4.
5.
.
____________________________________________________________________

Signatures

HINDALCO MAHAN

BHEL
BHEL Ref No: PW / TSX /HINDCO/
HINDALCO MAHAN Unit-1 61X150 MW
Plant area: BOILER

Page 22 of 24

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA
1.

PROCEDURE FOR DETERMINATION OF TOTAL EDTA CONCENTRATION IN
PROCESS SOLUTION DURING CHEMICAL CLEANING.
1. PRINCIPLE OF THE METHOD:
EDTA reacts with Zirconium ions under strong acid conditions to form a chelate. The
end point of the titration is indicated by a Xylenolorange indicator.
2. REAGENTS AND APPARATUS REQUIRED:
APPARATUS:
1. Erlenmeyer flask 300 ml capacity.
2. Pipettes
3. Hot plate
4. Magnetic stirrer
REAGENTS
1. Hydrochloric acid (conc.)
2. Standard Zirconium oxy chloride (ZrOCl2. 8H2O) 0.1 M solution in 1 N HCl
(Take a 1000 ml volumetric flask and add 32.23 gram of ZrOCl2.8 H2O and add
DM water to about 500 ml. To this add 85 ml of conc. HCl. Make up to 1000 ml
mark with DM water and mix well)
3. Ascorbic acid
4. Xylenolorange indicator.
3. TEST PROCEDUTE :
1. pipette out 10 cc of the water sample into a 300 ml Erlenmeyer Flask.
2. Add 10 ml of conc. HCl ( the pH value is about 1.0)
3. Add a spatula of ascorbic acid.
4. Boil of the solvent on the heating plate for about 5 minutes.(The yellow colour of
the ferric ion should disappear due to reduction to ferrous iron.
5. Immediately after the addition of 0.05 ml of 0.05 % xylenol orange indicator the
sample is titrated with 0.1M ZrOCl2 untill the colour changes from yellow to red
violet; The colour changes from yellow to red violet. The colour change shall
remain constant for at least 3 min.
4. CALCULATION :
The total EDTA concentration % = Volume of 0.1M ZrOCl2 consumed x 0.292

Signatures

HINDALCO MAHAN

BHEL
BHEL Ref No: PW / TSX /HINDCO/
HINDALCO MAHAN Unit-1 61X150 MW
Plant area: BOILER

Page 23 of 24

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA

2.

PROCEDURE FOR THE DETERMINATION OF TOTAL IRON CONCENTRATION IN
PROCESS SOLUTION DURING CHEMICAL CLEANING.
1. APPARATUS REQUIRED:
1.
2.
3.
4.

HACH DR/890 COLORIMETER
Volumetric flasks
Pipettes
Measuring cylinders

2. REAGENTS REQUIRED:
1. FerroVer reagent powder pouches (Supplied by HACH)
3. TEST METHOD:
1. Sample to be diluted with DM water so that the concentration of Iron will be less tha
3.00 ppm in the test solution.
2. 25 ml / 10 ml of the diluted solution will be taken in the cuvette. This will be used as a
blank.
3. Place the blank in the cell holder and cover the sample cell with the cap.
4. Zero the equipment and display will be showing 0.00 mg/L Fe.
5. Fill another sample cell with 25/10 ml sample
6. Add the contents of one FerroVer Iron Reagent Powder Pillow to the sample cell (the
prepared sample). Cap and invert to dissolve the reagent powder.
7. Start the timer for 3 mts period.
8. Place the prepared sample into the cell holder. Cover the sample cell with the
instrument cap.
9. Press READ
10. The concentration will be displayed
11. Multiply with dilution factor and report the ppm/ g/lit of Fe concentration.

Signatures

HINDALCO MAHAN

BHEL
BHEL Ref No: PW / TSX /HINDCO/
HINDALCO MAHAN Unit-1 61X150 MW
Plant area: BOILER

Page 24 of 24

PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA

3. ESTIMATION OF HYDRAZINE.
1. REAGENTS .
a. Standard Potassium bromate 0.1 N
Dissolve 2.7836 gram of Potassium bromate (KbrO3) and 10 gram of Potassium
bromide (KBr) in DM / Distilled water and make up to 1000 ml.
b. 0.1 % Methyl orange indicator solution.
c. Hydrochloric acid (conc.) AR.
2. PROCEEDURE.
a) place 10 ml of sample in a titration flask.
b) Add 10 ml of conc. HCl.
c) Add about 5 drops of Methyl orang indicator.
d) Titrate with standard KbrO3 titrant to the first appearance of yellow colour.
3. CALCULATION.
Hydrazine as N2H4, ppm

=

titre value X 80.

Signatures

HINDALCO MAHAN

BHEL

Contenu connexe

Tendances

Unit lightup synchronisation &amp; shutdown
Unit lightup synchronisation &amp; shutdownUnit lightup synchronisation &amp; shutdown
Unit lightup synchronisation &amp; shutdownAshvani Shukla
 
steam turbine turbine interlocks for (KWU turbine)
steam turbine turbine interlocks for (KWU turbine)steam turbine turbine interlocks for (KWU turbine)
steam turbine turbine interlocks for (KWU turbine)Billa ParameswaraRao
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownNitin Mahalle
 
Heat rate audit in thermal power plant
Heat rate audit in thermal power plantHeat rate audit in thermal power plant
Heat rate audit in thermal power plantSHIVAJI CHOUDHURY
 
POWER PLANT CHEMISTRY
POWER PLANT CHEMISTRYPOWER PLANT CHEMISTRY
POWER PLANT CHEMISTRYDilip Kumar
 
Steam Condenser performance and loss diagnostic
Steam Condenser performance and loss diagnosticSteam Condenser performance and loss diagnostic
Steam Condenser performance and loss diagnosticPichai Chaibamrung
 
Ammonia Formation over Steam Reforming Catalysts
Ammonia Formation over Steam Reforming CatalystsAmmonia Formation over Steam Reforming Catalysts
Ammonia Formation over Steam Reforming CatalystsGerard B. Hawkins
 
Performance calculation for feed water heater
Performance calculation  for feed water heaterPerformance calculation  for feed water heater
Performance calculation for feed water heaterSHIVAJI CHOUDHURY
 
Boiler Cycle water chemistry by Sudhanshu Dash
Boiler Cycle water chemistry by Sudhanshu DashBoiler Cycle water chemistry by Sudhanshu Dash
Boiler Cycle water chemistry by Sudhanshu DashSudhanshu Sekhar Dash
 
Water steam Circuit in Supercritical Boiler for 660MW Power Plant
Water steam Circuit in Supercritical Boiler for 660MW Power PlantWater steam Circuit in Supercritical Boiler for 660MW Power Plant
Water steam Circuit in Supercritical Boiler for 660MW Power PlantHareesh VS
 
Steam Reforming - (ATM) Approach to Equilibrium
Steam Reforming - (ATM) Approach to EquilibriumSteam Reforming - (ATM) Approach to Equilibrium
Steam Reforming - (ATM) Approach to EquilibriumGerard B. Hawkins
 
Boilers and Thermic Fluidheaters
Boilers and Thermic FluidheatersBoilers and Thermic Fluidheaters
Boilers and Thermic FluidheatersMusa Sabri
 
Operation of urea fertilizers plant
Operation of urea fertilizers plantOperation of urea fertilizers plant
Operation of urea fertilizers plantPrem Baboo
 
Boiler commissioning procedure
Boiler commissioning procedureBoiler commissioning procedure
Boiler commissioning procedureABVSAI
 
Boiler – fundamentals and best practices
Boiler – fundamentals and best practicesBoiler – fundamentals and best practices
Boiler – fundamentals and best practicesBassem Eleaba, MEng
 

Tendances (20)

Unit lightup synchronisation &amp; shutdown
Unit lightup synchronisation &amp; shutdownUnit lightup synchronisation &amp; shutdown
Unit lightup synchronisation &amp; shutdown
 
steam turbine turbine interlocks for (KWU turbine)
steam turbine turbine interlocks for (KWU turbine)steam turbine turbine interlocks for (KWU turbine)
steam turbine turbine interlocks for (KWU turbine)
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdown
 
Heat rate audit in thermal power plant
Heat rate audit in thermal power plantHeat rate audit in thermal power plant
Heat rate audit in thermal power plant
 
Condensate system
Condensate systemCondensate system
Condensate system
 
POWER PLANT CHEMISTRY
POWER PLANT CHEMISTRYPOWER PLANT CHEMISTRY
POWER PLANT CHEMISTRY
 
Boiler Operation and Maintenance Experiences
Boiler Operation and Maintenance ExperiencesBoiler Operation and Maintenance Experiences
Boiler Operation and Maintenance Experiences
 
Steam Condenser performance and loss diagnostic
Steam Condenser performance and loss diagnosticSteam Condenser performance and loss diagnostic
Steam Condenser performance and loss diagnostic
 
Ammonia Formation over Steam Reforming Catalysts
Ammonia Formation over Steam Reforming CatalystsAmmonia Formation over Steam Reforming Catalysts
Ammonia Formation over Steam Reforming Catalysts
 
Boiler Operation
Boiler OperationBoiler Operation
Boiler Operation
 
All chemical dosing system
All chemical dosing systemAll chemical dosing system
All chemical dosing system
 
Performance calculation for feed water heater
Performance calculation  for feed water heaterPerformance calculation  for feed water heater
Performance calculation for feed water heater
 
Boiler Cycle water chemistry by Sudhanshu Dash
Boiler Cycle water chemistry by Sudhanshu DashBoiler Cycle water chemistry by Sudhanshu Dash
Boiler Cycle water chemistry by Sudhanshu Dash
 
Water steam Circuit in Supercritical Boiler for 660MW Power Plant
Water steam Circuit in Supercritical Boiler for 660MW Power PlantWater steam Circuit in Supercritical Boiler for 660MW Power Plant
Water steam Circuit in Supercritical Boiler for 660MW Power Plant
 
Steam Reforming - (ATM) Approach to Equilibrium
Steam Reforming - (ATM) Approach to EquilibriumSteam Reforming - (ATM) Approach to Equilibrium
Steam Reforming - (ATM) Approach to Equilibrium
 
Boilers and Thermic Fluidheaters
Boilers and Thermic FluidheatersBoilers and Thermic Fluidheaters
Boilers and Thermic Fluidheaters
 
Operation of urea fertilizers plant
Operation of urea fertilizers plantOperation of urea fertilizers plant
Operation of urea fertilizers plant
 
Boiler commissioning procedure
Boiler commissioning procedureBoiler commissioning procedure
Boiler commissioning procedure
 
Heat rate of coal fired power plant
Heat rate of coal fired power plantHeat rate of coal fired power plant
Heat rate of coal fired power plant
 
Boiler – fundamentals and best practices
Boiler – fundamentals and best practicesBoiler – fundamentals and best practices
Boiler – fundamentals and best practices
 

Similaire à Edta cleaning procedurefor_150mw[1]

Chevron Phillips Wastewater treatment system
Chevron Phillips Wastewater treatment systemChevron Phillips Wastewater treatment system
Chevron Phillips Wastewater treatment systemmojarvinod
 
Developed method for treatment of industrial wastewater from edible oil indus...
Developed method for treatment of industrial wastewater from edible oil indus...Developed method for treatment of industrial wastewater from edible oil indus...
Developed method for treatment of industrial wastewater from edible oil indus...Medhat Elzahar
 
OLEFIN HYDROGENATION - VULCAN Series VHT-S101/S103
OLEFIN HYDROGENATION - VULCAN Series VHT-S101/S103OLEFIN HYDROGENATION - VULCAN Series VHT-S101/S103
OLEFIN HYDROGENATION - VULCAN Series VHT-S101/S103Gerard B. Hawkins
 
Application of Hydrodynamic cavitation as advanced oxidation process to treat...
Application of Hydrodynamic cavitation as advanced oxidation process to treat...Application of Hydrodynamic cavitation as advanced oxidation process to treat...
Application of Hydrodynamic cavitation as advanced oxidation process to treat...Sivakumar Kale
 
Report on Effluent Treatment Plant (ETP) Operation and Maintenance of Interst...
Report on Effluent Treatment Plant (ETP) Operation and Maintenance of Interst...Report on Effluent Treatment Plant (ETP) Operation and Maintenance of Interst...
Report on Effluent Treatment Plant (ETP) Operation and Maintenance of Interst...Kowshick Sen
 
Valudor DAF, dissolved air flotation, and SHURE technology combine with proce...
Valudor DAF, dissolved air flotation, and SHURE technology combine with proce...Valudor DAF, dissolved air flotation, and SHURE technology combine with proce...
Valudor DAF, dissolved air flotation, and SHURE technology combine with proce...William Toomey
 
Determination of Oxygen in Anhydrous Ammonia
Determination of Oxygen in Anhydrous AmmoniaDetermination of Oxygen in Anhydrous Ammonia
Determination of Oxygen in Anhydrous AmmoniaGerard B. Hawkins
 
Analysis of BHOPAL Plant Gas Tragedy
 Analysis of BHOPAL Plant Gas Tragedy Analysis of BHOPAL Plant Gas Tragedy
Analysis of BHOPAL Plant Gas TragedyRita EL Khoury
 
Determination of Inert Gas in Anhydrous Ammonia
Determination of Inert Gas in  Anhydrous AmmoniaDetermination of Inert Gas in  Anhydrous Ammonia
Determination of Inert Gas in Anhydrous AmmoniaGerard B. Hawkins
 
Jay 5 bw
Jay 5 bwJay 5 bw
Jay 5 bwJeroxxx
 
EXTRACTION OF ANTIOXIDANTS FROM ONION PEEL
EXTRACTION OF ANTIOXIDANTS FROM ONION PEELEXTRACTION OF ANTIOXIDANTS FROM ONION PEEL
EXTRACTION OF ANTIOXIDANTS FROM ONION PEELIRJET Journal
 
GPO Application Dataset
GPO Application DatasetGPO Application Dataset
GPO Application Datasetjnic
 
General Water Treatment For Cooling Water
General Water Treatment For Cooling WaterGeneral Water Treatment For Cooling Water
General Water Treatment For Cooling WaterGerard B. Hawkins
 
Implementation of Biological Effluent Treatment Plant for Waste Water Treatme...
Implementation of Biological Effluent Treatment Plant for Waste Water Treatme...Implementation of Biological Effluent Treatment Plant for Waste Water Treatme...
Implementation of Biological Effluent Treatment Plant for Waste Water Treatme...IJSRED
 

Similaire à Edta cleaning procedurefor_150mw[1] (20)

Bio toilets-ppt
Bio toilets-pptBio toilets-ppt
Bio toilets-ppt
 
Chevron Phillips Wastewater treatment system
Chevron Phillips Wastewater treatment systemChevron Phillips Wastewater treatment system
Chevron Phillips Wastewater treatment system
 
Developed method for treatment of industrial wastewater from edible oil indus...
Developed method for treatment of industrial wastewater from edible oil indus...Developed method for treatment of industrial wastewater from edible oil indus...
Developed method for treatment of industrial wastewater from edible oil indus...
 
Pickling & Passivation
Pickling & PassivationPickling & Passivation
Pickling & Passivation
 
Loctite 401 msds
Loctite 401 msdsLoctite 401 msds
Loctite 401 msds
 
OLEFIN HYDROGENATION - VULCAN Series VHT-S101/S103
OLEFIN HYDROGENATION - VULCAN Series VHT-S101/S103OLEFIN HYDROGENATION - VULCAN Series VHT-S101/S103
OLEFIN HYDROGENATION - VULCAN Series VHT-S101/S103
 
Application of Hydrodynamic cavitation as advanced oxidation process to treat...
Application of Hydrodynamic cavitation as advanced oxidation process to treat...Application of Hydrodynamic cavitation as advanced oxidation process to treat...
Application of Hydrodynamic cavitation as advanced oxidation process to treat...
 
Report on Effluent Treatment Plant (ETP) Operation and Maintenance of Interst...
Report on Effluent Treatment Plant (ETP) Operation and Maintenance of Interst...Report on Effluent Treatment Plant (ETP) Operation and Maintenance of Interst...
Report on Effluent Treatment Plant (ETP) Operation and Maintenance of Interst...
 
Valudor DAF, dissolved air flotation, and SHURE technology combine with proce...
Valudor DAF, dissolved air flotation, and SHURE technology combine with proce...Valudor DAF, dissolved air flotation, and SHURE technology combine with proce...
Valudor DAF, dissolved air flotation, and SHURE technology combine with proce...
 
Loctite 406 msds
Loctite 406 msdsLoctite 406 msds
Loctite 406 msds
 
Determination of Oxygen in Anhydrous Ammonia
Determination of Oxygen in Anhydrous AmmoniaDetermination of Oxygen in Anhydrous Ammonia
Determination of Oxygen in Anhydrous Ammonia
 
Analysis of BHOPAL Plant Gas Tragedy
 Analysis of BHOPAL Plant Gas Tragedy Analysis of BHOPAL Plant Gas Tragedy
Analysis of BHOPAL Plant Gas Tragedy
 
Determination of Inert Gas in Anhydrous Ammonia
Determination of Inert Gas in  Anhydrous AmmoniaDetermination of Inert Gas in  Anhydrous Ammonia
Determination of Inert Gas in Anhydrous Ammonia
 
Jay 5 bw
Jay 5 bwJay 5 bw
Jay 5 bw
 
EXTRACTION OF ANTIOXIDANTS FROM ONION PEEL
EXTRACTION OF ANTIOXIDANTS FROM ONION PEELEXTRACTION OF ANTIOXIDANTS FROM ONION PEEL
EXTRACTION OF ANTIOXIDANTS FROM ONION PEEL
 
HIGH PERFORMANCE THIN LAYER CHROMATOGRAPHY
HIGH PERFORMANCE THIN LAYER CHROMATOGRAPHYHIGH PERFORMANCE THIN LAYER CHROMATOGRAPHY
HIGH PERFORMANCE THIN LAYER CHROMATOGRAPHY
 
GPO Application Dataset
GPO Application DatasetGPO Application Dataset
GPO Application Dataset
 
General Water Treatment For Cooling Water
General Water Treatment For Cooling WaterGeneral Water Treatment For Cooling Water
General Water Treatment For Cooling Water
 
BenchMark Special Stains Product Guide
BenchMark Special Stains Product GuideBenchMark Special Stains Product Guide
BenchMark Special Stains Product Guide
 
Implementation of Biological Effluent Treatment Plant for Waste Water Treatme...
Implementation of Biological Effluent Treatment Plant for Waste Water Treatme...Implementation of Biological Effluent Treatment Plant for Waste Water Treatme...
Implementation of Biological Effluent Treatment Plant for Waste Water Treatme...
 

Dernier

Structuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdfStructuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdflaloo_007
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingNauman Safdar
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperityhemanthkumar470700
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon investment
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizharallensay1
 
Power point presentation on enterprise performance management
Power point presentation on enterprise performance managementPower point presentation on enterprise performance management
Power point presentation on enterprise performance managementVaishnaviGunji
 
Over the Top (OTT) Market Size & Growth Outlook 2024-2030
Over the Top (OTT) Market Size & Growth Outlook 2024-2030Over the Top (OTT) Market Size & Growth Outlook 2024-2030
Over the Top (OTT) Market Size & Growth Outlook 2024-2030tarushabhavsar
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165meghakumariji156
 
Buy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From SeosmmearthBuy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From SeosmmearthBuy Verified Binance Account
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateCannaBusinessPlans
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
Cracking the 'Career Pathing' Slideshare
Cracking the 'Career Pathing' SlideshareCracking the 'Career Pathing' Slideshare
Cracking the 'Career Pathing' SlideshareWorkforce Group
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfwill854175
 
Falcon Invoice Discounting: Tailored Financial Wings
Falcon Invoice Discounting: Tailored Financial WingsFalcon Invoice Discounting: Tailored Financial Wings
Falcon Invoice Discounting: Tailored Financial WingsFalcon Invoice Discounting
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...ssuserf63bd7
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon investment
 
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSCROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSpanmisemningshen123
 
BeMetals Investor Presentation_May 3, 2024.pdf
BeMetals Investor Presentation_May 3, 2024.pdfBeMetals Investor Presentation_May 3, 2024.pdf
BeMetals Investor Presentation_May 3, 2024.pdfDerekIwanaka1
 

Dernier (20)

Structuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdfStructuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdf
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
 
Power point presentation on enterprise performance management
Power point presentation on enterprise performance managementPower point presentation on enterprise performance management
Power point presentation on enterprise performance management
 
Over the Top (OTT) Market Size & Growth Outlook 2024-2030
Over the Top (OTT) Market Size & Growth Outlook 2024-2030Over the Top (OTT) Market Size & Growth Outlook 2024-2030
Over the Top (OTT) Market Size & Growth Outlook 2024-2030
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
 
Buy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From SeosmmearthBuy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From Seosmmearth
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck Template
 
Buy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail AccountsBuy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail Accounts
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Cracking the 'Career Pathing' Slideshare
Cracking the 'Career Pathing' SlideshareCracking the 'Career Pathing' Slideshare
Cracking the 'Career Pathing' Slideshare
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
Falcon Invoice Discounting: Tailored Financial Wings
Falcon Invoice Discounting: Tailored Financial WingsFalcon Invoice Discounting: Tailored Financial Wings
Falcon Invoice Discounting: Tailored Financial Wings
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSCROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
 
BeMetals Investor Presentation_May 3, 2024.pdf
BeMetals Investor Presentation_May 3, 2024.pdfBeMetals Investor Presentation_May 3, 2024.pdf
BeMetals Investor Presentation_May 3, 2024.pdf
 

Edta cleaning procedurefor_150mw[1]

  • 1. RECOMMENDED PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA (Ethylene Diamine Tetra Acetic Acid ) PROJECT: HINDALCO MAHAN ALUMINUM 6X150MW UNITS BHEL Ref No. BHEL/TSX/ DOC. NO. REV.NO: 1 PS WR BHARAT HEAVY ELECTRICALS LIMITED POWER SECTOR –WESTERN REGION Shree Mohini Complex,345 – Kingsway ,Nagpur – 440 031
  • 2. BHEL Ref No: PW / TSX /HINDCO/ HINDALCO MAHAN Unit-1 61X150 MW Plant area: BOILER Page 2 of 24 PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA PROJECT HINDALCO MAHAN ALUMINUM 6X150MW UNITS PROCEDURE PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA PURPOSE DOCUMENT FOR EXECUTION / INFORMATION DOCUMENT DOC.NO. BHEL/TSX 00 Santosh Kumar Rev.No. Prepared by Niranjan Ray Reviewed by Approved by Date BHARAT HEAVY ELECTRICALS LIMITED POWER SECTOR –WESTERN REGION Shree Mohini Complex,345 – Kingsway ,Nagpur – 440 031 Signatures HINDALCO MAHAN BHEL
  • 3. BHEL Ref No: PW / TSX /HINDCO/ HINDALCO MAHAN Unit-1 61X150 MW Plant area: BOILER Page 3 of 24 PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA 1.0 PLANT DETAILS 2.0 OBJECTIVES 3.0 PROPOSALS 4.0 SERVICES REQUIRED 5.0 EMERGENCY PROVISIONS 6.0 EMERGENCY PROCEDURES 7.0 STATE OF THE PLANT 8.0 PROCESS PROCEDURE 9.0 COMPLETION CRITERIA 10.0 CHEMICAL CLEANING WASTE TREATMENT & DISPOSAL 11.0 APPENDICES A) DRAWING B) ANALYTICAL PROCEDURES C) LOG SHEET FORMATS Signatures HINDALCO MAHAN BHEL
  • 4. BHEL Ref No: PW / TSX /HINDCO/ HINDALCO MAHAN Unit-1 61X150 MW Plant area: BOILER Page 4 of 24 PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA Sl. No 1.0 STATUS PLANT DETAILS The steam Generator is a natural circulation boiler with Plain water wall tubes. Boiler Design Data: SH outlet Pressure SH outlet Temperature Feed Water Temperature (at eco inlet) Maximum Continuous Rating Water Holding Capacity 1. Water wall + Drum (full) 2. Economizer 3. Superheater 4. Reheater 2.0 - 149 Kg/cm 2 - 540 0C - 250 0 C - 510 t/h. -115 -40 -65 -30 m3 m3 m3 m3 OBJECTIVE The objective of this procedure is to chemically clean and passivate the internal surfaces of the steam generating portion (water touched surfaces) and heating surfaces (Economizer) using specified chemicals employing a single step process. This will render the above mentioned surfaces free of mill scale, and other deposits and form uniform & smooth protective layer of magnetite. With this protective layer, the generating surfaces are rendered passive to generate adequate negative potential under the operating pH to resist corrosion. 3.0 PROPOSAL 3.1 The objectives are achieved by carrying out the following proposals. 3.2 By carrying out water rinsing to remove loose rust, debris, oil and grease, if any, left in the Boiler. 3.3 Then, it is subjected to acid cleaning for the removal of patchy mill scale and adherent rust. Signatures HINDALCO MAHAN BHEL
  • 5. BHEL Ref No: PW / TSX /HINDCO/ HINDALCO MAHAN Unit-1 61X150 MW Plant area: BOILER Page 5 of 24 PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA Sl. No STATUS The acid pickled surface is passivated for the formation of uniform and adherent magnetite layer. Both chemical cleaning and passivation process are completed in a single step. 4.0 SERVICES REQUIRED 4.1 Prior to the commencement of chemical cleaning, all the DM water storage tanks should be kept full and the de-mineralizing units kept in regenerated condition. Approximately, 300 m³ of DM water will be consumed for the entire process. At any time of acid cleaning, a minimum of two boiler volumes (app. 600 M3) of DM water should be available in ready stock to facilitate rapid flushing of the system in the event of chemistry upset. 4.2 All the required quantities of chemicals as given below should be made available prior to the commencement of the process. SPECIFICATION OF CHEMICALS & QUANTITY NAME OF CHEMICALS QTY/Each Boiler 1. Tri Sodium Phosphate (Purity, as P2O5 :17.5% Min) 110 kgs 2. Disodium Hydrogen Phosphate (99 % purity) 60 kgs 3. Ammoniated EDTA, 40% wt/wt as active EDTA ammoniated solution pH=9.0 to 9.8) (EDTA : Ethylene diamine tetra acetic acid- C10H16N2O8 ) Density : 1.18 15 tons 2. Ammonia solution (20% Min as NH3, sp gr:0.91) as per IS 799 / 1990 600 Liters 3. Hydrazine Hydrate (80% Min. conc). To IS 12086/1991 700 Litres 4. Bhelmax 250 kg 5. Bhelsol 250 Litres 4.3 Temporary drum water level gauge glass and (Tel-tale lamp indication) at control room and low point drain area. Signatures HINDALCO MAHAN BHEL
  • 6. BHEL Ref No: PW / TSX /HINDCO/ HINDALCO MAHAN Unit-1 61X150 MW Plant area: BOILER Page 6 of 24 PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA Sl. No 4.4 HT / LT Supply to be available. STATUS 4.5 Control supply to be available. 4.6 Instrument/service Air to be available. 4.7 Chemist/Express lab to be made available for testing during the process. 4.8 Flood lights / telephones / walkie-talkie are available. 4.9 For effluent treatment, compressed air facility and suitable perforated Carbon Steel / polythene tubing arrangement shall be made available. 4.10 SAFETY EQUIPMENTS: 1. Gum boots (Various sizes) 6 Pairs 2. Rubber gloves 6 Pairs 3. Rubber or Polythene aprons 6 Nos. 4. Helmets 12 Nos. 5. Safety goggles plain glass 6 Nos. 6. Face mask (Transparent, plastic) 4 Nos. 7. First aid box (containing dilute ammonium hydroxide, 50% sodium bicarbonate solution, eye lotion, bandages, tincture of iodine, cotton, burnol etc) 5.0 EMERGENCY PROVISIONS 5.1 Flushing and washing water supplies Ample supplies of rapid flushing and washing water supplies shall be provided at all possible points of discharge, spillage or escape of chemicals. Signatures HINDALCO MAHAN BHEL
  • 7. BHEL Ref No: PW / TSX /HINDCO/ HINDALCO MAHAN Unit-1 61X150 MW Plant area: BOILER Page 7 of 24 PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA Sl. No 5.2 5.3 STATUS Adequate provisions shall be made for emergency treatment of the eyes, comprising eye wash bottles, located conveniently to places where discharge, spillage or escape of chemicals can occur. Safety shower shall be provided. 5.4 A suitable first aid treatment room with outside telephone facilities shall be provided within a reasonable distance of the place where chemicals are being used. 5.5 The protective clothing and apparatus required for emergency use shall be made available near the acid cleaning area. 5.6 FIRST AID TREATMENT 5.7 Splashes of the eye 5.7.1 Immediately flood the eye with water. To be effective the eyelids must be opened. The eyelids should be pushed apart using the thumb and index finger of the left hand. The casualty will probably not be able to open the eye himself because of painful spasms. 5.7.2 If an eye wash bottle is used the jet should not be directed at the front of the eye. It should be directed in from the side, so that flow is over the surface of the eye. 5.7.3 Irrigation should be continued for 5 – 10 minutes after which the casualty should be taken to the first aid room. 5.7.4 Irrigation should be continued in the first aid room. Remember vision is saved by thorough irrigation; no other treatment can prevent damage if this is omitted. 5.7.5 After thorough irrigation the eye should be covered with a pad; the patient should be referred for medical opinion. 5.7.6 Irritation of the skin Signatures HINDALCO MAHAN BHEL
  • 8. BHEL Ref No: PW / TSX /HINDCO/ HINDALCO MAHAN Unit-1 61X150 MW Plant area: BOILER Page 8 of 24 PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA Sl. No 5.8 5.9 STATUS If signs of skin irritation occur the persons should be removed from contact and referred for medical opinion. In the event of the splashing of the skin with chemicals the effected area should be washed thoroughly avoiding spreading contamination to the face and eyes. GENERAL 5.9.1 Test area will be cordoned off and unauthorized persons entry shall be prohibited. Suitable signboard shall be displayed. 5.9.2 Whenever any inspection is made during the cleaning process, the location should be adequately ventilated. 5.10 SAFETY OF PLANT: A) If the light up after cleaning could not be done within 4 weeks after completion of cleaning, the system will be suitably preserved. B) Temperature limitations specified for various steps should not be exceeded. 6.0 EMERGENCY PROCEDURES: 6.1 The testing team should be aware of the operating procedures of fire extinguishers to be used for quenching minor or major fires. 6.2 The testing team should be aware of the procedure to be followed in case of accidents involving personnel injury. 6.3 In case of failure of running pump the stand by pump should be started immediately without delay. 6.4 An operator posted at the pump area, should be instructed to stop the pumps and properly isolate the system in the event of emergency. All operators should be well conversant with the emergency operating instructions. 7.0 STATE OF THE PLANT Signatures HINDALCO MAHAN BHEL
  • 9. BHEL Ref No: PW / TSX /HINDCO/ HINDALCO MAHAN Unit-1 61X150 MW Plant area: BOILER Page 9 of 24 PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA Sl. No 7.1 7.2 STATUS Readiness of the following is to be ensured. During the EDTA cleaning process, all the permanent boiler instruments are isolated except providing a temporary pressure gauge of 0 to 5.0 kg/cm2 in the drum for monitoring pressure in the drum during EDTA cleaning. Provisions should be made at the following locations for the measurement of temperature. A) Two locations in the drum (left & right) for the measurement of boiler Water temperature. Long thermocouples of around 400 mm length shall be installed directly in the spare / unused stubs in the drum. B) Water wall metal temperature measurements as given below: At AB elevation, 4 number thermocouples shall be installed on corner water wall tubes (outside the furnace) and at CD elevation 2 numbers thermocouples shall be installed in the front and rear water wall (outside the furnace) at accessible locations. C).Two more thermocouples with pads one each at left and right side of ECO coil shall be welded at suitable locations, inside the boiler (or penthouse) to measure the metal temp in the gas side. (Total 6 Nos thermocouples will be used for measurement of water wall tube metal temperature and 2 Nos for economizer tube temperature) Preening type temporary thermocouples are to be provided in the temp measurement points on the water walls and economizer. Provision has to be made for monitoring temperature in the control room. 7.3 SAMPLING DURING PROCESS To get representative samples of the process solution, sampling points with sample coolers are to be provided at the following Signatures HINDALCO MAHAN BHEL
  • 10. BHEL Ref No: PW / TSX /HINDCO/ HINDALCO MAHAN Unit-1 61X150 MW Plant area: BOILER Page 10 of 24 PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA Sl. No STATUS locations: A) Drum water sample to be drawn from CBD sampling cooler and from a spare tapping point in water side through the permanent saturated steam coolers. B) Two numbers of sampling point is to be provided from bottom ring header through hand-hole cover. 7.4 For rinsing, chemical cleaning and passivation processes, essential control and instruments viz. protections, interlock, alarms, measurement, annunciation etc. required for safe light-up of boiler are made available, as per mutually agreed list between M/S Hindalco Mahan and BHEL site. 7.5 All the related boiler auxiliaries are made ready and available for boiler light up. This includes chemical dozing pumps, tanks, fans, oil pumps etc. A checklist, containing minimum operational requirements to be made ready prior to commencement of Chemical cleaning is enclosed at 7.15. 7.6 Prior to the commencement of flushing/rinsing of the boiler, detergent flushing of pre-boiler system is to be completed. 7.7 In the steam drum, primary separators and screen driers are to be installed and secondary separators are not to be installed. In the drum, the screen plates shall be retained. orifices are not to be installed. 7.8 The flap in the eco recirculation line NRV can be removed for fast filling and draining of economizer (optional). The eco recirculation valve shall be kept open throughout the chemical cleaning process. Economizer inlet valve shall be kept closed. 7.9 O&M instruction for the boiler and other auxiliaries are to be available well in advance of the commencement of the cleaning process. 7.10 All the safety measures discussed and implemented in advance with suitable instruction/caution tags provided at strategic places/ Signatures HINDALCO MAHAN BHEL
  • 11. BHEL Ref No: PW / TSX /HINDCO/ HINDALCO MAHAN Unit-1 61X150 MW Plant area: BOILER Page 11 of 24 PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA Sl. No STATUS equipment. 7.11 Boiler water wall test tube coupons are placed at two ends inside the drum to see the effectiveness of the cleaning. 7.12 Proper effluent treatment arrangement is to be made available at site. 7.13 All fabrication work to be completed as per scheme provided. 7.14 Inhibitor efficiency test shall be carried out at BHEL Trichy or at inhibitor vendor’s works. 7.15 MINIMUM OPERATIONAL REQUIREMENTS. 1. Ensure the commissioning of the following including their protections, interlocks, measurements, alarms and annunciations:- ONE ID FAN, ONE FD FAN, ONE AIR PRE-HEATER, LIGHT OIL FIRING SYSTEM, FSSS, SADC, SCANNER AIR SYSTEM. Measurements, alarms, annunciations pertaining to secondary air flue gas, feed water, steam & boiler metal temp. 2. Ensure free expansion of the furnace and duct and provision of expansion markers 3. Blow down system of boiler 4. Proper drainage system of boiler area 5. Air leak test of two passes of ESP 6. Mechanical readiness of two passes of ESP. 7. Adequate quantity of light oil & readiness of light oil handling system. 8. Completion of pre-boiler system detergent flushing. Signatures HINDALCO MAHAN BHEL
  • 12. BHEL Ref No: PW / TSX /HINDCO/ HINDALCO MAHAN Unit-1 61X150 MW Plant area: BOILER Page 12 of 24 PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA Sl. No STATUS 9. Temporary sampling system along with the cooling arrangement for collecting samples from the header drains. 10. Water and steam systems readiness for operation 11. Air and flue gas system readiness for operation 12. Effluent treatment pit to hold approximately 600 m3 . 13. Drainage line to effluent treatment is ready 14. Readiness of BFP and feed system (optional) 15. Drum water sampling system along with sample cooling arrangement. 16. DG set, DG switchgear, emergency switch gear and availability of emergency supplies for:  Scanner air fan.  Emergency lighting. 17. UPS readiness. 18. Fire fighting system of concerned equipments 19. Equipment cooling water system shall be made ready. 20. Availability of adequate quantity of DM water. 21. Adequate capacity of instrument air and service air system 22. Availability of HP dozing system. 23. Availability of test coupons & their fixing arrangements. 24. Emergency operating instructions viz. AC power failure, DC. Power failure, APH fire etc. 25. Adequate lighting in operating areas. 26. Public address system at all operating locations, including telephone & walkie talkies at all working areas 27. Readiness of staircases, hand railings and platforms 28. Personal safety equipment. 29. Easy access and approaches to all the operating equipments. 30. SH metal temperature measurement shall be made ready for continuous monitoring in the control room. 31. Data logging printer at control room shall be made available to record the boiler parameters periodically. 32. Proper isolation of APH, which will not be taken into service, will be insured. Alternately, the same be kept running. 8.0 8.1 8.1.1 PROCESS PROCEDURE ALKALI FLUSHING: Signatures HINDALCO MAHAN BHEL
  • 13. BHEL Ref No: PW / TSX /HINDCO/ HINDALCO MAHAN Unit-1 61X150 MW Plant area: BOILER Page 13 of 24 PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA Sl. No STATUS 8.1.2 The requisite quantities of (a) Tri-sodium Phosphate (TSP) & (b) Di Sodium Hydrogen Phosphate to be added to the mixing tank along with DM Water and the solution will be thoroughly mixed by recirculation so that final solution in the Boiler contains 0.1 % TSP and 0.05 % DSP. The solution will be injected into the boiler through the bottom ring header drains and economizer drain operating the chemical filling pump. Further DM water will be taken in the boiler up to normal level. 8.1.3 Light up the boiler as per O&M instructions and gradually raise the boiler water temperature to 130–140 deg C. Trip the boiler and keep the fans running for cooling. Drain the boiler at 90 0 C to the plant water disposal system, by keeping open the drain valves fully (without any throttling). The drain solution will be diluted with plenty of service water. 8.2 8.2.1 HOT WATER RINSING 8.2.2 Once the draining is completed, refill the boiler with DM water Light up the boiler. Gradually raise the boiler water temperature to 130-1400 C. Trip the boiler and keep the fans running for cooling. 8.2.3 Drain the boiler in the hot condition to the plant’s water disposal system by keeping open the drain valves fully (without throttling). The pH and PO4 will be measured in the drain water. The pH and PO4 are to be reduced to a level below 7.5 and 10 ppm respectively 8.3 8.3.1 COLD WATER RINSING Cold water rinses will be done by fill and dump method. During these steps, draining will be done to the plant’s water disposal system. pH will be monitored during draining of each cold water rinse stage. The rinsing operation will be continued until the pH of the drain water is almost equal to pH of inlet water used for Signatures HINDALCO MAHAN BHEL
  • 14. BHEL Ref No: PW / TSX /HINDCO/ HINDALCO MAHAN Unit-1 61X150 MW Plant area: BOILER Page 14 of 24 PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA Sl. No 8.3.2 STATUS rinsing. Flush all sampling and blow down lines. Check all temperature / pressure measurements relevant to the process for monitoring at UCB and ensure their reliability. The following guide line should be followed besides O & M instruction for boiler light up. LIGHTING UP Drum air vents SH air vents & start up Vents is to be opened before lighting up the boiler. Initiate boiler light up as per O & M instructions. Drum level is to be monitored closely and controlled below normal level by operating down comer blow down from UCB or draining and filling the boiler at drain header. Drum level Temporary indication shall be displayed at UCB and near drain header. 8.4 8.4.1 EDTA CLEANING & PASSIVATION. 8.4.2 In this process the mixture of chemical solutions containing EDTA, inhibitor, ammonia (if required) and hydrazine in DM water is filled in the boiler. Boiler is fired and the temperature raised to 140-145 0 C and held for 4 hours and subsequently cooled. The removal of deposit constituents and subsequent Passivation of the metal surfaces will occur during this single step. 8.4.3 The required quantity of ammoniated EDTA (40% wt / wt) solution will be kept ready in the EDTA storage tank. 8.4.4 The inhibitors “BHEL MAX” & “BHELSOL”, Hydrazine hydrate and ammonia for addition in the Chemical dissolving tank will also be made available near the mixing tank. 8.4.5 All the Boiler Blow down valves are kept shut and drum vent valves & start up vent open during boiler filling. Signatures HINDALCO MAHAN BHEL
  • 15. BHEL Ref No: PW / TSX /HINDCO/ HINDALCO MAHAN Unit-1 61X150 MW Plant area: BOILER Page 15 of 24 PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA Sl. No 8.4.6 STATUS 40 m3 of DM water will be drawn in the dissolving tank. The temporary chemical fill pump will be started and system put into recirculation. The required quantity of Ammoniated EDTA (40% wt/wt) solution will be transferred from the EDTA storage tank to the dissolving tank. The EDTA concentration in the dissolving tank will be checked. Transferring the EDTA solution will be stopped, when the EDTA concentration reaches around 3 + 1% by weight. Required quantity of Hydrazine hydrate and inhibitors (BHEL Max & BHEL Sol) will also be added. Recirculation will be done till all the chemicals uniformly mixed up. With this one batch of EDTA Chemical solution will be ready for filling into the boiler. The quantities of various chemicals that are to be mixed per batch of 40 m3 is given below: 1. EDTA ammoniated (40 % ) concentrate : 2. BHELMAX : 3. BHELSOL : 4. N2H4.H2O (80%) : 8.4.7 3 to 4 m 3 60 kgs 60 litres 60 litres Ammonia will be added if required to adjust the pH between 9.0 to 9.8. DM water will be used to make up to 40 m 3 . This solution will be filled into the Boiler through LP drain header Boiler fill line with the temporary chemical fill pump. The cleaning solution is quite harmless w.r.t. corrosion and hence there is no time limitation for filling the boiler and retaining the solution inside the boiler. Repeat the preparation of Chemical solution and batch filling as explained in point no 8.4.5 till water level in the drum reaches the center line of the gauge glass. The composition of the filling solution shall be as below: 8.4.8 8.4.8.1 EDTA content Hydrazine pH : : : 3 + 1% W/v 1000 ppm (min) 9.0 to 9.8 The boiler will be lighted up as per normal operating procedure with minimum firing rate (say 2 oil guns in AB elevation) Signatures HINDALCO MAHAN BHEL
  • 16. BHEL Ref No: PW / TSX /HINDCO/ HINDALCO MAHAN Unit-1 61X150 MW Plant area: BOILER Page 16 of 24 PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA Sl. No STATUS 8.4.8.2 The drum and super heater vents are to be closed when steaming starts, say at 1 kg/cm 2 in the drum and keep open the SH start up vent. 8.4.8.3 The drain valve in S.H. header –1 will be kept in crack opened Condition. 8.4.8.4 Note the time at which the temperature of boiler water reaches 110 0C. 8.4.8.5 Continue raising the temperature of boiler water to a saturation temperature of 140 0C. 8.4.8.6 Once the temperature of boiler water reaches 140 0C, control the firing rate in such a way that the boiler water temperature is maintained at 140 to 145 0C, for a min period of 4 hours. Then trip the boiler. 8.4.8.7 Continue running the ID/FD fans to bring down the boiler water temperature. In case it appears that the results of iron concentration may not level out when temp is expected to be 110 0 C, ID/FD fans shall be stopped, suitably, during the cooling down phase & boiler shall be boxed up and kept in this condition to achieve the EDTA contact period of 8 hours with temperature exceeding 110 0C. 8.4.8.8 Samples have to be taken every 30 minutes from the sampling points at locations given as per 7.3, from the time when the temperature in the system has reached 110 0C and analyzed for pH, EDTA concentration, and Iron content. 8.4.8.9 After attaining the completion criteria of pickling process, as per clause 8.5, the system shall be allowed to cool with the ID & FD fans in operation (ID & FD fans are to be restarted, in case they have been stopped to meet the completion criteria, to bring down the boiler water temperature). Open the drum air vents when the pressure reaches to 1 kg/cm2. Boiler water temperature & Water Wall Metal temperature at the Signatures HINDALCO MAHAN BHEL
  • 17. BHEL Ref No: PW / TSX /HINDCO/ HINDALCO MAHAN Unit-1 61X150 MW Plant area: BOILER Page 17 of 24 PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA Sl. No 8.4.8.10 STATUS locations indicated as per 7.2 are to be measured and logged. When the temperature comes down to 95 0C, the system shall be drained completely in hot condition to the effluent pit by opening all the drain valves. 8.5 8.5.1 PROCESS COMPLETION CRITERIA 8.5.2 Cleaning process is to be continued till iron concentration in three consecutive samples show equilibrium status. 8.5.3 When the iron concentration in the cleaning solution is constant, it indicates that all the oxides have been dissolved. However, a minimum EDTA contact period of 6 hours from the time of attaining the required temperature (110 0C) shall be allowed. If the iron concentration values do not level out and attain equilibrium status, regardless of analytical results, the EDTA contact period with temperature exceeding 110 0C shall not be allowed for more than 8 hours (approx). 8.6 8.6.1 TREATED DM WATER RINSING: 8.6.2 Prepare a blended solution of ammonia & Hydrazine with calculated quantities in the Dissolving tank in order to achieve a solution pH 9.0 to 9.5 and hydrazine content 50 ppm in the DM water being filled in the boiler. Steam heats the solution to a temperature of 60 0C before admitting into the boiler. 8.6.3 Fill the boiler with the above treated DM water through low point drains and economizer as practiced earlier, up to just above the centre gauge glass. 8.6.4 Light up the boiler as per O&M instruction maintain drum level up to 100 mm above NWL 8.6.5 Raise boiler water temperature up to 110 0C and then shut down the boiler. Allow the boiler to cool down naturally. Signatures HINDALCO MAHAN BHEL
  • 18. BHEL Ref No: PW / TSX /HINDCO/ HINDALCO MAHAN Unit-1 61X150 MW Plant area: BOILER Page 18 of 24 PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA Sl. No STATUS 8.6.6 When the boiler water temperature comes down to 95 0C, drain the boiler to the effluent pit and allow the system for natural aeration. 8.6.7 Open upper & lower drums for inspection. Manually clean the drums if required. Refit the drum internals and restore the boiler and prepare it for regular operation for steam blowing, safety valve floating etc. 9.0 9.1 INSPECTION CRITERIA: 9.2 The test coupons placed at identified locations will be taken out. All coupons shall be free of deposits and shall have uniform coating of the protective layer. 9.3 The drum surface shall be visually inspected for uniform smooth coating of protective layer. The low point headers will be inspected and loose debris if any, will be removed. 10.0 10.1 CHEMICAL CLEANING WASTE TREATMENT & DISPOSAL. 10.2 Treatment and disposal of the waste and effluents of the chemical cleaning process shall comply with the requirements / stipulations of state pollution control board norms. 10.3 Hot DM water flushing shall be drained into plant normal drain. The organic spent EDTA chemical solution after the cleaning process is drained into a pit. The pH of the effluent will be in the range of 8.5 to 9.0 and hence no treatment for pH adjustment is required as it would meet the pH requirement for disposal. Typical relative composition of the process solution (Temp. 75 0C) immediately after draining is given below: Signatures HINDALCO MAHAN BHEL
  • 19. BHEL Ref No: PW / TSX /HINDCO/ HINDALCO MAHAN Unit-1 61X150 MW Plant area: BOILER Page 19 of 24 PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA Sl. No 10.4 11.0 11.1 11.1.1 11.1.2 STATUS 1. 2. 3. 4. EDTA <15 g/l N2H4 <0.05 g/l Fe <10.0 g/l Compressed air shall be used to destroy the residual Hydrazine & organics and the effluent shall be disposed after aeration for 10 days, as per state pollution control board norms. Effluent will be disposed to ash dyke in installments through existing ash slurry system (The organic chemical is completely bio-degradable). APPENDIX NOTE (Refer Drawings attached) Drains to be provided at lowest points of temporary piping. 11.1.3 All temporary connections to Boiler should be of radiographic quality. 11.1.4 Service water supply should be available near the pump operating areas. 11.1.5 Additional Check lists/Modifications in the lay-out, if found necessary, to be made at site in consultation with site Commissioning In-charge. 11.2 All the sampling points along with sample coolers and the temperature measurement points with necessary thermocouples shall be provided as indicated in 7.3 & 7.2 respectively. TERMINATION CRITERIA AT A GLANCE 11.2.1 Termination Criteria for each step will be as follows: (Ref.8.1,8.2,8.3) Alkali Flushing, Hot water flushing & cold water rinses: 11.2.2 pH: < 7.5 PO4 < 10 ppm (Ref. 8.4.) 11.2.2.1 Acid cleaning & Passivation: Cleaning process is to be continued till iron concentration in three Signatures HINDALCO MAHAN BHEL
  • 20. BHEL Ref No: PW / TSX /HINDCO/ HINDALCO MAHAN Unit-1 61X150 MW Plant area: BOILER Page 20 of 24 PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA Sl. No 11.2.2.2 STATUS consecutive samples show equilibrium status. 11.2.2.3 When the iron concentration in the cleaning solution is constant, it indicates that all the oxides have been dissolved. However, a minimum EDTA contact period of 6 hours from the time of attaining the required temperature (110 0C) shall be allowed. 11.2.2.4 If the iron concentration values do not level out and attain equilibrium status, regardless of analytical results, the EDTA contact period with temperature exceeding 110 0C shall not be allowed for more than 8 hours (approx). 11.2.3 (Ref 8.6) Declare the completion of pickling process once the EDTA strength and iron concentration level out and reach equilibrium. Treated DM Water Rinsing: Completion criteria will be with one treated DM water rinse. Inspection criteria: The test coupons placed at identified locations will be taken out. All coupons shall be free of deposits and shall have uniform coating of the protective layer. The drum surface shall be visually inspected for uniform smooth coating of protective layer. Chemical Cleaning Waste Treatment & Disposal: pH: 5.0 to 9.0 The effluent will be disposed after ten days of aeration as per local Pollution control board norms. Signatures HINDALCO MAHAN BHEL
  • 21. BHEL Ref No: PW / TSX /HINDCO/ HINDALCO MAHAN Unit-1 61X150 MW Plant area: BOILER Page 21 of 24 PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA LOG SHEET PROJECT : HINDALCO MAHAN 6X150MW UNITS DATE: 18/01/2012 UNIT NO. : 1 ACTIVITY: EDTA ACID CLEANING AND PASSIVATION I. ADDITION OF CHEMICALS: ____________________________________________________________________ Sl. No. DATE TIME NAME OF CHEMICAL ADDED QUANTITY _____________________________________________________________________ II. ANALYTICAL DATA: _____________ _________________________________________________ Sl. DATE TIME SAMPLE POINT TOTAL EDTA IRON pH No. HRS. % PPM 1. 2. 3. 4. 5. . ____________________________________________________________________ Signatures HINDALCO MAHAN BHEL
  • 22. BHEL Ref No: PW / TSX /HINDCO/ HINDALCO MAHAN Unit-1 61X150 MW Plant area: BOILER Page 22 of 24 PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA 1. PROCEDURE FOR DETERMINATION OF TOTAL EDTA CONCENTRATION IN PROCESS SOLUTION DURING CHEMICAL CLEANING. 1. PRINCIPLE OF THE METHOD: EDTA reacts with Zirconium ions under strong acid conditions to form a chelate. The end point of the titration is indicated by a Xylenolorange indicator. 2. REAGENTS AND APPARATUS REQUIRED: APPARATUS: 1. Erlenmeyer flask 300 ml capacity. 2. Pipettes 3. Hot plate 4. Magnetic stirrer REAGENTS 1. Hydrochloric acid (conc.) 2. Standard Zirconium oxy chloride (ZrOCl2. 8H2O) 0.1 M solution in 1 N HCl (Take a 1000 ml volumetric flask and add 32.23 gram of ZrOCl2.8 H2O and add DM water to about 500 ml. To this add 85 ml of conc. HCl. Make up to 1000 ml mark with DM water and mix well) 3. Ascorbic acid 4. Xylenolorange indicator. 3. TEST PROCEDUTE : 1. pipette out 10 cc of the water sample into a 300 ml Erlenmeyer Flask. 2. Add 10 ml of conc. HCl ( the pH value is about 1.0) 3. Add a spatula of ascorbic acid. 4. Boil of the solvent on the heating plate for about 5 minutes.(The yellow colour of the ferric ion should disappear due to reduction to ferrous iron. 5. Immediately after the addition of 0.05 ml of 0.05 % xylenol orange indicator the sample is titrated with 0.1M ZrOCl2 untill the colour changes from yellow to red violet; The colour changes from yellow to red violet. The colour change shall remain constant for at least 3 min. 4. CALCULATION : The total EDTA concentration % = Volume of 0.1M ZrOCl2 consumed x 0.292 Signatures HINDALCO MAHAN BHEL
  • 23. BHEL Ref No: PW / TSX /HINDCO/ HINDALCO MAHAN Unit-1 61X150 MW Plant area: BOILER Page 23 of 24 PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA 2. PROCEDURE FOR THE DETERMINATION OF TOTAL IRON CONCENTRATION IN PROCESS SOLUTION DURING CHEMICAL CLEANING. 1. APPARATUS REQUIRED: 1. 2. 3. 4. HACH DR/890 COLORIMETER Volumetric flasks Pipettes Measuring cylinders 2. REAGENTS REQUIRED: 1. FerroVer reagent powder pouches (Supplied by HACH) 3. TEST METHOD: 1. Sample to be diluted with DM water so that the concentration of Iron will be less tha 3.00 ppm in the test solution. 2. 25 ml / 10 ml of the diluted solution will be taken in the cuvette. This will be used as a blank. 3. Place the blank in the cell holder and cover the sample cell with the cap. 4. Zero the equipment and display will be showing 0.00 mg/L Fe. 5. Fill another sample cell with 25/10 ml sample 6. Add the contents of one FerroVer Iron Reagent Powder Pillow to the sample cell (the prepared sample). Cap and invert to dissolve the reagent powder. 7. Start the timer for 3 mts period. 8. Place the prepared sample into the cell holder. Cover the sample cell with the instrument cap. 9. Press READ 10. The concentration will be displayed 11. Multiply with dilution factor and report the ppm/ g/lit of Fe concentration. Signatures HINDALCO MAHAN BHEL
  • 24. BHEL Ref No: PW / TSX /HINDCO/ HINDALCO MAHAN Unit-1 61X150 MW Plant area: BOILER Page 24 of 24 PROCEDURE FOR CHEMICAL CLEANING OF BOILER WITH EDTA 3. ESTIMATION OF HYDRAZINE. 1. REAGENTS . a. Standard Potassium bromate 0.1 N Dissolve 2.7836 gram of Potassium bromate (KbrO3) and 10 gram of Potassium bromide (KBr) in DM / Distilled water and make up to 1000 ml. b. 0.1 % Methyl orange indicator solution. c. Hydrochloric acid (conc.) AR. 2. PROCEEDURE. a) place 10 ml of sample in a titration flask. b) Add 10 ml of conc. HCl. c) Add about 5 drops of Methyl orang indicator. d) Titrate with standard KbrO3 titrant to the first appearance of yellow colour. 3. CALCULATION. Hydrazine as N2H4, ppm = titre value X 80. Signatures HINDALCO MAHAN BHEL