PROJECT COST
MANAGEMENT
Defenition
■ Project Cost Management includes the processes involved in planning, estimating,
budgeting, financing, funding, managing, and controlling costs so that the project can
be completed within the approved budget
Main Processes
■ 7.1 Plan cost Management—The process that establishes the policies, procedures, and
documentation for planning, managing, expending, and controlling project costs.
■ 7.2 Estimate costs—The process of developing an approximation of the monetary
resources needed to complete project activities.
■ 7.3 determine Budget—The process of aggregating the estimated costs of individual
activities or work packages to establish an authorized cost baseline.
■ 7.4 control costs—The process of monitoring the status of the project to update the
project costs and managing changes to the cost baseline.
About Project Cost Management
■ Project Cost Management should consider the stakeholder requirements for
managing costs. Different stakeholders will measure project costs in different ways
and at different times
■ Project Cost Management is primarily concerned with the cost of the resources
needed to complete project activities. Project Cost Management should also consider
the effect of project decisions on the subsequent recurring cost of using, maintaining,
and supporting the product, service, or result of the project
Cont..
■ In many organizations, predicting and analyzing the prospective financial performance
of the project’s product is performed outside of the project.When such predictions
and analyses are included, Project Cost Management may address additional
processes and numerous general financial management techniques such as return on
investment, discounted cash flow, and investment payback analysis.
Process 1: Plan Cost Management
■ Plan Cost Management is the process that establishes the policies, procedures, and
documentation for planning, managing, expending, and controlling project costs.The
key benefit of this process is that it provides guidance and direction on how the project
costs will be managed throughout the project
Project Cost Management: Input
■ Project Mg Plan:
Scope Baseline, Schedule Baseline,etc
■ Proj Charter:
Summary Budget
■ Enterprise environtment Factor:
Culture, Market Condition of Product
■ Organizational Process Assets:
Financial Database, Lesson learned doc.
Tools andTechnique
■ Expert judgment,
guided by historical information, provides valuable insight about the environment and
information from prior similar projects. Expert judgment can also suggest whether to
combine methods and how to reconcile differences between them.
■ AnalyticalTechnique.
Organizational policies and procedures may influence which financial techniques are
employed in these decisions.Techniques may include (but are not limited to): payback
period, return on investment, internal rate of return, discounted cash flow, and net present
value.
■ Meetings
Project teams may hold planning meetings to develop the cost management plan.
Attendees at these meetings may include the project manager, the project sponsor,
selected project team members, selected stakeholders, anyone with responsibility for
project costs, and others as needed
Output
■ Cost Management Plan
component of the project management plan and describes how the project costs will
be planned, structured, and controlled
Process 2:Estimate Cost
■ Estimate Costs is the process of developing an approximation of the monetary
resources needed to complete project activities.The key benefit of this process is that
it determines the amount of cost required to complete project work
■ Cost estimates are a prediction that is based on the information known at a given
point in time. Cost estimates include the identification and consideration of costing
alternatives to initiate and complete the project. Cost tradeoffs and risks should be
considered, such as make versus buy, buy versus lease, and the sharing of resources in
order to achieve optimal costs for the project.
Inputs:
■ cost Management Plan
■ Human resource Management Plan
■ Scope Baseline
Project scope statement,WBS
■ Project Schedule
Gantt Chart
■ Risk register
Risks, which can be either threats or opportunities, typically have an impact on both activity and
overall project costs
■ Enterprise Environmental Factors
Market Condition, Published commercial information
■ Organizational Process Assets:
Cost estimating policies, Cost estimating templates, Historical information, and Lessons learned.
Tools andTechnique
■ Expert Judgment
Expert judgment, guided by historical information, provides valuable insight about the
environment and information from prior similar projects. Expert judgment can also be
used to determine whether to combine methods of estimating and how to reconcile
differences between them.
■ Analogous Estimating
Analogous cost estimating uses the values such as scope, cost, budget, and duration
or measures of scale such as size, weight, and complexity from a previous, similar
project as the basis for estimating the same parameter or measurement for a current
projec
■ Parametric Estimating
Parametric estimating uses a statistical relationship between relevant historical data
and other variables
■ Bottom-up Estimating
Bottom-up estimating is a method of estimating a component of work.The cost of
individual work packages or activities is estimated to the greatest level of specified
detail.The detailed cost is then summarized or “rolled up” to higher levels for
subsequent reporting and tracking purpose
■ three-Point Estimating
Most likely (cM).The cost of the activity, based on realistic effort assessment for the
required work and any predicted expenses.
Optimistic (cO).The activity cost based on analysis of the best-case scenario for the
activity.
Pessimistic (cP).The activity cost based on analysis of the worst-case scenario for the
activity
Depending on the assumed distribution of values within the range of the three estimates the
expected cost, cE, can be calculated using a formula. Formula:
• triangular distribution. cE = (cO + cM + cP) / 3
• Beta distribution (from a traditional PERT analysis). cE = (cO + 4cM + cP) / 6
■ Resserve analysis
Cost estimates may include contingency reserves (sometimes called contingency
allowances) to account for cost uncertainty
■ Cost of Quality
■ Project Management Software
Outputs
■ Activity cost Estimates
■ Project documents updates
Process 3:Determine Budget
■ Determine Budget is the process of aggregating the estimated costs of individual
activities or work packages to establish an authorized cost baseline.The key benefit of
this process is that it determines the cost baseline against which project performance
can be monitored and controlled
■ A project budget includes all the funds authorized to execute the project.The cost
baseline is the approved version of the time-phased project budget, but excludes
management reserves.
Inputs,Tools, Output
Input:
■ Cost Management Plan
■ Scope Baseline:
Project scope statement,WBS
■ Activity cost Estimates
■ Project Schedule
■ risk register
■ organizational Process Assets:
Cost budgeting-related policies, procedures, and guideline
Cost Budgeting tool
Reporting Method
Tools andTechnique
■ CostAggregation
Cost estimates are aggregated by work packages in accordance with the WBS.The
work package cost estimates are then aggregated for the higher component levels of
theWBS (such as control accounts) and ultimately for the entire project.
■ Reserve Analysis
Budget reserve analysis can establish both the contingency reserves and the
management reserves for the project
■ Funding Limit reconciliation
The expenditure of funds should be reconciled with any funding limits on the
commitment of funds for the project.
Output
■ Cost Baseline
The cost baseline is the approved version of the time-phased project budget,
excluding any management reserves, which can only be changed through formal
change control procedures and is used as a basis for comparison to actual results
■ Project Funding requirements
Total funding requirements and periodic funding requirements (e.g., quarterly,
annually) are derived from the cost baseline.The cost baseline will include projected
expenditures plus anticipated liabilities
■ Project documents updates:
Risk register,
Activity cost estimates,
Project schedule.
Process 4: Control costs
■ ControlCosts is the process of monitoring the status of the project to update the
project costs and managing changes to the cost baseline.The key benefit of this
process is that it provides the means to recognize variance from the plan in order to
take corrective action and minimize risk
■ Updating the budget requires knowledge of the actual costs spent to date. Any
increase to the authorized budget can only be approved through the Perform
Integrated ChangeControl process
includes
■ Influencing the factors that create changes to the authorized cost baseline;
■ Ensuring that all change requests are acted on in a timely manner
■ Managing the actual changes when and as they occur
■ Ensuring that cost expenditures do not exceed the authorized funding by period, byWBS
component, by activity, and in total for the project
■ Monitoring cost performance to isolate and understand variances from the approved cost
baseline
■ Monitoring work performance against funds expended
■ Preventing unapproved changes from being included in the reported cost or resource
usage
■ Informing appropriate stakeholders of all approved changes and associated cost
■ Bringing expected cost overruns within acceptable limits.
Inputs:
■ Project Management Plan:
Cost Baseline,Cost Management Plan
■ Project Funding requirements
■ Work Performance data
Work performance data includes information about project progress, such as which
activities have started, their progress, and which deliverables have finished.
Information also includes costs that have been authorized and incurred.
■ Organizational Process Assets:
cost control-related policies, procedures, and guidelines;
Tools andTechnique
■ EarnedValue Management
Earned value management (EVM) is a methodology that combines scope, schedule,
and resource measurements to assess project performance and progress
1. Planned value. Planned value (PV) is the authorized budget assigned to scheduled
work.
2. Earned value. Earned value (EV) is a measure of work performed expressed in terms
of the budget authorized for that work
3. Actual cost. Actual cost (AC) is the realized cost incurred for the work performed on
an activity during a specific time period
Outputs:
■ Work Performance Information
The calculated CV, SV, CPI, SPI,TCPI, andVAC values forWBS components, in particular the
work packages and control accounts, are documented and communicated to stakeholders.
■ Ccost Forecasts:
Calculated EAC value or a bottom-up EAC value
■ Change requests
■ Project Management Plan updates
■ Project documents updates:
Cost Estimates, Basis Estimates
■ Organizational Process Assets updates:
Cause of variances, Corrective Action, Financial Database

Contenu connexe

Tendances

Project Communications Management - PMBOK6
Project Communications Management - PMBOK6Project Communications Management - PMBOK6
Project Communications Management - PMBOK6Agus Suhanto
 
Project management
Project managementProject management
Project managementArsh Koul
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?Kenny Hirschmann
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost ManagementBhuWan Khadka
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimationReetesh Gupta
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
06. Project Management Process Groups
06. Project Management Process Groups06. Project Management Process Groups
06. Project Management Process GroupsBhuWan Khadka
 
An Introduction To Project Management
An Introduction To Project ManagementAn Introduction To Project Management
An Introduction To Project ManagementAshish Mittal
 
Project Cost Management
Project Cost Management Project Cost Management
Project Cost Management Muhammad Hanif
 
Project cost management PMBOK 5th Edition
Project cost management PMBOK 5th EditionProject cost management PMBOK 5th Edition
Project cost management PMBOK 5th Editionpankajsh10
 
Project Time Management
Project Time ManagementProject Time Management
Project Time ManagementSerdar Temiz
 
Project Quality Management PPT.pptx
Project Quality Management PPT.pptxProject Quality Management PPT.pptx
Project Quality Management PPT.pptxZiyad Zaidi
 

Tendances (20)

PMP_Project Cost Management
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost Management
 
Project Communications Management - PMBOK6
Project Communications Management - PMBOK6Project Communications Management - PMBOK6
Project Communications Management - PMBOK6
 
Project management
Project managementProject management
Project management
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 
Budgeting
BudgetingBudgeting
Budgeting
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
06. Project Management Process Groups
06. Project Management Process Groups06. Project Management Process Groups
06. Project Management Process Groups
 
Project cost control
Project cost controlProject cost control
Project cost control
 
An Introduction To Project Management
An Introduction To Project ManagementAn Introduction To Project Management
An Introduction To Project Management
 
Project Cost Management
Project Cost Management Project Cost Management
Project Cost Management
 
Project cost management
Project cost managementProject cost management
Project cost management
 
Project cost management PMBOK 5th Edition
Project cost management PMBOK 5th EditionProject cost management PMBOK 5th Edition
Project cost management PMBOK 5th Edition
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Project Quality Management PPT.pptx
Project Quality Management PPT.pptxProject Quality Management PPT.pptx
Project Quality Management PPT.pptx
 

Similaire à Cost Management PMBOK

project cost management.pptx
project cost management.pptxproject cost management.pptx
project cost management.pptxInayatSheikh1
 
cost Management V4
cost Management V4cost Management V4
cost Management V4Qussay Karam
 
Pmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementPmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementYudha Pratama, PMP
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimationssuser9d62d6
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimationSomashekar S.M
 
Project Planning and Control
Project Planning and Control Project Planning and Control
Project Planning and Control drpvkhatrissn
 
4- Project Cost Management.ppt
4- Project Cost Management.ppt4- Project Cost Management.ppt
4- Project Cost Management.pptMohamadAGhareb
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfHuyNguyen657394
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenetAla Ibrahim
 
Cost management
Cost managementCost management
Cost managementshkadry
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptsheryl90
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptsheryl90
 
Managing the Consulting Engagement
Managing the Consulting EngagementManaging the Consulting Engagement
Managing the Consulting EngagementSaumya Ganguly
 
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.pptProfDrAnbalaganChinn
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Agus Suhanto
 
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docxSheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docxbjohn46
 

Similaire à Cost Management PMBOK (20)

PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
 
project cost management.pptx
project cost management.pptxproject cost management.pptx
project cost management.pptx
 
cost Management V4
cost Management V4cost Management V4
cost Management V4
 
Pmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementPmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost management
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
 
Session 9 4th edition PMP
Session 9 4th edition PMPSession 9 4th edition PMP
Session 9 4th edition PMP
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Project Planning and Control
Project Planning and Control Project Planning and Control
Project Planning and Control
 
Project cost management
Project cost management Project cost management
Project cost management
 
4- Project Cost Management.ppt
4- Project Cost Management.ppt4- Project Cost Management.ppt
4- Project Cost Management.ppt
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdf
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
 
Cost management
Cost managementCost management
Cost management
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
Managing the Consulting Engagement
Managing the Consulting EngagementManaging the Consulting Engagement
Managing the Consulting Engagement
 
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
 
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docxSheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
 

Dernier

TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...Nguyen Thanh Tu Collection
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfSherif Taha
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptxMaritesTamaniVerdade
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxheathfieldcps1
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - Englishneillewis46
 
Interdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxInterdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxPooja Bhuva
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structuredhanjurrannsibayan2
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Jisc
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxAreebaZafar22
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibitjbellavia9
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...pradhanghanshyam7136
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfNirmal Dwivedi
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.pptRamjanShidvankar
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfPoh-Sun Goh
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...Nguyen Thanh Tu Collection
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSCeline George
 
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Pooja Bhuva
 
Wellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptxWellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptxJisc
 

Dernier (20)

TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
Interdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxInterdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptx
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
 
Wellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptxWellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptx
 

Cost Management PMBOK

  • 2. Defenition ■ Project Cost Management includes the processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs so that the project can be completed within the approved budget
  • 3. Main Processes ■ 7.1 Plan cost Management—The process that establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs. ■ 7.2 Estimate costs—The process of developing an approximation of the monetary resources needed to complete project activities. ■ 7.3 determine Budget—The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline. ■ 7.4 control costs—The process of monitoring the status of the project to update the project costs and managing changes to the cost baseline.
  • 4. About Project Cost Management ■ Project Cost Management should consider the stakeholder requirements for managing costs. Different stakeholders will measure project costs in different ways and at different times ■ Project Cost Management is primarily concerned with the cost of the resources needed to complete project activities. Project Cost Management should also consider the effect of project decisions on the subsequent recurring cost of using, maintaining, and supporting the product, service, or result of the project
  • 5. Cont.. ■ In many organizations, predicting and analyzing the prospective financial performance of the project’s product is performed outside of the project.When such predictions and analyses are included, Project Cost Management may address additional processes and numerous general financial management techniques such as return on investment, discounted cash flow, and investment payback analysis.
  • 6. Process 1: Plan Cost Management ■ Plan Cost Management is the process that establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs.The key benefit of this process is that it provides guidance and direction on how the project costs will be managed throughout the project
  • 7. Project Cost Management: Input ■ Project Mg Plan: Scope Baseline, Schedule Baseline,etc ■ Proj Charter: Summary Budget ■ Enterprise environtment Factor: Culture, Market Condition of Product ■ Organizational Process Assets: Financial Database, Lesson learned doc.
  • 8. Tools andTechnique ■ Expert judgment, guided by historical information, provides valuable insight about the environment and information from prior similar projects. Expert judgment can also suggest whether to combine methods and how to reconcile differences between them. ■ AnalyticalTechnique. Organizational policies and procedures may influence which financial techniques are employed in these decisions.Techniques may include (but are not limited to): payback period, return on investment, internal rate of return, discounted cash flow, and net present value. ■ Meetings Project teams may hold planning meetings to develop the cost management plan. Attendees at these meetings may include the project manager, the project sponsor, selected project team members, selected stakeholders, anyone with responsibility for project costs, and others as needed
  • 9. Output ■ Cost Management Plan component of the project management plan and describes how the project costs will be planned, structured, and controlled
  • 10. Process 2:Estimate Cost ■ Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities.The key benefit of this process is that it determines the amount of cost required to complete project work
  • 11. ■ Cost estimates are a prediction that is based on the information known at a given point in time. Cost estimates include the identification and consideration of costing alternatives to initiate and complete the project. Cost tradeoffs and risks should be considered, such as make versus buy, buy versus lease, and the sharing of resources in order to achieve optimal costs for the project.
  • 12. Inputs: ■ cost Management Plan ■ Human resource Management Plan ■ Scope Baseline Project scope statement,WBS ■ Project Schedule Gantt Chart ■ Risk register Risks, which can be either threats or opportunities, typically have an impact on both activity and overall project costs ■ Enterprise Environmental Factors Market Condition, Published commercial information ■ Organizational Process Assets: Cost estimating policies, Cost estimating templates, Historical information, and Lessons learned.
  • 13. Tools andTechnique ■ Expert Judgment Expert judgment, guided by historical information, provides valuable insight about the environment and information from prior similar projects. Expert judgment can also be used to determine whether to combine methods of estimating and how to reconcile differences between them. ■ Analogous Estimating Analogous cost estimating uses the values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous, similar project as the basis for estimating the same parameter or measurement for a current projec
  • 14. ■ Parametric Estimating Parametric estimating uses a statistical relationship between relevant historical data and other variables ■ Bottom-up Estimating Bottom-up estimating is a method of estimating a component of work.The cost of individual work packages or activities is estimated to the greatest level of specified detail.The detailed cost is then summarized or “rolled up” to higher levels for subsequent reporting and tracking purpose
  • 15. ■ three-Point Estimating Most likely (cM).The cost of the activity, based on realistic effort assessment for the required work and any predicted expenses. Optimistic (cO).The activity cost based on analysis of the best-case scenario for the activity. Pessimistic (cP).The activity cost based on analysis of the worst-case scenario for the activity Depending on the assumed distribution of values within the range of the three estimates the expected cost, cE, can be calculated using a formula. Formula: • triangular distribution. cE = (cO + cM + cP) / 3 • Beta distribution (from a traditional PERT analysis). cE = (cO + 4cM + cP) / 6
  • 16. ■ Resserve analysis Cost estimates may include contingency reserves (sometimes called contingency allowances) to account for cost uncertainty ■ Cost of Quality ■ Project Management Software
  • 17. Outputs ■ Activity cost Estimates ■ Project documents updates
  • 18. Process 3:Determine Budget ■ Determine Budget is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.The key benefit of this process is that it determines the cost baseline against which project performance can be monitored and controlled ■ A project budget includes all the funds authorized to execute the project.The cost baseline is the approved version of the time-phased project budget, but excludes management reserves.
  • 20. Input: ■ Cost Management Plan ■ Scope Baseline: Project scope statement,WBS ■ Activity cost Estimates ■ Project Schedule ■ risk register ■ organizational Process Assets: Cost budgeting-related policies, procedures, and guideline Cost Budgeting tool Reporting Method
  • 21. Tools andTechnique ■ CostAggregation Cost estimates are aggregated by work packages in accordance with the WBS.The work package cost estimates are then aggregated for the higher component levels of theWBS (such as control accounts) and ultimately for the entire project. ■ Reserve Analysis Budget reserve analysis can establish both the contingency reserves and the management reserves for the project ■ Funding Limit reconciliation The expenditure of funds should be reconciled with any funding limits on the commitment of funds for the project.
  • 22. Output ■ Cost Baseline The cost baseline is the approved version of the time-phased project budget, excluding any management reserves, which can only be changed through formal change control procedures and is used as a basis for comparison to actual results
  • 23. ■ Project Funding requirements Total funding requirements and periodic funding requirements (e.g., quarterly, annually) are derived from the cost baseline.The cost baseline will include projected expenditures plus anticipated liabilities ■ Project documents updates: Risk register, Activity cost estimates, Project schedule.
  • 24. Process 4: Control costs ■ ControlCosts is the process of monitoring the status of the project to update the project costs and managing changes to the cost baseline.The key benefit of this process is that it provides the means to recognize variance from the plan in order to take corrective action and minimize risk ■ Updating the budget requires knowledge of the actual costs spent to date. Any increase to the authorized budget can only be approved through the Perform Integrated ChangeControl process
  • 25. includes ■ Influencing the factors that create changes to the authorized cost baseline; ■ Ensuring that all change requests are acted on in a timely manner ■ Managing the actual changes when and as they occur ■ Ensuring that cost expenditures do not exceed the authorized funding by period, byWBS component, by activity, and in total for the project ■ Monitoring cost performance to isolate and understand variances from the approved cost baseline ■ Monitoring work performance against funds expended ■ Preventing unapproved changes from being included in the reported cost or resource usage ■ Informing appropriate stakeholders of all approved changes and associated cost ■ Bringing expected cost overruns within acceptable limits.
  • 26. Inputs: ■ Project Management Plan: Cost Baseline,Cost Management Plan ■ Project Funding requirements ■ Work Performance data Work performance data includes information about project progress, such as which activities have started, their progress, and which deliverables have finished. Information also includes costs that have been authorized and incurred. ■ Organizational Process Assets: cost control-related policies, procedures, and guidelines;
  • 27. Tools andTechnique ■ EarnedValue Management Earned value management (EVM) is a methodology that combines scope, schedule, and resource measurements to assess project performance and progress 1. Planned value. Planned value (PV) is the authorized budget assigned to scheduled work. 2. Earned value. Earned value (EV) is a measure of work performed expressed in terms of the budget authorized for that work 3. Actual cost. Actual cost (AC) is the realized cost incurred for the work performed on an activity during a specific time period
  • 28. Outputs: ■ Work Performance Information The calculated CV, SV, CPI, SPI,TCPI, andVAC values forWBS components, in particular the work packages and control accounts, are documented and communicated to stakeholders. ■ Ccost Forecasts: Calculated EAC value or a bottom-up EAC value ■ Change requests ■ Project Management Plan updates ■ Project documents updates: Cost Estimates, Basis Estimates ■ Organizational Process Assets updates: Cause of variances, Corrective Action, Financial Database