SlideShare une entreprise Scribd logo
1  sur  16
Presented by:-Ashima Thakur & Baljinder
Capital budgeting techniques under certainty;
and
II. Capital budgeting techniques under
uncertainty.
Risk can be defined as the chance that the actual outcome will differ from the
expected outcome. Uncertainty relates to the situation where a range of differing
outcome is possible, but it is not possible to assign probabilities to this range of
outcomes.
 Conventional Techniques for Risk Analysis:
(a) Payback
(b) Risk-adjusted Discount Rate
(c) Certainty Equivalent
Meaning:
It is the number of years required to recover the original cash outlay invested in a
project.
Methods to compute PBP:
A ) The first method can be applied when the CFAT is uniform. In such a situation
the initial cost of the investment is divided by the constant annual cash flow: For
example, if an investment of Rs.100000 in a machine is expected to generate cash
inflow of Rs.20,000 p.a. for 10 years.
Its PBP will be calculated using following formula:
PBP=Initial Investment/ constant annual cash inflow = 1,00,000 /20,000=5 yrs
b) The second method is used when a project’s CFAT are not equal. In such a
situation PBP is calculated by the process of cumulating CFAT till the time when
cumulative cash flow becomes equal to the original investment outlays.
For example, A firm requires an initial cash outflow of Rs. 20,000 and the annual
cash inflows for 5 years are Rs. 6000, Rs. 8000, Rs. 5000, Rs. 4000 and Rs. 4000
respectively.
Calculate PBP.
Here, When we cumulate the cash flows for the first three years, Rs. 19,000 is
recovered. In the fourth year Rs.4000 cash flow is generated by the project but we
need to recover only Rs.1000 so the time required recovering Rs. 1000 will be
(Rs.1000/Rs.4000)× 12months = 3 months. Thus, the PBP is 3 years and 3 months
(3.25 years).
Decision Rule:
 The PBP can be used as a decision criterion to select investment proposal. If the
PBP is less than the maximum acceptable payback period, accept the project.
If the PBP is greater than the maximum acceptable payback period, reject the
project.
To allow for risk, the businessmen required a premium over and above an alternative
which is risk free. It is proposed that risk premium be incorporated into the capital
budgeting analysis through the discount rate. i.e. If the time preference for the money
is to be recognized by discounting estimated future cash flows, at some risk free rate,
to there present value, then, to allow for the riskiness of the future cash flow a risk
premium rate may be added to risk free discount rate. Such a composite discount
would account for both time preference and risk preference.
RADR= Risk free rate + Risk Premium OR
k = Rf + Rp
 The RADR accounts for risk by varying discount rate depending on the degree of
risk of investment projects. The following figure portrays the relationship between
amount of risk and the required k.
 The following equation can be used:-
 NPV = ΣNCFt / ( 1+k )t - CO
Where k is a risk-adjusted rate.
The risk adjusted approach can be used for both NPV & IRR.
If NPV method is used for evaluation, the NPV would be calculated using risk
adjusted rate.
If NPV is positive, the proposal would qualify for acceptance, if
it is negative, the proposal would be rejected.
In case of IRR, the IRR would be compared with the risk adjusted required
rate of return.
If the ‘r’ exceeds risk adjusted rate, the proposal would be
accepted, otherwise not.
For example, if an investment project has following cash flows, its NPV using RADR will be as
follows:
Risk free rate is 6% and Risk adjusted rate is 10%.
Year CFAT
(RS.)
PV @10 PV( Rs.)
1
2
3
50000
40000
45000
LESS:
0.909
0.826
0.751
ΣPV
Investment
45450
33040
33795
---------
112285
150000
-------
The certainty equivalent coefficient (α) can be determined as a relationship between the
certain cash flows and the uncertain cash flows.
For example, if a company expected a risky cash flow of Rs. 90,000 and a risk free cash
flow of Rs. 65,000 then
(α1 ) will be calculated as follows:-
(α)t =NCFt* /NCFt = risk free cash flows / risky cashflows=65,000 /90,000
The certainty equivalent coefficient (α ) t assumes a value between 0 and 1 and varies
inversely with risk. The higher the risk, the lower the (α)t and the lower the risk, the
higher the (α)t .
The certainty equivalent approach can be expressed in the form of equation as
follows:
NPV=Σαt NCFt / (1+kf)t
where, NCFt = Net cash flow,
α t= the certainty equivalent coefficient,
kf = Risk free rate
(a) Sensitivity Analysis
(b) Scenario Analysis
(c)Simulation Analysis
1) The sensitivity analysis helps in identifying how sensitive are the various
estimated variables of the project. It shows how sensitive is a project’s NPV or IRR
for a given change in particular variables.
Steps:
The following three steps are involved in the use of sensitivity analysis.
1. Identify the variables which can influence the project’s NPV or IRR.
2. Define the underlying relationship between the variables.
3. Analyze the impact of the change in each of the variables on the project’s
NPV or IRR.
The Project’s NPV or IRR can be computed under following three assumptions
in sensitivity analysis.
1. Pessimistic (i.e. the worst),
2. Expected (i.e. the most likely)
3. Optimistic (i.e. the best)
For example, A company has two mutually exclusive projects for
process improvement. The management has developed following
estimates of the annual cash flows for each project having a life of
fifteen years and 12% discount rate.
PROJECT A
Net investments 90000
CFAT Estimates PVAIF12%,
15yrs
PV NPV
pessimistic 10000 6.811 68110 (21890)
Most likely 15000 6.811 102165 12165
optimistic 21000 6.811 143031 53031
SENSTIVITY ANALYSIS:-
PROJECT A
Net investments 90000
CFAT Estimates PVAIF12%,
15yrs
PV NPV
pessimistic 13500 6.811 91948.5 1948.5
Most likely 15000 6.811 102165 12165
optimistic 18000 6.811 122598 32598
The NPV calculations of both the projects suggest that the projects are equally
desirable on the basis of the most likely estimates of cash flows.
However, the Project– A is riskier than Project – B because its NPV can be negative
to the extent of Rs. 21,890 but there is no possibility of incurring any losses with
project B as all the NPVs are positive.
As the two projects are mutually exclusive, the actual selection of the projects
depends on decision maker’s attitude towards the risk. If he is ready to take risk, he
will select Project A, because it has the potential of yielding NPV much higher than
(Rs. 53031) Project B. But if he is risk averse, he will select project B.
The another way to examine the risk of investment is to analyze the impact of
alternative combination of variables , called the scenarios , on the project NPV.
EXAMPLE:- In the expected scenario, it may be possible to increase the sales
volume of 1 lac units to 1,25000 units . If the company reduces the selling price
from Rs. 15 to Rs. 13.50, resorts to aggressive advertisement campaign, their by
increasing unit variable cost to Rs.7.1( 5% increase) & fixed cost is rs.44,000.
Calculate the NPV.
OPTIMISTIC :-1,25,000
PESSIMISTIC:-75,000
NEUTRAL:- 1,00,000
REVENUE = 1250 *!6.50=20625RS.
VARIABLES BASE VALUE PESSISMISTIC OPTIMISTIC
SALES VOLUME 1000 750 1250
SELLING PRICE
/UNIT
RS.15 13.50 16.50
VARIABLE COST /
UNIT
7.1 7.43 6.75
FIXED COST 4400 4840 4400
 Sensitivity analysis and Scenario analysis are quite useful to understand the
uncertainty of the investment projects. But both the methods do not consider the
interactions between variables and also, they do not reflect on the probability of
the change in variables.
Monte simulation considers the interaction among variables & probabilities of
change in variables & its impact on NPV of cash inflows . In this a computer generates
a very large no. of scenarios according to the probability distribution of variables.
Steps:-
1)Identification of the variables , which influences the cash inflows.
Initial investment ,Market size ,Fixed cost & variable cost , market growth rate
2) Specify the formula which relates the variables.
3)Assign the probabilities to each variables
4)Develop a computer program, that randomly selects 1 value from the probability
with each variable & uses these values, to calculate projects NPV.
Presentation on capital budgeting

Contenu connexe

Tendances

Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar GSocial Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar GMohan Kumar G
 
6 financial evaluation
6 financial evaluation6 financial evaluation
6 financial evaluationharshgakhar
 
Introduction To Value At Risk
Introduction To Value At RiskIntroduction To Value At Risk
Introduction To Value At RiskAlan Anderson
 
Portfolio selection final
Portfolio selection finalPortfolio selection final
Portfolio selection finalsumit payal
 
Capital Asset Pricing Model (CAPM)
Capital Asset Pricing Model (CAPM)Capital Asset Pricing Model (CAPM)
Capital Asset Pricing Model (CAPM)VadivelM9
 
Sharpe index model
Sharpe index modelSharpe index model
Sharpe index modelAshwini Das
 
Portfolio construction
Portfolio        constructionPortfolio        construction
Portfolio constructionRavi Singh
 
Fixed income securities- Analysis and valuation
Fixed income securities- Analysis and valuationFixed income securities- Analysis and valuation
Fixed income securities- Analysis and valuation13 Llama Interactive
 
PORTFOLIO PERFORMANCE EVALUATION
PORTFOLIO PERFORMANCE EVALUATIONPORTFOLIO PERFORMANCE EVALUATION
PORTFOLIO PERFORMANCE EVALUATIONDinesh Kumar
 

Tendances (20)

Chapter 7
Chapter 7Chapter 7
Chapter 7
 
Single index model
Single index model Single index model
Single index model
 
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar GSocial Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
 
CAPM
CAPMCAPM
CAPM
 
Risk in capital budgeting
Risk in capital budgetingRisk in capital budgeting
Risk in capital budgeting
 
6 financial evaluation
6 financial evaluation6 financial evaluation
6 financial evaluation
 
Divident policy
Divident policyDivident policy
Divident policy
 
Risk analysis in capital budgeting
Risk analysis in capital budgeting Risk analysis in capital budgeting
Risk analysis in capital budgeting
 
Risk & return analysis
Risk & return analysisRisk & return analysis
Risk & return analysis
 
Introduction To Value At Risk
Introduction To Value At RiskIntroduction To Value At Risk
Introduction To Value At Risk
 
Portfolio selection final
Portfolio selection finalPortfolio selection final
Portfolio selection final
 
Capital Asset Pricing Model (CAPM)
Capital Asset Pricing Model (CAPM)Capital Asset Pricing Model (CAPM)
Capital Asset Pricing Model (CAPM)
 
Fundamental analysis
Fundamental analysisFundamental analysis
Fundamental analysis
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Sharpe index model
Sharpe index modelSharpe index model
Sharpe index model
 
Portfolio construction
Portfolio        constructionPortfolio        construction
Portfolio construction
 
Modern Portfolio Theory
Modern Portfolio TheoryModern Portfolio Theory
Modern Portfolio Theory
 
Fixed income securities- Analysis and valuation
Fixed income securities- Analysis and valuationFixed income securities- Analysis and valuation
Fixed income securities- Analysis and valuation
 
Portfolio analysis
Portfolio analysisPortfolio analysis
Portfolio analysis
 
PORTFOLIO PERFORMANCE EVALUATION
PORTFOLIO PERFORMANCE EVALUATIONPORTFOLIO PERFORMANCE EVALUATION
PORTFOLIO PERFORMANCE EVALUATION
 

En vedette

Capital Budgeting
Capital BudgetingCapital Budgeting
Capital BudgetingDayasagar S
 
Risk In Capital Budgeting
Risk In Capital BudgetingRisk In Capital Budgeting
Risk In Capital BudgetingNoman
 
Futurum training capital budgeting (intermediate)
Futurum training capital budgeting (intermediate)Futurum training capital budgeting (intermediate)
Futurum training capital budgeting (intermediate)mputrawal
 
1902capital budgeting (1)
1902capital budgeting (1)1902capital budgeting (1)
1902capital budgeting (1)Anuj Malhotra
 
Prudent Capital Allocation - My Investment Thesis
Prudent Capital Allocation - My Investment ThesisPrudent Capital Allocation - My Investment Thesis
Prudent Capital Allocation - My Investment ThesisHely Chavan
 
Seminar on the National Strategy of the Implementation of the Code of Conduct...
Seminar on the National Strategy of the Implementation of the Code of Conduct...Seminar on the National Strategy of the Implementation of the Code of Conduct...
Seminar on the National Strategy of the Implementation of the Code of Conduct...OECD Governance
 
Capital Investment And Budgeting
Capital Investment And BudgetingCapital Investment And Budgeting
Capital Investment And BudgetingShubham Goyal
 
Bba 2204 fin mgt week 11 capital budget cashflow & risk
Bba 2204 fin mgt week 11 capital budget cashflow & riskBba 2204 fin mgt week 11 capital budget cashflow & risk
Bba 2204 fin mgt week 11 capital budget cashflow & riskStephen Ong
 
Capital Budgeting - Business Finance
Capital Budgeting - Business FinanceCapital Budgeting - Business Finance
Capital Budgeting - Business FinanceGlenn Besin
 
Capital Budgeting Decision
Capital Budgeting DecisionCapital Budgeting Decision
Capital Budgeting DecisionAshish Khera
 
Reliance industries ltd
Reliance industries ltdReliance industries ltd
Reliance industries ltdTanay Roy, CFA
 
RISK ANALYSIS IN CAPITAL BUDGETING
RISK ANALYSIS IN CAPITAL BUDGETINGRISK ANALYSIS IN CAPITAL BUDGETING
RISK ANALYSIS IN CAPITAL BUDGETINGPANKAJ PANDEY
 
case study-capital budgeting
case study-capital budgetingcase study-capital budgeting
case study-capital budgetinginfinite_7
 

En vedette (20)

Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
 
Risk In Capital Budgeting
Risk In Capital BudgetingRisk In Capital Budgeting
Risk In Capital Budgeting
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Futurum training capital budgeting (intermediate)
Futurum training capital budgeting (intermediate)Futurum training capital budgeting (intermediate)
Futurum training capital budgeting (intermediate)
 
Group g
Group gGroup g
Group g
 
1902capital budgeting (1)
1902capital budgeting (1)1902capital budgeting (1)
1902capital budgeting (1)
 
Prudent Capital Allocation - My Investment Thesis
Prudent Capital Allocation - My Investment ThesisPrudent Capital Allocation - My Investment Thesis
Prudent Capital Allocation - My Investment Thesis
 
Capital budgeting simulation diagram
Capital budgeting simulation diagramCapital budgeting simulation diagram
Capital budgeting simulation diagram
 
NCFTE 2010
NCFTE 2010NCFTE 2010
NCFTE 2010
 
Seminar on the National Strategy of the Implementation of the Code of Conduct...
Seminar on the National Strategy of the Implementation of the Code of Conduct...Seminar on the National Strategy of the Implementation of the Code of Conduct...
Seminar on the National Strategy of the Implementation of the Code of Conduct...
 
Capital Investment And Budgeting
Capital Investment And BudgetingCapital Investment And Budgeting
Capital Investment And Budgeting
 
Bba 2204 fin mgt week 11 capital budget cashflow & risk
Bba 2204 fin mgt week 11 capital budget cashflow & riskBba 2204 fin mgt week 11 capital budget cashflow & risk
Bba 2204 fin mgt week 11 capital budget cashflow & risk
 
Capital Budgeting Decisions
Capital Budgeting DecisionsCapital Budgeting Decisions
Capital Budgeting Decisions
 
Capital budgeting -2
Capital budgeting -2Capital budgeting -2
Capital budgeting -2
 
Capital Budgeting - Business Finance
Capital Budgeting - Business FinanceCapital Budgeting - Business Finance
Capital Budgeting - Business Finance
 
Capital Budgeting Decision
Capital Budgeting DecisionCapital Budgeting Decision
Capital Budgeting Decision
 
Reliance industries ltd
Reliance industries ltdReliance industries ltd
Reliance industries ltd
 
RISK ANALYSIS IN CAPITAL BUDGETING
RISK ANALYSIS IN CAPITAL BUDGETINGRISK ANALYSIS IN CAPITAL BUDGETING
RISK ANALYSIS IN CAPITAL BUDGETING
 
case study-capital budgeting
case study-capital budgetingcase study-capital budgeting
case study-capital budgeting
 

Similaire à Presentation on capital budgeting

CAPITAL BUDGETING DECISIONS.ppt
CAPITAL BUDGETING DECISIONS.pptCAPITAL BUDGETING DECISIONS.ppt
CAPITAL BUDGETING DECISIONS.pptDr.K.Sivaperumal
 
Risk analysis in investment
Risk analysis in investmentRisk analysis in investment
Risk analysis in investmenthimanshujaiswal
 
Capital Budgeting Rules 04
Capital Budgeting Rules 04Capital Budgeting Rules 04
Capital Budgeting Rules 04rajeevgupta
 
Chap 18 risk management & capital budgeting
Chap 18   risk management & capital budgetingChap 18   risk management & capital budgeting
Chap 18 risk management & capital budgetingArindam Khan
 
Capital budgeting methods lecture notes
Capital budgeting methods lecture notesCapital budgeting methods lecture notes
Capital budgeting methods lecture notesWarui Maina
 
Capital budgeting practice
Capital budgeting practiceCapital budgeting practice
Capital budgeting practiceRam sam
 
Radr and certainty equivalent techniques
Radr and certainty equivalent techniquesRadr and certainty equivalent techniques
Radr and certainty equivalent techniquesPreethi Reddy
 
The_Basics_of_Capital_Budgeting.ppt
The_Basics_of_Capital_Budgeting.pptThe_Basics_of_Capital_Budgeting.ppt
The_Basics_of_Capital_Budgeting.pptFilyanFAnggriawan
 
Capital Budgeting : capital budgeting decision
Capital Budgeting : capital budgeting decisionCapital Budgeting : capital budgeting decision
Capital Budgeting : capital budgeting decisionRavindra Nath Shukla
 
Fin 2732 investment decisions
Fin 2732 investment decisionsFin 2732 investment decisions
Fin 2732 investment decisionsYashGupta744
 
Chapter 10: Risk and Refinements In Capital Budgeting
Chapter 10: Risk and Refinements In Capital BudgetingChapter 10: Risk and Refinements In Capital Budgeting
Chapter 10: Risk and Refinements In Capital BudgetingFiaz Ahmad
 
Chapter 10:Risk and Refinements In Capital Budgeting
Chapter 10:Risk and Refinements In Capital BudgetingChapter 10:Risk and Refinements In Capital Budgeting
Chapter 10:Risk and Refinements In Capital BudgetingInocentshuja Ahmad
 
Chapter 10 - Basics of Capital Budgeting.pptx
Chapter 10 - Basics of Capital Budgeting.pptxChapter 10 - Basics of Capital Budgeting.pptx
Chapter 10 - Basics of Capital Budgeting.pptxJaylouAguilar1
 
FN6033-CORP FIN-LECTURE 5A.ppt
FN6033-CORP FIN-LECTURE 5A.pptFN6033-CORP FIN-LECTURE 5A.ppt
FN6033-CORP FIN-LECTURE 5A.ppthass6
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgetingyashpal01
 
Captial bugting
Captial bugtingCaptial bugting
Captial bugting3prem
 
Capital Budgeting- Q.pptx
Capital Budgeting- Q.pptxCapital Budgeting- Q.pptx
Capital Budgeting- Q.pptxMohd Sarim
 

Similaire à Presentation on capital budgeting (20)

Pm 6
Pm 6Pm 6
Pm 6
 
CAPITAL BUDGETING DECISIONS.ppt
CAPITAL BUDGETING DECISIONS.pptCAPITAL BUDGETING DECISIONS.ppt
CAPITAL BUDGETING DECISIONS.ppt
 
Risk analysis in investment
Risk analysis in investmentRisk analysis in investment
Risk analysis in investment
 
Pm 6 updated
Pm 6 updatedPm 6 updated
Pm 6 updated
 
Capital Budgeting Rules 04
Capital Budgeting Rules 04Capital Budgeting Rules 04
Capital Budgeting Rules 04
 
Chap 18 risk management & capital budgeting
Chap 18   risk management & capital budgetingChap 18   risk management & capital budgeting
Chap 18 risk management & capital budgeting
 
Capital budgeting methods lecture notes
Capital budgeting methods lecture notesCapital budgeting methods lecture notes
Capital budgeting methods lecture notes
 
Capital budgeting practice
Capital budgeting practiceCapital budgeting practice
Capital budgeting practice
 
Radr and certainty equivalent techniques
Radr and certainty equivalent techniquesRadr and certainty equivalent techniques
Radr and certainty equivalent techniques
 
The_Basics_of_Capital_Budgeting.ppt
The_Basics_of_Capital_Budgeting.pptThe_Basics_of_Capital_Budgeting.ppt
The_Basics_of_Capital_Budgeting.ppt
 
Capital budgeting unit_2
Capital budgeting unit_2Capital budgeting unit_2
Capital budgeting unit_2
 
Capital Budgeting : capital budgeting decision
Capital Budgeting : capital budgeting decisionCapital Budgeting : capital budgeting decision
Capital Budgeting : capital budgeting decision
 
Fin 2732 investment decisions
Fin 2732 investment decisionsFin 2732 investment decisions
Fin 2732 investment decisions
 
Chapter 10: Risk and Refinements In Capital Budgeting
Chapter 10: Risk and Refinements In Capital BudgetingChapter 10: Risk and Refinements In Capital Budgeting
Chapter 10: Risk and Refinements In Capital Budgeting
 
Chapter 10:Risk and Refinements In Capital Budgeting
Chapter 10:Risk and Refinements In Capital BudgetingChapter 10:Risk and Refinements In Capital Budgeting
Chapter 10:Risk and Refinements In Capital Budgeting
 
Chapter 10 - Basics of Capital Budgeting.pptx
Chapter 10 - Basics of Capital Budgeting.pptxChapter 10 - Basics of Capital Budgeting.pptx
Chapter 10 - Basics of Capital Budgeting.pptx
 
FN6033-CORP FIN-LECTURE 5A.ppt
FN6033-CORP FIN-LECTURE 5A.pptFN6033-CORP FIN-LECTURE 5A.ppt
FN6033-CORP FIN-LECTURE 5A.ppt
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
 
Captial bugting
Captial bugtingCaptial bugting
Captial bugting
 
Capital Budgeting- Q.pptx
Capital Budgeting- Q.pptxCapital Budgeting- Q.pptx
Capital Budgeting- Q.pptx
 

Plus de Ashima Thakur

project risk management
project risk managementproject risk management
project risk managementAshima Thakur
 
Venture capital ashima
Venture capital  ashimaVenture capital  ashima
Venture capital ashimaAshima Thakur
 
Introduction to msme sector
Introduction to msme sectorIntroduction to msme sector
Introduction to msme sectorAshima Thakur
 
133761133 2-project-financing-in-india-ppt
133761133 2-project-financing-in-india-ppt133761133 2-project-financing-in-india-ppt
133761133 2-project-financing-in-india-pptAshima Thakur
 
operational risk management in banks
operational risk management in banksoperational risk management in banks
operational risk management in banksAshima Thakur
 
operational risk managemnt
operational risk managemntoperational risk managemnt
operational risk managemntAshima Thakur
 
Bancassurance 121118023946-phpapp01
Bancassurance 121118023946-phpapp01Bancassurance 121118023946-phpapp01
Bancassurance 121118023946-phpapp01Ashima Thakur
 
Bank risk management
Bank risk managementBank risk management
Bank risk managementAshima Thakur
 

Plus de Ashima Thakur (10)

project risk management
project risk managementproject risk management
project risk management
 
risk management
risk managementrisk management
risk management
 
camel model
camel modelcamel model
camel model
 
Venture capital ashima
Venture capital  ashimaVenture capital  ashima
Venture capital ashima
 
Introduction to msme sector
Introduction to msme sectorIntroduction to msme sector
Introduction to msme sector
 
133761133 2-project-financing-in-india-ppt
133761133 2-project-financing-in-india-ppt133761133 2-project-financing-in-india-ppt
133761133 2-project-financing-in-india-ppt
 
operational risk management in banks
operational risk management in banksoperational risk management in banks
operational risk management in banks
 
operational risk managemnt
operational risk managemntoperational risk managemnt
operational risk managemnt
 
Bancassurance 121118023946-phpapp01
Bancassurance 121118023946-phpapp01Bancassurance 121118023946-phpapp01
Bancassurance 121118023946-phpapp01
 
Bank risk management
Bank risk managementBank risk management
Bank risk management
 

Dernier

Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfChris Hunter
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.pptRamjanShidvankar
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...Nguyen Thanh Tu Collection
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docxPoojaSen20
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxAreebaZafar22
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docxPoojaSen20
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsMebane Rash
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIFood Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIShubhangi Sonawane
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxVishalSingh1417
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesEnergy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesShubhangi Sonawane
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...christianmathematics
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfAyushMahapatra5
 

Dernier (20)

Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIFood Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesEnergy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
Asian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptxAsian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptx
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 

Presentation on capital budgeting

  • 2. Capital budgeting techniques under certainty; and II. Capital budgeting techniques under uncertainty.
  • 3. Risk can be defined as the chance that the actual outcome will differ from the expected outcome. Uncertainty relates to the situation where a range of differing outcome is possible, but it is not possible to assign probabilities to this range of outcomes.  Conventional Techniques for Risk Analysis: (a) Payback (b) Risk-adjusted Discount Rate (c) Certainty Equivalent
  • 4. Meaning: It is the number of years required to recover the original cash outlay invested in a project. Methods to compute PBP: A ) The first method can be applied when the CFAT is uniform. In such a situation the initial cost of the investment is divided by the constant annual cash flow: For example, if an investment of Rs.100000 in a machine is expected to generate cash inflow of Rs.20,000 p.a. for 10 years. Its PBP will be calculated using following formula: PBP=Initial Investment/ constant annual cash inflow = 1,00,000 /20,000=5 yrs
  • 5. b) The second method is used when a project’s CFAT are not equal. In such a situation PBP is calculated by the process of cumulating CFAT till the time when cumulative cash flow becomes equal to the original investment outlays. For example, A firm requires an initial cash outflow of Rs. 20,000 and the annual cash inflows for 5 years are Rs. 6000, Rs. 8000, Rs. 5000, Rs. 4000 and Rs. 4000 respectively. Calculate PBP. Here, When we cumulate the cash flows for the first three years, Rs. 19,000 is recovered. In the fourth year Rs.4000 cash flow is generated by the project but we need to recover only Rs.1000 so the time required recovering Rs. 1000 will be (Rs.1000/Rs.4000)× 12months = 3 months. Thus, the PBP is 3 years and 3 months (3.25 years). Decision Rule:  The PBP can be used as a decision criterion to select investment proposal. If the PBP is less than the maximum acceptable payback period, accept the project. If the PBP is greater than the maximum acceptable payback period, reject the project.
  • 6. To allow for risk, the businessmen required a premium over and above an alternative which is risk free. It is proposed that risk premium be incorporated into the capital budgeting analysis through the discount rate. i.e. If the time preference for the money is to be recognized by discounting estimated future cash flows, at some risk free rate, to there present value, then, to allow for the riskiness of the future cash flow a risk premium rate may be added to risk free discount rate. Such a composite discount would account for both time preference and risk preference. RADR= Risk free rate + Risk Premium OR k = Rf + Rp  The RADR accounts for risk by varying discount rate depending on the degree of risk of investment projects. The following figure portrays the relationship between amount of risk and the required k.  The following equation can be used:-  NPV = ΣNCFt / ( 1+k )t - CO Where k is a risk-adjusted rate.
  • 7. The risk adjusted approach can be used for both NPV & IRR. If NPV method is used for evaluation, the NPV would be calculated using risk adjusted rate. If NPV is positive, the proposal would qualify for acceptance, if it is negative, the proposal would be rejected. In case of IRR, the IRR would be compared with the risk adjusted required rate of return. If the ‘r’ exceeds risk adjusted rate, the proposal would be accepted, otherwise not. For example, if an investment project has following cash flows, its NPV using RADR will be as follows: Risk free rate is 6% and Risk adjusted rate is 10%. Year CFAT (RS.) PV @10 PV( Rs.) 1 2 3 50000 40000 45000 LESS: 0.909 0.826 0.751 ΣPV Investment 45450 33040 33795 --------- 112285 150000 -------
  • 8. The certainty equivalent coefficient (α) can be determined as a relationship between the certain cash flows and the uncertain cash flows. For example, if a company expected a risky cash flow of Rs. 90,000 and a risk free cash flow of Rs. 65,000 then (α1 ) will be calculated as follows:- (α)t =NCFt* /NCFt = risk free cash flows / risky cashflows=65,000 /90,000 The certainty equivalent coefficient (α ) t assumes a value between 0 and 1 and varies inversely with risk. The higher the risk, the lower the (α)t and the lower the risk, the higher the (α)t . The certainty equivalent approach can be expressed in the form of equation as follows: NPV=Σαt NCFt / (1+kf)t where, NCFt = Net cash flow, α t= the certainty equivalent coefficient, kf = Risk free rate
  • 9. (a) Sensitivity Analysis (b) Scenario Analysis (c)Simulation Analysis 1) The sensitivity analysis helps in identifying how sensitive are the various estimated variables of the project. It shows how sensitive is a project’s NPV or IRR for a given change in particular variables. Steps: The following three steps are involved in the use of sensitivity analysis. 1. Identify the variables which can influence the project’s NPV or IRR. 2. Define the underlying relationship between the variables. 3. Analyze the impact of the change in each of the variables on the project’s NPV or IRR.
  • 10. The Project’s NPV or IRR can be computed under following three assumptions in sensitivity analysis. 1. Pessimistic (i.e. the worst), 2. Expected (i.e. the most likely) 3. Optimistic (i.e. the best) For example, A company has two mutually exclusive projects for process improvement. The management has developed following estimates of the annual cash flows for each project having a life of fifteen years and 12% discount rate.
  • 11. PROJECT A Net investments 90000 CFAT Estimates PVAIF12%, 15yrs PV NPV pessimistic 10000 6.811 68110 (21890) Most likely 15000 6.811 102165 12165 optimistic 21000 6.811 143031 53031 SENSTIVITY ANALYSIS:- PROJECT A Net investments 90000 CFAT Estimates PVAIF12%, 15yrs PV NPV pessimistic 13500 6.811 91948.5 1948.5 Most likely 15000 6.811 102165 12165 optimistic 18000 6.811 122598 32598
  • 12. The NPV calculations of both the projects suggest that the projects are equally desirable on the basis of the most likely estimates of cash flows. However, the Project– A is riskier than Project – B because its NPV can be negative to the extent of Rs. 21,890 but there is no possibility of incurring any losses with project B as all the NPVs are positive. As the two projects are mutually exclusive, the actual selection of the projects depends on decision maker’s attitude towards the risk. If he is ready to take risk, he will select Project A, because it has the potential of yielding NPV much higher than (Rs. 53031) Project B. But if he is risk averse, he will select project B.
  • 13. The another way to examine the risk of investment is to analyze the impact of alternative combination of variables , called the scenarios , on the project NPV. EXAMPLE:- In the expected scenario, it may be possible to increase the sales volume of 1 lac units to 1,25000 units . If the company reduces the selling price from Rs. 15 to Rs. 13.50, resorts to aggressive advertisement campaign, their by increasing unit variable cost to Rs.7.1( 5% increase) & fixed cost is rs.44,000. Calculate the NPV. OPTIMISTIC :-1,25,000 PESSIMISTIC:-75,000 NEUTRAL:- 1,00,000
  • 14. REVENUE = 1250 *!6.50=20625RS. VARIABLES BASE VALUE PESSISMISTIC OPTIMISTIC SALES VOLUME 1000 750 1250 SELLING PRICE /UNIT RS.15 13.50 16.50 VARIABLE COST / UNIT 7.1 7.43 6.75 FIXED COST 4400 4840 4400
  • 15.  Sensitivity analysis and Scenario analysis are quite useful to understand the uncertainty of the investment projects. But both the methods do not consider the interactions between variables and also, they do not reflect on the probability of the change in variables. Monte simulation considers the interaction among variables & probabilities of change in variables & its impact on NPV of cash inflows . In this a computer generates a very large no. of scenarios according to the probability distribution of variables. Steps:- 1)Identification of the variables , which influences the cash inflows. Initial investment ,Market size ,Fixed cost & variable cost , market growth rate 2) Specify the formula which relates the variables. 3)Assign the probabilities to each variables 4)Develop a computer program, that randomly selects 1 value from the probability with each variable & uses these values, to calculate projects NPV.