Project Management
Key Concepts
Cost Forecasting
What is it?
As the project progresses, the project team may
develop forecasts for how much it will cost to
complete the project, and compare these to the
planned Budget (Budget at Completion).
Cost Forecasting
What is it?
Project Forecasting techniques can include:
• Estimate at Completion (EAC)
• Estimate to Complete (ETC)
• Variance at Completion (VAC)
• To Complete Performance Index (TCPI)
Cost Forecasting
Project budget of $10,000, where 30%
completed, against 40% planned and $5,000
spent so far.
Cost Forecasting
Estimate at Completion (EAC)
Is the expected total cost of completing all the work.
EAC = AC + BAC – EV (If future work will be completed at planned rate)
EAC = BAC/CPI) (If CPI remains the same)
EAC = AC + [(BAC – EV)/(CPI x SPI)] (If both the CPI and SPI influence the remaining work)
EAC = AC + Bottom-up ETC (If the initial plan is no longer valid)
Project budget of $10,000, where 30%
completed, against 40% planned and $5,000
spent so far.
EAC = $5,000 + ($10,000 - $3000)
= $5,000 + $7,000
= $12,000
Cost Forecasting
Estimate at Completion (EAC)
Is the expected total cost of completing all the work.
EAC = AC + BAC – EV (If future work will be completed at planned rate)
EAC = BAC/CPI [CPI = EV/AC] (If CPI remains the same)
EAC = AC + [(BAC – EV)/(CPI x SPI)] (If both the CPI and SPI influence the remaining work)
EAC = AC + Bottom-up ETC (If the initial plan is no longer valid)
Project budget of $10,000, where 30%
completed, against 40% planned and $5,000
spent so far.
EAC = $10,000 / ($3,000/$5000)
= $10,000 / 0.60
= $16,667
Cost Forecasting
Estimate at Completion (EAC)
Is the expected total cost of completing all the work.
EAC = AC + BAC – EV (If future work will be completed at planned rate)
EAC = BAC/CPI [CPI = EV/AC] (If CPI remains the same)
EAC = AC + [(BAC – EV)/(CPI x SPI)] (If both the CPI and SPI influence the remaining work)
EAC = AC + Bottom-up ETC (If the initial plan is no longer valid)
Project budget of $10,000, where 30% completed,
against 40% planned and $5,000 spent so far.
EAC = $5,000 + ($10,000-$3000)/((EV/AC) x (EV/PV))
(0.45)
= $5,000 + ($7,000/(0.60 x 0.75)) $15,555
= $20,555
Cost Forecasting
Estimate to Complete (ETC)
Is the expected cost to finish all the remaining project work.
ETC = EAC – AC (Estimate at Completion – Actual Cost)
Project budget of $10,000, where 30% completed,
against 40% planned and $5,000 spent so far.
($12,000)
ETC = ($5000 + ($10,000-$3,000)) - $5,000
= $7,000
Cost Forecasting
Variance at Completion (VAC)
Is the estimated difference in cost at the completion of the project.
VAC = BAC – EAC
Positive: Ahead of Schedule; Negative: Behind Schedule
Project budget of $10,000, where 30%
completed, against 40% planned and $5,000
spent so far.
($7,000)
VAC = $10,000 – ($5000 + ($10,000-$3,000))
= -$2,000
Cost Forecasting
To Complete Performance Index (TCPI)
The efficiency that must be maintained in order to complete your
project as planned.
• TCPI = (BAC – EV)/(BAC – AC)
• > 1 Harder to Complete, < 1 Easier to Complete
Project budget of $10,000, where 30%
completed, against 40% planned and $5,000
spent so far.
TCPI = ($10,000 - $3,000) / ($10,000 - $5000)
= $7,000 / $5,000
= 1.4 (harder to complete)

Contenu connexe

Tendances

Techniques in black box testing
Techniques in black box testingTechniques in black box testing
Techniques in black box testing
Duy Tan Geek
 

Tendances (8)

PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
EV ِAV PV example
EV ِAV PV exampleEV ِAV PV example
EV ِAV PV example
 
Earnvalue analysis in Software engineering
Earnvalue analysis in Software engineeringEarnvalue analysis in Software engineering
Earnvalue analysis in Software engineering
 
Work Summary
Work SummaryWork Summary
Work Summary
 
Calculating ETC In 4 Different Scenarios
Calculating ETC In 4 Different ScenariosCalculating ETC In 4 Different Scenarios
Calculating ETC In 4 Different Scenarios
 
E.c.v Introduction
E.c.v IntroductionE.c.v Introduction
E.c.v Introduction
 
Techniques in black box testing
Techniques in black box testingTechniques in black box testing
Techniques in black box testing
 

Similaire à 7.4 Forecasting Techniques

Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
sagarlesley
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Serdar Temiz
 

Similaire à 7.4 Forecasting Techniques (20)

Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
Earned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examEarned value for pmp and pmi acp exam
Earned value for pmp and pmi acp exam
 
Project Management 3.2 cost
Project Management 3.2 costProject Management 3.2 cost
Project Management 3.2 cost
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
CAPM study session 4
CAPM study session 4CAPM study session 4
CAPM study session 4
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
 
Pppl evms training_02
Pppl evms training_02Pppl evms training_02
Pppl evms training_02
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 

Plus de DavidMcLachlan1

Plus de DavidMcLachlan1 (20)

10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication Management
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
 
12.1 Procurement Contracts
12.1 Procurement Contracts12.1 Procurement Contracts
12.1 Procurement Contracts
 
12.2 Conduct Procurements
12.2 Conduct Procurements12.2 Conduct Procurements
12.2 Conduct Procurements
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control Procurements
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope Management
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project Knowledge
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
 
Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2
 
Scenario - The Project Management Environment
Scenario - The Project Management EnvironmentScenario - The Project Management Environment
Scenario - The Project Management Environment
 
Agile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentAgile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile Environment
 
Agile Scenarios - Core Practices
Agile Scenarios - Core PracticesAgile Scenarios - Core Practices
Agile Scenarios - Core Practices
 
Agile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningAgile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave Planning
 
6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks
 
5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks
 
7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment
 
4.0 The Agile Core Practices
4.0 The Agile Core Practices4.0 The Agile Core Practices
4.0 The Agile Core Practices
 
3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles
 

Dernier

Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
ZurliaSoop
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
KarakKing
 
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdfVishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
ssuserdda66b
 

Dernier (20)

How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdfVishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Dyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxDyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptx
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 

7.4 Forecasting Techniques

  • 3. What is it? As the project progresses, the project team may develop forecasts for how much it will cost to complete the project, and compare these to the planned Budget (Budget at Completion). Cost Forecasting
  • 4. What is it? Project Forecasting techniques can include: • Estimate at Completion (EAC) • Estimate to Complete (ETC) • Variance at Completion (VAC) • To Complete Performance Index (TCPI) Cost Forecasting Project budget of $10,000, where 30% completed, against 40% planned and $5,000 spent so far.
  • 5. Cost Forecasting Estimate at Completion (EAC) Is the expected total cost of completing all the work. EAC = AC + BAC – EV (If future work will be completed at planned rate) EAC = BAC/CPI) (If CPI remains the same) EAC = AC + [(BAC – EV)/(CPI x SPI)] (If both the CPI and SPI influence the remaining work) EAC = AC + Bottom-up ETC (If the initial plan is no longer valid) Project budget of $10,000, where 30% completed, against 40% planned and $5,000 spent so far. EAC = $5,000 + ($10,000 - $3000) = $5,000 + $7,000 = $12,000
  • 6. Cost Forecasting Estimate at Completion (EAC) Is the expected total cost of completing all the work. EAC = AC + BAC – EV (If future work will be completed at planned rate) EAC = BAC/CPI [CPI = EV/AC] (If CPI remains the same) EAC = AC + [(BAC – EV)/(CPI x SPI)] (If both the CPI and SPI influence the remaining work) EAC = AC + Bottom-up ETC (If the initial plan is no longer valid) Project budget of $10,000, where 30% completed, against 40% planned and $5,000 spent so far. EAC = $10,000 / ($3,000/$5000) = $10,000 / 0.60 = $16,667
  • 7. Cost Forecasting Estimate at Completion (EAC) Is the expected total cost of completing all the work. EAC = AC + BAC – EV (If future work will be completed at planned rate) EAC = BAC/CPI [CPI = EV/AC] (If CPI remains the same) EAC = AC + [(BAC – EV)/(CPI x SPI)] (If both the CPI and SPI influence the remaining work) EAC = AC + Bottom-up ETC (If the initial plan is no longer valid) Project budget of $10,000, where 30% completed, against 40% planned and $5,000 spent so far. EAC = $5,000 + ($10,000-$3000)/((EV/AC) x (EV/PV)) (0.45) = $5,000 + ($7,000/(0.60 x 0.75)) $15,555 = $20,555
  • 8. Cost Forecasting Estimate to Complete (ETC) Is the expected cost to finish all the remaining project work. ETC = EAC – AC (Estimate at Completion – Actual Cost) Project budget of $10,000, where 30% completed, against 40% planned and $5,000 spent so far. ($12,000) ETC = ($5000 + ($10,000-$3,000)) - $5,000 = $7,000
  • 9. Cost Forecasting Variance at Completion (VAC) Is the estimated difference in cost at the completion of the project. VAC = BAC – EAC Positive: Ahead of Schedule; Negative: Behind Schedule Project budget of $10,000, where 30% completed, against 40% planned and $5,000 spent so far. ($7,000) VAC = $10,000 – ($5000 + ($10,000-$3,000)) = -$2,000
  • 10. Cost Forecasting To Complete Performance Index (TCPI) The efficiency that must be maintained in order to complete your project as planned. • TCPI = (BAC – EV)/(BAC – AC) • > 1 Harder to Complete, < 1 Easier to Complete Project budget of $10,000, where 30% completed, against 40% planned and $5,000 spent so far. TCPI = ($10,000 - $3,000) / ($10,000 - $5000) = $7,000 / $5,000 = 1.4 (harder to complete)