SlideShare une entreprise Scribd logo
1  sur  5
IAS 11: Construction Contracts




                          Roshankumar S Pimpalkar




roshankumar.2007@rediffmail.com
This standard prescribes the accounting of costs and revenues associated
      with construction contracts.

      Key Definitions:

      Construction contract is a contract specifically negotiated for the construction
      of an asset or a combination of assets that are closely interrelated or
      interdependent in terms of design, technology and function or their ultimate
      purpose or use.

      Fixed Price contract is a construction contract in which the contractor agrees
      to a fixed contract price or a fixed rate per unit of output, which in some cases
      is subject to cost escalation clauses.

      Cost Plus contract is a construction contract in which a contractor is
      reimbursed for allowable or otherwise defined costs, plus a percentage of
      these costs or a fixed price.

      Guidance by IFRIC 15: Agreements for Construction of Real Estate.

      An agreement for construction of a real estate is a construction contract within
      the scope of IAS 11 only when the buyer is able to specify the major structural
      elements of the design of the real estate before the construction begins and/or
      specify major structural changes once construction is in progress (whether he
      exercises that ability or not). If the buyer does not have that ability then IAS 18
      applies.

      Combining and Segmenting Construction Contracts

      When a contract covers number of assets construction of each asset should
      be considered as a separate construction contract when:

             Separate proposals have been submitted for each asset
             Each asset has been submitted for separate negotiation and the
             contractor and customer have been able to accept or reject that part of
             the contract relating to each asset and
             The costs and revenues of each asset can be identified.

      A group of contract, whether with a single customer or with several
      customers, should be treated as single construction contract when:

             The group of contract is negotiated as single package
             The contracts are so closely interrelated that they are, in effect, a part
             of a single project with an overall profit margin, and
             The contracts are performed concurrently or in a continuous sequence.

      A contract may provide construction of an additional asset at the option of the
      customer or may be amended to include the construction of an additional




roshankumar.2007@rediffmail.com
asset. The construction of an additional asset should be treated as a separate
      construction contract when:

             The asset differs significantly in design, technology or function from the
             asset or asset covered by the original contract, or
             The price of the asset is negotiated without regard to the original
             contract price.




      Contract Revenue

      Contract revenue should comprise:

              The initial amount of revenue agreed in the contract; and
              Variations in the work, claim and incentive payments:
                  o To the extent that is probable that they will result in revenue i.e.
                      the customer will approve the variation and amount of
                      revenue arising out of variation; and
                  o They are capable of being reliably measured
              Incentive payments are additional amounts paid to the contractor is
              specified performance standards are met or exceeded. It is included in
              the contract revenue when:
                  o The contract is sufficiently advanced that it is probable that the
                      specified performance standards will be met or exceeded, and
                  o The amount of incentive payment can be measured reliably.
              A claim is an amount which a contractor seeks from the customer or
              another party as a reimbursement for costs not included in contract
              price. It is included in contract price when:
                  o Negotiations have reached advanced stage such that it is
                      probable that the customer will accept the claim; and
                  o The amount of claim can be measured reliably.
              Probability means more likely than not.

       Contract Cost

       Contract costs should comprise of

              Costs that relate directly to the specific contract
              Costs that are attributable to the contract in general and can be
              allocated to the contract, and
              Such other costs as are specifically chargeable to the customer under
              the terms of the contract




roshankumar.2007@rediffmail.com
Costs incurred in securing the contract are also included in contract
              costs they can be identified, reliably measured and it is probable that
              the contract will be obtained. However if such costs are recognised as
              an expense in the period in which they are incurred then they are not
              included in contract cost when the contract is obtained in a subsequent
              period.

       Recognition

       Contract revenue and contract costs associated with a construction contract
       should be recognised as revenue and expenses respectively by reference to
       the stage of completion of the contract activity at the end of the reporting
       period when the outcome of the construction contract can be estimated
       reliably.

       Any expected loss on the contract should be recognised as an expense
       immediately.

       Fixed Price Contract

       In this type of contract the outcome can be estimated reliably when all of the
       following conditions are satisfied:

              Total contract revenue can be measured reliably
              It is probable that economic benefits associated with contract will flow
              to the enterprise
              Both the contract cost to complete the contract and stage of
              completion can be measured reliably, and
              Contract costs attributable to the contract can be measured reliably
              and can be identified clearly, so that the actual costs incurred can be
              compared with prior estimates.

       Cost Plus Contract

       In this type of contract outcome can be estimated reliably when all of the
       following conditions are satisfied

              It is probable that the economic benefits associated with the contract
              will flow to the enterprise; and
              Contract costs attributable to the contract, whether or not specifically
              reimbursable, can be clearly identified and measured reliably.

       Capitalisation of costs

       Contract costs incurred that relate to future activity on the contract are
       recognised as an asset provided it is probable that they will be recovered.




roshankumar.2007@rediffmail.com
Such costs represents amount due from customer and are classified as work
       in progress.

       When an uncertainty about the collectability of revenue already
       recognised in the statement of comprehensive income arises, the
       uncollectable amount is recognised as an expense rather than an adjustment
       to contract revenue.

       When the outcome of the construction contract cannot be estimated
       reliably:

              Revenue should be recognised only to the extent of contract costs
              incurred and if the recovery is probable; and
              Contract costs should be recognised as an expense in the period in
              which they are incurred

        In this case no profit is recognised. Once the outcome of construction
       contract can be estimated reliably, profit can be recognised.

       When it is probable that that total contract cost will exceed total contract
       revenue, the expected loss should be recognised as an expense
       immediately. In such case amount of loss to be recognised is expected loss
       plus profit recognised earlier less loss recognised in current year.

        Determining the stage of completion

       Depending on the nature of construction contract the method used to
       determine the stage of completion of the contract are as follows:

              The ratio – contract cost incurred to for the work performed to date /
              estimated total contract cost
              Surveys of work performed; or
              Completion of physical proportion of contract




roshankumar.2007@rediffmail.com

Contenu connexe

Tendances

3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
Praveen Premkumar
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
guestdb5e498
 
The architect as contract administrator a legal perspective - presentation ...
The architect as contract administrator   a legal perspective - presentation ...The architect as contract administrator   a legal perspective - presentation ...
The architect as contract administrator a legal perspective - presentation ...
Zainab Zainordin
 

Tendances (20)

3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
 
Lump Sum Contract
Lump Sum ContractLump Sum Contract
Lump Sum Contract
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
contract procedure
contract procedurecontract procedure
contract procedure
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
 
Types and forms of contracts
Types and forms of contracts Types and forms of contracts
Types and forms of contracts
 
The architect as contract administrator a legal perspective - presentation ...
The architect as contract administrator   a legal perspective - presentation ...The architect as contract administrator   a legal perspective - presentation ...
The architect as contract administrator a legal perspective - presentation ...
 
Tendering clauses of contract
Tendering clauses of contractTendering clauses of contract
Tendering clauses of contract
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...
 
Contract administration iowa AGC
Contract administration iowa AGCContract administration iowa AGC
Contract administration iowa AGC
 
ACH 216 Lecture 04c (Project Award)
ACH 216 Lecture 04c (Project Award)ACH 216 Lecture 04c (Project Award)
ACH 216 Lecture 04c (Project Award)
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contracts
 
types of contracts
 types of contracts types of contracts
types of contracts
 
contract administration PPT
 contract administration PPT contract administration PPT
contract administration PPT
 
Key terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendmentsKey terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendments
 

En vedette (19)

Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Quality costing
Quality costingQuality costing
Quality costing
 
IAS 2
IAS 2IAS 2
IAS 2
 
Chapter24 cashflowstatements2008
Chapter24 cashflowstatements2008Chapter24 cashflowstatements2008
Chapter24 cashflowstatements2008
 
Financial accounting standards
Financial accounting standardsFinancial accounting standards
Financial accounting standards
 
Inventory(ias 2)
Inventory(ias 2) Inventory(ias 2)
Inventory(ias 2)
 
IAS 7
IAS 7IAS 7
IAS 7
 
Types of Companies, Meetings and important documents for company registration
Types of Companies, Meetings and important documents for company registrationTypes of Companies, Meetings and important documents for company registration
Types of Companies, Meetings and important documents for company registration
 
Business and Corporate Law
Business and Corporate LawBusiness and Corporate Law
Business and Corporate Law
 
Management accounting
Management accountingManagement accounting
Management accounting
 
Ias 23 Borrowing Costs
Ias 23 Borrowing CostsIas 23 Borrowing Costs
Ias 23 Borrowing Costs
 
Property plant and equipment IAS 16 (Assignment)
Property plant and equipment IAS 16 (Assignment)Property plant and equipment IAS 16 (Assignment)
Property plant and equipment IAS 16 (Assignment)
 
IAS 1
IAS 1IAS 1
IAS 1
 
Ias 1
Ias 1Ias 1
Ias 1
 
Ind AS 7
Ind AS 7Ind AS 7
Ind AS 7
 
IAS 16 Property Plant And Equipment
IAS 16 Property Plant And EquipmentIAS 16 Property Plant And Equipment
IAS 16 Property Plant And Equipment
 
Ias 7 Cash Flow Statements
Ias 7 Cash Flow StatementsIas 7 Cash Flow Statements
Ias 7 Cash Flow Statements
 
Company secretarial practice__objectives
Company secretarial practice__objectivesCompany secretarial practice__objectives
Company secretarial practice__objectives
 
Corporate law
Corporate lawCorporate law
Corporate law
 

Similaire à IAS 11

ICDS - IIIConstruction contract
ICDS - IIIConstruction contract ICDS - IIIConstruction contract
ICDS - IIIConstruction contract
Madhuri Devi
 
Chapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptxChapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptx
sulevrunda
 
Financial management of construction contracts
Financial management of construction contractsFinancial management of construction contracts
Financial management of construction contracts
idnobleg77
 
5 Risks Construction Owners Face
5 Risks Construction Owners Face5 Risks Construction Owners Face
5 Risks Construction Owners Face
Mark McCarthy
 

Similaire à IAS 11 (20)

ICDS : Construction Contracts
ICDS : Construction ContractsICDS : Construction Contracts
ICDS : Construction Contracts
 
Project procuremenet contract in ethiopia
Project procuremenet contract in ethiopiaProject procuremenet contract in ethiopia
Project procuremenet contract in ethiopia
 
AS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party TransactionsAS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party Transactions
 
Construction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of ResidencesConstruction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of Residences
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdf
 
ICDS - IIIConstruction contract
ICDS - IIIConstruction contract ICDS - IIIConstruction contract
ICDS - IIIConstruction contract
 
Job,batch and contract costing
Job,batch and contract costingJob,batch and contract costing
Job,batch and contract costing
 
Chapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptxChapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptx
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Advance 1020 1045
Advance 1020 1045Advance 1020 1045
Advance 1020 1045
 
Final types of contracts- different types of contracts
Final types of contracts- different types of contractsFinal types of contracts- different types of contracts
Final types of contracts- different types of contracts
 
Vietnam Accounting Standards - VAS 15 Construction contracts
Vietnam Accounting Standards - VAS 15 Construction contractsVietnam Accounting Standards - VAS 15 Construction contracts
Vietnam Accounting Standards - VAS 15 Construction contracts
 
Contracts
ContractsContracts
Contracts
 
Contract Costing
Contract CostingContract Costing
Contract Costing
 
6 main rules for engineering to order contracts
6 main rules for engineering to order contracts6 main rules for engineering to order contracts
6 main rules for engineering to order contracts
 
Financial management of construction contracts
Financial management of construction contractsFinancial management of construction contracts
Financial management of construction contracts
 
Contract costing, BCOM (HONS)
Contract costing, BCOM (HONS)Contract costing, BCOM (HONS)
Contract costing, BCOM (HONS)
 
5 Risks Construction Owners Face
5 Risks Construction Owners Face5 Risks Construction Owners Face
5 Risks Construction Owners Face
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract
 
Contract Costing.pptx
Contract Costing.pptxContract Costing.pptx
Contract Costing.pptx
 

Plus de RS P

IAS 24
IAS 24IAS 24
IAS 24
RS P
 
IAS 23
IAS 23IAS 23
IAS 23
RS P
 
IAS 21
IAS 21IAS 21
IAS 21
RS P
 
IAS 18
IAS 18IAS 18
IAS 18
RS P
 
IAS 17
IAS 17IAS 17
IAS 17
RS P
 
IAS 16: Property, Plant and Equipment
IAS 16: Property, Plant and EquipmentIAS 16: Property, Plant and Equipment
IAS 16: Property, Plant and Equipment
RS P
 
IAS 12
IAS 12IAS 12
IAS 12
RS P
 
IAS 14: Segment Reporting
IAS 14: Segment ReportingIAS 14: Segment Reporting
IAS 14: Segment Reporting
RS P
 
IAS 10
IAS 10IAS 10
IAS 10
RS P
 
IAS 8
IAS 8IAS 8
IAS 8
RS P
 
Undestanding cash flow statement
Undestanding cash flow statementUndestanding cash flow statement
Undestanding cash flow statement
RS P
 
Libor scandal
Libor scandalLibor scandal
Libor scandal
RS P
 
Bottom fishing
Bottom fishingBottom fishing
Bottom fishing
RS P
 
Robert vadra vs iac
Robert vadra vs iacRobert vadra vs iac
Robert vadra vs iac
RS P
 
Bartering
BarteringBartering
Bartering
RS P
 
Hedging learn with fun
Hedging  learn with funHedging  learn with fun
Hedging learn with fun
RS P
 
Outright monetary transaction
Outright monetary transactionOutright monetary transaction
Outright monetary transaction
RS P
 
Crowding out
Crowding outCrowding out
Crowding out
RS P
 
GAAR
GAARGAAR
GAAR
RS P
 

Plus de RS P (20)

IAS 24
IAS 24IAS 24
IAS 24
 
IAS 23
IAS 23IAS 23
IAS 23
 
IAS 21
IAS 21IAS 21
IAS 21
 
IAS 18
IAS 18IAS 18
IAS 18
 
IAS 17
IAS 17IAS 17
IAS 17
 
IAS 16: Property, Plant and Equipment
IAS 16: Property, Plant and EquipmentIAS 16: Property, Plant and Equipment
IAS 16: Property, Plant and Equipment
 
IAS 12
IAS 12IAS 12
IAS 12
 
IAS 14: Segment Reporting
IAS 14: Segment ReportingIAS 14: Segment Reporting
IAS 14: Segment Reporting
 
IAS 10
IAS 10IAS 10
IAS 10
 
IAS 8
IAS 8IAS 8
IAS 8
 
Undestanding cash flow statement
Undestanding cash flow statementUndestanding cash flow statement
Undestanding cash flow statement
 
Libor scandal
Libor scandalLibor scandal
Libor scandal
 
Bottom fishing
Bottom fishingBottom fishing
Bottom fishing
 
Robert vadra vs iac
Robert vadra vs iacRobert vadra vs iac
Robert vadra vs iac
 
Bartering
BarteringBartering
Bartering
 
Hedging learn with fun
Hedging  learn with funHedging  learn with fun
Hedging learn with fun
 
Outright monetary transaction
Outright monetary transactionOutright monetary transaction
Outright monetary transaction
 
Crowding out
Crowding outCrowding out
Crowding out
 
GAAR
GAARGAAR
GAAR
 
Interest
InterestInterest
Interest
 

Dernier

1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
QucHHunhnh
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
PECB
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
kauryashika82
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 

Dernier (20)

Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIFood Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Role Of Transgenic Animal In Target Validation-1.pptx
Role Of Transgenic Animal In Target Validation-1.pptxRole Of Transgenic Animal In Target Validation-1.pptx
Role Of Transgenic Animal In Target Validation-1.pptx
 

IAS 11

  • 1. IAS 11: Construction Contracts Roshankumar S Pimpalkar roshankumar.2007@rediffmail.com
  • 2. This standard prescribes the accounting of costs and revenues associated with construction contracts. Key Definitions: Construction contract is a contract specifically negotiated for the construction of an asset or a combination of assets that are closely interrelated or interdependent in terms of design, technology and function or their ultimate purpose or use. Fixed Price contract is a construction contract in which the contractor agrees to a fixed contract price or a fixed rate per unit of output, which in some cases is subject to cost escalation clauses. Cost Plus contract is a construction contract in which a contractor is reimbursed for allowable or otherwise defined costs, plus a percentage of these costs or a fixed price. Guidance by IFRIC 15: Agreements for Construction of Real Estate. An agreement for construction of a real estate is a construction contract within the scope of IAS 11 only when the buyer is able to specify the major structural elements of the design of the real estate before the construction begins and/or specify major structural changes once construction is in progress (whether he exercises that ability or not). If the buyer does not have that ability then IAS 18 applies. Combining and Segmenting Construction Contracts When a contract covers number of assets construction of each asset should be considered as a separate construction contract when: Separate proposals have been submitted for each asset Each asset has been submitted for separate negotiation and the contractor and customer have been able to accept or reject that part of the contract relating to each asset and The costs and revenues of each asset can be identified. A group of contract, whether with a single customer or with several customers, should be treated as single construction contract when: The group of contract is negotiated as single package The contracts are so closely interrelated that they are, in effect, a part of a single project with an overall profit margin, and The contracts are performed concurrently or in a continuous sequence. A contract may provide construction of an additional asset at the option of the customer or may be amended to include the construction of an additional roshankumar.2007@rediffmail.com
  • 3. asset. The construction of an additional asset should be treated as a separate construction contract when: The asset differs significantly in design, technology or function from the asset or asset covered by the original contract, or The price of the asset is negotiated without regard to the original contract price. Contract Revenue Contract revenue should comprise: The initial amount of revenue agreed in the contract; and Variations in the work, claim and incentive payments: o To the extent that is probable that they will result in revenue i.e. the customer will approve the variation and amount of revenue arising out of variation; and o They are capable of being reliably measured Incentive payments are additional amounts paid to the contractor is specified performance standards are met or exceeded. It is included in the contract revenue when: o The contract is sufficiently advanced that it is probable that the specified performance standards will be met or exceeded, and o The amount of incentive payment can be measured reliably. A claim is an amount which a contractor seeks from the customer or another party as a reimbursement for costs not included in contract price. It is included in contract price when: o Negotiations have reached advanced stage such that it is probable that the customer will accept the claim; and o The amount of claim can be measured reliably. Probability means more likely than not. Contract Cost Contract costs should comprise of Costs that relate directly to the specific contract Costs that are attributable to the contract in general and can be allocated to the contract, and Such other costs as are specifically chargeable to the customer under the terms of the contract roshankumar.2007@rediffmail.com
  • 4. Costs incurred in securing the contract are also included in contract costs they can be identified, reliably measured and it is probable that the contract will be obtained. However if such costs are recognised as an expense in the period in which they are incurred then they are not included in contract cost when the contract is obtained in a subsequent period. Recognition Contract revenue and contract costs associated with a construction contract should be recognised as revenue and expenses respectively by reference to the stage of completion of the contract activity at the end of the reporting period when the outcome of the construction contract can be estimated reliably. Any expected loss on the contract should be recognised as an expense immediately. Fixed Price Contract In this type of contract the outcome can be estimated reliably when all of the following conditions are satisfied: Total contract revenue can be measured reliably It is probable that economic benefits associated with contract will flow to the enterprise Both the contract cost to complete the contract and stage of completion can be measured reliably, and Contract costs attributable to the contract can be measured reliably and can be identified clearly, so that the actual costs incurred can be compared with prior estimates. Cost Plus Contract In this type of contract outcome can be estimated reliably when all of the following conditions are satisfied It is probable that the economic benefits associated with the contract will flow to the enterprise; and Contract costs attributable to the contract, whether or not specifically reimbursable, can be clearly identified and measured reliably. Capitalisation of costs Contract costs incurred that relate to future activity on the contract are recognised as an asset provided it is probable that they will be recovered. roshankumar.2007@rediffmail.com
  • 5. Such costs represents amount due from customer and are classified as work in progress. When an uncertainty about the collectability of revenue already recognised in the statement of comprehensive income arises, the uncollectable amount is recognised as an expense rather than an adjustment to contract revenue. When the outcome of the construction contract cannot be estimated reliably: Revenue should be recognised only to the extent of contract costs incurred and if the recovery is probable; and Contract costs should be recognised as an expense in the period in which they are incurred In this case no profit is recognised. Once the outcome of construction contract can be estimated reliably, profit can be recognised. When it is probable that that total contract cost will exceed total contract revenue, the expected loss should be recognised as an expense immediately. In such case amount of loss to be recognised is expected loss plus profit recognised earlier less loss recognised in current year. Determining the stage of completion Depending on the nature of construction contract the method used to determine the stage of completion of the contract are as follows: The ratio – contract cost incurred to for the work performed to date / estimated total contract cost Surveys of work performed; or Completion of physical proportion of contract roshankumar.2007@rediffmail.com