Operation Management
Shubham Chaudhari
(14005)
Delhi Metro –Project Management
Abstract:
The city of Delhi, capital of India, has been facing problems such as
traffic growth, congestion, pollution, increased accidents
since last decade. To ameliorate both the quality and availability
of mass transport system with an aim to address the aforementioned
issues, a non-polluting rail-based mass transit system was sought to
be an effective solution by Government of India (GoI)
and Government of the National Capital Territory of Delhi (GNCTD).
In order to achieve this challenging objective, a tremendous amount
of efforts have been directed towards planning, design and
implementation of this metro project. This study attempted to
analyse and elucidate the overall Delhi metro rail project
implementation through its inception till completion. It explains
various infrastructure aspects such as economical, environmental,
social that are being/were considered for this project. The Delhi
metro project was divided into four phases for its implementation
with a total length of the rail network to be approximately 404km.
Presently, Phase I and II have been successfully implemented and are
in operation. Phase III and IV are scheduled to be completed till 2016
and 2020 respectively. This project has set many records for its
successful implementation such as early completion of phase I,
achievement in terms of environment-friendly design and
implementation and is being viewed as one of the inspirational
model for metro projects planned to be undertaken all over the
world. The initiatives for introducing the metro system in Delhi were
taken in the early 1990s. In 1995,
the Government of India (GoI) and the Government of the National C
apital Territory of Delhi(GNCTD) formed the Delhi Metro Rail
Corporation Ltd (DMRC) under the Companies Act to construct the
Delhi Metro.
Mission:
 To cover the whole Delhi and adjoining areas with a metro
network by the year 2021.
 To serve the customers including ‘differently abled’
Commuters with passion.
 To sustain the image of being number one in the transportation
sector in India and to be among the top 3 Metro Rail systems in
Asia with regards to:
● Safety ● reliability ●punctuality ● quality and●responsiveness to
the customers
 To make Delhi metro self-sustainable.
Reason:
 Population of over 1 million.
 More registered vehicles than Mumbai, Kolkata & Chennai put
together.
 Automobiles contributing to more than 2/3rd
of the total
atmospheric pollution.
 High rate of road accidents.
Key Architects:
 The Central Road Research Institute (CRRI),New Delhi
 Metropolitan Transport Team (MTT) of the Indian Railways
 Delhi Development Authority(DDA)
 The Study Group of the Ministry of Railways
 RITES (Rail India Technical & Economics Services)
 Mr. E. Sreedharan ,Managing Director, DMRC
•Key Objectives-
 The main objective of the project is to improve Delhi’s urban
environment by reducing traffic congestion and pollution. The
Project is expected to help reduce traffic congestion, exhaust
emissions, and other types of urban pollution caused by motor
vehicles and to play a large role in improving Delhi’s transit
system.
 Outcomes-
 Delhi Mass Rapid Transit System is essentially a “social sector”
project, whose benefits will pervade over wide sections of the
economy. I phase will generate the following benefits to the city.
 21.82 lakhs commuter trips per day will be siphoned off the roads.
 2600 less buses on the roads. Increasing in average speed of the
buses from 10.5 km/h to 14km/h.
 Metro will reduce journey time of 50 to 75 %
 Saving of 2 million man-hours per day due to reduced journey
time.
 Saving in fuel cost worth Rs.5 billion per year.
 Space saving-The metro can carry traffic as 9 lanes/33 lanes of
motor cars(either ways)
 Delhi will experience a net benefit of Rs.437.23 lacks per days.
More comfortable & safe travel for the commuters.
 Reduction in atmospheric pollution levels by 50%.
Swot Analysis:
7 lessons from The Delhi Metro Project
1. An Experienced Leader
2. Lean Structure & Costs
3. Ownership From Every Staffer
4. Reverse Countdown Clocks
5. Project Management Tools
6. Transparency with Stakeholders
7. Constant Improvement
Project Evaluation
The successful completion of the project effectively silenced the
critics who had been sceptical about the ability of an Indian public
sector organization to complete any project, let alone one as
complex and costly as the Delhi Metro, on time and within the
budget..
RESULTS ANDANALYSIS
The case of Delhi metro showed the critical dependence of adoption
and implementation of more sustainable forms of urban transport on
supportive national policies accompanied by financial incentives.DM
achieved its milestone of success by making a feasible and most
comfortable mode of public transport leading to a reduction in traffic
congestion, reduction in noise and air pollution and ultimately
enhanced the overall productivity of citizen of the city and
businesses. The achievement of Delhi metro can be contributed to
various key factors as follows:
 Local buy-in:
Delhi Metro demonstrated the importance of local ownership of the
project. Autonomy achieved since the beginning of the project
played a vital role in dealing with the political issues. This led to cost
savings by better utilization of local resources, and improved
responsiveness of the design and extraction of desired
outcomes through construction. A firm belief by local
implementation teams in the benefits of their schemes made public
acceptance easy to gain.
 Multi-tiered financing:
By adopting alternative financing strategy thereby arranging funds
through a variety of international, national, state and local
stakeholders, DMRC could get to relative comparative advantages of
different funding actors in order to satisfy their short term and long
term financing needs.
 Dedicated agency:
 Delhi metro is largely benefited from clear governance
arrangements. The creation of a special organization called
DMRC for this project by Government of India and
Government of the National Capital of Delhi minimized the
need for coordination across multiple agencies thereby
streamlining design and construction.
 Incremental implementation: Due to the implementation of
DM project in various phases, it offered advantages such as
improved design, time savings, cost savings through feedback
and modification as well as greater public acceptance and
increased ridership.
 Environmental concerns: By
adopting various environmental effective strategies such as
environmental management system, reduction in carbon
dioxide emission by the adoption of regenerative braking
systems in the DMRC trains, DMRC gained acclamation all over
the world for this project.
CONCLUSION
The Delhi metro project is planned, implemented and operated by a
special organization by the name
‘Delhi metro rail corporation (DMRC)’, established jointly by
Government of India and Government of
the National Capital of Delhi in 1995. The project was/is being
planned and executed in four phases-Phase I, II, III, IV. The network is
presently comprising of five colour-coded regular lines (Red, Blue,
Green, Yellow, Violet), and a sixth line called Airport Express(Orange
Line), with a total length of 208kilometres (129 mi), serving156
stations (with 6 more Airport Express stations) having a mix of
underground, at-grade, and elevated stations. Phase I and II are
operational now with the airport express line while Phase III is in
implementation stage and phase IV is in planning stage. The total
cost estimated for Phase I and II was 300 Billion ($6 Billion) and for
Phase III isRs.352.42 Billion ($7.04 Billion).Phase III and IV are
scheduled to be completed by 2016 and 2020 respectively.
Considering the financial aspects, Japan Bank for international
Cooperation is giving a loan to
the project approximately to the extent of 60% of project cost. Gover
nment of India, Ministry of UrbanDevelopment and the Government
of the National Capital Territory of Delhi are each investing 15% of
the project cost. The remaining is met through interest-free loans
and property development. The O&M costs are essentially met by
ticket sales. Due to the incorporation of environment-friendly
techniques for implementation such as adoption of environmental
management system, reduction in carbon dioxide emission by the
adoption of
regenerative braking systems in the DMRC trains, the project has
been awarded certificates for these ‘green initiatives’. During the
implementation of Phase III and IV and post its completion, more
issues, development opportunities, aggravated positive and negative
impacts will be evolved and will be interesting in the future to dig
into the analysis of its overall planning, design, and implementation.
Delhi metro case study
Delhi metro case study

Contenu connexe

Tendances

The delhi-metro-project
The delhi-metro-projectThe delhi-metro-project
The delhi-metro-projectVikas Saini
 
Chennai metro rail
Chennai metro railChennai metro rail
Chennai metro raillibin paul
 
Delhi metro project evaluation
Delhi metro project evaluationDelhi metro project evaluation
Delhi metro project evaluationgouravranjan27
 
Delhi metro and Economics
Delhi metro and EconomicsDelhi metro and Economics
Delhi metro and EconomicsKunal Bhadane
 
Delhi metro presentation(SCHOOL/COLLEGE)
Delhi metro presentation(SCHOOL/COLLEGE)Delhi metro presentation(SCHOOL/COLLEGE)
Delhi metro presentation(SCHOOL/COLLEGE)Aashna Sharma
 
Delhi metro rail corporation secondary research
Delhi metro rail corporation secondary researchDelhi metro rail corporation secondary research
Delhi metro rail corporation secondary researchSunil Dayma
 
Mumbai metro project Phase I
Mumbai metro project Phase IMumbai metro project Phase I
Mumbai metro project Phase IKaran Shah
 
Hyderabad metro rail – for a better livable city
Hyderabad metro rail – for a better livable cityHyderabad metro rail – for a better livable city
Hyderabad metro rail – for a better livable cityPramod Kumar
 
Stakeholder analysis of Delhi Metro
Stakeholder analysis of Delhi MetroStakeholder analysis of Delhi Metro
Stakeholder analysis of Delhi Metrojerry christo
 
Delhi Metro Railway's Stakeholder Management
Delhi Metro Railway's Stakeholder Management Delhi Metro Railway's Stakeholder Management
Delhi Metro Railway's Stakeholder Management SIDDHARTH SWAIN
 
Analysis of Impact of East West Metro Corridor on Land Use
Analysis of Impact of East West Metro Corridor on Land UseAnalysis of Impact of East West Metro Corridor on Land Use
Analysis of Impact of East West Metro Corridor on Land UseAnirban Mahajan
 
Ahmedabad Metro Project
Ahmedabad Metro ProjectAhmedabad Metro Project
Ahmedabad Metro ProjectASHISH SINGH
 
INDUSTRIAL CORRIDOR - MAKE IN INDIA
INDUSTRIAL CORRIDOR - MAKE IN INDIAINDUSTRIAL CORRIDOR - MAKE IN INDIA
INDUSTRIAL CORRIDOR - MAKE IN INDIANetsourcing .in
 
Chhatrapati Shivaji International Airport
Chhatrapati Shivaji International AirportChhatrapati Shivaji International Airport
Chhatrapati Shivaji International AirportRohit Kumar Tiwari
 
Narayana Hrudayalaya Heart Hospital - Cardiac Care For the Poor
Narayana Hrudayalaya Heart Hospital - Cardiac Care For the PoorNarayana Hrudayalaya Heart Hospital - Cardiac Care For the Poor
Narayana Hrudayalaya Heart Hospital - Cardiac Care For the PoorManeesh Garg
 

Tendances (20)

Delhi metro case study
Delhi metro case studyDelhi metro case study
Delhi metro case study
 
The delhi-metro-project
The delhi-metro-projectThe delhi-metro-project
The delhi-metro-project
 
Chennai metro rail
Chennai metro railChennai metro rail
Chennai metro rail
 
Delhi metro project evaluation
Delhi metro project evaluationDelhi metro project evaluation
Delhi metro project evaluation
 
Delhi metro and Economics
Delhi metro and EconomicsDelhi metro and Economics
Delhi metro and Economics
 
Delhi metro presentation(SCHOOL/COLLEGE)
Delhi metro presentation(SCHOOL/COLLEGE)Delhi metro presentation(SCHOOL/COLLEGE)
Delhi metro presentation(SCHOOL/COLLEGE)
 
Delhi metro rail corporation secondary research
Delhi metro rail corporation secondary researchDelhi metro rail corporation secondary research
Delhi metro rail corporation secondary research
 
Mumbai metro project Phase I
Mumbai metro project Phase IMumbai metro project Phase I
Mumbai metro project Phase I
 
Hyderabad metro rail – for a better livable city
Hyderabad metro rail – for a better livable cityHyderabad metro rail – for a better livable city
Hyderabad metro rail – for a better livable city
 
Delhi metro
Delhi metroDelhi metro
Delhi metro
 
Stakeholder analysis of Delhi Metro
Stakeholder analysis of Delhi MetroStakeholder analysis of Delhi Metro
Stakeholder analysis of Delhi Metro
 
Delhi Metro Railway's Stakeholder Management
Delhi Metro Railway's Stakeholder Management Delhi Metro Railway's Stakeholder Management
Delhi Metro Railway's Stakeholder Management
 
Analysis of Impact of East West Metro Corridor on Land Use
Analysis of Impact of East West Metro Corridor on Land UseAnalysis of Impact of East West Metro Corridor on Land Use
Analysis of Impact of East West Metro Corridor on Land Use
 
Delhi Metro
Delhi MetroDelhi Metro
Delhi Metro
 
Ahmedabad Metro Project
Ahmedabad Metro ProjectAhmedabad Metro Project
Ahmedabad Metro Project
 
Best Practices in BRT Presentation
Best Practices in BRT PresentationBest Practices in BRT Presentation
Best Practices in BRT Presentation
 
INDUSTRIAL CORRIDOR - MAKE IN INDIA
INDUSTRIAL CORRIDOR - MAKE IN INDIAINDUSTRIAL CORRIDOR - MAKE IN INDIA
INDUSTRIAL CORRIDOR - MAKE IN INDIA
 
Chhatrapati Shivaji International Airport
Chhatrapati Shivaji International AirportChhatrapati Shivaji International Airport
Chhatrapati Shivaji International Airport
 
Sagarmala
SagarmalaSagarmala
Sagarmala
 
Narayana Hrudayalaya Heart Hospital - Cardiac Care For the Poor
Narayana Hrudayalaya Heart Hospital - Cardiac Care For the PoorNarayana Hrudayalaya Heart Hospital - Cardiac Care For the Poor
Narayana Hrudayalaya Heart Hospital - Cardiac Care For the Poor
 

Similaire à Delhi metro case study

36551105 delhi-metro-120908024323-phpapp01
36551105 delhi-metro-120908024323-phpapp0136551105 delhi-metro-120908024323-phpapp01
36551105 delhi-metro-120908024323-phpapp01Akshay Gaikwad
 
Introduction to metro system (1).pptx
Introduction to metro system (1).pptxIntroduction to metro system (1).pptx
Introduction to metro system (1).pptxBalpreetSingh47890
 
Metro Rail in India ppt
Metro Rail in India pptMetro Rail in India ppt
Metro Rail in India pptNikita James
 
a study of suspentable transportation system in ahmedabad & dehli
a study of suspentable transportation system in ahmedabad & dehlia study of suspentable transportation system in ahmedabad & dehli
a study of suspentable transportation system in ahmedabad & dehliRONAKMODI36
 
A study of sustainable transportation system in ahmedabad and delhi
A study of sustainable transportation system in ahmedabad and delhiA study of sustainable transportation system in ahmedabad and delhi
A study of sustainable transportation system in ahmedabad and delhiIJARIIT
 
Dhaka Metro Rail Project.pptx
Dhaka Metro Rail Project.pptxDhaka Metro Rail Project.pptx
Dhaka Metro Rail Project.pptxZunayet Shibly
 
Public-Private Partnership in Urban Transport
Public-Private Partnership in Urban TransportPublic-Private Partnership in Urban Transport
Public-Private Partnership in Urban TransportJaspal Singh
 
Transit Oriented Development - TOD - Human Settlement Planning - Architecture
Transit Oriented Development - TOD - Human Settlement Planning - Architecture Transit Oriented Development - TOD - Human Settlement Planning - Architecture
Transit Oriented Development - TOD - Human Settlement Planning - Architecture YuktaYogeesh1
 
Infrastructure Management - DMRC Study
Infrastructure Management - DMRC StudyInfrastructure Management - DMRC Study
Infrastructure Management - DMRC StudyMohit Gaur
 
Riding on Debt: Financial Assessment of Delhi Metro After Phase III
Riding on Debt: Financial Assessment of Delhi Metro After Phase IIIRiding on Debt: Financial Assessment of Delhi Metro After Phase III
Riding on Debt: Financial Assessment of Delhi Metro After Phase IIICentre for Financial Accountability
 
Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008
Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008
Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008Anil Kumar Gupta
 
Effective learning from delhi brts –a case study of pune brts
Effective learning from delhi brts –a case study of pune brtsEffective learning from delhi brts –a case study of pune brts
Effective learning from delhi brts –a case study of pune brtseSAT Journals
 
DMRC REPORT ON UNDERGROUND CONSTRUCTION
DMRC REPORT ON UNDERGROUND CONSTRUCTIONDMRC REPORT ON UNDERGROUND CONSTRUCTION
DMRC REPORT ON UNDERGROUND CONSTRUCTIONMd Shadab
 
Role of transport economist
Role of transport economistRole of transport economist
Role of transport economistMegha Kashyap
 
bajaj two wheeler manufacturing plan electrical
bajaj two wheeler manufacturing plan electricalbajaj two wheeler manufacturing plan electrical
bajaj two wheeler manufacturing plan electricalShiva Kumar HM
 
DMRC_COLLEGE_REPORT
DMRC_COLLEGE_REPORTDMRC_COLLEGE_REPORT
DMRC_COLLEGE_REPORTPOOJA SHARMA
 
× Le transport rapide personnalisé et systèmes de transport automatisés en Inde
×	Le transport rapide personnalisé et systèmes de transport automatisés en Inde×	Le transport rapide personnalisé et systèmes de transport automatisés en Inde
× Le transport rapide personnalisé et systèmes de transport automatisés en IndeVéronique SEEL (Michaut)
 

Similaire à Delhi metro case study (20)

36551105 delhi-metro-120908024323-phpapp01
36551105 delhi-metro-120908024323-phpapp0136551105 delhi-metro-120908024323-phpapp01
36551105 delhi-metro-120908024323-phpapp01
 
Introduction to metro system (1).pptx
Introduction to metro system (1).pptxIntroduction to metro system (1).pptx
Introduction to metro system (1).pptx
 
Metro Rail in India ppt
Metro Rail in India pptMetro Rail in India ppt
Metro Rail in India ppt
 
a study of suspentable transportation system in ahmedabad & dehli
a study of suspentable transportation system in ahmedabad & dehlia study of suspentable transportation system in ahmedabad & dehli
a study of suspentable transportation system in ahmedabad & dehli
 
A study of sustainable transportation system in ahmedabad and delhi
A study of sustainable transportation system in ahmedabad and delhiA study of sustainable transportation system in ahmedabad and delhi
A study of sustainable transportation system in ahmedabad and delhi
 
Dhaka Metro Rail Project.pptx
Dhaka Metro Rail Project.pptxDhaka Metro Rail Project.pptx
Dhaka Metro Rail Project.pptx
 
Public-Private Partnership in Urban Transport
Public-Private Partnership in Urban TransportPublic-Private Partnership in Urban Transport
Public-Private Partnership in Urban Transport
 
Transit Oriented Development - TOD - Human Settlement Planning - Architecture
Transit Oriented Development - TOD - Human Settlement Planning - Architecture Transit Oriented Development - TOD - Human Settlement Planning - Architecture
Transit Oriented Development - TOD - Human Settlement Planning - Architecture
 
12
1212
12
 
Role of Auto-Rickshaws and Taxis in Sustainable Transport - RK Singh
Role of Auto-Rickshaws and Taxis in Sustainable Transport - RK SinghRole of Auto-Rickshaws and Taxis in Sustainable Transport - RK Singh
Role of Auto-Rickshaws and Taxis in Sustainable Transport - RK Singh
 
Infrastructure Management - DMRC Study
Infrastructure Management - DMRC StudyInfrastructure Management - DMRC Study
Infrastructure Management - DMRC Study
 
Riding on Debt: Financial Assessment of Delhi Metro After Phase III
Riding on Debt: Financial Assessment of Delhi Metro After Phase IIIRiding on Debt: Financial Assessment of Delhi Metro After Phase III
Riding on Debt: Financial Assessment of Delhi Metro After Phase III
 
Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008
Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008
Management Control System in SPVs for Infratsructure Projects_A K Gupta_05082008
 
Effective learning from delhi brts –a case study of pune brts
Effective learning from delhi brts –a case study of pune brtsEffective learning from delhi brts –a case study of pune brts
Effective learning from delhi brts –a case study of pune brts
 
DMRC REPORT ON UNDERGROUND CONSTRUCTION
DMRC REPORT ON UNDERGROUND CONSTRUCTIONDMRC REPORT ON UNDERGROUND CONSTRUCTION
DMRC REPORT ON UNDERGROUND CONSTRUCTION
 
Role of transport economist
Role of transport economistRole of transport economist
Role of transport economist
 
Metro
MetroMetro
Metro
 
bajaj two wheeler manufacturing plan electrical
bajaj two wheeler manufacturing plan electricalbajaj two wheeler manufacturing plan electrical
bajaj two wheeler manufacturing plan electrical
 
DMRC_COLLEGE_REPORT
DMRC_COLLEGE_REPORTDMRC_COLLEGE_REPORT
DMRC_COLLEGE_REPORT
 
× Le transport rapide personnalisé et systèmes de transport automatisés en Inde
×	Le transport rapide personnalisé et systèmes de transport automatisés en Inde×	Le transport rapide personnalisé et systèmes de transport automatisés en Inde
× Le transport rapide personnalisé et systèmes de transport automatisés en Inde
 

Dernier

Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Disha Kariya
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxVishalSingh1417
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfAyushMahapatra5
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Shubhangi Sonawane
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.christianmathematics
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxAreebaZafar22
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docxPoojaSen20
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.pptRamjanShidvankar
 
Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.MateoGardella
 

Dernier (20)

Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.
 

Delhi metro case study

  • 2. Abstract: The city of Delhi, capital of India, has been facing problems such as traffic growth, congestion, pollution, increased accidents since last decade. To ameliorate both the quality and availability of mass transport system with an aim to address the aforementioned issues, a non-polluting rail-based mass transit system was sought to be an effective solution by Government of India (GoI) and Government of the National Capital Territory of Delhi (GNCTD). In order to achieve this challenging objective, a tremendous amount of efforts have been directed towards planning, design and implementation of this metro project. This study attempted to analyse and elucidate the overall Delhi metro rail project implementation through its inception till completion. It explains various infrastructure aspects such as economical, environmental, social that are being/were considered for this project. The Delhi metro project was divided into four phases for its implementation with a total length of the rail network to be approximately 404km. Presently, Phase I and II have been successfully implemented and are in operation. Phase III and IV are scheduled to be completed till 2016 and 2020 respectively. This project has set many records for its successful implementation such as early completion of phase I, achievement in terms of environment-friendly design and implementation and is being viewed as one of the inspirational model for metro projects planned to be undertaken all over the world. The initiatives for introducing the metro system in Delhi were taken in the early 1990s. In 1995, the Government of India (GoI) and the Government of the National C apital Territory of Delhi(GNCTD) formed the Delhi Metro Rail Corporation Ltd (DMRC) under the Companies Act to construct the Delhi Metro.
  • 3. Mission:  To cover the whole Delhi and adjoining areas with a metro network by the year 2021.  To serve the customers including ‘differently abled’ Commuters with passion.  To sustain the image of being number one in the transportation sector in India and to be among the top 3 Metro Rail systems in Asia with regards to: ● Safety ● reliability ●punctuality ● quality and●responsiveness to the customers  To make Delhi metro self-sustainable. Reason:  Population of over 1 million.  More registered vehicles than Mumbai, Kolkata & Chennai put together.  Automobiles contributing to more than 2/3rd of the total atmospheric pollution.  High rate of road accidents. Key Architects:  The Central Road Research Institute (CRRI),New Delhi  Metropolitan Transport Team (MTT) of the Indian Railways  Delhi Development Authority(DDA)  The Study Group of the Ministry of Railways  RITES (Rail India Technical & Economics Services)  Mr. E. Sreedharan ,Managing Director, DMRC
  • 4. •Key Objectives-  The main objective of the project is to improve Delhi’s urban environment by reducing traffic congestion and pollution. The Project is expected to help reduce traffic congestion, exhaust emissions, and other types of urban pollution caused by motor vehicles and to play a large role in improving Delhi’s transit system.  Outcomes-  Delhi Mass Rapid Transit System is essentially a “social sector” project, whose benefits will pervade over wide sections of the economy. I phase will generate the following benefits to the city.  21.82 lakhs commuter trips per day will be siphoned off the roads.  2600 less buses on the roads. Increasing in average speed of the buses from 10.5 km/h to 14km/h.  Metro will reduce journey time of 50 to 75 %  Saving of 2 million man-hours per day due to reduced journey time.  Saving in fuel cost worth Rs.5 billion per year.  Space saving-The metro can carry traffic as 9 lanes/33 lanes of motor cars(either ways)  Delhi will experience a net benefit of Rs.437.23 lacks per days. More comfortable & safe travel for the commuters.  Reduction in atmospheric pollution levels by 50%.
  • 6. 7 lessons from The Delhi Metro Project 1. An Experienced Leader 2. Lean Structure & Costs 3. Ownership From Every Staffer 4. Reverse Countdown Clocks 5. Project Management Tools 6. Transparency with Stakeholders 7. Constant Improvement Project Evaluation The successful completion of the project effectively silenced the critics who had been sceptical about the ability of an Indian public sector organization to complete any project, let alone one as complex and costly as the Delhi Metro, on time and within the budget.. RESULTS ANDANALYSIS The case of Delhi metro showed the critical dependence of adoption and implementation of more sustainable forms of urban transport on supportive national policies accompanied by financial incentives.DM achieved its milestone of success by making a feasible and most comfortable mode of public transport leading to a reduction in traffic congestion, reduction in noise and air pollution and ultimately enhanced the overall productivity of citizen of the city and businesses. The achievement of Delhi metro can be contributed to various key factors as follows:  Local buy-in: Delhi Metro demonstrated the importance of local ownership of the project. Autonomy achieved since the beginning of the project played a vital role in dealing with the political issues. This led to cost
  • 7. savings by better utilization of local resources, and improved responsiveness of the design and extraction of desired outcomes through construction. A firm belief by local implementation teams in the benefits of their schemes made public acceptance easy to gain.  Multi-tiered financing: By adopting alternative financing strategy thereby arranging funds through a variety of international, national, state and local stakeholders, DMRC could get to relative comparative advantages of different funding actors in order to satisfy their short term and long term financing needs.  Dedicated agency:  Delhi metro is largely benefited from clear governance arrangements. The creation of a special organization called DMRC for this project by Government of India and Government of the National Capital of Delhi minimized the need for coordination across multiple agencies thereby streamlining design and construction.  Incremental implementation: Due to the implementation of DM project in various phases, it offered advantages such as improved design, time savings, cost savings through feedback and modification as well as greater public acceptance and increased ridership.  Environmental concerns: By adopting various environmental effective strategies such as environmental management system, reduction in carbon dioxide emission by the adoption of regenerative braking systems in the DMRC trains, DMRC gained acclamation all over the world for this project.
  • 8. CONCLUSION The Delhi metro project is planned, implemented and operated by a special organization by the name ‘Delhi metro rail corporation (DMRC)’, established jointly by Government of India and Government of the National Capital of Delhi in 1995. The project was/is being planned and executed in four phases-Phase I, II, III, IV. The network is presently comprising of five colour-coded regular lines (Red, Blue, Green, Yellow, Violet), and a sixth line called Airport Express(Orange Line), with a total length of 208kilometres (129 mi), serving156 stations (with 6 more Airport Express stations) having a mix of underground, at-grade, and elevated stations. Phase I and II are operational now with the airport express line while Phase III is in implementation stage and phase IV is in planning stage. The total cost estimated for Phase I and II was 300 Billion ($6 Billion) and for Phase III isRs.352.42 Billion ($7.04 Billion).Phase III and IV are scheduled to be completed by 2016 and 2020 respectively. Considering the financial aspects, Japan Bank for international Cooperation is giving a loan to the project approximately to the extent of 60% of project cost. Gover nment of India, Ministry of UrbanDevelopment and the Government of the National Capital Territory of Delhi are each investing 15% of the project cost. The remaining is met through interest-free loans and property development. The O&M costs are essentially met by ticket sales. Due to the incorporation of environment-friendly techniques for implementation such as adoption of environmental management system, reduction in carbon dioxide emission by the adoption of regenerative braking systems in the DMRC trains, the project has been awarded certificates for these ‘green initiatives’. During the implementation of Phase III and IV and post its completion, more issues, development opportunities, aggravated positive and negative impacts will be evolved and will be interesting in the future to dig into the analysis of its overall planning, design, and implementation.