Residential DevelopmentProcess/ Pro forma
Table of Contents Introduction					5 The Lot and Block Survey System		7 - 14 Development of Regional Impact		15 - 27 Site Plan Preparation				28 - 39 Samples of Master Plan communities/	40 - 49  Individual Parcels Infrastructure Process				50 - 60
Table of Contents con’t Sample of Municipality Permit		61 - 63  Package Requirements Sample of Municipality Permit		64 - 66  Process and Schedule Phasing the Community			67 - 71 Conclusion						72
Getting Started ,[object Object]
If you think you are ready, be prepared for a long, tedious and sometimes arduous venture!
The initial start up process will take thousands of man hours for conceptual design and development, and can take any where, from 6 month's to 2 years in duration to complete the initial design and Municipality approval process for a Master Plan Project.,[object Object]
Land Use, Acquisition and Development Overview and Start of the  Development Process
 Lot and Block Survey System  The system begins with a large tract of land. This large tract is typically defined by one of the earlier survey systems such as metes and boundsor the Public Land Survey System. A subdivision survey is conducted to divide the original tract into smaller lots and a plat map is created. Usually this subdivision survey employs a metes and bounds system to delineate individual lots within the main tract. Each lot on the plat map is assigned an identifier, usually a number or letter. The plat map is then officially recorded with a government entity such as a city engineer or a recorder of deeds. This plan becomes the legal description of all the lots in the subdivision. A mere reference to the individual lot and the map's place of record is all that is required for a proper legal description.
		In real estate, a lot is a tract or parcel of land owned or meant to be owned by some owner(s). A lot is essentially considered a parcel of real property in some countries or immovable property (meaning practically the same thing) in other countries. Possible owner(s) of a lot can be one or more person(s) or another legal entity, such as a company/corporation, organization, government, or trust. A common form of ownership of a lot is called fee simple in some countries. Lots can come in various sizes and shapes. To be considered a single lot, the land described as the "lot" must be contiguous. Two separate parcels are considered two lots not one. Often a lot is sized for a single house or other building. Many lots are rectangular in shape, although other shapes are possible as long as the boundaries are well-defined.
		Methods of determining or documenting the boundaries of lots include metes and bounds, quadrant method, and use of a plat diagram. Use of the metes and bounds method may be compared to drawing a polygon. Metes are points which are like the vertices (corners) of a polygon. Bounds are line segments between two adjacent metes. Bounds are usually straight lines, but can be curved as long as they are clearly defined. The part of the boundary of the lot next to a street or road is the frontage. Developers try to provide at least one side of frontage for every lot, so owners can have transportation access to their lots. As the name implies, street frontage determines which side of the lot is the front, with the opposite side being the back.
		Local governments often pass zoning laws which control what buildings can be built on a lot and what they can be used for. For example, certain areas are zoned for residential buildings such as houses. Other areas can be commercially, agriculturally, or industrially zoned. Sometimes zoning laws establish other restrictions such as a minimum lot area and/or frontage length for building a house or other building, maximum building size, or minimum setbacks from a lot boundary for building a structure. This is in addition to building codes which must be met. Also minimum lot sizes and separations must be met when wells and septic systems are used. In urban areas, sewers and water lines often provide service to households. There may also be restrictions based on covenants established by private parties such as the developer. There may be easements for utilities to run water, sewage, electric power, or telephone lines through a lot.
		Something which is meant to improve the value or usefulness of a lot can be called an appurtenance to the lot. Structures such as buildings, driveways, sidewalks, patios or other pavement, wells, septic systems, signs, and similar improvements which are considered permanently attached to the land in the lot are considered as real property, usually part of the lot but often parts of a building, such as condominiums, are owned separately. Such structures owned by the lot owner(s), as well as easements which help the lot owners or users, can be considered appurtenances to the lot. A lot without such structures can be called a vacant lot, spare ground, an empty lot, or an unimproved or undeveloped lot.
		Many times, developers divide a large tract of land into lots to make a subdivision out of it. Certain areas of the land are dedicated (given to local government for permanent upkeep) as streets and sometimes alleys for transportation and access to lots. Areas between the streets are divided up into lots to be sold to future owners. The layout of the lots is mapped on a plat diagram, which is recorded with the government, typically the countyrecorder's office. The blocks between streets and the individual lots in each block are given an identifier, usually a number or letter.
		Land originally granted by the government was commonly done by documents called patents. Lots of land can be sold/ bought by the owners or conveyed in other ways. Such conveyances are made by documents called deeds which should be recorded by the government, typically the county recorder's office. Deeds specify the lot by including a description such as one determined by the "metes and bounds" or quadrant methods, or referring to a lot number and block number in a recorded plat diagram. Deeds often mention that appurtenances to the lot are included in order to convey any structures and other improvements also.
Sample of PLSS
Development of Regional Impact
DRI- "…..means any development which, because of its character, magnitude, or location, would have a substantial effect upon the health, safety, or welfare of citizens of more than one county."
DRI Purpose ,[object Object]
Provides Extra- Jurisdictional Approach
Allows for State and Regional Agency Expertise and Technical Assistance
Assesses and Mitigates Project Impacts to State and Regional Resources and Facilities,[object Object]
Retail Service Development
Hotel and Motel Development
Recreational Vehicle Development
Multi- Use Development
Airports
Attractions and Recreational Facilities
Hospitals
Industrial Facilities
Mining Operations
Office Development
Petroleum Storage Facilities
Port Facilities,[object Object]
Defines what Constitutes a "Significant Impact"
Establishes Uniform Standards for Mitigation of Regional Impacts
Listed Vegetation and Wildlife Species
Archaeological and Historical Resources
Public Facilities
Transportation
Air Quality
Adequate Housing
Weather Event Preparedness,[object Object]
Files and Completes' Application for Development Approval
Participates in the Review Process and Responds to Questions
Participates in the Public Hearing
May Appeal the Adopted Development Order
Implements the Development Order and Provides Mitigation
Submits Annual Reports ,[object Object]
Participates in the DRI Review Process
Conducts the Public Hearing
Adopts or Denies the Development Order
Includes Conditions (Mitigation) of Approval or Denial of the Development Order
Primary Enforcer of the Development Order,[object Object]
Lead Role for Coordinating the Review Process with local, regional, state and federal agencies (Pre- Application Conference, Sufficiency Review and Regional Assessment Report)
Recommends Conditions of Approval or Denial to Local Government,[object Object]
Adopt Rules
Agreement Authority
Determines when a Development Qualifies for DRI Review
Binding Letters of DRI Status or Vested Rights
Clearance Letters
Monitoring and Enforcement
Approves Preliminary Development Agreements
May Appeal the Adopted Development Order,[object Object]
Sample of a Proposed Airport DRI
Steps Necessary to Record a Subdivision Plat  ,[object Object]
Preliminary Subdivision Plan Approval
Final Engineering Approval
Final Plat Approval
Subdivision Review Fees      (All fees are to be paid at the time of plat recording)
Land Acquisition/ Entitlement  		Planned Urban Development, or PUD, is a zoning class that allows for residential and commercial buildings. The PUD classification allows builders to develop residential, retail, and professional buildings into one community, as well as recreation areas such as parks, so that residents can live, work, and play locally.  		A parcel of land is selected, land use is designated and requested by the potential buyer and approved by the governing municipality. Infrastructure Engineering, Surveying and Geotechnical firms are selected by the potential developer. Land use's typically are residential, mixed use, commercial,  as well as recreation areas such as parks.
Preparing a Site Plan What is a Site Plan?A Site Plan is a drawing depicting the site of a proposed or existing project. Some of the key elements of a Site Plan are property boundaries, land topography, vegetation, proposed and/or existing structures, easements, wells, and roadways.  Why is a Site Plan Needed?A site plan is required for most appointments, permit applications, pre-application meetings, and submittals.  It provides a visual image of your proposal and is used to assist in determining if your project conforms to land use policies and regulations. 	A Site Plan submitted as part of a permit application needs to show all of the following items. 
Sample of Site Plan Submittal Requirements  Submittal Requirements ,[object Object]
Storm water Calculations (2 copies)

Contenu connexe

Tendances

Tendances (20)

Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
Valuation - professional prractice and valuation
Valuation - professional prractice and valuationValuation - professional prractice and valuation
Valuation - professional prractice and valuation
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
 
Valuation
ValuationValuation
Valuation
 
Construction Project Management.
Construction Project Management.Construction Project Management.
Construction Project Management.
 
Building approval.ppt
Building approval.pptBuilding approval.ppt
Building approval.ppt
 
Boq sample
Boq sampleBoq sample
Boq sample
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
 
Master Plan
Master PlanMaster Plan
Master Plan
 
Labour Laws and Financial Aspects of Construction Project _ Unit 3 _ Construc...
Labour Laws and Financial Aspects of Construction Project _ Unit 3 _ Construc...Labour Laws and Financial Aspects of Construction Project _ Unit 3 _ Construc...
Labour Laws and Financial Aspects of Construction Project _ Unit 3 _ Construc...
 
Nepal National Building Code: Need, Formulation and Implementation Strategy
Nepal National Building Code: Need, Formulation and Implementation StrategyNepal National Building Code: Need, Formulation and Implementation Strategy
Nepal National Building Code: Need, Formulation and Implementation Strategy
 
Valuation part of Building
Valuation part of Building Valuation part of Building
Valuation part of Building
 
RERA and its impact
RERA and its impactRERA and its impact
RERA and its impact
 
Development Plan
Development PlanDevelopment Plan
Development Plan
 
Master plan (Town Planning)
Master plan (Town Planning)Master plan (Town Planning)
Master plan (Town Planning)
 
Land Development Process - Orange County, Florida
Land Development Process - Orange County, FloridaLand Development Process - Orange County, Florida
Land Development Process - Orange County, Florida
 
Tenders, their types and process
Tenders, their types and processTenders, their types and process
Tenders, their types and process
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Process
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Urban Planning Site Analysis and Selection
Urban Planning Site Analysis and SelectionUrban Planning Site Analysis and Selection
Urban Planning Site Analysis and Selection
 

En vedette

Subdivision, partition and amalgamation
Subdivision, partition and amalgamationSubdivision, partition and amalgamation
Subdivision, partition and amalgamation
FAROUQ
 

En vedette (8)

Business plan for Housing development
Business plan for Housing developmentBusiness plan for Housing development
Business plan for Housing development
 
Real Estate Development Modeling Basics
Real Estate Development Modeling BasicsReal Estate Development Modeling Basics
Real Estate Development Modeling Basics
 
Chp 15. amalgamation
Chp 15. amalgamationChp 15. amalgamation
Chp 15. amalgamation
 
Premium for land alienation
Premium for land alienationPremium for land alienation
Premium for land alienation
 
Amalgamation ppt
Amalgamation pptAmalgamation ppt
Amalgamation ppt
 
Making Housing Affordable
Making Housing AffordableMaking Housing Affordable
Making Housing Affordable
 
Subdivision, partition and amalgamation
Subdivision, partition and amalgamationSubdivision, partition and amalgamation
Subdivision, partition and amalgamation
 
Real Estate Development Case Presentation
Real Estate Development Case PresentationReal Estate Development Case Presentation
Real Estate Development Case Presentation
 

Similaire à Residential Land Development Process

Fundamental Skills for Real Estate Development Professionals II – Project Ent...
Fundamental Skills for Real Estate Development Professionals II – Project Ent...Fundamental Skills for Real Estate Development Professionals II – Project Ent...
Fundamental Skills for Real Estate Development Professionals II – Project Ent...
Virtual ULI
 
Lisa stormcon presentation number one ieca
Lisa stormcon presentation number one iecaLisa stormcon presentation number one ieca
Lisa stormcon presentation number one ieca
Lisa Nisenson
 
General Plan, Zoning And Entitlements
General Plan, Zoning And EntitlementsGeneral Plan, Zoning And Entitlements
General Plan, Zoning And Entitlements
APMeyerhoff
 
Zoning and subdivision of land
Zoning and subdivision of landZoning and subdivision of land
Zoning and subdivision of land
ctlachu
 
Mapd conservation development presentation 6 7-12
Mapd conservation development presentation 6 7-12Mapd conservation development presentation 6 7-12
Mapd conservation development presentation 6 7-12
Christopher Hayes
 
Form-Based Design Ord.
Form-Based Design Ord.Form-Based Design Ord.
Form-Based Design Ord.
Laura Oxley
 

Similaire à Residential Land Development Process (20)

Residentiallanddevelopmentprocess 101020023443-phpapp01
Residentiallanddevelopmentprocess 101020023443-phpapp01Residentiallanddevelopmentprocess 101020023443-phpapp01
Residentiallanddevelopmentprocess 101020023443-phpapp01
 
Zoning
ZoningZoning
Zoning
 
Fundamental Skills for Real Estate Development Professionals II – Project Ent...
Fundamental Skills for Real Estate Development Professionals II – Project Ent...Fundamental Skills for Real Estate Development Professionals II – Project Ent...
Fundamental Skills for Real Estate Development Professionals II – Project Ent...
 
Planning 101
Planning 101Planning 101
Planning 101
 
Implementation Planning
Implementation PlanningImplementation Planning
Implementation Planning
 
Comp Plan Update 2015
Comp Plan Update 2015Comp Plan Update 2015
Comp Plan Update 2015
 
Fundamental Skills for Real Estate Development Professionals II Con't Project
Fundamental Skills for Real Estate Development Professionals II Con't ProjectFundamental Skills for Real Estate Development Professionals II Con't Project
Fundamental Skills for Real Estate Development Professionals II Con't Project
 
Fundamental Skills for Real Estate Development Professionals II. Con't Projec...
Fundamental Skills for Real Estate Development Professionals II. Con't Projec...Fundamental Skills for Real Estate Development Professionals II. Con't Projec...
Fundamental Skills for Real Estate Development Professionals II. Con't Projec...
 
Lisa stormcon presentation number one ieca
Lisa stormcon presentation number one iecaLisa stormcon presentation number one ieca
Lisa stormcon presentation number one ieca
 
A guide to planning and logistics - Babergh
A guide to planning and logistics - Babergh A guide to planning and logistics - Babergh
A guide to planning and logistics - Babergh
 
General Plan, Zoning And Entitlements
General Plan, Zoning And EntitlementsGeneral Plan, Zoning And Entitlements
General Plan, Zoning And Entitlements
 
Zoning and subdivision of land
Zoning and subdivision of landZoning and subdivision of land
Zoning and subdivision of land
 
Planning - Knowledge is Power
Planning -  Knowledge is PowerPlanning -  Knowledge is Power
Planning - Knowledge is Power
 
Streamlining Approval Procedure for Real Estate Projects (SAPREP) - 19 sept '14
Streamlining Approval Procedure for Real Estate Projects (SAPREP) -  19 sept '14Streamlining Approval Procedure for Real Estate Projects (SAPREP) -  19 sept '14
Streamlining Approval Procedure for Real Estate Projects (SAPREP) - 19 sept '14
 
Transferable Development Rights
Transferable Development RightsTransferable Development Rights
Transferable Development Rights
 
Conservation Restrictions in Conservation Subdivisions
Conservation Restrictions in Conservation SubdivisionsConservation Restrictions in Conservation Subdivisions
Conservation Restrictions in Conservation Subdivisions
 
Mapd conservation development presentation 6 7-12
Mapd conservation development presentation 6 7-12Mapd conservation development presentation 6 7-12
Mapd conservation development presentation 6 7-12
 
Form-Based Design Ord.
Form-Based Design Ord.Form-Based Design Ord.
Form-Based Design Ord.
 
Marine park design
Marine park designMarine park design
Marine park design
 
West Loop Design Guidelines Draft
West Loop Design Guidelines DraftWest Loop Design Guidelines Draft
West Loop Design Guidelines Draft
 

Dernier

Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 

Dernier (20)

HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the Classroom
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptx
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
 

Residential Land Development Process

  • 2. Table of Contents Introduction 5 The Lot and Block Survey System 7 - 14 Development of Regional Impact 15 - 27 Site Plan Preparation 28 - 39 Samples of Master Plan communities/ 40 - 49 Individual Parcels Infrastructure Process 50 - 60
  • 3. Table of Contents con’t Sample of Municipality Permit 61 - 63 Package Requirements Sample of Municipality Permit 64 - 66 Process and Schedule Phasing the Community 67 - 71 Conclusion 72
  • 4.
  • 5. If you think you are ready, be prepared for a long, tedious and sometimes arduous venture!
  • 6.
  • 7. Land Use, Acquisition and Development Overview and Start of the Development Process
  • 8. Lot and Block Survey System The system begins with a large tract of land. This large tract is typically defined by one of the earlier survey systems such as metes and boundsor the Public Land Survey System. A subdivision survey is conducted to divide the original tract into smaller lots and a plat map is created. Usually this subdivision survey employs a metes and bounds system to delineate individual lots within the main tract. Each lot on the plat map is assigned an identifier, usually a number or letter. The plat map is then officially recorded with a government entity such as a city engineer or a recorder of deeds. This plan becomes the legal description of all the lots in the subdivision. A mere reference to the individual lot and the map's place of record is all that is required for a proper legal description.
  • 9. In real estate, a lot is a tract or parcel of land owned or meant to be owned by some owner(s). A lot is essentially considered a parcel of real property in some countries or immovable property (meaning practically the same thing) in other countries. Possible owner(s) of a lot can be one or more person(s) or another legal entity, such as a company/corporation, organization, government, or trust. A common form of ownership of a lot is called fee simple in some countries. Lots can come in various sizes and shapes. To be considered a single lot, the land described as the "lot" must be contiguous. Two separate parcels are considered two lots not one. Often a lot is sized for a single house or other building. Many lots are rectangular in shape, although other shapes are possible as long as the boundaries are well-defined.
  • 10. Methods of determining or documenting the boundaries of lots include metes and bounds, quadrant method, and use of a plat diagram. Use of the metes and bounds method may be compared to drawing a polygon. Metes are points which are like the vertices (corners) of a polygon. Bounds are line segments between two adjacent metes. Bounds are usually straight lines, but can be curved as long as they are clearly defined. The part of the boundary of the lot next to a street or road is the frontage. Developers try to provide at least one side of frontage for every lot, so owners can have transportation access to their lots. As the name implies, street frontage determines which side of the lot is the front, with the opposite side being the back.
  • 11. Local governments often pass zoning laws which control what buildings can be built on a lot and what they can be used for. For example, certain areas are zoned for residential buildings such as houses. Other areas can be commercially, agriculturally, or industrially zoned. Sometimes zoning laws establish other restrictions such as a minimum lot area and/or frontage length for building a house or other building, maximum building size, or minimum setbacks from a lot boundary for building a structure. This is in addition to building codes which must be met. Also minimum lot sizes and separations must be met when wells and septic systems are used. In urban areas, sewers and water lines often provide service to households. There may also be restrictions based on covenants established by private parties such as the developer. There may be easements for utilities to run water, sewage, electric power, or telephone lines through a lot.
  • 12. Something which is meant to improve the value or usefulness of a lot can be called an appurtenance to the lot. Structures such as buildings, driveways, sidewalks, patios or other pavement, wells, septic systems, signs, and similar improvements which are considered permanently attached to the land in the lot are considered as real property, usually part of the lot but often parts of a building, such as condominiums, are owned separately. Such structures owned by the lot owner(s), as well as easements which help the lot owners or users, can be considered appurtenances to the lot. A lot without such structures can be called a vacant lot, spare ground, an empty lot, or an unimproved or undeveloped lot.
  • 13. Many times, developers divide a large tract of land into lots to make a subdivision out of it. Certain areas of the land are dedicated (given to local government for permanent upkeep) as streets and sometimes alleys for transportation and access to lots. Areas between the streets are divided up into lots to be sold to future owners. The layout of the lots is mapped on a plat diagram, which is recorded with the government, typically the countyrecorder's office. The blocks between streets and the individual lots in each block are given an identifier, usually a number or letter.
  • 14. Land originally granted by the government was commonly done by documents called patents. Lots of land can be sold/ bought by the owners or conveyed in other ways. Such conveyances are made by documents called deeds which should be recorded by the government, typically the county recorder's office. Deeds specify the lot by including a description such as one determined by the "metes and bounds" or quadrant methods, or referring to a lot number and block number in a recorded plat diagram. Deeds often mention that appurtenances to the lot are included in order to convey any structures and other improvements also.
  • 17. DRI- "…..means any development which, because of its character, magnitude, or location, would have a substantial effect upon the health, safety, or welfare of citizens of more than one county."
  • 18.
  • 20. Allows for State and Regional Agency Expertise and Technical Assistance
  • 21.
  • 23. Hotel and Motel Development
  • 33.
  • 34. Defines what Constitutes a "Significant Impact"
  • 35. Establishes Uniform Standards for Mitigation of Regional Impacts
  • 36. Listed Vegetation and Wildlife Species
  • 42.
  • 43. Files and Completes' Application for Development Approval
  • 44. Participates in the Review Process and Responds to Questions
  • 45. Participates in the Public Hearing
  • 46. May Appeal the Adopted Development Order
  • 47. Implements the Development Order and Provides Mitigation
  • 48.
  • 49. Participates in the DRI Review Process
  • 51. Adopts or Denies the Development Order
  • 52. Includes Conditions (Mitigation) of Approval or Denial of the Development Order
  • 53.
  • 54. Lead Role for Coordinating the Review Process with local, regional, state and federal agencies (Pre- Application Conference, Sufficiency Review and Regional Assessment Report)
  • 55.
  • 58. Determines when a Development Qualifies for DRI Review
  • 59. Binding Letters of DRI Status or Vested Rights
  • 63.
  • 64. Sample of a Proposed Airport DRI
  • 65.
  • 69. Subdivision Review Fees (All fees are to be paid at the time of plat recording)
  • 70. Land Acquisition/ Entitlement Planned Urban Development, or PUD, is a zoning class that allows for residential and commercial buildings. The PUD classification allows builders to develop residential, retail, and professional buildings into one community, as well as recreation areas such as parks, so that residents can live, work, and play locally. A parcel of land is selected, land use is designated and requested by the potential buyer and approved by the governing municipality. Infrastructure Engineering, Surveying and Geotechnical firms are selected by the potential developer. Land use's typically are residential, mixed use, commercial, as well as recreation areas such as parks.
  • 71. Preparing a Site Plan What is a Site Plan?A Site Plan is a drawing depicting the site of a proposed or existing project. Some of the key elements of a Site Plan are property boundaries, land topography, vegetation, proposed and/or existing structures, easements, wells, and roadways.  Why is a Site Plan Needed?A site plan is required for most appointments, permit applications, pre-application meetings, and submittals.  It provides a visual image of your proposal and is used to assist in determining if your project conforms to land use policies and regulations. A Site Plan submitted as part of a permit application needs to show all of the following items. 
  • 72.
  • 75. Lift Station Calculations(if applicable, 2 copies)
  • 76. Site Plan Application & Application Fee
  • 77. Concurrency Application (whichever is applicable) & Review Fee
  • 78. Application for Arbor(for tree removal)& Arbor Permit Fee
  • 79.
  • 80. Statement of intended use of site
  • 81. Legal Description of the property and size of parcel in acres or square feet
  • 82. Name, Address, Telephone Number and Fax Number of:
  • 83. Owner or Owners of record
  • 84. Engineer (plans must be sealed by a Registered Engineer)
  • 86. Vicinity Map, showing relationship of proposed development to the surrounding streets and thoroughfares.
  • 87.
  • 88.
  • 90. Height and dimensions of Building
  • 91. Number of Dwelling Units and Density for Multi-Family Site Plans
  • 92. Projected Number of Employees
  • 93. If Restaurant, show Number of Seats & Occupancy Load
  • 94. Square footage for Proposed Development – gross square footage, non-storage area, square footage of each story, gross square footage of sales area, etc.
  • 95.
  • 96. All Parking Spaces Designated
  • 98. Number and Location of Handicapped Spaces
  • 99. Number and Designation of Loading Spaces
  • 100. Number of square feet of Paved Parking and Driveway Area
  • 101. Surface Materials of Driveways
  • 102. Cross-sections at fifty (50) foot intervals or greater for off-site improvements as recommended by the Development Review Manager
  • 103.
  • 104. Internal Traffic Circulation Plan, including directional arrows, and signs to direct traffic flow
  • 105. Location of Traffic Control Signs and Signal Devices
  • 106. Designate Location of Sidewalks
  • 107. Coordinate Walkways, Driveways, etc., with facilities in adjacent developments
  • 108. All Proposed Streets and Alleys
  • 109.
  • 110. Water: Size, material, and location of water mains, plus valves and fire hydrants, plus engineering plans and specifications.
  • 111.
  • 112. Application for Arbor Permit and tree survey.
  • 113.
  • 114. Sidewalks, streets, alleys, and easements (note widths and type)
  • 115. Drainage systems to include natural and structural (size and materials, invert elevation)
  • 116. Size and location nearest water mains, valves, and fire hydrants
  • 117. Sanitary sewer systems (size, invert elevations, etc., to be included)
  • 118.
  • 121. Sample 2: Master Planned Development
  • 125. Sample of Individual Parcel/ Plat
  • 126. Parcel Located in Plat Map
  • 131. Infrastructure Process Infrastructure is the basic physical and organizational structures needed for the operation of a society or enterprise, or the services and facilities necessary for an economy to function. The term typically refers to the technical structures that support a society, such as roads, water supply, sewers, power grids, telecommunications, and so forth. In some contexts, the term may also include basic social services such as schools, hospitals, Transportation , Energy , Water management, Communications , Waste management and Geophysical.
  • 132. Most infrastructure is designed by civil engineers, except for telecommunications, electricity and monitoring networks, that are designed mainly by electrical engineers. In the case of urban infrastructure, the general layout of roads, sidewalks and public places may sometimes be designed by urbanists or architects, although the detailed design will still be performed by civil engineers. In terms of engineering tasks, the design and construction management process usually follows these steps:
  • 133.
  • 134. Conduct a preliminary survey and obtain information from existing air photos, maps, plans, etc.
  • 135. Identify possible conflicts with other assets or topographical features;
  • 136. Perform environmental impact studies: Evaluate the impact on the human environment (Noise pollution, odors, electromagnetic interference, etc..); Evaluate the impact on the natural environment (disturbance of natural ecosystems); Evaluate possible presence of contaminated soils;
  • 137.
  • 138.
  • 139. Obtain As Built drawings of existing infrastructure;
  • 140. Dig exploratory pits where required to survey underground infrastructure;
  • 141. Perform a geotechnical survey to determine the bearing capacity of soils and rock;
  • 142.
  • 143. Prepare a detailed bill of materials;
  • 144. Prepare a detailed cost estimate;
  • 145.
  • 146. Obtain authorization from any owners or operators of assets affected by the work;
  • 147.
  • 148. Organize and announce a Call for Tenders;
  • 149. Answer contractor questions and issue addenda during the tendering process;
  • 150.
  • 151. Obtain a detailed work schedule and list of subcontractors from the GC.
  • 152. Obtain detailed traffic diversion and emergency plans from the GC;
  • 153. Obtain proof of certification, insurance and bonds;
  • 154. Examine shop drawings submitted by the GC;
  • 155. Receive reports from the materials quality control lab;
  • 156. When required, review Change request s from the GC, and issue Construction Directives and Change Orders;
  • 157. Follow work progress and authorize partial payments;
  • 158. When substantially completed, inspect the work and prepare a list of deficiencies;
  • 159.
  • 160. Prepare "As Built" drawings;
  • 161.
  • 162. TO SUBMIT FOR A RESIDENTIAL PERMIT YOU MUST HAVE: PARCEL ID NUMBER / ADDRESS / OR LEGAL PRINTOUT (PROPERTY APPRAISAL SITE) & UNIT OR SUITE NUMBER IF APPLICABLE (IF APARTMENT/CONDO NUMBER OF DWELLING UNITS PER BUILDING) 2 SETS OF SITE PLANS 2 SETS OF ARCHITECT OR ENGINEER SEALED PLANS 2 SETS OF ENERGY CALCULATIONS (3RD COPY OF THE TOP 2 PAGES) 2 SETS OF RAISED SEALED TRUSS PROFILES PRODUCT APPROVAL FORM (2 COPIES) GAS SPREAD SHEET FORM (IF APPLICABLE ) 1 APPLICATION FILLED OUT COMPLETELY
  • 163.
  • 164. 1 NOTICE OF COMMENCEMENT (IF WORK OVER $2500 - NOT REQUIRED FOR TENTS)
  • 165. 1 POWER OF ATTORNEY (IF CONTRACTOR HAS NOT SIGNED ALL REQUIRED PAPERWORK OR IS NOT APPEARING IN PERSON)
  • 166. 1 OWNER BUILDER FORM (IF NO CONTRACTOR)
  • 167. 1 ESTOPPEL LETTER (IF REQUIRED)
  • 168. 1 ARBOR PERMIT (IF REQUIRED)
  • 169. IF NOT COUNTY WATER & SEWER, NEED UTILITY LETTER FROM PROVIDER OR WELL / SEPTIC PERMIT/LETTER (OR LIFT STATION)
  • 170.
  • 171. Application Submittal(1 day)The application and other required documentation is submitted to the Building Department Addressing (1-2 days - if not in a platted sub)The application is passed to addressing which will assign or verify an address for the 911 system. Zoning Division (1-2 days)Zoning will review and verify the site and building plans for setback and any other land development requirements. Impact fees will also be set
  • 172. Flood Prone Areas(1-2 days - if required)Flood Prone will review the application and inform or notify the applicant of any necessary requirements Wetlands Areas(2-3 days - if required)Wetlands will review the application and inform or notify the applicant of any necessary requirements Plan Review (3-5 working days)The plans will be reviewed. A list of inspections that will be required is relayed to the customer Update and IssueA permit tech will contact the customer with what fees they will need to pay and any items required prior to the permit being issued. The customer will come to the County Services Building to pay and will receive the permit.
  • 173. Phasing of the Project
  • 174. As you can see, there is a lot of coordination and cooperation required between the Developer and the Governing Municipality, the relationship established in the beginning of the process will become essential if a project is going to be successful, cost effective and a harmonious place for future occupants. At this stage of the process, the Master Plan Community has been approved and Land development permits have been issued by the governing municipality. The land development and infrastructure process will be segmented or phased to mirror the vertical construction process. As mentioned at the beginning of the presentation, the subdivision will have a total number of 400 units. The project will be phased into four groups of 100 units each, if the phasing is coordinated correctly with the infrastructure process, each phase can act as a independent project within the overall community.
  • 175. To illustrate the process, the land development and infrastructure process will start in Phase 1 and continue to Phase 2, once Phase 1 has passed all governing authority's applicable inspections (roads, storm water system, sewer system, compliant water testing of the water supply system and all required hardscapes are completed), then vertical construction of Phase 1 can begin. Each building lot must have the following: (water supply stub out, sewer stub out, electrical service provisions and communications), this is to prevent any major delays in completion of the project by missed critical components of the infrastructure process. As Phase 2 is completed, Phase 3 can begin the land development and infrastructure process, Phase 2 is now ready for vertical construction, and once Phase 3 is completed, Phase 4 can begin the land development and infrastructure process, and again Phase 3 is ready for vertical construction and finally Phase 4 is completed and is for vertical construction.
  • 177. Phase 1Phase 3 Phase 4 Phase 2
  • 178. Conclusion The overall process started with a large proposed subdivision and finished with the sample of permit requirements, and the permit process schedule for an individual lot. The next presentation will be Part 3, and will focus on the vertical construction process of a single unit within the subdivision. Some of the topics covered in the vertical construction process will be: Types and methods of single family detached housing construction, Cost Calculations, Site office setup, Model Selection and Trap System, Marketing/ Branding Product and Grand opening of the Community, Sales Contract Procedure, Options Selection Center, Purchasing and Estimating Function, QA/ QC inline inspection program, OSHA/ MSDS/ SWPPP Procedure's, Customer Care/ Warranty Standards, Start Rates (Even Flow Construction Process) and Obtaining The Certificate of Occupancy.