Booking Sheets Rise & Fall Method
Recording your levels – Rise & Fall Method – copy readings on a piece of paper BM –1st  reading taken was 2.250 (this is a back sight) (D) Last reading taken was .486(which is a foresight) (C) 5th  reading taken was 2.400( a foresight) 2nd  reading taken of  2.825 (this is a intermediate site) BM C D A (B) 3rd  reading taken was 1.976(which is a foresight) (C) 6th reading taken new instrument position was 1.880 (which is a back sight) B (B) 4th  reading taken new position of instrument was 2.120 (which is a back sight) Now we’ll have a look at how they go onto a booking sheet Triangles indicate instrument positions Letters indicate staff positions
Completed booking sheet example
First Remember the rules for completing the booking sheet The first reading you take is always a Backsight (BS) The last reading you take is always a Foresight (FS) The readings you take in between are Intermediate sights (IS)
Completing the sheet – step 1 ,[object Object]
 back sight at BM first
 Then intermediate site, one line down
 Then foresight one line down again
Then our instrument is moved (c.p. change point), our first reading from here is a backsight, but still goes on the line for staff reading B – etc. complete the rest
 In the remarks column you can also note the staff reading points, A,B,C, etc.,[object Object]

Contenu connexe

Tendances

Site surveying report1
Site surveying report1Site surveying report1
Site surveying report1Est
 
Unit No 2 Theodolite Surveying and Traversing.pptx
Unit No 2  Theodolite Surveying and Traversing.pptxUnit No 2  Theodolite Surveying and Traversing.pptx
Unit No 2 Theodolite Surveying and Traversing.pptxADCET, Ashta
 
Site surveying-Leveling
Site surveying-LevelingSite surveying-Leveling
Site surveying-LevelingShane Ah
 
Leveling, Instruments of Leveling, Bearings (Surveying, ECE)
Leveling, Instruments of Leveling, Bearings (Surveying, ECE) Leveling, Instruments of Leveling, Bearings (Surveying, ECE)
Leveling, Instruments of Leveling, Bearings (Surveying, ECE) Kaushal Mehta
 
Aerial photogrammetry vs. terrestrial photogrammetry
Aerial photogrammetry vs. terrestrial photogrammetryAerial photogrammetry vs. terrestrial photogrammetry
Aerial photogrammetry vs. terrestrial photogrammetryNI BT
 
Project 1- Levelling
Project 1- Levelling Project 1- Levelling
Project 1- Levelling seenyee
 
Surveying Levelling & Contouring Unit 2 Notes updating.pptx (1).pdf
Surveying Levelling & Contouring Unit 2 Notes updating.pptx (1).pdfSurveying Levelling & Contouring Unit 2 Notes updating.pptx (1).pdf
Surveying Levelling & Contouring Unit 2 Notes updating.pptx (1).pdfDenish Jangid
 
Traverse Survey Part 1/2
Traverse Survey Part 1/2Traverse Survey Part 1/2
Traverse Survey Part 1/2Muhammad Zubair
 
tacheometric surveying
tacheometric surveyingtacheometric surveying
tacheometric surveyingMujeeb Muji
 
2.horizontal curves
2.horizontal curves2.horizontal curves
2.horizontal curvesfenta dejene
 
Ch2 occurrence-of-groundwater-1
Ch2 occurrence-of-groundwater-1Ch2 occurrence-of-groundwater-1
Ch2 occurrence-of-groundwater-1Usama Waly
 
LEVELING AND CONTOURING
LEVELING AND CONTOURINGLEVELING AND CONTOURING
LEVELING AND CONTOURINGANAND JIBHKATE
 
Site surveying-report-leveling
Site surveying-report-levelingSite surveying-report-leveling
Site surveying-report-levelingXinYee Khoo
 
Meandering Rivers
Meandering RiversMeandering Rivers
Meandering RiversUmer Khayam
 
Compass surveying_Surveying, Civil Engineering
Compass surveying_Surveying, Civil EngineeringCompass surveying_Surveying, Civil Engineering
Compass surveying_Surveying, Civil EngineeringA Makwana
 
SURVEYING-LEVELING-MODERN SURVEYING INSTRUMENTS
SURVEYING-LEVELING-MODERN SURVEYING INSTRUMENTSSURVEYING-LEVELING-MODERN SURVEYING INSTRUMENTS
SURVEYING-LEVELING-MODERN SURVEYING INSTRUMENTSVISHNU VIJAYAN
 
Topic 2 area & volume
Topic 2   area & volumeTopic 2   area & volume
Topic 2 area & volumekmasz kamal
 
Photogyammetry-Notes2.pdf
Photogyammetry-Notes2.pdfPhotogyammetry-Notes2.pdf
Photogyammetry-Notes2.pdfpoola2015
 

Tendances (20)

Site surveying report1
Site surveying report1Site surveying report1
Site surveying report1
 
Unit No 2 Theodolite Surveying and Traversing.pptx
Unit No 2  Theodolite Surveying and Traversing.pptxUnit No 2  Theodolite Surveying and Traversing.pptx
Unit No 2 Theodolite Surveying and Traversing.pptx
 
Site surveying-Leveling
Site surveying-LevelingSite surveying-Leveling
Site surveying-Leveling
 
Leveling, Instruments of Leveling, Bearings (Surveying, ECE)
Leveling, Instruments of Leveling, Bearings (Surveying, ECE) Leveling, Instruments of Leveling, Bearings (Surveying, ECE)
Leveling, Instruments of Leveling, Bearings (Surveying, ECE)
 
Aerial photogrammetry vs. terrestrial photogrammetry
Aerial photogrammetry vs. terrestrial photogrammetryAerial photogrammetry vs. terrestrial photogrammetry
Aerial photogrammetry vs. terrestrial photogrammetry
 
Project 1- Levelling
Project 1- Levelling Project 1- Levelling
Project 1- Levelling
 
Levelling
LevellingLevelling
Levelling
 
Surveying Levelling & Contouring Unit 2 Notes updating.pptx (1).pdf
Surveying Levelling & Contouring Unit 2 Notes updating.pptx (1).pdfSurveying Levelling & Contouring Unit 2 Notes updating.pptx (1).pdf
Surveying Levelling & Contouring Unit 2 Notes updating.pptx (1).pdf
 
Traverse Survey Part 1/2
Traverse Survey Part 1/2Traverse Survey Part 1/2
Traverse Survey Part 1/2
 
tacheometric surveying
tacheometric surveyingtacheometric surveying
tacheometric surveying
 
Introduction to surveying
Introduction to surveyingIntroduction to surveying
Introduction to surveying
 
2.horizontal curves
2.horizontal curves2.horizontal curves
2.horizontal curves
 
Ch2 occurrence-of-groundwater-1
Ch2 occurrence-of-groundwater-1Ch2 occurrence-of-groundwater-1
Ch2 occurrence-of-groundwater-1
 
LEVELING AND CONTOURING
LEVELING AND CONTOURINGLEVELING AND CONTOURING
LEVELING AND CONTOURING
 
Site surveying-report-leveling
Site surveying-report-levelingSite surveying-report-leveling
Site surveying-report-leveling
 
Meandering Rivers
Meandering RiversMeandering Rivers
Meandering Rivers
 
Compass surveying_Surveying, Civil Engineering
Compass surveying_Surveying, Civil EngineeringCompass surveying_Surveying, Civil Engineering
Compass surveying_Surveying, Civil Engineering
 
SURVEYING-LEVELING-MODERN SURVEYING INSTRUMENTS
SURVEYING-LEVELING-MODERN SURVEYING INSTRUMENTSSURVEYING-LEVELING-MODERN SURVEYING INSTRUMENTS
SURVEYING-LEVELING-MODERN SURVEYING INSTRUMENTS
 
Topic 2 area & volume
Topic 2   area & volumeTopic 2   area & volume
Topic 2 area & volume
 
Photogyammetry-Notes2.pdf
Photogyammetry-Notes2.pdfPhotogyammetry-Notes2.pdf
Photogyammetry-Notes2.pdf
 

Plus de jbusse

CPCCCA3009A Construct Advanced Roofs Octagonal end roof
CPCCCA3009A Construct Advanced Roofs Octagonal end roofCPCCCA3009A Construct Advanced Roofs Octagonal end roof
CPCCCA3009A Construct Advanced Roofs Octagonal end roofjbusse
 
CPCCCA3009A Construct Advanced Roofs Oblique roof
CPCCCA3009A Construct Advanced Roofs Oblique roofCPCCCA3009A Construct Advanced Roofs Oblique roof
CPCCCA3009A Construct Advanced Roofs Oblique roofjbusse
 
Lecture2
Lecture2Lecture2
Lecture2jbusse
 
Installation JB2011
Installation JB2011Installation JB2011
Installation JB2011jbusse
 
4 internal lining
4 internal lining4 internal lining
4 internal liningjbusse
 
4. associated issues
4. associated issues4. associated issues
4. associated issuesjbusse
 
3. application of timber in environmental building
3. application of timber in environmental building3. application of timber in environmental building
3. application of timber in environmental buildingjbusse
 
2. timber as a sustainable building material
2. timber as a sustainable building material2. timber as a sustainable building material
2. timber as a sustainable building materialjbusse
 
1. ecologically sustainable development
1. ecologically sustainable development1. ecologically sustainable development
1. ecologically sustainable developmentjbusse
 
Using span tables as1684 2
Using span tables   as1684 2Using span tables   as1684 2
Using span tables as1684 2jbusse
 
Genral code sub floor
Genral code sub floorGenral code sub floor
Genral code sub floorjbusse
 
Sub floor code
Sub floor codeSub floor code
Sub floor codejbusse
 
Explosive power tools
Explosive power toolsExplosive power tools
Explosive power toolsjbusse
 
Roof framing cdujb
Roof framing cdujbRoof framing cdujb
Roof framing cdujbjbusse
 

Plus de jbusse (14)

CPCCCA3009A Construct Advanced Roofs Octagonal end roof
CPCCCA3009A Construct Advanced Roofs Octagonal end roofCPCCCA3009A Construct Advanced Roofs Octagonal end roof
CPCCCA3009A Construct Advanced Roofs Octagonal end roof
 
CPCCCA3009A Construct Advanced Roofs Oblique roof
CPCCCA3009A Construct Advanced Roofs Oblique roofCPCCCA3009A Construct Advanced Roofs Oblique roof
CPCCCA3009A Construct Advanced Roofs Oblique roof
 
Lecture2
Lecture2Lecture2
Lecture2
 
Installation JB2011
Installation JB2011Installation JB2011
Installation JB2011
 
4 internal lining
4 internal lining4 internal lining
4 internal lining
 
4. associated issues
4. associated issues4. associated issues
4. associated issues
 
3. application of timber in environmental building
3. application of timber in environmental building3. application of timber in environmental building
3. application of timber in environmental building
 
2. timber as a sustainable building material
2. timber as a sustainable building material2. timber as a sustainable building material
2. timber as a sustainable building material
 
1. ecologically sustainable development
1. ecologically sustainable development1. ecologically sustainable development
1. ecologically sustainable development
 
Using span tables as1684 2
Using span tables   as1684 2Using span tables   as1684 2
Using span tables as1684 2
 
Genral code sub floor
Genral code sub floorGenral code sub floor
Genral code sub floor
 
Sub floor code
Sub floor codeSub floor code
Sub floor code
 
Explosive power tools
Explosive power toolsExplosive power tools
Explosive power tools
 
Roof framing cdujb
Roof framing cdujbRoof framing cdujb
Roof framing cdujb
 

Booking sheets, 2011 v1

  • 1. Booking Sheets Rise & Fall Method
  • 2. Recording your levels – Rise & Fall Method – copy readings on a piece of paper BM –1st reading taken was 2.250 (this is a back sight) (D) Last reading taken was .486(which is a foresight) (C) 5th reading taken was 2.400( a foresight) 2nd reading taken of 2.825 (this is a intermediate site) BM C D A (B) 3rd reading taken was 1.976(which is a foresight) (C) 6th reading taken new instrument position was 1.880 (which is a back sight) B (B) 4th reading taken new position of instrument was 2.120 (which is a back sight) Now we’ll have a look at how they go onto a booking sheet Triangles indicate instrument positions Letters indicate staff positions
  • 4. First Remember the rules for completing the booking sheet The first reading you take is always a Backsight (BS) The last reading you take is always a Foresight (FS) The readings you take in between are Intermediate sights (IS)
  • 5.
  • 6. back sight at BM first
  • 7. Then intermediate site, one line down
  • 8. Then foresight one line down again
  • 9. Then our instrument is moved (c.p. change point), our first reading from here is a backsight, but still goes on the line for staff reading B – etc. complete the rest
  • 10.
  • 11. This is simply deducting one reading from the previous and posting the answer in the rise & fall column
  • 12.
  • 13.
  • 14. Total the columns
  • 15. Take FS away from BS
  • 16. Take Fall away from Rise
  • 17.
  • 18. eg. 47.195 - .575 = 46.620
  • 19. 46.620 + .849 = 47.469 and so on
  • 21.
  • 22. Take the last RL away from the firstAgain All Answers should EQUAL !
  • 23. Review the completed booking sheet