SlideShare une entreprise Scribd logo
1  sur  38
AMRITSAR COLLEGE OF ENGINEERING & TECHNOLOGY
TRAINING REPORT
Submitted in partial fulfillment of the requirement for the award of
Degree in
ELECTRICAL AND ELECTRONICS ENGINEERING
BY
Punjab Technical University
Jallandhar
Submitted to:- Submitted by:-
Er. Ajaypal Singh Atinder Pal Singh Virk
Om Prakash
Narinder Sharma
Neeraj
A
SUMMER TRAINING
REPORT ON
PUNJAB STATE POWER CORPORATION LTD.
TRANSFORMER REPAIR WORKSHOP
AMRITSAR
A
Summer training Report Submitted
In Partial Fulfillment of the Requirements
for the award of Degree of
Bachelor of Technology
In
Electrical & Electronics Engineering
By
Atinder Pal Singh Virk
Om Prakash
Narinder Sharma
Neeraj
 Punjab State Power Corporation Limited
 Workshop Organization Headed by Chief Engg. Of
Workshop = Iqbal Singh
 Aim – To repair damaged Transformer at cheap rates
instead of paying high amounts to privates
sectors
 2 major circles = Amritsar [4] , Patiala [8]
 Working = Monthly target to repair 120 units
 25 KVA = 1 unit
 63 KVA = 1.5 unit
 100 KVA = 2 unit
 200 KVA = 4 unit
Introduction to Organisation
Additional
Superintending
Engineer
Junior Engineer Fore Man
FitterHelper
TRW Yard
Washing
Section
TRW Store
Tank
Repaiing
Section
Core Ovening
Section
Box-Up
Section
Dehyration
Filling
Section
Pre Testing
Painting
Final
Testing
TRW Store
 A transformer is a Static
device, which transfers
electric power from one
circuit to another.
 Does so without change
of frequency.
 Has voltage at the recei-
-ving end lower or higher
from the supply circuit.
Working Principle:- The main principle of operation of
a transformer Faraday’s law of
electromagnetic induction
According to Faraday’s law,
“Rate of change of flux linkage with respect to time is
directly proportional to the induced EMF in a conductor
or coil".
 A transformer consists of a rectangular core
of soft iron in the form of sheets (.35mm to
.5mm for 50Hz to 25Hz frequency).
 Two separate coils of insulated wires, a
primary coil and a secondary coil are wound
on the core. These coils are well insulated
from one another.
Core Type
In this type of
T/F the winding
surround the major
part of core.
Shell Type
In this the core
surround the
major part of the
winding
 There are generally two types of
transformer
 Step up transformer
 Step down transformer
 Some important types are given as:
 Auto-transformer
 Poly-phase transformer
 Leakage transformer
 Resonant transformer
 Instrument transformers
 A step up transformer
is a device that
converts low
alternatic voltage to
high alternating
voltage.
 In another word, a
transformer in which
Ns>Np that is called
step up transformer.
 A step down
transformer is a
device that
converts high
alternatic voltage
to low alternatic
voltage.
 In another word, a
transformer in
which Np>Ns that
is called step down
transformer.
 An autotransformer
with a sliding brush
contact
 An autotransformer
has only a single
winding with two
end terminals, plus
a third at an
intermediate tap
point.
For three-phase
supplies,
 A bank of three
individual single-
phase
transformers can
be used,
 OR all three
phases can be
made as a single
three-phase
transformer.
 Current transformers,
designed to be looped
around conductor.
 A current transformer
is a measurement
device
 provide a current in its
secondary coil
proportional to the
current flowing in its
primary.
 BUCHHOLZ RELAY: It is a very
sensitive gas and oil operated
instrument which safely detect
the formation of gas or sudden
pressure inside the oil transformer.
 CONSERVATOR:- It is used
to provide adequate space
for the expansion of oil when
transformer is loaded or when
ambient temperature changes
 TANK:- Basically this is a container
used to keep windings and insulation
oil. The tank is Made up of Mild
Steel.
 SILICA GEL BREATHER:It absorb
the moisture from the air. it is a
chemical material these are the
only one main component inside
the breather basically silica gel is
a brown colored one after the
absorption silica gel become pink
 OIL LEVEL INDICATOR: It is used
to show the oil level in the transfor-
-mer. this is a ordinary part situated
on the side of the conservator for
proper oil checking oil tank wants a
specific amount of oil.
 RADIATORS:- These are used for
the purpose for the cooling of the
transformer oil. The oil circulates
all the time from these radiator
parts
 Winding temprature indicator: used to
show the temperature of transformer
winding.
 TEMPERATURE METER (O.T/W.T):
These are used for taking the readings of
O.T.I - Oil Temperature Indicator and W.T.I
- Winding Temperature Indicator
 Tap-changer: This is used for the tapping
of the Transformer at different levels.
WINDINGS
 PRIMARY WINDING - In the case of power
transmission primary windings are the
main element external connection from
the power is connected to the winding.
 SECONDARY WINDING - This is a another
winding for reducing power (in the case of
step down purpose) .
M
Primary Wining Secondary Wining
 This is a outer unit, this is used to
prevent unwanted leakage of
electricity.
TRW Yard
Washing
Section
TRW Store
Tank
Repairing
Section
Core Ovening
Section
Box-Up
Section
Dehydration
Filling
Section
Pre Testing
Painting
Final
Testing
TRW Store
 Transformer Workshop Yard (TWY):- The
damage transformers are received here. All types of
transformer of 25KV, 63kv, 100kv and 200kv rating
received in damage condition.
 Transformer Repair Workshop Store (TRWS),
Tank & Washing:- In this section the power oil &
windings taken out from the Tank and blank tank is
send for washing in washing section
 Repairing Section: In this
section damage windings are
repaired if all windings are
burnt then whole windings
were replaced with new
windings.
 The core shown in fig. is made of
Silicon steel with thickness 0.35 to
0.5mm. These laminated core legs
are tighten with white tape. So,
that the flux in the coils will linked
properly with the other coil.
 The channel's shown in IInd fig.
are also use tighten the core and
Also fix the whole set of core and
Windings in the tank. The main
difference required between the
channel and windings should at
least 16-20mm which can be
increased or decreased according
to the requirement.
It is noted that for 25KV, 63KV, 100KV, 200KV
or any Rating Transformer the turn ratio will
not less than 43780 and not more than
44220.
Connections:- The distribution transformer
connection always in star- delta
connections means the connections of
Primary are in Delta connections and the
connection of Secondary in Star Connections.
 Core Ovening Section:- Core ovening
section is the most important part of
repairing transformer.
This is used to remove the moisture from
the core and windings of the transformer. In
this the core is placed inside the oven at 40-
60C temp in Summer season and 100-120C
in Winter season.
 BOXUP Section:- This is the section where the core
is placed inside the Tank and core is fixed inside the
core and all outer connections were made the
LT and HT were first fixed with
the Brass made rods and then
that rods were fixed with Porc-
-elain Brushes .
 Dehydration Filling Section:- The oil used in the
transformer are Power oil or Mineral oil. It provides
cooling to the transformer. Before filling the oil in the
transformer it is heated at 60KV/minute means 60KV
is applied to the oil for one minute in oil testing
machine. If the oil is withstand with this voltage then
it is further used for filling.
 Pre Testing:- In this everything is tested like IR
value, the oil Temp like after filling the oil in tank it
is again tested with 40KV/min. The requirement is
25KV/min but for overload safety purpose it is
tested at 40KV/min.
 Final Testing :- The final testing is divided into
four parts
(a) HVHP (High Voltage & High Pressure)
(b) DVDF (Double Voltage Double Frequency)
(c) No Load Losses
(d) Full Load Losses
Maximum Transformer
Efficiency
The efficiency varies as with respect to 2 independent quantities
namely, current and power factor
 Thus at any particular power factor, the efficiency is maximum if
core loss = Iron loss .This can be obtained by differentiating the
expression of efficiency with respect to I2 assuming power factor, and
all the voltages constant.
 At any particular I2 maximum efficiency happens at unity power factor.
 This can be obtained by differentiating the expression of efficiency
with respect to power factor, and assuming I2 and all the voltages
constant.
 Maximum efficiency happens when both these conditions are satisfied.
Losses
 Iron or core losses – caused by alternating flux
in core
 Hysteresis losses – During each A.C. cycle current
flows which magnetize and demagnetize the core. As a
result of which energy is lost in each cycle
 Eddy Current losses – Due to consequent heating of
material it results in loss of power
 Copper losses or ohmic losses - Due to ohmic
resistance in transformer winding
 Small losses which are mostly neglected
 Stray load losses – leakage field induces Eddy
currents in tank walls , bolts etc.
 Dielectric losses - occurs in insulation material
basically in oil and solid insulation
Open circuit Test
 It is used to determine Lm1 (Xm1)and Rc1
 Usually performed on the low voltage side
 The test is performed at rated voltage and frequency under
 no load
Short circuit Test
 It is used to determine Llp (Xeq) and Rp(Req)
 Usually performed on the high voltage side
 This test is performed at reduced voltage and rated frequency
with the output of the low voltage winding short circuited such
that rated current flows on the high voltage side.
 For Voltage Step Up
 For Voltage Step Down
 Amplifying Systems
 Loud Speakers
Any Queries

Contenu connexe

Tendances

HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
Shankar Singh
 
Transformer testing
Transformer testingTransformer testing
Transformer testing
ajayknows
 
Transformer repairing & manufacturing.pptx
Transformer repairing & manufacturing.pptxTransformer repairing & manufacturing.pptx
Transformer repairing & manufacturing.pptx
VishalSen33
 

Tendances (20)

Operation and maintenance of transformer
Operation and maintenance of transformerOperation and maintenance of transformer
Operation and maintenance of transformer
 
33/11 KV SUBSTATION
33/11 KV SUBSTATION33/11 KV SUBSTATION
33/11 KV SUBSTATION
 
132 kv sub-station, power transmission
132 kv sub-station, power transmission132 kv sub-station, power transmission
132 kv sub-station, power transmission
 
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
 
Installation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersInstallation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of Transformers
 
Power Transformer in DPL
Power Transformer in DPLPower Transformer in DPL
Power Transformer in DPL
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentation
 
220KV Substation Training Report
220KV Substation Training Report220KV Substation Training Report
220KV Substation Training Report
 
Power Transformer ( Summer Training presentation BHEL )
Power Transformer ( Summer Training presentation BHEL )Power Transformer ( Summer Training presentation BHEL )
Power Transformer ( Summer Training presentation BHEL )
 
Introduction to power transformers
Introduction to power transformersIntroduction to power transformers
Introduction to power transformers
 
Transformer Parts and functions
Transformer Parts and functionsTransformer Parts and functions
Transformer Parts and functions
 
speed control of three phase induction motor
speed control of three phase induction motorspeed control of three phase induction motor
speed control of three phase induction motor
 
power transformer and its usage
power transformer and its usage power transformer and its usage
power transformer and its usage
 
Transformer protection
Transformer protectionTransformer protection
Transformer protection
 
Substation
Substation Substation
Substation
 
Presentation on Distribution Transformer by nirob dhilon chowdhury
Presentation on Distribution Transformer by nirob dhilon chowdhuryPresentation on Distribution Transformer by nirob dhilon chowdhury
Presentation on Distribution Transformer by nirob dhilon chowdhury
 
Ppt on protection of power transformers
Ppt on protection of power transformersPpt on protection of power transformers
Ppt on protection of power transformers
 
Transformer testing
Transformer testingTransformer testing
Transformer testing
 
Transformer repairing & manufacturing.pptx
Transformer repairing & manufacturing.pptxTransformer repairing & manufacturing.pptx
Transformer repairing & manufacturing.pptx
 
TRANSFORMER PPT
TRANSFORMER PPT TRANSFORMER PPT
TRANSFORMER PPT
 

En vedette

Industrial training report
Industrial training report Industrial training report
Industrial training report
Pritam Samanta
 
Transformers Project report
Transformers Project reportTransformers Project report
Transformers Project report
Tanuj Gupta
 
E bomb seminar report
E bomb seminar reportE bomb seminar report
E bomb seminar report
Deepak Mittal
 

En vedette (20)

Industrial training report
Industrial training report Industrial training report
Industrial training report
 
Transformer manufacturing and Internship Report
Transformer manufacturing and Internship ReportTransformer manufacturing and Internship Report
Transformer manufacturing and Internship Report
 
Summer traning on Power Transformer Construction
Summer traning on Power Transformer ConstructionSummer traning on Power Transformer Construction
Summer traning on Power Transformer Construction
 
Transformer construction,types and working
Transformer construction,types and workingTransformer construction,types and working
Transformer construction,types and working
 
Transformer
TransformerTransformer
Transformer
 
Transformers Project report
Transformers Project reportTransformers Project report
Transformers Project report
 
transformer ppt
transformer ppttransformer ppt
transformer ppt
 
E bomb seminar report
E bomb seminar reportE bomb seminar report
E bomb seminar report
 
Transformers for Electric Arc-Melting Furnaces with Direct Voltage Regulation
Transformers for Electric Arc-Melting Furnaces with Direct Voltage RegulationTransformers for Electric Arc-Melting Furnaces with Direct Voltage Regulation
Transformers for Electric Arc-Melting Furnaces with Direct Voltage Regulation
 
POWER TRANSFORMER WINDINGS WITHOUT PAPER INSULATION
POWER TRANSFORMER WINDINGS WITHOUT PAPER INSULATIONPOWER TRANSFORMER WINDINGS WITHOUT PAPER INSULATION
POWER TRANSFORMER WINDINGS WITHOUT PAPER INSULATION
 
PROJECT REPORT
PROJECT REPORTPROJECT REPORT
PROJECT REPORT
 
DRE New & Refurbished Medical Equipment 2014 Catalog
DRE New & Refurbished Medical Equipment 2014 CatalogDRE New & Refurbished Medical Equipment 2014 Catalog
DRE New & Refurbished Medical Equipment 2014 Catalog
 
Human Respiratory System
Human Respiratory SystemHuman Respiratory System
Human Respiratory System
 
Solar water pumping systems
Solar water pumping systemsSolar water pumping systems
Solar water pumping systems
 
Impulse test for power transformers
Impulse test for power transformersImpulse test for power transformers
Impulse test for power transformers
 
Areva "Manufacturing of transformer, uses & it’s accessories"
Areva "Manufacturing of transformer, uses & it’s accessories"Areva "Manufacturing of transformer, uses & it’s accessories"
Areva "Manufacturing of transformer, uses & it’s accessories"
 
WIRELESS POWER TRANSFER
WIRELESS POWER TRANSFERWIRELESS POWER TRANSFER
WIRELESS POWER TRANSFER
 
Transformer basic
Transformer basicTransformer basic
Transformer basic
 
SIWES TECHNICAL REPORT BY OLADEJI ADEOLA
SIWES TECHNICAL REPORT BY OLADEJI ADEOLASIWES TECHNICAL REPORT BY OLADEJI ADEOLA
SIWES TECHNICAL REPORT BY OLADEJI ADEOLA
 
Anatomy of the ventilator
Anatomy of the ventilatorAnatomy of the ventilator
Anatomy of the ventilator
 

Similaire à Transformer Repair Workshop Report [EEE]

transformer Sales, after sales & service presentation
transformer Sales, after sales & service presentationtransformer Sales, after sales & service presentation
transformer Sales, after sales & service presentation
Fawaz Baik
 
Presentation_Power_Transformers-1
Presentation_Power_Transformers-1Presentation_Power_Transformers-1
Presentation_Power_Transformers-1
Nageswar Rao
 

Similaire à Transformer Repair Workshop Report [EEE] (20)

Kanti Thermal Power Station
Kanti Thermal Power StationKanti Thermal Power Station
Kanti Thermal Power Station
 
transformers.ppt
transformers.ppttransformers.ppt
transformers.ppt
 
Transformer ppt
Transformer pptTransformer ppt
Transformer ppt
 
Presentation Design of Computer aided design of power transformer
Presentation Design of Computer aided design of power transformerPresentation Design of Computer aided design of power transformer
Presentation Design of Computer aided design of power transformer
 
5_Basics of Electrical Machines.pptx
5_Basics of Electrical Machines.pptx5_Basics of Electrical Machines.pptx
5_Basics of Electrical Machines.pptx
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance
 
Industrial visit report uttam transformers
Industrial visit report  uttam transformersIndustrial visit report  uttam transformers
Industrial visit report uttam transformers
 
Transformers pptxx.ppt
Transformers pptxx.pptTransformers pptxx.ppt
Transformers pptxx.ppt
 
TRANSFORMER DESIGN.pptx
TRANSFORMER DESIGN.pptxTRANSFORMER DESIGN.pptx
TRANSFORMER DESIGN.pptx
 
TELK Industrial Visit Report
TELK Industrial Visit ReportTELK Industrial Visit Report
TELK Industrial Visit Report
 
Power transformers
Power transformersPower transformers
Power transformers
 
Maintenance schedule of Substation.
Maintenance schedule of Substation.Maintenance schedule of Substation.
Maintenance schedule of Substation.
 
transformer Sales, after sales & service presentation
transformer Sales, after sales & service presentationtransformer Sales, after sales & service presentation
transformer Sales, after sales & service presentation
 
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, AllahabadSummer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
 
Transformers
TransformersTransformers
Transformers
 
Presentation_Power_Transformers-1
Presentation_Power_Transformers-1Presentation_Power_Transformers-1
Presentation_Power_Transformers-1
 
Tap Changer
Tap ChangerTap Changer
Tap Changer
 
Transformers
TransformersTransformers
Transformers
 
Transformer Presentation-1.pptx
Transformer Presentation-1.pptxTransformer Presentation-1.pptx
Transformer Presentation-1.pptx
 
Transformer
TransformerTransformer
Transformer
 

Dernier

Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
negromaestrong
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
QucHHunhnh
 

Dernier (20)

Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
Role Of Transgenic Animal In Target Validation-1.pptx
Role Of Transgenic Animal In Target Validation-1.pptxRole Of Transgenic Animal In Target Validation-1.pptx
Role Of Transgenic Animal In Target Validation-1.pptx
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 

Transformer Repair Workshop Report [EEE]

  • 1. AMRITSAR COLLEGE OF ENGINEERING & TECHNOLOGY TRAINING REPORT Submitted in partial fulfillment of the requirement for the award of Degree in ELECTRICAL AND ELECTRONICS ENGINEERING BY Punjab Technical University Jallandhar Submitted to:- Submitted by:- Er. Ajaypal Singh Atinder Pal Singh Virk Om Prakash Narinder Sharma Neeraj
  • 2. A SUMMER TRAINING REPORT ON PUNJAB STATE POWER CORPORATION LTD. TRANSFORMER REPAIR WORKSHOP AMRITSAR A Summer training Report Submitted In Partial Fulfillment of the Requirements for the award of Degree of Bachelor of Technology In Electrical & Electronics Engineering By Atinder Pal Singh Virk Om Prakash Narinder Sharma Neeraj
  • 3.  Punjab State Power Corporation Limited  Workshop Organization Headed by Chief Engg. Of Workshop = Iqbal Singh  Aim – To repair damaged Transformer at cheap rates instead of paying high amounts to privates sectors  2 major circles = Amritsar [4] , Patiala [8]  Working = Monthly target to repair 120 units  25 KVA = 1 unit  63 KVA = 1.5 unit  100 KVA = 2 unit  200 KVA = 4 unit Introduction to Organisation
  • 5. TRW Yard Washing Section TRW Store Tank Repaiing Section Core Ovening Section Box-Up Section Dehyration Filling Section Pre Testing Painting Final Testing TRW Store
  • 6.  A transformer is a Static device, which transfers electric power from one circuit to another.  Does so without change of frequency.  Has voltage at the recei- -ving end lower or higher from the supply circuit.
  • 7.
  • 8. Working Principle:- The main principle of operation of a transformer Faraday’s law of electromagnetic induction According to Faraday’s law, “Rate of change of flux linkage with respect to time is directly proportional to the induced EMF in a conductor or coil".
  • 9.  A transformer consists of a rectangular core of soft iron in the form of sheets (.35mm to .5mm for 50Hz to 25Hz frequency).  Two separate coils of insulated wires, a primary coil and a secondary coil are wound on the core. These coils are well insulated from one another.
  • 10. Core Type In this type of T/F the winding surround the major part of core. Shell Type In this the core surround the major part of the winding
  • 11.
  • 12.  There are generally two types of transformer  Step up transformer  Step down transformer  Some important types are given as:  Auto-transformer  Poly-phase transformer  Leakage transformer  Resonant transformer  Instrument transformers
  • 13.  A step up transformer is a device that converts low alternatic voltage to high alternating voltage.  In another word, a transformer in which Ns>Np that is called step up transformer.
  • 14.  A step down transformer is a device that converts high alternatic voltage to low alternatic voltage.  In another word, a transformer in which Np>Ns that is called step down transformer.
  • 15.  An autotransformer with a sliding brush contact  An autotransformer has only a single winding with two end terminals, plus a third at an intermediate tap point.
  • 16. For three-phase supplies,  A bank of three individual single- phase transformers can be used,  OR all three phases can be made as a single three-phase transformer.
  • 17.  Current transformers, designed to be looped around conductor.  A current transformer is a measurement device  provide a current in its secondary coil proportional to the current flowing in its primary.
  • 18.
  • 19.  BUCHHOLZ RELAY: It is a very sensitive gas and oil operated instrument which safely detect the formation of gas or sudden pressure inside the oil transformer.  CONSERVATOR:- It is used to provide adequate space for the expansion of oil when transformer is loaded or when ambient temperature changes
  • 20.  TANK:- Basically this is a container used to keep windings and insulation oil. The tank is Made up of Mild Steel.  SILICA GEL BREATHER:It absorb the moisture from the air. it is a chemical material these are the only one main component inside the breather basically silica gel is a brown colored one after the absorption silica gel become pink
  • 21.  OIL LEVEL INDICATOR: It is used to show the oil level in the transfor- -mer. this is a ordinary part situated on the side of the conservator for proper oil checking oil tank wants a specific amount of oil.  RADIATORS:- These are used for the purpose for the cooling of the transformer oil. The oil circulates all the time from these radiator parts
  • 22.  Winding temprature indicator: used to show the temperature of transformer winding.  TEMPERATURE METER (O.T/W.T): These are used for taking the readings of O.T.I - Oil Temperature Indicator and W.T.I - Winding Temperature Indicator  Tap-changer: This is used for the tapping of the Transformer at different levels.
  • 23. WINDINGS  PRIMARY WINDING - In the case of power transmission primary windings are the main element external connection from the power is connected to the winding.  SECONDARY WINDING - This is a another winding for reducing power (in the case of step down purpose) . M Primary Wining Secondary Wining
  • 24.  This is a outer unit, this is used to prevent unwanted leakage of electricity.
  • 25. TRW Yard Washing Section TRW Store Tank Repairing Section Core Ovening Section Box-Up Section Dehydration Filling Section Pre Testing Painting Final Testing TRW Store
  • 26.  Transformer Workshop Yard (TWY):- The damage transformers are received here. All types of transformer of 25KV, 63kv, 100kv and 200kv rating received in damage condition.  Transformer Repair Workshop Store (TRWS), Tank & Washing:- In this section the power oil & windings taken out from the Tank and blank tank is send for washing in washing section  Repairing Section: In this section damage windings are repaired if all windings are burnt then whole windings were replaced with new windings.
  • 27.  The core shown in fig. is made of Silicon steel with thickness 0.35 to 0.5mm. These laminated core legs are tighten with white tape. So, that the flux in the coils will linked properly with the other coil.  The channel's shown in IInd fig. are also use tighten the core and Also fix the whole set of core and Windings in the tank. The main difference required between the channel and windings should at least 16-20mm which can be increased or decreased according to the requirement.
  • 28. It is noted that for 25KV, 63KV, 100KV, 200KV or any Rating Transformer the turn ratio will not less than 43780 and not more than 44220. Connections:- The distribution transformer connection always in star- delta connections means the connections of Primary are in Delta connections and the connection of Secondary in Star Connections.
  • 29.  Core Ovening Section:- Core ovening section is the most important part of repairing transformer. This is used to remove the moisture from the core and windings of the transformer. In this the core is placed inside the oven at 40- 60C temp in Summer season and 100-120C in Winter season.
  • 30.  BOXUP Section:- This is the section where the core is placed inside the Tank and core is fixed inside the core and all outer connections were made the LT and HT were first fixed with the Brass made rods and then that rods were fixed with Porc- -elain Brushes .  Dehydration Filling Section:- The oil used in the transformer are Power oil or Mineral oil. It provides cooling to the transformer. Before filling the oil in the transformer it is heated at 60KV/minute means 60KV is applied to the oil for one minute in oil testing machine. If the oil is withstand with this voltage then it is further used for filling.
  • 31.  Pre Testing:- In this everything is tested like IR value, the oil Temp like after filling the oil in tank it is again tested with 40KV/min. The requirement is 25KV/min but for overload safety purpose it is tested at 40KV/min.  Final Testing :- The final testing is divided into four parts (a) HVHP (High Voltage & High Pressure) (b) DVDF (Double Voltage Double Frequency) (c) No Load Losses (d) Full Load Losses
  • 32. Maximum Transformer Efficiency The efficiency varies as with respect to 2 independent quantities namely, current and power factor  Thus at any particular power factor, the efficiency is maximum if core loss = Iron loss .This can be obtained by differentiating the expression of efficiency with respect to I2 assuming power factor, and all the voltages constant.  At any particular I2 maximum efficiency happens at unity power factor.  This can be obtained by differentiating the expression of efficiency with respect to power factor, and assuming I2 and all the voltages constant.  Maximum efficiency happens when both these conditions are satisfied.
  • 33. Losses  Iron or core losses – caused by alternating flux in core  Hysteresis losses – During each A.C. cycle current flows which magnetize and demagnetize the core. As a result of which energy is lost in each cycle  Eddy Current losses – Due to consequent heating of material it results in loss of power  Copper losses or ohmic losses - Due to ohmic resistance in transformer winding  Small losses which are mostly neglected  Stray load losses – leakage field induces Eddy currents in tank walls , bolts etc.  Dielectric losses - occurs in insulation material basically in oil and solid insulation
  • 34. Open circuit Test  It is used to determine Lm1 (Xm1)and Rc1  Usually performed on the low voltage side  The test is performed at rated voltage and frequency under  no load
  • 35. Short circuit Test  It is used to determine Llp (Xeq) and Rp(Req)  Usually performed on the high voltage side  This test is performed at reduced voltage and rated frequency with the output of the low voltage winding short circuited such that rated current flows on the high voltage side.
  • 36.  For Voltage Step Up  For Voltage Step Down  Amplifying Systems  Loud Speakers
  • 37.