Understanding Constraints in Primavera P6
Constraints are applied to Activities when
relationships do not provide the required result
and are often a result of External Dependencies.
Typical applications of a constraint are to constrain an
activity to a date for:
 The availability of a site to commence work.
 The supply of information by a client.
 The required finish date of a project.
Constraints are often entered against Milestone activities
to represent contract dates and may be directly related
to contract items using Notebook Topics.
Constraints are covered in detail in
the Constraints chapter.
Understanding Relationships
There are four types of dependencies available in
Primavera P6:
 Finish-to-Start (FS) (also known as conventional)
 Start-to-Start (SS)
 Start-to-Finish (SF)
 Finish-to-Finish (FF)
Two other terms you must understand are:
Predecessor, an activity that controls the start or
finish of another immediate subsequent activity.
Successor, an activity where the start or finish
depends on the start or finish of another immediately
preceding activity.
The following pictures show how the dependencies
appear graphically in the Bar Chart and Activity
Network (also known as PERT, Network Diagram and
Relationship Diagram Views):
The FS (or conventional) dependency looks like this:
Eastwood Harris Supplies Project Management
Training Manuals, Project Management
Training Presentations and Consulting on
Primavera P6 and Microsoft Project
2010 across Australia.

Contenu connexe

Tendances

Tendances (20)

Primavera p6 advanced project planning
Primavera p6 advanced project planningPrimavera p6 advanced project planning
Primavera p6 advanced project planning
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedules
 
Project Management Techniques
Project Management TechniquesProject Management Techniques
Project Management Techniques
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
Primavera Training P6
Primavera Training P6Primavera Training P6
Primavera Training P6
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricks
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6
 
Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Primavera Project Management
Primavera Project ManagementPrimavera Project Management
Primavera Project Management
 
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
 
PM using P6
PM using P6PM using P6
PM using P6
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)
 

En vedette

Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Charlie Jackson
 
Oracle primavera eppm presentation
Oracle primavera eppm presentationOracle primavera eppm presentation
Oracle primavera eppm presentation
Thanh Hoang Lam
 
Primavera
PrimaveraPrimavera
Primavera
hlksd
 

En vedette (20)

Activity Duration Types Explained with example in Primavera
Activity Duration Types Explained with example in PrimaveraActivity Duration Types Explained with example in Primavera
Activity Duration Types Explained with example in Primavera
 
Pdf primavera tutorial
Pdf primavera tutorialPdf primavera tutorial
Pdf primavera tutorial
 
Understanding p6 dates
Understanding p6 datesUnderstanding p6 dates
Understanding p6 dates
 
Primavera Project Management P6 Course Session 1
Primavera Project Management P6 Course Session 1Primavera Project Management P6 Course Session 1
Primavera Project Management P6 Course Session 1
 
P6 Version 7 Tricks and Traps
P6 Version 7 Tricks and TrapsP6 Version 7 Tricks and Traps
P6 Version 7 Tricks and Traps
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
 
Oracle Primavera P6 R16.1
Oracle Primavera P6 R16.1Oracle Primavera P6 R16.1
Oracle Primavera P6 R16.1
 
Primavera p6 v8.2 session 1
Primavera p6 v8.2 session 1Primavera p6 v8.2 session 1
Primavera p6 v8.2 session 1
 
Primavera P6 Online Training
Primavera  P6 Online TrainingPrimavera  P6 Online Training
Primavera P6 Online Training
 
Authentic Global Connections Learning2 Saigon2016
Authentic Global Connections Learning2 Saigon2016 Authentic Global Connections Learning2 Saigon2016
Authentic Global Connections Learning2 Saigon2016
 
P6 professional standalone_install_and_config_guide
P6 professional standalone_install_and_config_guideP6 professional standalone_install_and_config_guide
P6 professional standalone_install_and_config_guide
 
P6 as cost management system - Oracle Primavera P6 Collaborate 14
P6 as cost management system - Oracle Primavera P6 Collaborate 14P6 as cost management system - Oracle Primavera P6 Collaborate 14
P6 as cost management system - Oracle Primavera P6 Collaborate 14
 
Installing Oracle Primavera P6 Professional standalone
Installing Oracle Primavera P6 Professional standaloneInstalling Oracle Primavera P6 Professional standalone
Installing Oracle Primavera P6 Professional standalone
 
Primavera P6 installation
Primavera P6 installationPrimavera P6 installation
Primavera P6 installation
 
P6 r8
P6 r8P6 r8
P6 r8
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
 
Oracle primavera eppm presentation
Oracle primavera eppm presentationOracle primavera eppm presentation
Oracle primavera eppm presentation
 
Successfully Manage Cost and Schedule with Primavera Unifier and Primavera P6
Successfully Manage Cost and Schedule with Primavera Unifier and Primavera P6Successfully Manage Cost and Schedule with Primavera Unifier and Primavera P6
Successfully Manage Cost and Schedule with Primavera Unifier and Primavera P6
 
Introduction, development and analysis of banana curve in project management....
Introduction, development and analysis of banana curve in project management....Introduction, development and analysis of banana curve in project management....
Introduction, development and analysis of banana curve in project management....
 
Primavera
PrimaveraPrimavera
Primavera
 

Similaire à Understanding Constraints and Relationships in Primavera P6 8.2

Functional specification documents of
Functional specification documents ofFunctional specification documents of
Functional specification documents of
rtu
 
Analysis Questionnaire - White Paper
Analysis Questionnaire - White PaperAnalysis Questionnaire - White Paper
Analysis Questionnaire - White Paper
Saurabh Goel
 
Week10 Analysing Client Requirements
Week10 Analysing Client RequirementsWeek10 Analysing Client Requirements
Week10 Analysing Client Requirements
hapy
 
L05 time management
L05 time managementL05 time management
L05 time management
Asa Chan
 
Determining Requirements Complexity - White Paper
Determining Requirements Complexity - White PaperDetermining Requirements Complexity - White Paper
Determining Requirements Complexity - White Paper
Saurabh Goel
 
SRE-Week-09-Refining-the-system-definition-05052023-114706pm.pptx
SRE-Week-09-Refining-the-system-definition-05052023-114706pm.pptxSRE-Week-09-Refining-the-system-definition-05052023-114706pm.pptx
SRE-Week-09-Refining-the-system-definition-05052023-114706pm.pptx
Hassankhalid894940
 
BoardSprintUser Story ScenarioDesignDevelopmentTestUAT Release1U .docx
BoardSprintUser Story ScenarioDesignDevelopmentTestUAT Release1U .docxBoardSprintUser Story ScenarioDesignDevelopmentTestUAT Release1U .docx
BoardSprintUser Story ScenarioDesignDevelopmentTestUAT Release1U .docx
jasoninnes20
 

Similaire à Understanding Constraints and Relationships in Primavera P6 8.2 (20)

Functional specification documents of
Functional specification documents ofFunctional specification documents of
Functional specification documents of
 
Analysis Questionnaire - White Paper
Analysis Questionnaire - White PaperAnalysis Questionnaire - White Paper
Analysis Questionnaire - White Paper
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
02-Key Definitions .pdf
02-Key Definitions .pdf02-Key Definitions .pdf
02-Key Definitions .pdf
 
Week10 Analysing Client Requirements
Week10 Analysing Client RequirementsWeek10 Analysing Client Requirements
Week10 Analysing Client Requirements
 
L05 time management
L05 time managementL05 time management
L05 time management
 
Determining Requirements Complexity - White Paper
Determining Requirements Complexity - White PaperDetermining Requirements Complexity - White Paper
Determining Requirements Complexity - White Paper
 
Sample BRS
Sample BRSSample BRS
Sample BRS
 
Lecture 6
Lecture 6Lecture 6
Lecture 6
 
SRE-Week-09-Refining-the-system-definition-05052023-114706pm.pptx
SRE-Week-09-Refining-the-system-definition-05052023-114706pm.pptxSRE-Week-09-Refining-the-system-definition-05052023-114706pm.pptx
SRE-Week-09-Refining-the-system-definition-05052023-114706pm.pptx
 
Unit ii update
Unit ii updateUnit ii update
Unit ii update
 
Project Time Managment.pptx
Project Time Managment.pptxProject Time Managment.pptx
Project Time Managment.pptx
 
Srs
SrsSrs
Srs
 
105 project time management
105 project time management105 project time management
105 project time management
 
6.3 sequence activities
6.3 sequence activities6.3 sequence activities
6.3 sequence activities
 
Basics CPM&PERT.ppt
Basics CPM&PERT.pptBasics CPM&PERT.ppt
Basics CPM&PERT.ppt
 
Estimation Techniques V1.0
Estimation Techniques V1.0Estimation Techniques V1.0
Estimation Techniques V1.0
 
BoardSprintUser Story ScenarioDesignDevelopmentTestUAT Release1U .docx
BoardSprintUser Story ScenarioDesignDevelopmentTestUAT Release1U .docxBoardSprintUser Story ScenarioDesignDevelopmentTestUAT Release1U .docx
BoardSprintUser Story ScenarioDesignDevelopmentTestUAT Release1U .docx
 
Whitepaper - Project Analysis Process at Konstant
Whitepaper - Project Analysis Process at KonstantWhitepaper - Project Analysis Process at Konstant
Whitepaper - Project Analysis Process at Konstant
 

Plus de danieljohn810

Plus de danieljohn810 (20)

Change Management Training – Gaining Support from Staff
Change Management Training – Gaining Support from StaffChange Management Training – Gaining Support from Staff
Change Management Training – Gaining Support from Staff
 
Diploma in Project Management – How to Create a Work Breakdown Structure (WBS...
Diploma in Project Management – How to Create a Work Breakdown Structure (WBS...Diploma in Project Management – How to Create a Work Breakdown Structure (WBS...
Diploma in Project Management – How to Create a Work Breakdown Structure (WBS...
 
Basic Principles of Project Management
Basic Principles of Project ManagementBasic Principles of Project Management
Basic Principles of Project Management
 
Destination Wedding Etiquette
Destination Wedding EtiquetteDestination Wedding Etiquette
Destination Wedding Etiquette
 
Diploma of Project Management – How to Set Up Project Activity Sequences
Diploma of Project Management – How to Set Up Project Activity SequencesDiploma of Project Management – How to Set Up Project Activity Sequences
Diploma of Project Management – How to Set Up Project Activity Sequences
 
Australian Workplace Health and Safety Resources
Australian Workplace Health and Safety ResourcesAustralian Workplace Health and Safety Resources
Australian Workplace Health and Safety Resources
 
Cert IV OHS - WHS Responsibilities and Legislative Requirements
Cert IV OHS - WHS Responsibilities and Legislative RequirementsCert IV OHS - WHS Responsibilities and Legislative Requirements
Cert IV OHS - WHS Responsibilities and Legislative Requirements
 
Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)
 
Certificate IV OHS - Glossary of Common OHS Terms
Certificate IV OHS - Glossary of Common OHS TermsCertificate IV OHS - Glossary of Common OHS Terms
Certificate IV OHS - Glossary of Common OHS Terms
 
Writing Meeting Agendas - Business Writing Skills Training Courses
Writing Meeting Agendas - Business Writing Skills Training CoursesWriting Meeting Agendas - Business Writing Skills Training Courses
Writing Meeting Agendas - Business Writing Skills Training Courses
 
Diploma of Project Management - Activity Resource Estimating (Outputs)
Diploma of Project Management - Activity Resource Estimating (Outputs)Diploma of Project Management - Activity Resource Estimating (Outputs)
Diploma of Project Management - Activity Resource Estimating (Outputs)
 
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
 
Schedule Development - Diploma in Project Management
Schedule Development - Diploma in Project Management Schedule Development - Diploma in Project Management
Schedule Development - Diploma in Project Management
 
Occupational Health and Safety Training -The Role of Managers in WHS
Occupational Health and Safety Training -The Role of Managers in WHSOccupational Health and Safety Training -The Role of Managers in WHS
Occupational Health and Safety Training -The Role of Managers in WHS
 
Executive Assistant Training - Advanced PA Training
Executive Assistant Training - Advanced PA TrainingExecutive Assistant Training - Advanced PA Training
Executive Assistant Training - Advanced PA Training
 
Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...
Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...
Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...
 
Occupational Health and Safety Training - WHS Needs and Priorities
Occupational Health and Safety Training - WHS Needs and PrioritiesOccupational Health and Safety Training - WHS Needs and Priorities
Occupational Health and Safety Training - WHS Needs and Priorities
 
Office 365 Excel Essentials Training Course.pdf
Office 365 Excel Essentials Training Course.pdfOffice 365 Excel Essentials Training Course.pdf
Office 365 Excel Essentials Training Course.pdf
 
Glossary of OHS Terms - Diploma in Occupational Health and Safety
Glossary of OHS Terms - Diploma in Occupational Health and SafetyGlossary of OHS Terms - Diploma in Occupational Health and Safety
Glossary of OHS Terms - Diploma in Occupational Health and Safety
 
How to Measure the Relevance and Accuracy of OHS Information
How to Measure the Relevance and Accuracy of OHS InformationHow to Measure the Relevance and Accuracy of OHS Information
How to Measure the Relevance and Accuracy of OHS Information
 

Dernier

Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
PECB
 
Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.
MateoGardella
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
negromaestrong
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
QucHHunhnh
 

Dernier (20)

Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 

Understanding Constraints and Relationships in Primavera P6 8.2

  • 1.
  • 3. Constraints are applied to Activities when relationships do not provide the required result and are often a result of External Dependencies.
  • 4. Typical applications of a constraint are to constrain an activity to a date for:  The availability of a site to commence work.  The supply of information by a client.  The required finish date of a project.
  • 5. Constraints are often entered against Milestone activities to represent contract dates and may be directly related to contract items using Notebook Topics. Constraints are covered in detail in the Constraints chapter.
  • 7. There are four types of dependencies available in Primavera P6:  Finish-to-Start (FS) (also known as conventional)  Start-to-Start (SS)  Start-to-Finish (SF)  Finish-to-Finish (FF)
  • 8. Two other terms you must understand are: Predecessor, an activity that controls the start or finish of another immediate subsequent activity. Successor, an activity where the start or finish depends on the start or finish of another immediately preceding activity.
  • 9. The following pictures show how the dependencies appear graphically in the Bar Chart and Activity Network (also known as PERT, Network Diagram and Relationship Diagram Views): The FS (or conventional) dependency looks like this:
  • 10.
  • 11. Eastwood Harris Supplies Project Management Training Manuals, Project Management Training Presentations and Consulting on Primavera P6 and Microsoft Project 2010 across Australia.