PROJECT MANAGEMENT
IS : 14580 – PART 1
▪ MANAGEMENT
▪ PLANNING
▪ REVIEW
▪ REPORTlNG AND
▪ TERMINATION PROCEDURES
BROAD CONTENTS
▪ ORGANISATION AND MANAGEMENT OF PROJECTS.
▪ PLANNING THE PROJECT.
▪ REVIEW PROCEDURES FOR PROJECT COORDINATION AND
CONTROL.
▪ REPORTING DOCUMENTATION AND PROCEDURES.
▪ PROJECT TERMINATION/ CLOSURE.
SECTION 1
ORGANISATION AND
MANAGEMENT OF PROJECTS
PROJECT CYCLE
• FORMULATION
• IMPLEMENTATION
• COMMISSIONING
PROJECT TYPES
• TIME SCALE
• COST
• PURPOSE
• DIRECT PRODUCTION OF GOODS
• SECTORS OF THE ECONOMY – AGICULTURE, INDUSTRY, MINING?
• OWNERSHIP – PUBLIC, PRIVATE JOINT SECTORS?
•SPECIFIC PURPOSE
PROJECT ORGANISATIONS
• INNOVATIVE APPROACHES TO OVERCOME PROBLEMS
• SOUND AND EXPERIENCE BASED SOLUTIONS
• IMPLEMENTATION
• COMMISSIONING
THE PROJECT ORGANIZATION STRUCTURE COULD BE OF 3 TYPES:
• FUNCTIONAL ORGANIZATION STRUCTURE
• MATRIX ORGANIZATION STRUCTURE
• PROJECTISED ORGANIZATION STRUCTURE
ORGANISATION CHART FOR A LARGE PROJECT DRIVEN CONSTRUCTION COMPANY
• FIRST OF ALL DEFINE AN IDEAL ORGANIZATION SO THAT WEAKNESSES OF EXISTING
ORGANIZATION COULD BE FORESEEN.
• THE PROJECT ORGANIZATION SHOULD BE ADAPTABLE TO CHANGES AS THE PROJECT
MOVES FROM PHASE TO PHASE.
• THE NUMBER/TYPE OF PERSONNELAND THEIR PRIME FUNCTION, AUTHORITY AND
RESPONSIBILITY REQUIRED SHOULD BE DEFINED.
• THE CURRENT ORGANIZATIONAL CAPABILITIES AND THE NEED TO EMPLOY
CONSULTANTS SHOULD BE ASSESSED.
• THE MOTIVATION AND COMMITMENT OF PROJECT GROUPS SHOULD BE ENSURED.
FACTORS TO BE TAKEN INTO ACCOUNT FOR DEVELOPING A PROJECT
ORGANIZATION:
PROJECT MANAGEMENT
PRINCIPLES FOR PROJECT MANAGEMENT
• FORWARD LOOKING.
• MADE AT THE LOWEST FEASIBLE LEVEL CONSISTENT WITH RESPONSIBILITY AND
AUTHORITY.
• CAREFUL SELECTION OF PROJECT MANAGERS AND PROJECT TEAMS.
• THE AUTHORITY SHOULD ALWAYS MATCH WITH PROJECT RESPONSIBILITIES AT ALL
LEVELS.
THE AIM OF PROJECT MANAGEMENT IS TO SUCCESSFULLY ACHIEVE THE OBJECTIVES OF
THE PROJECT BY COMPLETING IT ON SCHEDULE, WITHIN COST AND PERFORMANCE
CRITERIA WITH PRESCRIBED HUMAN, PHYSICAL RESOURCE AND OTHER CONSTRAINTS.
THE PRINCIPAL ROLE OFA PROJECT MANAGER
• TO HELP FORMULATE OBJECTIVES AND POLICIES FOR THE PROJECT AND
OPERATIONALISE THEM TO ENSURE THAT THESE ARE ADEQUATELY MET.
• TO ENSURE AVAILABILITYAND EFFECTIVE UTILIZATION OF PROJECT RESOURCES.
• TO PREPARE AND ENSURE APPROVAL OF ALL PROJECT PLANS.
• TO APPROVE ALL OPERATIONAL PLANS AND PROCEDURES AND INFORM PROJECT
STAFF OF THEIR DUTIES AND RESPONSIBILITIES.
• TO MONITOR AND CONTROL PROGRESS, PERFORMANCE QUALITY AND EXPENDITURE.
• TO ENSURE SAFETY STANDARDS AND CONFORMITY TO LEGAL REQUIREMENTS.
• TO ENSURE ESTABLISHMENT AND OPERATION OF COMMUNICATION, INFORMATION
AND REPORTING SYSTEM.
• TO SERVE AS THE PRIME POINT OF CONTACT FOR THE PROJECT.
PROJECT MANAGEMENT SHOULD PERFORM THE FOLLOWING
FUNCTIONS:
• DEFINE THE SCOPE AND WORK CONTENT OF THE PROJECT.
• DECIDE HOW TO GET THE PROJECT ACTIVITIES EXECUTED.
• ADAPT THE ORGANIZATION AS THE PROJECT PROGRESSES.
• DEVELOPA SUITABLE PROJECT ORGANIZATION.
• PREPARE IMPLEMENTATION PLANS AND INVOLVE ALL CONCERNED PROJECT
PARTICIPANTS ENSURING THAT ALL PROJECT COMPONENTS AND ELEMENTS ARE
INTERRELATED, INTEGRATED AND COORDINATED.
• DEFINE CONTRACTING STRATEGY AND POLICY, PREPARE THE CONTRACT PLAN AND
SPECIFY CONTRACTORS RESPONSIBILITIES.
• DEVELOP TIME SCHEDULES, BUDGETS AND IDENTIFY KEY MILESTONES.
• DESIGN MONITORING AND CONTROL, INFORMATION AND REPORTING SYSTEMS AND
ENSURE THEIR PROPER OPERATION.
• DEFINE METHODS AND PROCEDURES TO MANAGE CHANGE FROM ITS INITIAL STAGE
TO ITS FINALIZATION.
• SPECIFY TRAINING REQUIREMENTS AND MAKE APPROPRIATE PROVISIONS.
CONTRACT MANAGEMENT
• ITEM RATE CONTRACT
• PERCENTAGE RATE CONTRACT
• LUMP SUM RATE CONTRACT
• COST PLUS CONTRACT
STANDARD PROCEDURES SHOULD BE DEVELOPED FOR:
• PRE-TENDER PLANNING;
• PRE-QUALIFICATION OF AGENCIES AND SUPPLIERS;
• INVITATION AND RECEIPT OF TENDERS;
• OPENING, EVALUATION AND NEGOTIATION OF TENDERS;
• AWARD OF CONTRACT;
• RELEASE OF WORK ORDERS, DESIGNS AND DRAWINGS;
• MEASUREMENTS AND PAYMENTS;
• MODIFICATIONS AND CHANGES IN CONTRACTS;
• TERMINATION / CLOSING AND OFF-LOADING CONTRACTS;
• MONITORING, REPORTING AND REVIEWING PROGRESS AND PERFORMANCE OF CONTRACTS.
TYPES OF CONTRACTS :
FAMILIARIZATION AND TRAINING
• AFTER THE BASIC PROJECT MANAGEMENT AND CONTROL SYSTEMS HAVE BEEN
DEVELOPED AND AGREED, ALL THOSE WHO HAVE TO PARTICIPATE IN THE PROJECT
SHOULD BE APPROPRIATELY FAMILIARIZED AND TRAINED TO OPERATE/USE THEM.
THIS WOULD HELP IN CREATING TEAM ENVIRONMENT, ESTABLISHING LINES OF
COMMUNICATION, BREAKING BARRIERS BETWEEN ORGANIZATIONS AND REDUCING
CONFUSION AND MISUNDERSTANDING AS TO WHO DOES WHAT, WHEN AND WHY.
• IN ADDITION TO PROJECT SPECIFIC TRAINING, SUPPLEMENTARY EDUCATIONAL
COURSES MAY BE ORGANIZED TO PROVIDE BACKGROUND INFORMATION IN THE
APPLICATION OF NETWORK BASED TECHNIQUES.
SECTION 2
PLANNING THE PROJECT
PLANNING IS THE PROCESS BY WHICH A MANAGER LOOKS TO THE FUTURE AND
DISCOVERS ALTERNATIVE COURSES OF ACTION. A PROJECT PLAN SHOULD GIVE DETAILS
ABOUT PRODUCT/WORK (QUANTITY AND QUALITY), TIMESCALE, RESOURCES, COST AND
ORGANIZATION; ALSO MONITORING AND CONTROL.
IT WILL INVOLVE:
• CONSCIOUS AND EXPLICIT AWARENESS OF THE ULTIMATE
• CORPORATE GOALS;
• ESTABLISHMENT OF PROJECT OBJECTIVES;
• ARTICULATION AND EVALUATION OF ALTERNATIVES;
• SELECTION OF MOST SUITABLE ALTERNATIVE; AND
• IDENTIFICATION OF ACTIVITIES REQUIRED TO ACHIEVE
• THE OBJECTIVES.
LEVELS OF PLANNING
• CORPORATE MANAGEMENT,
• PROJECT MANAGEMENT,
• OPERATIONAL MANAGEMENT
• PROJECT PLAN
• STAGE PLAN
• DETAILED PLAN
• INDIVIDUAL WORK PLAN
• EQUIPMENT LOADING PLAN
TO CATER TO THE NEEDS OF DIFFERENT PROJECT MANAGEMENT
LEVELS, THERE MAY BE HIERARCHY OF PLANS, WHICH MAY CONSIST
OF THE FOLLOWING:
COMPONENTS OF PROJECT PLANS
• DEFINE LOGICAL RELATIONSHIPS AMONGST ACTIVITIES WHICH MAY BE
REPRESENTED IN THE FORM OF. AN ACTIVITY NETWORK.
• IDENTIFY THE RESOURCES REQUIRED FOR EACH ACTIVITY.
• PROVIDE A TIME SCHEDULE OF ACTIVITIES CONSISTENT WITH RESOURCE
REQUIREMENTS AND THE TOTAL RESOURCES AVAILABLE TO THE PROJECT.
• IDENTIFY THE MILESTONES IN -PROJECTS AND STAGES FOR MAJOR ASSESSMENT AND
REVIEW.
• IDENTIFY INTERNALAND EXTERNAL DEPENDENCIES ON ACTIVITIES.
TECHNICAL / WORK PLANS
RESOURCE PLANS
• HOW RESOURCES WOULD BE OBTAINED AND ALLOCATED.
• THE WORK SCHEDULE FOR EACH INDIVIDUAL/ GROUP RESOURCE.
• METHODS OF DISPOSITION OF EXCESS RESOURCES, IF ANY.
QUALITY PLANS
• AGREEMENT ON QUALITY WITH ALL CONCERNED;
• PREVENTION, DETECTION AND RECTIFICATION OF FAULTS;
• SETTING APPROPRIATE AND MEASURABLE QUALITY CRITERIA FOR EACH PRODUCT;
• ESTABLISHMENT OF SYSTEMS AND PROCEDURES TO ASSESS AND DEMONSTRATE
WHETHER QUALITY GOALS HAVE BEEN ACHIEVED;
• RESOURCING OF QUALITY CONTROLACTIVITIES.
COST AND CASH FLOW PLANS
• REQUIRED TO MAKE NECESSARY FINANCIAL PROVISIONS,
• THE COST ESTIMATE OF EACH ACTIVITY SHOULD BE WORKED OUT,
• THE CASH FLOW PLANS CAN BE DERIVED BY TRANSLATING THE TECHNICAL PLAN
INTO FINANCIAL TERMS,
• PERFORMANCE BUDGETING IS THE TECHNIQUE USED TO RELATE THE FINANCIAL
ASPECTS OF THE PROJECT WITH ITS PHYSICALASPECTS,
• ZERO-BASE BUDGETING IS THE TECHNIQUE TO ENSURE COST EFFECTIVENESS OF THE
PROJECT AT EVERY STAGE.
STEPS IN PROJECT PLANNING
• IDENTIFY THE PROJECT OBJECTIVES AND COMPONENTS
• IDENTIFY THE ACTIVITIES
• IDENTIFY DEPENDENCIES
• PRODUCE ACTIVITY NETWORK
• DETERMINE TIME AND RESOURCE REQUIREMENT OF ACTIVITIES
• TIME ANALYSE THE NETWORK
• RESOURCE AND COST ANALYSIS
PROJECT PLANNING TECHNIQUES
• TIME TAKEN BY AN ACTIVITY IS REPRESENTED BY A HORIZONTAL LINE, THE LENGTH
OF THE LINE BEING PROPORTIONAL TO THE TIME DURATION OF THE ACTIVITY.
• IN ORDER THAT SEVERAL ACTIVITIES CAN BE REPRESENTED ON THE SAME CHART, A
FRAMEWORK OR RULING IS SETUP, GIVING TIME FLOWING FROM LEFT TO RIGHT,
THE ACTIVITIES BEING LISTED FROM TOP TO BOTTOM.
• THE BAR CHARTS CAN BE USED BOTH FOR DEPICTING THE PLANS AS WELL AS THE
PROGRESS OF ACTIVITIES.
BAR CHARTS (GANTT CHARTS)
• THE BAR CHARTS DO NOT
DEPICT THE PRECEDENCE
RELATIONSHIP BETWEEN
ACTIVITIES.
BAR CHARTS (GANTT CHARTS)
PROJECT (WORK) BREAKDOWN STRUCTURE
• COMPONENT/PRODUCT BREAKDOWN STRUCTURE
• ACTIVITY BREAKDOWN
• THE WORK BREAKDOWN STRUCTURE
NETWORK TECHNIQUES
• THE TECHNIQUES CRITICAL PATH METHOD (CPM) AND PROGRAMME EVALUATION,
AND REVIEW TECHNIQUE (PERT), WHICH ARE MORE OR LESS IDENTICAL, ARE
COMMONLY KNOWN BY THE NAME OF NETWORK TECHNIQUE.
• THE ONLY DIFFERENCE BEING, THAT CPM USES DETERMINISTIC TIME ESTIMATES
WHILE PERT USES PROBABLE TIME ESTIMATES.
ACTIVITY-ON-ARROW NETWORK
• TWO FUNDAMENTAL RULES THAT DETERMINE THE PRECEDENCE RELATIONSHIPS
INDICATED BY THE NETWORK ARE AS FOLLOWS:
A. AN ACTIVITY CAN BEGIN ONLY AFTER ITS PRECEDING EVENT HAS BEEN ACHIEVED.
B. AN EVENT IS SAID TO HAVE BEEN ACHIEVED ONLY AFTER ALL THE ACTIVITIES LEADING
INTO THE EVENT HAVE BEEN COMPLETED.
DUMMY ACTIVITIES
• DUMMY ACTIVITIES IN NETWORKS ARE NECESSARY TO INDICATE THE CORRECT
PRECEDENCE RELATIONSHIP, THOUGH THE DUMMY ACTIVITIES DO NOT EXIST IN THE
PHYSICAL PROCESS.
• FOR EXAMPLE IN THE NETWORK SHOWN BELOW ACTIVITY 5-7 IS A DUMMY ACTIVITY.
DANGLING ACTIVITY
• AN ACTIVITY IN THE NETWORK WHICH IS STANDING
OUT AND HAS NO SUCCESSOR ACTIVITIES.
• ITS RELATIONSHIP TO THE PROJECT COMPLETION IS
NOT CLEAR.
CYCLE IN NETWORK
• REPRESENTS A PHYSICAL INCONSISTENCY.
• ALLACTIVITY ARROWS ARE DRAWN FROM LEFT TO RIGHT.
• EVENTS ARE NUMBERED IN SUCH A WAY THAT EVERY ACTIVITY HAS A HIGHER
SUCCEEDING EVENT NUMBER THAN ITS PRECEDING EVENT NUMBER.
• THE PROJECT IS IDENTIFIED BY A UNIQUE STARTING EVENT AND A UNIQUE ENDING
EVENT OF THE PROJECT.
• ALL OTHER EVENTS IN THE PROJECT HAVE AT LEAST ONE ACTIVITY LEADING INTO IT
AND AT LEAST ONE ACTIVITY STARTING FROM IT.
DANGLING ACTIVITIES AND CYCLES IN NETWORKS CAN BE AVOIDED BY FOLLOWING
SOME SIMPLE CONVENTIONS AS:
PRECEDENCE NETWORKS
• ALSO KNOWN AS ACTIVITY-ON-NODE NETWORKS.
• THE BASIC DIFFERENCE BETWEEN THIS AND THE ACTIVITY-ON-ARROW
REPRESENTATION IS THAT HERE THE ACTIVITIES ARE REPRESENTED BY THE NODES,
AND THE DEPENDENCIES BY ARROWS.
TIME ESTIMATES
• IN ORDER TO PLAN THE SCHEDULE OF ACTIVITIES, IT IS NECESSARY TO ESTIMATE THE TIME
DURATION OF EACH ACTIVITY.
• THE INITIAL TIME ESTIMATE OF AN ACTIVITY IS CALLED THE ‘NORMAL EXPECTED DURATION’.
• THE TERM ‘NORMAL’ IN THIS CONTEXT MEANS THE NORMAL LEVEL OF RESOURCES AND
TECHNOLOGY WHICH THE ORGANIZATION WOULD USE HAD THE ACTIVITY BEEN EXECUTED IN
ISOLATION WITH NO CLASH OF RESOURCES WITH ANY OTHER ACTIVITY.
• IN THE PRECEDENCE NETWORKS, THE ACTIVITY DURATION IS USUALLY INDICATED IN THE LEFT
BOTTOM CORNER OF THE ACTIVITY NODE.
• IN PRECEDENCE NETWORKS, THE DEPENDENCIES MAY BE DEFINED AS START-TO-START
DEPENDENCIES AND THE DEPENDENCY TIME MAY INDICATE THE AMOUNT OF TIME THAT MUST
ELAPSE AFTER THE START OF PREDECESSOR ACTIVITY BEFORE THE START OF THE SUCCESSOR
ACTIVITY.
• THIS DEPENDENCY TIME MAY BE DIFFERENT FROM THE DURATION OF THE PREDECESSOR ACTIVITY
AND IS INDICATED AS A SUBSCRIPT TO THE DEPENDENCYARROW.
MILESTONES IN PROJECT
• A MILESTONE MAY BE THE COMPLETION OF A PHASE OR A SIGNIFICANT STAGE IN THE
PHASE OF THE PROJECT.
• REPRESENT THE COMPLETION OF A NUMBER OF ACTIVITIES LEADING INTO A
SIGNIFICANT EVENT.
• THE EVENT REPRESENTING THE MILESTONE IN AN ACTIVITY-ON-ARROW NETWORK IS
CALLED A ‘MILESTONE EVENT’.
• A SQUARE INSTEAD OF A CIRCLE MAY BE USED.
TIME ANALYSIS
THE TIME ANALYSIS IS CARRIED OUT IN TWO STAGES :
• THE FORWARD PASS
• THE BACKWARD PASS
The following notations are used:
• tij, = Normal expected duration of activity ‘ij’ (Activity with preceding event ‘i’ and succeeding event ‘j’);
• T E(n) =Earliest time of event ‘n’; • T L(n) = Latest allowable time of event ‘n’;
• Sln= Slack time of event ‘n’; • EST ij = Early start time of activity ‘i-j’;
• EFTij = Early finish time of activity ‘i-j’; • LSTij = Latest start time of activity ‘i-j’;
• LFTij = Latest finish time of activity ‘i-j’; • Flij = Total float of activity ‘i-j’;
• FFij = Free float of activity ‘i-j’.
A). FORWARD PASS
• THIS INVOLVES THE FORWARD TRAVERSAL OF THE NETWORK FROM THE PROJECT
STARTING EVENT TO THE PROJECT ENDING EVENT.
• DURING THIS PASS, THE EARLIEST START AND FINISH TIMES OF ACTIVITIES, EARLIEST
TIMES OF EVENTS AND THE EARLIEST COMPLETION TIME OF THE PROJECT ARE
WORKED OUT.
B). BACKWARD PASS
• THIS INVOLVES THE BACKWARD TRAVERSAL OF THE PROJECT FROM THE PROJECT
ENDING EVENT TO THE PROJECT STARTING EVENT.
• DURING THIS PASS, THE LATEST STARTING AND FINISH TIMES OF ACTIVITIES, THE
LATEST ALLOWABLE TIME OF EVENTS, EVENT SLACKS AND ACTIVITY FLOATS ARE
WORKED OUT, AND THE CRITICALACTIVITIES ARE IDENTIFIED.
CRITICAL PATH, SLACK AND FLOAT
• EVENT TIME CHARACTERISTICS - THIS DIFFERENCE BETWEEN THE LATEST
ALLOWABLE TIME AND THE EARLIEST TIME OF AN EVENT IS CALLED THE EVENT
SLACK.
• ACTIVITY TIME CHARACTERISTICS - EARLIEST START TIME OF AN ACTIVITY IS THE
EARLIEST TIME ITS PRECEDING EVENT IS ACHIEVED. EARLIEST FINISH TIME OF AN
ACTIVITY IS GIVEN BY ADDING ITS DURATION TO ITS EARLIEST START TIME. SO, THE
EARLIEST START AND FINISH TIMES OF AN ACTIVITY ARE RELATED TO ITS PRECEDING
EVENT:
ESTij= TE(i) ,
EFTij = ESTii + tii = TE(i) + tii
• SIMILARLY,
LFTij = TL(j),
LSTij = LFTij - tij = TL(j) - tij
• ACTIVITY FLOATS - THE DIFFERENCE BETWEEN THE EARLIEST AND THE LATEST TIMES
OF AN ACTIVITY IS CALLED ‘ACTIVITY FLOAT’, THAT IS,
• Flij = LSTij - ESTij = LFTij - EFTij = TL(j) – TE(i) – tij
• CRITICAL ACTIVITIES, CRITICAL PATH - THE ACTIVITIES WITH ZERO TOTAL FLOAT (OR
IN GENERAL, WITH MINIMUM TOTAL FLOAT IF THE PROJECT TARGET DATE IS
DIFFERENT FROM ITS EARLIEST ACHIEVEMENT DATE) ARE CALLED THE CRITICAL
ACTIVITIES.
NETWORK ANALYSIS
AND BAR CHART
• VERY USEFUL TOOL FOR THE
REPRESENTATION AND ANALYSIS OF
PRECEDENCE RELATIONSHIP,
• BAR CHART PRESENTS A MORE
USEFUL VISUAL REPRESENTATION OF
THE PROJECT SCHEDULE.
SQUARED NETWORK
• SQUARED NETWORK IS A METHOD OF TRANSLATING AN ACTIVITY-ON-ARROW
NETWORK DIAGRAM INTO A BAR CHART.
EACH ACTIVITY WILL THEN EITHER:
• ‘CONTINUE’AS A SINGLE ACTIVITY;
• ‘BURST’ INTO TWO OR MORE ACTIVITIES;
• ‘MERGE’ INTO AN EVENT WITH ONE OR MORE OTHER ACTIVITIES.
CHECKLISTS
• CHECKLISTS CAN BE USED FOR SEVERAL PURPOSES AND IN SEVERAL WAYS IN
COMPUTER PROJECT PLANNING AND CONTROL.
TYPES OF CHECKLISTS:
• TASK LISTS
• DOCUMENT LISTS
• RESPONSIBILITY LISTS
SECTION 3
REVIEW PROCEDURES FOR PROJECT
COORDINATION AND CONTROL
NEED AND SCOPE OF PROJECT REVIEW
• FOR A COMPLEX PROJECT, A SCIENTIFIC REVIEW PROCEDURE IS REQUIRED.
• THE PROJECT REVIEW PROCEDURE SHOULD HAVE INBUILT MECHANISM FOR CHECKING
THE QUALITY OF VARIOUS SYSTEMS, SUB-SYSTEMS.
• FOR A SMALLER PROJECT, THE REVIEW CYCLE CAN BE SET ON DEMAND AT THE INITIAL
PLANNING STAGE.
• FOR A LARGER PROJECT, A COMPREHENSIVE SYSTEM OF PROJECT COORDINATION AND
PROJECT CONTROL IS TO BE SET UP.
• IN THE DEVELOPMENT PHASE, THE REVIEW SHOULD INCORPORATE APPOINTMENT OF
KEY TEAM MEMBERS, DEFINING THE SCOPE, ESTABLISHMENT OF MASTER PLAN, ETC.
• FOR THE IMPLEMENTATION PHASE, REVIEW SHOULD COVER SETTING UP OF
ORGANIZATIONAL AND COMMUNICATION CHANNELS, IDENTIFICATION OF TEAMS,
APPOINTMENT OF TEAM MEMBERS, ETC.
• WHILE NEARING COMPLETION OF THE PROJECT, THE PROCEDURES RELATING TO THE
REVIEW OF THE DESCRIPTION OF THE FINAL PRODUCT, SETTLEMENT OF FINAL
ACCOUNTS, DOCUMENTATION OF RESULTS ETC.
PROJECT REVIEW CYCLE
REVIEW PROCEDURE
• PROJECT REVIEW PROCEDURE REQUIRES INVOLVEMENT OF SENIOR MANAGEMENT
TO RATIFY PROJECT MANAGEMENT DECISIONS, IMPLEMENTATION BY PROJECT
TEAMS AND PROJECT ORGANIZATION FOR PREPARATION OF PLANS AND
ESTABLISHMENT OF UPDATION MECHANISM, ANALYSIS AND MONITORING OF THE
PROJECT BY PROJECT ORGANIZATION.
USE OF NETWORKS FOR PROJECT CONTROL
• NETWORK PROVIDES A VALUABLE DATA FOR THE PROJECT IN ITS ENTIRETY.
• THE NETWORK ALSO PROVIDES A MECHANISM-FOR EVALUATING THE PERFORMANCE,
A SCHEDULE OF ACTIVITIES, RESOURCE STATUS AND VARIOUS COST ASPECTS
CONCERNING VARIOUS ACTIVITIES INDIVIDUALLY AND FOR VARIOUS WORK
PACKAGES COLLECTIVELYAND THE PROJECT AS A WHOLE.
PERIODIC RE-ASSESSMENT OF THE PROJECT BECOMES NECESSARY TO BRING BACK THE
PROJECT TO ITS NORMAL COURSE IF ANY DEVIATION IS ENCOUNTERED.
PROJECT MONITORING, ANALYSIS AND UPDATION
A. PROJECT MONITORING
• SOURCES OF DATA
✓ GENERAL DESCRIPTION OF THE PROJECT INCLUDING THE OBJECTIVES;
✓ SCOPE OF SERVICES REQUIRED AT THE VARIOUS LEVELS OF THE PROJECT;
✓ PROJECT ORGANIZATION INCLUDING THAT OF CLIENTS, CONSULTANTS AND OTHER
PARTICIPATING DIVISIONS AND THE DEFINED INTER-RELATIONSHIPS AMONGST THEM;
✓ DIVISION OF RESPONSIBILITY BETWEEN THE VARIOUS PARTICIPANTS;
✓ PROJECT CONTROL SYSTEM AS DESCRIBED AT THE PLANNING STAGE;
✓ PROJECT COMPLETION DATES INCLUDING THAT OF MILESTONES, ASSEMBLIES, SUB -
ASSEMBLIES AND VARIOUS OTHER COMPONENTS;
✓ COMMUNICATION CHANNELS AS DEFINED IN THE PLAN, FOR EXAMPLE, GENERAL
CORRESPONDENCE, ENGINEERING AND MANUFACTURING INFORMATION, CORRESPONDENCE
WITH THE VENDORS AND SUBCONTRACTORS, CORRESPONDENCE WITH THE CLIENTS AND
CONSULTANTS AND OTHER PROJECT DOCUMENTATION;
✓ APPROVED DOCUMENTS AND THEIR DISTRIBUTION AMONG PROJECT PARTICIPANTS AND
OTHER OWNERSHIP DOCUMENTS;
✓ PROJECT REPORTS COMPRISING OF PERIODICAL PROGRESS REPORT, RESOURCE STATUS
REPORT, COST STATUS REPORT, ETC;
✓ CHANGE ORDER PROCEDURE INCLUDING DEVIATIONS;
✓ PROCUREMENT PROCEDURE FOR EQUIPMENTS AND MATERIAL, TAX DATA, CUSTOMS
CLEARANCE PROCEDURES, MANAGEMENT OF FOREIGN EXCHANGE AND ASSOCIATED
QUALITY CHECKS AND EXPEDITING PROCEDURES;
✓ TENDERING PROCEDURE AND DOCUMENTATION, FOR SITE ACTIVITIES AND COORDINATION
PROCEDURES;
✓ BILLING AND ACCOUNTING PROCEDURES.
• METHODS OF DATA COLLECTION
✓ DATA ON TIME ASPECTS
✓ DATA ON RESOURCE ASPECTS
✓ DATA ON COST ASPECTS
• SCOPE, CHARACTERISTICS AND TECHNIQUES
✓ A MULTI-LEVEL SYSTEM OF PROJECT MONITORING IS NEEDED FOR ESTABLISHING
ANY MEANINGFUL REVIEW PROCEDURE. FOR A TYPICAL LARGE PROJECT WITH
THREE LEVELS OF PLANNING,
✓ LEVEL-I WILL DEAL WITH THE PROJECT IN ITS ENTIRETY BUT THE LEVEL OF
CONTROL WILLABE SUCH AS TO BE EXERCISED BY THE TOP MANAGEMENT.
✓ AT LEVEL-II, THE PROJECT IS BROKEN DOWN INTO THE LEVELS OF PARTICIPATING
DIVISIONS OR THE FUNCTIONAL LEVEL.
✓ LEVEL-III IS THE WORKING LEVEL DETAIL.
B). PROJECT UPDATION
• LEVEL-I NETWORK WHICH DEALS WITH THE CORPORATE ACTIVITIES MUST BE
EXPLODED INTO LEVEL-II
• LEVEL-II COVERING ALL PARTICIPATING DIVISIONS. THESE ARE FURTHER EXPLODED
INTO LEVEL-III
• LEVEL-III DEPICTING VARIOUS TASKS BEING PERFORMED. IN THE MULTI-LEVEL
PROJECT ENVIRONMENT, ANALYSIS BY THE COMPUTERS BECOMES ESSENTIAL.
C). PROJECT ANALYSIS
AT THE PLANNING STAGE,
• LEVEL - I IS ENVISAGED TO THE CORPORATE LEVEL NETWORK,
• LEVEL - II IS DIVISIONAL LEVEL
• LEVEL - III IS WORKING LEVEL DOCUMENT.
THE COST OF WORK PERFORMED SHOULD BE COLLECTED ON THE FOLLOWING THREE ASPECTS:
• BUDGETED COST OF WORK PERFORMED,
• PLANNED COST OF WORK PERFORMED, AND
• ACTUAL COST OF WORK PERFORMED.
PROJECT MANAGEMENT DECISIONS AND IMPLEMENTATION
THE INFORMATION GENERATED AFTER EACH CYCLE OF PROJECT REVIEW MAY BE DIVIDED INTO
THE FOLLOWING:
• FOR INFORMATION
• FOR DECISION MAKING
• FOR ACTION
SECTION 4
REPORTING DOCUMENTATION
AND PROCEDURES
TABLES ON TIME SCHEDULES AND ACTUALS / ANTICIPATIONS
• ACTIVITY LIST SHOWING SCHEDULE AND ACTUAL / ANTICIPATED TIME AGAINST
EACH ACTIVITY.
• LIST OF CRITICALACTIVITIES
• LIST OF KEY/MILESTONE EVENTS SHOWING EARLIEST/ LATEST OCCURRENCE,
SCHEDULE OCCURRENCE, ACTUAL/ ANTICIPATED COMPLETION TIME
• LIST OF EVENTS FALLING ON THE CRITICAL PATH SHOWING EARLIEST/LATEST
OCCURRENCE, SCHEDULE OCCURRENCE, ACTUAL/ANTICIPATED COMPLETION TIME
• EXCEPTION REPORT TO HIGHLIGHT SIGNIFICANT VARIATIONS.
FLOAT ORDER LIST
• A FLOAT ORDER LIST DEPICTING ACTIVITIES, IN THE ASCENDING ORDER OF THE
TOTAL FLOAT AVAILABLE SHOULD BE PREPARED.
TABULAR PRESENTATION
TABLES ON RESOURCES
• REPORTS RELATING TO MATERIALS, MAN-POWER, MACHINES AND EQUIPMENTS
SHOULD REFLECT THE UTILIZATION OF THESE RESOURCES AGAINST THE PLAN.
• REPORTS PERTAINING TO RESOURCES REQUIRED AND AVAILABLE SHOULD ALSO BE
PREPARED LINKING WITH PROJECT SCHEDULES.
• DETAILED REPORTS ON MATERIAL REQUIREMENTS CAN BE PREPARED ON THE BASIS
OF WORK PACKAGES AND ACTIVITIES.
• SEPARATE REPORT FOR DEPLOYMENT AND UTILIZATION OF EQUIPMENTS ON
CRITICALACTIVITIES CAN ALSO BE GENERATED.
TABLES ON COST
• THE BASIC UNIT OF COSTING SHOULD BE WORK PACKAGE.
• EXCEPTION REPORTS SHOULD BE MADE FOR VARIANCES BEYOND SPECIFIED
TOLERANCE LIMITS AS AND WHEN REQUIRED.
GRAPHICAL PRESENTATION
• SQUARED NETWORK
• COMMISSIONING SCHEDULE NETWORK
• BAR CHART
• MILESTONE BAR CHART
• S-CURVES AND HISTOGRAMS
• MANUAL LOADING AND STATUS CHARTS
OF VARIOUS RESOURCES CAN ALSO BE
PREPARED.
GRAPHICAL PRESENTATION SHOULD BE SIMPLE AND SELF CONTAINED. THE GRAPHICAL
PRESENTATION SUGGESTED ARE:
S-CURVES AND HISTOGRAMS
NARRATIVE PRESENTATION
• THE NARRATIVE PORTION OF THE REPORT, EXPRESSED IN
WORDS, SHOULD BE USED TO HIGHLIGHT:
• SPECIAL PROBLEMS,
• EXCEPTIONAL SITUATIONS,
• NEW DEVELOPMENTS AND CHANGES,
• CORRECTIVE ACTIONS TAKEN AND REQUIRED, AND
• SUGGESTIONS FOR FUTURE.
THESE REPORTS SHOULD BE SIMPLE AND CONCISE.
SECTION 5
PROJECT TERMINATION / CLOSURE
PROJECT TERMINATION / CLOSURE
PROJECT CLOSE-OUT PLAN AND SCHEDULE WILL BE UPON:
• FROZEN PROJECT OBJECTIVES, MEANS-FOR ACHIEVING THEM AND AUTHORIZATION
FOR COMMENCEMENT OF WORK.
• CHANGES IN THE PROJECT PLAN.
• PROJECT PERFORMANCE VIS-A-VIS THE PROJECT OBJECTIVES.
• UPDATED RESULTS AND MODIFIED PLANS.
TYPES OF PROJECT TERMINATION / CLOSURE
• PROJECT CLOSE-OUT OR NORMAL PROJECT TERMINATION
• PREMATURE PROJECT TERMINATION
RESPONSIBILITY OF PROJECT MANAGER
• MAKING ALL NECESSARY DECISIONS FOR SUGGESTING ALTERNATIVE PLANS FOR
CONTINUATION OR FOR TERMINATION OF THE PROJECT.
• PREPARATION OF PROJECT CLOSE-OUT PLAN AND SCHEDULE.
• ACTING AS FOCAL POINT FOR COMMUNICATION BETWEEN PROJECT AUTHORITIES
AND THE PROJECT/SUB-PROJECT GROUPS
• TAKING STOCK AND RECORDING THE ACCOMPLISHMENT OF ALL WORK PACKAGES
• DOCUMENTING RESULTS IN TERMS OF ACHIEVEMENT OF PROJECT OBJECTIVES AND
PROJECT CLOSURE/TERMINATION PROCEDURES.
• HANDING OVER ‘OPERATION AND MAINTENANCE PROCEDURES MANUALS’, AS-BUILT-
DRAWINGS, RECORDS OF DEVIATIONS, ETC.
• ORGANIZING FOR THE COMPLETION AND CLOSURE OF THE PROJECT MANAGEMENT
ACTIVITIES
STEPS FOR PROJECT CLOSURE / TERMINATION
A). PROJECT CLOSE-OUT PLAN AND SCHEDULE
• PREPARATION OF A COMPLETE RECORD OF ANY CHANGES MADE IN THE PROJECT
OBJECTIVES.
• PREPARATION OF RECORD OF TECHNICAL PERFORMANCE.
• ESTABLISHING PROCEDURES FOR START-UP OPERATIONS, CHECK-OUT DETAILS OF
ALL SYSTEMS/EQUIPMENTS AND PROCEDURES FOR TOTAL OPERATIONS.
• PREPARATION OF RECORD OF IMPLEMENTATION OF VARIOUS SYSTEMS
• PREPARATION OF RECORD OF FORMULATION AND MAINTENANCE OF QUALITY
STANDARDS FOR WORK / SYSTEMS.
• PREPARATION OF RECORD OF SPECIALACTIONS TAKEN TO COPE WITH CHANGES,
• PREPARATION OF RECORD OF SPECIAL TOOLS AND TACKLES USED, METHODS AND
PROCEDURE ADOPTED.
B). REASSIGNMENT OF PROJECT STAFF
• REASSIGNMENT OF PROJECT STAFF TO OTHER SIMILAR PROJECTS.
• REASSIGNMENT OF PROJECT STAFF TO OTHER ALLIED AREA PROJECTS.
• REASSIGNMENT OF PROJECT STAFF FOR OPERATIONS AND MAINTENANCE.
• REASSIGNMENT OF PROJECTS STAFF AS CONSULTANT/ TRAINER.
• PREPARATION OF GUIDELINES FOR FUTURE COURSE OF ACTION
• PREPARATION AND EXECUTION OF ALL TERMINALAGREEMENTS
• AFTER THE PROJECT OBJECTIVES ARE FROZEN AND PROJECT SCOPE ALONG WITH
THE CONTRACTUAL OBLIGATION IS AGREED WITH THE PROJECT AUTHORITIES,
PROJECT MANAGER PREPARES THE PLAN WITH WBS, ESTABLISHES THE CONTROL
MECHANISM AND DEFINES PROCEDURES FOR UPDATION.
DIVEST PROJECT RESOURCES
• RESOURCES DRAWN FROM THE COMMON POOL MUST BE RELEASED FOR USE IN
OTHER PROJECTS ONCE THE NEED OF THE CURRENT PROJECT IS MET AS DETAILED IN
THE PROJECT PLAN.
• THE RESOURCES UNIQUE TO THE PROJECT AND NON-CONSUMABLE IN NATURE AS
ALSO LEFT OVER CONSUMABLES.
• OTHER RESOURCES PROVIDED BY PROJECT AUTHORITIES MAY EITHER BE ABSORBED
AS PROJECT PROPERTY.
• FINALIZATION OF TERMS OF REFERENCE FOR SMOOTH OPERATIONS OF THE
SKELETAL STAFF SET UP SPECIALLY FOR WINDING UP OF THE PROJECT.
THE DIVESTING OF PROJECT RESOURCES SHOULD BE DONE IN THE FOLLOWING MANNER:
RECOMMENDATIONS FOR ACTIONS, IF ANY, REQUIRED FOR FUTURE
• PROJECT OBJECTIVES; • PROJECT PLAN; • PROJECT CONTROL;
• PROJECT UPDATION AND REVIEW MECHANISM; PROJECT ORGANIZATION;
• PROJECT STAFF SELECTION, RECRUITMENT, PLACEMENT AND TRAINING;
• EFFICIENCY, EFFICACY AND PROPER USE OF VARIOUS RESOURCES;
• EFFICIENCY, EFFICACY AND PROPER USE OF VARIOUS RESOURCES;
• SYSTEMS DEVELOPED AND IMPLEMENTED FROM START TO FINISH OF THE PROJECT
• PROJECT PROCESS, METHOD AND PROCEDURES FOLLOWED;
• UNIQUE FEATURES OF THE PROJECT AND LEARNINGS;
• TEMPORARY ARRANGEMENTS MADE AND FUTURE PLAN OF ACTION;
• DIFFICULTIES ENCOUNTERED AND PRECAUTIONS TAKEN
• QUALITY/PERFORMANCE/TECHNOLOGY PLANNED VERSUS ACHIEVED;
• SAFETY REQUIREMENTS AND EARLY WARNING SIGNALS
• INTERFACES MANAGED WITH INTERNALAND EXTERNAL ENVIRONMENT / ORGANISATIONS;
• RECOMMENDATIONS FOR CHANGE OF PROCEDURES ETC.
• INSTRUCTIONS FOR ALL SYSTEMS / SUB-SYSTEMS WITH PRECAUTIONS NEEDED.
THE PROJECT MANAGER BASED ON HIS EXPERIENCE WOULD MAKE RECOMMENDATIONS IN AREAS
SUCH AS:
PREPARE A TERMINATION / CLOSURE REPORT
• CONTENTS OF THE REPORT
• HISTORIC RECORDS CONTAINING PROJECT DOCUMENTATION
• A FORMAL ANALYSIS IN THE FORM OF PROJECT REPORT CONTAINING PROJECT DATA
LIKE COSTS, SCHEDULES, TECHNICAL PERFORMANCE, ORIGINAL PLAN.
• A REPORT ON FINANCIAL CLOSING STATING HOW THE FUNDS HAVE BEEN RAISED AND
SPENT WITH TOTAL COMMERCIAL IMPLICATIONS AT THE TIME OF PROJECT CLOSURE.
DOCUMENTATION REGARDING:
• AS-BUILT-DRAWINGS.
• OPERATING PROCEDURES.
• OPERATION AND MAINTENANCE MANUALS.
• GUIDELINES FOR TRAINING OF OPERATION AND MAINTENANCE STAFF.
• POSITION DESCRIPTION, PLACEMENT, AND RECRUITMENT GUIDELINES.
• TRANSFER OF RESPONSIBILITY.
• RELEASE OF RESOURCES.
• PROJECT ACCEPTANCE AND OPERATIONS REPORT WITH SYSTEMS CHECK-OUT AND
START-UP RESULTS (INDIVIDUALAND COLLECTIVE).
• QUALITY/PERFORMANCE/TECHNOLOGY DOCUMENTS
• DEVIATIONS AND REMEDIALACTION REPORT
• SPECIAL FEATURES

Contenu connexe

Tendances

Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & managementManit Agarwal
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Managementsrinivas2036
 
Construction project management
Construction project managementConstruction project management
Construction project managementSenthil Kannan
 
Construction Project management
Construction Project management Construction Project management
Construction Project management Anupama holla
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction ManagementShahin MB
 
Project management in construction
Project management in constructionProject management in construction
Project management in constructionNAVNEET KUMAR JHA
 
Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...A Makwana
 
Quality control IN CONSTRUCTION
Quality control IN CONSTRUCTIONQuality control IN CONSTRUCTION
Quality control IN CONSTRUCTIONSANJEEV Wazir
 
Construction phases
Construction phasesConstruction phases
Construction phasesMeesum Zaidi
 
5 principles of construction project management
5 principles of construction project management5 principles of construction project management
5 principles of construction project managementreachfirst01
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Schedulingakashpadole
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & ScheduleVîñõđ Kůmåř
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in constructionMahSobeh
 

Tendances (20)

Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
Tender
TenderTender
Tender
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
 
Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...
 
Quality control IN CONSTRUCTION
Quality control IN CONSTRUCTIONQuality control IN CONSTRUCTION
Quality control IN CONSTRUCTION
 
Construction phases
Construction phasesConstruction phases
Construction phases
 
5 principles of construction project management
5 principles of construction project management5 principles of construction project management
5 principles of construction project management
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Construction contract
Construction contract Construction contract
Construction contract
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in construction
 
Bills of quantities
Bills of quantitiesBills of quantities
Bills of quantities
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 

Similaire à Construction Project Management

Project organisation and erp implementation method
Project organisation and erp implementation methodProject organisation and erp implementation method
Project organisation and erp implementation methodGaurav Kumar
 
Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project kaishwarya3
 
Pmp – pmbok 5th edition chapter4 project integration management final
Pmp – pmbok 5th edition chapter4 project integration management finalPmp – pmbok 5th edition chapter4 project integration management final
Pmp – pmbok 5th edition chapter4 project integration management finalYudha Pratama, PMP
 
Pmp – pmbok 5th edition develop project charter
Pmp – pmbok 5th edition develop project charterPmp – pmbok 5th edition develop project charter
Pmp – pmbok 5th edition develop project charterYudha Pratama, PMP
 
Rational unified process
Rational unified processRational unified process
Rational unified processnaveed428
 
Modern management techniques
Modern management techniquesModern management techniques
Modern management techniquesAbhishek Agarwal
 
Heartbeats & Bloodstreams.pptx
Heartbeats & Bloodstreams.pptxHeartbeats & Bloodstreams.pptx
Heartbeats & Bloodstreams.pptxmalikshanii458
 
Management Control of Projects
Management Control of ProjectsManagement Control of Projects
Management Control of ProjectsE P John
 
Pmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementPmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementYudha Pratama, PMP
 
IT Strategic Plan Template
IT Strategic Plan TemplateIT Strategic Plan Template
IT Strategic Plan TemplateSam Musa
 
Business Case Strategies For Integrating Comissioning With Construction And P...
Business Case Strategies For Integrating Comissioning With Construction And P...Business Case Strategies For Integrating Comissioning With Construction And P...
Business Case Strategies For Integrating Comissioning With Construction And P...mike benedetto
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project ManagementSlav Karaslavov
 
CV_Alana Miles-2015-
CV_Alana Miles-2015-CV_Alana Miles-2015-
CV_Alana Miles-2015-Alana Miles
 
04 project integration management
04  project integration management04  project integration management
04 project integration managementAla Ibrahim
 

Similaire à Construction Project Management (20)

Project organisation and erp implementation method
Project organisation and erp implementation methodProject organisation and erp implementation method
Project organisation and erp implementation method
 
Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project
 
Pmp – pmbok 5th edition chapter4 project integration management final
Pmp – pmbok 5th edition chapter4 project integration management finalPmp – pmbok 5th edition chapter4 project integration management final
Pmp – pmbok 5th edition chapter4 project integration management final
 
Pmp – pmbok 5th edition develop project charter
Pmp – pmbok 5th edition develop project charterPmp – pmbok 5th edition develop project charter
Pmp – pmbok 5th edition develop project charter
 
Salvador Velasco Téllez - CIO
Salvador Velasco Téllez - CIOSalvador Velasco Téllez - CIO
Salvador Velasco Téllez - CIO
 
Rational unified process
Rational unified processRational unified process
Rational unified process
 
Modern management techniques
Modern management techniquesModern management techniques
Modern management techniques
 
Heartbeats & Bloodstreams.pptx
Heartbeats & Bloodstreams.pptxHeartbeats & Bloodstreams.pptx
Heartbeats & Bloodstreams.pptx
 
Project management
Project managementProject management
Project management
 
Management Control of Projects
Management Control of ProjectsManagement Control of Projects
Management Control of Projects
 
Pmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementPmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost management
 
IT Strategic Plan Template
IT Strategic Plan TemplateIT Strategic Plan Template
IT Strategic Plan Template
 
PM UNIT 1.pptx
PM UNIT 1.pptxPM UNIT 1.pptx
PM UNIT 1.pptx
 
Business Case Strategies For Integrating Comissioning With Construction And P...
Business Case Strategies For Integrating Comissioning With Construction And P...Business Case Strategies For Integrating Comissioning With Construction And P...
Business Case Strategies For Integrating Comissioning With Construction And P...
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Proj Mgmt.ppt
Proj Mgmt.pptProj Mgmt.ppt
Proj Mgmt.ppt
 
CV_Alana Miles-2015-
CV_Alana Miles-2015-CV_Alana Miles-2015-
CV_Alana Miles-2015-
 
04 project integration management
04  project integration management04  project integration management
04 project integration management
 
PROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENT
PROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENTPROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENT
PROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENT
 
project influnceing
project influnceingproject influnceing
project influnceing
 

Plus de Rajat Nainwal

Wildlife presentation
Wildlife presentationWildlife presentation
Wildlife presentationRajat Nainwal
 
Vernacular Architecture
Vernacular Architecture Vernacular Architecture
Vernacular Architecture Rajat Nainwal
 
Timber, its use and conections
Timber, its use and conectionsTimber, its use and conections
Timber, its use and conectionsRajat Nainwal
 
Sustainable water supply
Sustainable water supplySustainable water supply
Sustainable water supplyRajat Nainwal
 
The international centre goa
The international centre goaThe international centre goa
The international centre goaRajat Nainwal
 
Sustainable transport
Sustainable transportSustainable transport
Sustainable transportRajat Nainwal
 
Sustainable energy and power
Sustainable energy and powerSustainable energy and power
Sustainable energy and powerRajat Nainwal
 
Storm water management and its techniques
Storm water management and its techniquesStorm water management and its techniques
Storm water management and its techniquesRajat Nainwal
 
St. peter's basillica
St. peter's basillicaSt. peter's basillica
St. peter's basillicaRajat Nainwal
 
Solid wast managment
Solid wast managmentSolid wast managment
Solid wast managmentRajat Nainwal
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteRajat Nainwal
 
Presentation on developmental plan
Presentation on developmental  planPresentation on developmental  plan
Presentation on developmental planRajat Nainwal
 

Plus de Rajat Nainwal (20)

Wildlife presentation
Wildlife presentationWildlife presentation
Wildlife presentation
 
Vernacular Architecture
Vernacular Architecture Vernacular Architecture
Vernacular Architecture
 
Types of windows
Types of windowsTypes of windows
Types of windows
 
Types of steel
Types of steelTypes of steel
Types of steel
 
Timber, its use and conections
Timber, its use and conectionsTimber, its use and conections
Timber, its use and conections
 
Sustainable water supply
Sustainable water supplySustainable water supply
Sustainable water supply
 
The international centre goa
The international centre goaThe international centre goa
The international centre goa
 
Technosphere
TechnosphereTechnosphere
Technosphere
 
Sustainable transport
Sustainable transportSustainable transport
Sustainable transport
 
Sustainable housing
Sustainable housingSustainable housing
Sustainable housing
 
Sustainable energy and power
Sustainable energy and powerSustainable energy and power
Sustainable energy and power
 
Supernova noida
Supernova   noidaSupernova   noida
Supernova noida
 
Storm water management and its techniques
Storm water management and its techniquesStorm water management and its techniques
Storm water management and its techniques
 
St. peter's basillica
St. peter's basillicaSt. peter's basillica
St. peter's basillica
 
Steel manufacturing
Steel manufacturingSteel manufacturing
Steel manufacturing
 
Steel and its types
Steel and its typesSteel and its types
Steel and its types
 
Solid wast managment
Solid wast managmentSolid wast managment
Solid wast managment
 
Shear walls
Shear wallsShear walls
Shear walls
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Presentation on developmental plan
Presentation on developmental  planPresentation on developmental  plan
Presentation on developmental plan
 

Dernier

Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Association for Project Management
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin ClassesCeline George
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the ClassroomPooky Knightsmith
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and ModificationsMJDuyan
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...pradhanghanshyam7136
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsMebane Rash
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdfVishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdfssuserdda66b
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...ZurliaSoop
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...Nguyen Thanh Tu Collection
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentationcamerronhm
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxRamakrishna Reddy Bijjam
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfPoh-Sun Goh
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxheathfieldcps1
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Dyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxDyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxcallscotland1987
 

Dernier (20)

Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the Classroom
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdfVishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Dyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxDyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptx
 

Construction Project Management

  • 1. PROJECT MANAGEMENT IS : 14580 – PART 1 ▪ MANAGEMENT ▪ PLANNING ▪ REVIEW ▪ REPORTlNG AND ▪ TERMINATION PROCEDURES
  • 2. BROAD CONTENTS ▪ ORGANISATION AND MANAGEMENT OF PROJECTS. ▪ PLANNING THE PROJECT. ▪ REVIEW PROCEDURES FOR PROJECT COORDINATION AND CONTROL. ▪ REPORTING DOCUMENTATION AND PROCEDURES. ▪ PROJECT TERMINATION/ CLOSURE.
  • 4. PROJECT CYCLE • FORMULATION • IMPLEMENTATION • COMMISSIONING PROJECT TYPES • TIME SCALE • COST • PURPOSE • DIRECT PRODUCTION OF GOODS • SECTORS OF THE ECONOMY – AGICULTURE, INDUSTRY, MINING? • OWNERSHIP – PUBLIC, PRIVATE JOINT SECTORS? •SPECIFIC PURPOSE
  • 5. PROJECT ORGANISATIONS • INNOVATIVE APPROACHES TO OVERCOME PROBLEMS • SOUND AND EXPERIENCE BASED SOLUTIONS • IMPLEMENTATION • COMMISSIONING THE PROJECT ORGANIZATION STRUCTURE COULD BE OF 3 TYPES: • FUNCTIONAL ORGANIZATION STRUCTURE • MATRIX ORGANIZATION STRUCTURE • PROJECTISED ORGANIZATION STRUCTURE
  • 6. ORGANISATION CHART FOR A LARGE PROJECT DRIVEN CONSTRUCTION COMPANY
  • 7. • FIRST OF ALL DEFINE AN IDEAL ORGANIZATION SO THAT WEAKNESSES OF EXISTING ORGANIZATION COULD BE FORESEEN. • THE PROJECT ORGANIZATION SHOULD BE ADAPTABLE TO CHANGES AS THE PROJECT MOVES FROM PHASE TO PHASE. • THE NUMBER/TYPE OF PERSONNELAND THEIR PRIME FUNCTION, AUTHORITY AND RESPONSIBILITY REQUIRED SHOULD BE DEFINED. • THE CURRENT ORGANIZATIONAL CAPABILITIES AND THE NEED TO EMPLOY CONSULTANTS SHOULD BE ASSESSED. • THE MOTIVATION AND COMMITMENT OF PROJECT GROUPS SHOULD BE ENSURED. FACTORS TO BE TAKEN INTO ACCOUNT FOR DEVELOPING A PROJECT ORGANIZATION:
  • 8. PROJECT MANAGEMENT PRINCIPLES FOR PROJECT MANAGEMENT • FORWARD LOOKING. • MADE AT THE LOWEST FEASIBLE LEVEL CONSISTENT WITH RESPONSIBILITY AND AUTHORITY. • CAREFUL SELECTION OF PROJECT MANAGERS AND PROJECT TEAMS. • THE AUTHORITY SHOULD ALWAYS MATCH WITH PROJECT RESPONSIBILITIES AT ALL LEVELS. THE AIM OF PROJECT MANAGEMENT IS TO SUCCESSFULLY ACHIEVE THE OBJECTIVES OF THE PROJECT BY COMPLETING IT ON SCHEDULE, WITHIN COST AND PERFORMANCE CRITERIA WITH PRESCRIBED HUMAN, PHYSICAL RESOURCE AND OTHER CONSTRAINTS.
  • 9. THE PRINCIPAL ROLE OFA PROJECT MANAGER • TO HELP FORMULATE OBJECTIVES AND POLICIES FOR THE PROJECT AND OPERATIONALISE THEM TO ENSURE THAT THESE ARE ADEQUATELY MET. • TO ENSURE AVAILABILITYAND EFFECTIVE UTILIZATION OF PROJECT RESOURCES. • TO PREPARE AND ENSURE APPROVAL OF ALL PROJECT PLANS. • TO APPROVE ALL OPERATIONAL PLANS AND PROCEDURES AND INFORM PROJECT STAFF OF THEIR DUTIES AND RESPONSIBILITIES. • TO MONITOR AND CONTROL PROGRESS, PERFORMANCE QUALITY AND EXPENDITURE. • TO ENSURE SAFETY STANDARDS AND CONFORMITY TO LEGAL REQUIREMENTS. • TO ENSURE ESTABLISHMENT AND OPERATION OF COMMUNICATION, INFORMATION AND REPORTING SYSTEM. • TO SERVE AS THE PRIME POINT OF CONTACT FOR THE PROJECT.
  • 10. PROJECT MANAGEMENT SHOULD PERFORM THE FOLLOWING FUNCTIONS: • DEFINE THE SCOPE AND WORK CONTENT OF THE PROJECT. • DECIDE HOW TO GET THE PROJECT ACTIVITIES EXECUTED. • ADAPT THE ORGANIZATION AS THE PROJECT PROGRESSES. • DEVELOPA SUITABLE PROJECT ORGANIZATION. • PREPARE IMPLEMENTATION PLANS AND INVOLVE ALL CONCERNED PROJECT PARTICIPANTS ENSURING THAT ALL PROJECT COMPONENTS AND ELEMENTS ARE INTERRELATED, INTEGRATED AND COORDINATED. • DEFINE CONTRACTING STRATEGY AND POLICY, PREPARE THE CONTRACT PLAN AND SPECIFY CONTRACTORS RESPONSIBILITIES. • DEVELOP TIME SCHEDULES, BUDGETS AND IDENTIFY KEY MILESTONES. • DESIGN MONITORING AND CONTROL, INFORMATION AND REPORTING SYSTEMS AND ENSURE THEIR PROPER OPERATION. • DEFINE METHODS AND PROCEDURES TO MANAGE CHANGE FROM ITS INITIAL STAGE TO ITS FINALIZATION. • SPECIFY TRAINING REQUIREMENTS AND MAKE APPROPRIATE PROVISIONS.
  • 11. CONTRACT MANAGEMENT • ITEM RATE CONTRACT • PERCENTAGE RATE CONTRACT • LUMP SUM RATE CONTRACT • COST PLUS CONTRACT STANDARD PROCEDURES SHOULD BE DEVELOPED FOR: • PRE-TENDER PLANNING; • PRE-QUALIFICATION OF AGENCIES AND SUPPLIERS; • INVITATION AND RECEIPT OF TENDERS; • OPENING, EVALUATION AND NEGOTIATION OF TENDERS; • AWARD OF CONTRACT; • RELEASE OF WORK ORDERS, DESIGNS AND DRAWINGS; • MEASUREMENTS AND PAYMENTS; • MODIFICATIONS AND CHANGES IN CONTRACTS; • TERMINATION / CLOSING AND OFF-LOADING CONTRACTS; • MONITORING, REPORTING AND REVIEWING PROGRESS AND PERFORMANCE OF CONTRACTS. TYPES OF CONTRACTS :
  • 12. FAMILIARIZATION AND TRAINING • AFTER THE BASIC PROJECT MANAGEMENT AND CONTROL SYSTEMS HAVE BEEN DEVELOPED AND AGREED, ALL THOSE WHO HAVE TO PARTICIPATE IN THE PROJECT SHOULD BE APPROPRIATELY FAMILIARIZED AND TRAINED TO OPERATE/USE THEM. THIS WOULD HELP IN CREATING TEAM ENVIRONMENT, ESTABLISHING LINES OF COMMUNICATION, BREAKING BARRIERS BETWEEN ORGANIZATIONS AND REDUCING CONFUSION AND MISUNDERSTANDING AS TO WHO DOES WHAT, WHEN AND WHY. • IN ADDITION TO PROJECT SPECIFIC TRAINING, SUPPLEMENTARY EDUCATIONAL COURSES MAY BE ORGANIZED TO PROVIDE BACKGROUND INFORMATION IN THE APPLICATION OF NETWORK BASED TECHNIQUES.
  • 14. PLANNING IS THE PROCESS BY WHICH A MANAGER LOOKS TO THE FUTURE AND DISCOVERS ALTERNATIVE COURSES OF ACTION. A PROJECT PLAN SHOULD GIVE DETAILS ABOUT PRODUCT/WORK (QUANTITY AND QUALITY), TIMESCALE, RESOURCES, COST AND ORGANIZATION; ALSO MONITORING AND CONTROL. IT WILL INVOLVE: • CONSCIOUS AND EXPLICIT AWARENESS OF THE ULTIMATE • CORPORATE GOALS; • ESTABLISHMENT OF PROJECT OBJECTIVES; • ARTICULATION AND EVALUATION OF ALTERNATIVES; • SELECTION OF MOST SUITABLE ALTERNATIVE; AND • IDENTIFICATION OF ACTIVITIES REQUIRED TO ACHIEVE • THE OBJECTIVES.
  • 15. LEVELS OF PLANNING • CORPORATE MANAGEMENT, • PROJECT MANAGEMENT, • OPERATIONAL MANAGEMENT • PROJECT PLAN • STAGE PLAN • DETAILED PLAN • INDIVIDUAL WORK PLAN • EQUIPMENT LOADING PLAN TO CATER TO THE NEEDS OF DIFFERENT PROJECT MANAGEMENT LEVELS, THERE MAY BE HIERARCHY OF PLANS, WHICH MAY CONSIST OF THE FOLLOWING:
  • 16. COMPONENTS OF PROJECT PLANS • DEFINE LOGICAL RELATIONSHIPS AMONGST ACTIVITIES WHICH MAY BE REPRESENTED IN THE FORM OF. AN ACTIVITY NETWORK. • IDENTIFY THE RESOURCES REQUIRED FOR EACH ACTIVITY. • PROVIDE A TIME SCHEDULE OF ACTIVITIES CONSISTENT WITH RESOURCE REQUIREMENTS AND THE TOTAL RESOURCES AVAILABLE TO THE PROJECT. • IDENTIFY THE MILESTONES IN -PROJECTS AND STAGES FOR MAJOR ASSESSMENT AND REVIEW. • IDENTIFY INTERNALAND EXTERNAL DEPENDENCIES ON ACTIVITIES. TECHNICAL / WORK PLANS RESOURCE PLANS • HOW RESOURCES WOULD BE OBTAINED AND ALLOCATED. • THE WORK SCHEDULE FOR EACH INDIVIDUAL/ GROUP RESOURCE. • METHODS OF DISPOSITION OF EXCESS RESOURCES, IF ANY.
  • 17. QUALITY PLANS • AGREEMENT ON QUALITY WITH ALL CONCERNED; • PREVENTION, DETECTION AND RECTIFICATION OF FAULTS; • SETTING APPROPRIATE AND MEASURABLE QUALITY CRITERIA FOR EACH PRODUCT; • ESTABLISHMENT OF SYSTEMS AND PROCEDURES TO ASSESS AND DEMONSTRATE WHETHER QUALITY GOALS HAVE BEEN ACHIEVED; • RESOURCING OF QUALITY CONTROLACTIVITIES. COST AND CASH FLOW PLANS • REQUIRED TO MAKE NECESSARY FINANCIAL PROVISIONS, • THE COST ESTIMATE OF EACH ACTIVITY SHOULD BE WORKED OUT, • THE CASH FLOW PLANS CAN BE DERIVED BY TRANSLATING THE TECHNICAL PLAN INTO FINANCIAL TERMS, • PERFORMANCE BUDGETING IS THE TECHNIQUE USED TO RELATE THE FINANCIAL ASPECTS OF THE PROJECT WITH ITS PHYSICALASPECTS, • ZERO-BASE BUDGETING IS THE TECHNIQUE TO ENSURE COST EFFECTIVENESS OF THE PROJECT AT EVERY STAGE.
  • 18. STEPS IN PROJECT PLANNING • IDENTIFY THE PROJECT OBJECTIVES AND COMPONENTS • IDENTIFY THE ACTIVITIES • IDENTIFY DEPENDENCIES • PRODUCE ACTIVITY NETWORK • DETERMINE TIME AND RESOURCE REQUIREMENT OF ACTIVITIES • TIME ANALYSE THE NETWORK • RESOURCE AND COST ANALYSIS
  • 19. PROJECT PLANNING TECHNIQUES • TIME TAKEN BY AN ACTIVITY IS REPRESENTED BY A HORIZONTAL LINE, THE LENGTH OF THE LINE BEING PROPORTIONAL TO THE TIME DURATION OF THE ACTIVITY. • IN ORDER THAT SEVERAL ACTIVITIES CAN BE REPRESENTED ON THE SAME CHART, A FRAMEWORK OR RULING IS SETUP, GIVING TIME FLOWING FROM LEFT TO RIGHT, THE ACTIVITIES BEING LISTED FROM TOP TO BOTTOM. • THE BAR CHARTS CAN BE USED BOTH FOR DEPICTING THE PLANS AS WELL AS THE PROGRESS OF ACTIVITIES. BAR CHARTS (GANTT CHARTS) • THE BAR CHARTS DO NOT DEPICT THE PRECEDENCE RELATIONSHIP BETWEEN ACTIVITIES. BAR CHARTS (GANTT CHARTS)
  • 20. PROJECT (WORK) BREAKDOWN STRUCTURE • COMPONENT/PRODUCT BREAKDOWN STRUCTURE • ACTIVITY BREAKDOWN • THE WORK BREAKDOWN STRUCTURE NETWORK TECHNIQUES • THE TECHNIQUES CRITICAL PATH METHOD (CPM) AND PROGRAMME EVALUATION, AND REVIEW TECHNIQUE (PERT), WHICH ARE MORE OR LESS IDENTICAL, ARE COMMONLY KNOWN BY THE NAME OF NETWORK TECHNIQUE. • THE ONLY DIFFERENCE BEING, THAT CPM USES DETERMINISTIC TIME ESTIMATES WHILE PERT USES PROBABLE TIME ESTIMATES.
  • 21. ACTIVITY-ON-ARROW NETWORK • TWO FUNDAMENTAL RULES THAT DETERMINE THE PRECEDENCE RELATIONSHIPS INDICATED BY THE NETWORK ARE AS FOLLOWS: A. AN ACTIVITY CAN BEGIN ONLY AFTER ITS PRECEDING EVENT HAS BEEN ACHIEVED. B. AN EVENT IS SAID TO HAVE BEEN ACHIEVED ONLY AFTER ALL THE ACTIVITIES LEADING INTO THE EVENT HAVE BEEN COMPLETED.
  • 22. DUMMY ACTIVITIES • DUMMY ACTIVITIES IN NETWORKS ARE NECESSARY TO INDICATE THE CORRECT PRECEDENCE RELATIONSHIP, THOUGH THE DUMMY ACTIVITIES DO NOT EXIST IN THE PHYSICAL PROCESS. • FOR EXAMPLE IN THE NETWORK SHOWN BELOW ACTIVITY 5-7 IS A DUMMY ACTIVITY. DANGLING ACTIVITY • AN ACTIVITY IN THE NETWORK WHICH IS STANDING OUT AND HAS NO SUCCESSOR ACTIVITIES. • ITS RELATIONSHIP TO THE PROJECT COMPLETION IS NOT CLEAR.
  • 23. CYCLE IN NETWORK • REPRESENTS A PHYSICAL INCONSISTENCY. • ALLACTIVITY ARROWS ARE DRAWN FROM LEFT TO RIGHT. • EVENTS ARE NUMBERED IN SUCH A WAY THAT EVERY ACTIVITY HAS A HIGHER SUCCEEDING EVENT NUMBER THAN ITS PRECEDING EVENT NUMBER. • THE PROJECT IS IDENTIFIED BY A UNIQUE STARTING EVENT AND A UNIQUE ENDING EVENT OF THE PROJECT. • ALL OTHER EVENTS IN THE PROJECT HAVE AT LEAST ONE ACTIVITY LEADING INTO IT AND AT LEAST ONE ACTIVITY STARTING FROM IT. DANGLING ACTIVITIES AND CYCLES IN NETWORKS CAN BE AVOIDED BY FOLLOWING SOME SIMPLE CONVENTIONS AS:
  • 24. PRECEDENCE NETWORKS • ALSO KNOWN AS ACTIVITY-ON-NODE NETWORKS. • THE BASIC DIFFERENCE BETWEEN THIS AND THE ACTIVITY-ON-ARROW REPRESENTATION IS THAT HERE THE ACTIVITIES ARE REPRESENTED BY THE NODES, AND THE DEPENDENCIES BY ARROWS.
  • 25. TIME ESTIMATES • IN ORDER TO PLAN THE SCHEDULE OF ACTIVITIES, IT IS NECESSARY TO ESTIMATE THE TIME DURATION OF EACH ACTIVITY. • THE INITIAL TIME ESTIMATE OF AN ACTIVITY IS CALLED THE ‘NORMAL EXPECTED DURATION’. • THE TERM ‘NORMAL’ IN THIS CONTEXT MEANS THE NORMAL LEVEL OF RESOURCES AND TECHNOLOGY WHICH THE ORGANIZATION WOULD USE HAD THE ACTIVITY BEEN EXECUTED IN ISOLATION WITH NO CLASH OF RESOURCES WITH ANY OTHER ACTIVITY. • IN THE PRECEDENCE NETWORKS, THE ACTIVITY DURATION IS USUALLY INDICATED IN THE LEFT BOTTOM CORNER OF THE ACTIVITY NODE. • IN PRECEDENCE NETWORKS, THE DEPENDENCIES MAY BE DEFINED AS START-TO-START DEPENDENCIES AND THE DEPENDENCY TIME MAY INDICATE THE AMOUNT OF TIME THAT MUST ELAPSE AFTER THE START OF PREDECESSOR ACTIVITY BEFORE THE START OF THE SUCCESSOR ACTIVITY. • THIS DEPENDENCY TIME MAY BE DIFFERENT FROM THE DURATION OF THE PREDECESSOR ACTIVITY AND IS INDICATED AS A SUBSCRIPT TO THE DEPENDENCYARROW.
  • 26. MILESTONES IN PROJECT • A MILESTONE MAY BE THE COMPLETION OF A PHASE OR A SIGNIFICANT STAGE IN THE PHASE OF THE PROJECT. • REPRESENT THE COMPLETION OF A NUMBER OF ACTIVITIES LEADING INTO A SIGNIFICANT EVENT. • THE EVENT REPRESENTING THE MILESTONE IN AN ACTIVITY-ON-ARROW NETWORK IS CALLED A ‘MILESTONE EVENT’. • A SQUARE INSTEAD OF A CIRCLE MAY BE USED. TIME ANALYSIS THE TIME ANALYSIS IS CARRIED OUT IN TWO STAGES : • THE FORWARD PASS • THE BACKWARD PASS The following notations are used: • tij, = Normal expected duration of activity ‘ij’ (Activity with preceding event ‘i’ and succeeding event ‘j’); • T E(n) =Earliest time of event ‘n’; • T L(n) = Latest allowable time of event ‘n’; • Sln= Slack time of event ‘n’; • EST ij = Early start time of activity ‘i-j’; • EFTij = Early finish time of activity ‘i-j’; • LSTij = Latest start time of activity ‘i-j’; • LFTij = Latest finish time of activity ‘i-j’; • Flij = Total float of activity ‘i-j’; • FFij = Free float of activity ‘i-j’.
  • 27. A). FORWARD PASS • THIS INVOLVES THE FORWARD TRAVERSAL OF THE NETWORK FROM THE PROJECT STARTING EVENT TO THE PROJECT ENDING EVENT. • DURING THIS PASS, THE EARLIEST START AND FINISH TIMES OF ACTIVITIES, EARLIEST TIMES OF EVENTS AND THE EARLIEST COMPLETION TIME OF THE PROJECT ARE WORKED OUT. B). BACKWARD PASS • THIS INVOLVES THE BACKWARD TRAVERSAL OF THE PROJECT FROM THE PROJECT ENDING EVENT TO THE PROJECT STARTING EVENT. • DURING THIS PASS, THE LATEST STARTING AND FINISH TIMES OF ACTIVITIES, THE LATEST ALLOWABLE TIME OF EVENTS, EVENT SLACKS AND ACTIVITY FLOATS ARE WORKED OUT, AND THE CRITICALACTIVITIES ARE IDENTIFIED.
  • 28. CRITICAL PATH, SLACK AND FLOAT • EVENT TIME CHARACTERISTICS - THIS DIFFERENCE BETWEEN THE LATEST ALLOWABLE TIME AND THE EARLIEST TIME OF AN EVENT IS CALLED THE EVENT SLACK. • ACTIVITY TIME CHARACTERISTICS - EARLIEST START TIME OF AN ACTIVITY IS THE EARLIEST TIME ITS PRECEDING EVENT IS ACHIEVED. EARLIEST FINISH TIME OF AN ACTIVITY IS GIVEN BY ADDING ITS DURATION TO ITS EARLIEST START TIME. SO, THE EARLIEST START AND FINISH TIMES OF AN ACTIVITY ARE RELATED TO ITS PRECEDING EVENT: ESTij= TE(i) , EFTij = ESTii + tii = TE(i) + tii • SIMILARLY, LFTij = TL(j), LSTij = LFTij - tij = TL(j) - tij
  • 29. • ACTIVITY FLOATS - THE DIFFERENCE BETWEEN THE EARLIEST AND THE LATEST TIMES OF AN ACTIVITY IS CALLED ‘ACTIVITY FLOAT’, THAT IS, • Flij = LSTij - ESTij = LFTij - EFTij = TL(j) – TE(i) – tij • CRITICAL ACTIVITIES, CRITICAL PATH - THE ACTIVITIES WITH ZERO TOTAL FLOAT (OR IN GENERAL, WITH MINIMUM TOTAL FLOAT IF THE PROJECT TARGET DATE IS DIFFERENT FROM ITS EARLIEST ACHIEVEMENT DATE) ARE CALLED THE CRITICAL ACTIVITIES. NETWORK ANALYSIS AND BAR CHART • VERY USEFUL TOOL FOR THE REPRESENTATION AND ANALYSIS OF PRECEDENCE RELATIONSHIP, • BAR CHART PRESENTS A MORE USEFUL VISUAL REPRESENTATION OF THE PROJECT SCHEDULE.
  • 30. SQUARED NETWORK • SQUARED NETWORK IS A METHOD OF TRANSLATING AN ACTIVITY-ON-ARROW NETWORK DIAGRAM INTO A BAR CHART. EACH ACTIVITY WILL THEN EITHER: • ‘CONTINUE’AS A SINGLE ACTIVITY; • ‘BURST’ INTO TWO OR MORE ACTIVITIES; • ‘MERGE’ INTO AN EVENT WITH ONE OR MORE OTHER ACTIVITIES. CHECKLISTS • CHECKLISTS CAN BE USED FOR SEVERAL PURPOSES AND IN SEVERAL WAYS IN COMPUTER PROJECT PLANNING AND CONTROL. TYPES OF CHECKLISTS: • TASK LISTS • DOCUMENT LISTS • RESPONSIBILITY LISTS
  • 31. SECTION 3 REVIEW PROCEDURES FOR PROJECT COORDINATION AND CONTROL
  • 32. NEED AND SCOPE OF PROJECT REVIEW • FOR A COMPLEX PROJECT, A SCIENTIFIC REVIEW PROCEDURE IS REQUIRED. • THE PROJECT REVIEW PROCEDURE SHOULD HAVE INBUILT MECHANISM FOR CHECKING THE QUALITY OF VARIOUS SYSTEMS, SUB-SYSTEMS. • FOR A SMALLER PROJECT, THE REVIEW CYCLE CAN BE SET ON DEMAND AT THE INITIAL PLANNING STAGE. • FOR A LARGER PROJECT, A COMPREHENSIVE SYSTEM OF PROJECT COORDINATION AND PROJECT CONTROL IS TO BE SET UP. • IN THE DEVELOPMENT PHASE, THE REVIEW SHOULD INCORPORATE APPOINTMENT OF KEY TEAM MEMBERS, DEFINING THE SCOPE, ESTABLISHMENT OF MASTER PLAN, ETC. • FOR THE IMPLEMENTATION PHASE, REVIEW SHOULD COVER SETTING UP OF ORGANIZATIONAL AND COMMUNICATION CHANNELS, IDENTIFICATION OF TEAMS, APPOINTMENT OF TEAM MEMBERS, ETC. • WHILE NEARING COMPLETION OF THE PROJECT, THE PROCEDURES RELATING TO THE REVIEW OF THE DESCRIPTION OF THE FINAL PRODUCT, SETTLEMENT OF FINAL ACCOUNTS, DOCUMENTATION OF RESULTS ETC.
  • 33. PROJECT REVIEW CYCLE REVIEW PROCEDURE • PROJECT REVIEW PROCEDURE REQUIRES INVOLVEMENT OF SENIOR MANAGEMENT TO RATIFY PROJECT MANAGEMENT DECISIONS, IMPLEMENTATION BY PROJECT TEAMS AND PROJECT ORGANIZATION FOR PREPARATION OF PLANS AND ESTABLISHMENT OF UPDATION MECHANISM, ANALYSIS AND MONITORING OF THE PROJECT BY PROJECT ORGANIZATION. USE OF NETWORKS FOR PROJECT CONTROL • NETWORK PROVIDES A VALUABLE DATA FOR THE PROJECT IN ITS ENTIRETY. • THE NETWORK ALSO PROVIDES A MECHANISM-FOR EVALUATING THE PERFORMANCE, A SCHEDULE OF ACTIVITIES, RESOURCE STATUS AND VARIOUS COST ASPECTS CONCERNING VARIOUS ACTIVITIES INDIVIDUALLY AND FOR VARIOUS WORK PACKAGES COLLECTIVELYAND THE PROJECT AS A WHOLE. PERIODIC RE-ASSESSMENT OF THE PROJECT BECOMES NECESSARY TO BRING BACK THE PROJECT TO ITS NORMAL COURSE IF ANY DEVIATION IS ENCOUNTERED.
  • 34. PROJECT MONITORING, ANALYSIS AND UPDATION A. PROJECT MONITORING • SOURCES OF DATA ✓ GENERAL DESCRIPTION OF THE PROJECT INCLUDING THE OBJECTIVES; ✓ SCOPE OF SERVICES REQUIRED AT THE VARIOUS LEVELS OF THE PROJECT; ✓ PROJECT ORGANIZATION INCLUDING THAT OF CLIENTS, CONSULTANTS AND OTHER PARTICIPATING DIVISIONS AND THE DEFINED INTER-RELATIONSHIPS AMONGST THEM; ✓ DIVISION OF RESPONSIBILITY BETWEEN THE VARIOUS PARTICIPANTS; ✓ PROJECT CONTROL SYSTEM AS DESCRIBED AT THE PLANNING STAGE; ✓ PROJECT COMPLETION DATES INCLUDING THAT OF MILESTONES, ASSEMBLIES, SUB - ASSEMBLIES AND VARIOUS OTHER COMPONENTS; ✓ COMMUNICATION CHANNELS AS DEFINED IN THE PLAN, FOR EXAMPLE, GENERAL CORRESPONDENCE, ENGINEERING AND MANUFACTURING INFORMATION, CORRESPONDENCE WITH THE VENDORS AND SUBCONTRACTORS, CORRESPONDENCE WITH THE CLIENTS AND CONSULTANTS AND OTHER PROJECT DOCUMENTATION;
  • 35. ✓ APPROVED DOCUMENTS AND THEIR DISTRIBUTION AMONG PROJECT PARTICIPANTS AND OTHER OWNERSHIP DOCUMENTS; ✓ PROJECT REPORTS COMPRISING OF PERIODICAL PROGRESS REPORT, RESOURCE STATUS REPORT, COST STATUS REPORT, ETC; ✓ CHANGE ORDER PROCEDURE INCLUDING DEVIATIONS; ✓ PROCUREMENT PROCEDURE FOR EQUIPMENTS AND MATERIAL, TAX DATA, CUSTOMS CLEARANCE PROCEDURES, MANAGEMENT OF FOREIGN EXCHANGE AND ASSOCIATED QUALITY CHECKS AND EXPEDITING PROCEDURES; ✓ TENDERING PROCEDURE AND DOCUMENTATION, FOR SITE ACTIVITIES AND COORDINATION PROCEDURES; ✓ BILLING AND ACCOUNTING PROCEDURES. • METHODS OF DATA COLLECTION ✓ DATA ON TIME ASPECTS ✓ DATA ON RESOURCE ASPECTS ✓ DATA ON COST ASPECTS
  • 36. • SCOPE, CHARACTERISTICS AND TECHNIQUES ✓ A MULTI-LEVEL SYSTEM OF PROJECT MONITORING IS NEEDED FOR ESTABLISHING ANY MEANINGFUL REVIEW PROCEDURE. FOR A TYPICAL LARGE PROJECT WITH THREE LEVELS OF PLANNING, ✓ LEVEL-I WILL DEAL WITH THE PROJECT IN ITS ENTIRETY BUT THE LEVEL OF CONTROL WILLABE SUCH AS TO BE EXERCISED BY THE TOP MANAGEMENT. ✓ AT LEVEL-II, THE PROJECT IS BROKEN DOWN INTO THE LEVELS OF PARTICIPATING DIVISIONS OR THE FUNCTIONAL LEVEL. ✓ LEVEL-III IS THE WORKING LEVEL DETAIL. B). PROJECT UPDATION • LEVEL-I NETWORK WHICH DEALS WITH THE CORPORATE ACTIVITIES MUST BE EXPLODED INTO LEVEL-II • LEVEL-II COVERING ALL PARTICIPATING DIVISIONS. THESE ARE FURTHER EXPLODED INTO LEVEL-III • LEVEL-III DEPICTING VARIOUS TASKS BEING PERFORMED. IN THE MULTI-LEVEL PROJECT ENVIRONMENT, ANALYSIS BY THE COMPUTERS BECOMES ESSENTIAL.
  • 37. C). PROJECT ANALYSIS AT THE PLANNING STAGE, • LEVEL - I IS ENVISAGED TO THE CORPORATE LEVEL NETWORK, • LEVEL - II IS DIVISIONAL LEVEL • LEVEL - III IS WORKING LEVEL DOCUMENT. THE COST OF WORK PERFORMED SHOULD BE COLLECTED ON THE FOLLOWING THREE ASPECTS: • BUDGETED COST OF WORK PERFORMED, • PLANNED COST OF WORK PERFORMED, AND • ACTUAL COST OF WORK PERFORMED. PROJECT MANAGEMENT DECISIONS AND IMPLEMENTATION THE INFORMATION GENERATED AFTER EACH CYCLE OF PROJECT REVIEW MAY BE DIVIDED INTO THE FOLLOWING: • FOR INFORMATION • FOR DECISION MAKING • FOR ACTION
  • 39. TABLES ON TIME SCHEDULES AND ACTUALS / ANTICIPATIONS • ACTIVITY LIST SHOWING SCHEDULE AND ACTUAL / ANTICIPATED TIME AGAINST EACH ACTIVITY. • LIST OF CRITICALACTIVITIES • LIST OF KEY/MILESTONE EVENTS SHOWING EARLIEST/ LATEST OCCURRENCE, SCHEDULE OCCURRENCE, ACTUAL/ ANTICIPATED COMPLETION TIME • LIST OF EVENTS FALLING ON THE CRITICAL PATH SHOWING EARLIEST/LATEST OCCURRENCE, SCHEDULE OCCURRENCE, ACTUAL/ANTICIPATED COMPLETION TIME • EXCEPTION REPORT TO HIGHLIGHT SIGNIFICANT VARIATIONS. FLOAT ORDER LIST • A FLOAT ORDER LIST DEPICTING ACTIVITIES, IN THE ASCENDING ORDER OF THE TOTAL FLOAT AVAILABLE SHOULD BE PREPARED. TABULAR PRESENTATION
  • 40. TABLES ON RESOURCES • REPORTS RELATING TO MATERIALS, MAN-POWER, MACHINES AND EQUIPMENTS SHOULD REFLECT THE UTILIZATION OF THESE RESOURCES AGAINST THE PLAN. • REPORTS PERTAINING TO RESOURCES REQUIRED AND AVAILABLE SHOULD ALSO BE PREPARED LINKING WITH PROJECT SCHEDULES. • DETAILED REPORTS ON MATERIAL REQUIREMENTS CAN BE PREPARED ON THE BASIS OF WORK PACKAGES AND ACTIVITIES. • SEPARATE REPORT FOR DEPLOYMENT AND UTILIZATION OF EQUIPMENTS ON CRITICALACTIVITIES CAN ALSO BE GENERATED. TABLES ON COST • THE BASIC UNIT OF COSTING SHOULD BE WORK PACKAGE. • EXCEPTION REPORTS SHOULD BE MADE FOR VARIANCES BEYOND SPECIFIED TOLERANCE LIMITS AS AND WHEN REQUIRED.
  • 41. GRAPHICAL PRESENTATION • SQUARED NETWORK • COMMISSIONING SCHEDULE NETWORK • BAR CHART • MILESTONE BAR CHART • S-CURVES AND HISTOGRAMS • MANUAL LOADING AND STATUS CHARTS OF VARIOUS RESOURCES CAN ALSO BE PREPARED. GRAPHICAL PRESENTATION SHOULD BE SIMPLE AND SELF CONTAINED. THE GRAPHICAL PRESENTATION SUGGESTED ARE: S-CURVES AND HISTOGRAMS
  • 42. NARRATIVE PRESENTATION • THE NARRATIVE PORTION OF THE REPORT, EXPRESSED IN WORDS, SHOULD BE USED TO HIGHLIGHT: • SPECIAL PROBLEMS, • EXCEPTIONAL SITUATIONS, • NEW DEVELOPMENTS AND CHANGES, • CORRECTIVE ACTIONS TAKEN AND REQUIRED, AND • SUGGESTIONS FOR FUTURE. THESE REPORTS SHOULD BE SIMPLE AND CONCISE.
  • 44. PROJECT TERMINATION / CLOSURE PROJECT CLOSE-OUT PLAN AND SCHEDULE WILL BE UPON: • FROZEN PROJECT OBJECTIVES, MEANS-FOR ACHIEVING THEM AND AUTHORIZATION FOR COMMENCEMENT OF WORK. • CHANGES IN THE PROJECT PLAN. • PROJECT PERFORMANCE VIS-A-VIS THE PROJECT OBJECTIVES. • UPDATED RESULTS AND MODIFIED PLANS. TYPES OF PROJECT TERMINATION / CLOSURE • PROJECT CLOSE-OUT OR NORMAL PROJECT TERMINATION • PREMATURE PROJECT TERMINATION
  • 45. RESPONSIBILITY OF PROJECT MANAGER • MAKING ALL NECESSARY DECISIONS FOR SUGGESTING ALTERNATIVE PLANS FOR CONTINUATION OR FOR TERMINATION OF THE PROJECT. • PREPARATION OF PROJECT CLOSE-OUT PLAN AND SCHEDULE. • ACTING AS FOCAL POINT FOR COMMUNICATION BETWEEN PROJECT AUTHORITIES AND THE PROJECT/SUB-PROJECT GROUPS • TAKING STOCK AND RECORDING THE ACCOMPLISHMENT OF ALL WORK PACKAGES • DOCUMENTING RESULTS IN TERMS OF ACHIEVEMENT OF PROJECT OBJECTIVES AND PROJECT CLOSURE/TERMINATION PROCEDURES. • HANDING OVER ‘OPERATION AND MAINTENANCE PROCEDURES MANUALS’, AS-BUILT- DRAWINGS, RECORDS OF DEVIATIONS, ETC. • ORGANIZING FOR THE COMPLETION AND CLOSURE OF THE PROJECT MANAGEMENT ACTIVITIES
  • 46. STEPS FOR PROJECT CLOSURE / TERMINATION A). PROJECT CLOSE-OUT PLAN AND SCHEDULE • PREPARATION OF A COMPLETE RECORD OF ANY CHANGES MADE IN THE PROJECT OBJECTIVES. • PREPARATION OF RECORD OF TECHNICAL PERFORMANCE. • ESTABLISHING PROCEDURES FOR START-UP OPERATIONS, CHECK-OUT DETAILS OF ALL SYSTEMS/EQUIPMENTS AND PROCEDURES FOR TOTAL OPERATIONS. • PREPARATION OF RECORD OF IMPLEMENTATION OF VARIOUS SYSTEMS • PREPARATION OF RECORD OF FORMULATION AND MAINTENANCE OF QUALITY STANDARDS FOR WORK / SYSTEMS. • PREPARATION OF RECORD OF SPECIALACTIONS TAKEN TO COPE WITH CHANGES, • PREPARATION OF RECORD OF SPECIAL TOOLS AND TACKLES USED, METHODS AND PROCEDURE ADOPTED.
  • 47. B). REASSIGNMENT OF PROJECT STAFF • REASSIGNMENT OF PROJECT STAFF TO OTHER SIMILAR PROJECTS. • REASSIGNMENT OF PROJECT STAFF TO OTHER ALLIED AREA PROJECTS. • REASSIGNMENT OF PROJECT STAFF FOR OPERATIONS AND MAINTENANCE. • REASSIGNMENT OF PROJECTS STAFF AS CONSULTANT/ TRAINER. • PREPARATION OF GUIDELINES FOR FUTURE COURSE OF ACTION • PREPARATION AND EXECUTION OF ALL TERMINALAGREEMENTS • AFTER THE PROJECT OBJECTIVES ARE FROZEN AND PROJECT SCOPE ALONG WITH THE CONTRACTUAL OBLIGATION IS AGREED WITH THE PROJECT AUTHORITIES, PROJECT MANAGER PREPARES THE PLAN WITH WBS, ESTABLISHES THE CONTROL MECHANISM AND DEFINES PROCEDURES FOR UPDATION.
  • 48. DIVEST PROJECT RESOURCES • RESOURCES DRAWN FROM THE COMMON POOL MUST BE RELEASED FOR USE IN OTHER PROJECTS ONCE THE NEED OF THE CURRENT PROJECT IS MET AS DETAILED IN THE PROJECT PLAN. • THE RESOURCES UNIQUE TO THE PROJECT AND NON-CONSUMABLE IN NATURE AS ALSO LEFT OVER CONSUMABLES. • OTHER RESOURCES PROVIDED BY PROJECT AUTHORITIES MAY EITHER BE ABSORBED AS PROJECT PROPERTY. • FINALIZATION OF TERMS OF REFERENCE FOR SMOOTH OPERATIONS OF THE SKELETAL STAFF SET UP SPECIALLY FOR WINDING UP OF THE PROJECT. THE DIVESTING OF PROJECT RESOURCES SHOULD BE DONE IN THE FOLLOWING MANNER:
  • 49. RECOMMENDATIONS FOR ACTIONS, IF ANY, REQUIRED FOR FUTURE • PROJECT OBJECTIVES; • PROJECT PLAN; • PROJECT CONTROL; • PROJECT UPDATION AND REVIEW MECHANISM; PROJECT ORGANIZATION; • PROJECT STAFF SELECTION, RECRUITMENT, PLACEMENT AND TRAINING; • EFFICIENCY, EFFICACY AND PROPER USE OF VARIOUS RESOURCES; • EFFICIENCY, EFFICACY AND PROPER USE OF VARIOUS RESOURCES; • SYSTEMS DEVELOPED AND IMPLEMENTED FROM START TO FINISH OF THE PROJECT • PROJECT PROCESS, METHOD AND PROCEDURES FOLLOWED; • UNIQUE FEATURES OF THE PROJECT AND LEARNINGS; • TEMPORARY ARRANGEMENTS MADE AND FUTURE PLAN OF ACTION; • DIFFICULTIES ENCOUNTERED AND PRECAUTIONS TAKEN • QUALITY/PERFORMANCE/TECHNOLOGY PLANNED VERSUS ACHIEVED; • SAFETY REQUIREMENTS AND EARLY WARNING SIGNALS • INTERFACES MANAGED WITH INTERNALAND EXTERNAL ENVIRONMENT / ORGANISATIONS; • RECOMMENDATIONS FOR CHANGE OF PROCEDURES ETC. • INSTRUCTIONS FOR ALL SYSTEMS / SUB-SYSTEMS WITH PRECAUTIONS NEEDED. THE PROJECT MANAGER BASED ON HIS EXPERIENCE WOULD MAKE RECOMMENDATIONS IN AREAS SUCH AS:
  • 50. PREPARE A TERMINATION / CLOSURE REPORT • CONTENTS OF THE REPORT • HISTORIC RECORDS CONTAINING PROJECT DOCUMENTATION • A FORMAL ANALYSIS IN THE FORM OF PROJECT REPORT CONTAINING PROJECT DATA LIKE COSTS, SCHEDULES, TECHNICAL PERFORMANCE, ORIGINAL PLAN. • A REPORT ON FINANCIAL CLOSING STATING HOW THE FUNDS HAVE BEEN RAISED AND SPENT WITH TOTAL COMMERCIAL IMPLICATIONS AT THE TIME OF PROJECT CLOSURE.
  • 51. DOCUMENTATION REGARDING: • AS-BUILT-DRAWINGS. • OPERATING PROCEDURES. • OPERATION AND MAINTENANCE MANUALS. • GUIDELINES FOR TRAINING OF OPERATION AND MAINTENANCE STAFF. • POSITION DESCRIPTION, PLACEMENT, AND RECRUITMENT GUIDELINES. • TRANSFER OF RESPONSIBILITY. • RELEASE OF RESOURCES. • PROJECT ACCEPTANCE AND OPERATIONS REPORT WITH SYSTEMS CHECK-OUT AND START-UP RESULTS (INDIVIDUALAND COLLECTIVE). • QUALITY/PERFORMANCE/TECHNOLOGY DOCUMENTS • DEVIATIONS AND REMEDIALACTION REPORT • SPECIAL FEATURES