CHAPTER TWO QUESTIONS WITH ANSWERS
Q1. A substation supplies power by four feeders to its consumers. Feeder no 1 supplies six
consumers whose individual demands are 70 kW, 90 kW, 20 kW, 50 kW, 10 kW and 20 kW, while
maximum demand on the feeder is 200kW. Feeder no 2 supplies four consumers whose daily
maximum demands are 60 kW, 40 kW, 70 kW and 30 kW while the maximum demand on feeder no
2 is 160 kW. Feeders no 3 and 4 have daily maximum demands of 150 kW and 200 kW respectively,
while the maximum demand on the station is 600 kW.

Determine the diversity factors for the consumers of feeder no 1 and feeder no 2 and for the four
feeders.

Ans: 1.3; 1.25 and 1.183

Q2. A generating station has the following daily loads:

0 to 6 hr       4000 kW

6 to 8 hr       3000kW

8 to 12 hr      8000kW

12 to 14 hr     2000kW

14 to 18 hr     7500kW

18 to 20 hr     3000kW

20 to 24 hr     4500kW

Sketch load duration curve and determine the load factor and plant capacity factor assuming
capacity of the plant is 11000 kW.

Ans: 0.625, 0.4545

Q3. An industrial consumer having a maximum demand of 100 kW, maintains a load factor 60%. The
tariff rates are Rs. 1500 per KVA of maximum demand per annum plus paise 30 per kWh of energy
consumed. If the average pf is 0.8 lagging, calculate the total energy consumed per annum and
annual bill.



Q4. Compute the cost of electrical energy and average unit cost for consuming 450 kWh under block
rate quoted as below:

First 50 kWh at Rs. 3.80 per kWh

Next 50 kWh at Rs. 3.20 per kWh

Next 50 kWh at Rs. 2.80 per kWh
Next 50 kWh at Rs. 2.40 per kWh

Excess over 200 kWh at Rs. 2.10 per kWh.

Q5. A synchronous motor having a power consumption of 50 kW is connected in parallel with a load
of 200 kW having pf 0.8 lagging. The excitation of motor is adjusted until the combined pf becomes
0.9 lagging. Calculate the kVA input to the motor.

Ans: 57.76 kVA

Q6. It is desired to correct the power factor 0.95 by means of static condensers connected across
each phase of a 3-phase, 400 V, 50 Hz motor installation having a maximum load of 50 kVA at pf of
0.75 lagging. What must be the capacity of each delta – connected capacitor?

Ans: 244 uF

Q7.A factory having a load of 5 MW at 0.8 lagging for 2000 hours per annum buys energy on tariff of
Rs 500 per kVA plus Rs 2.5 per kWh consumed. If the power factor is improved to 0.95 lagging by
means of capacitors costing Rs 1350 per kVA and having a power loss of 200 watts per kVA, calculate
the annual charge for electrical energy (a) before and (b) after the installation of capacitors and (c)
the saving effected by their use. Allow 8% per annum for interest and depreciation on the
capacitors.

Q8. A consumer has an annual consumption of 70080 kWh. The charge is Rs 100 per kW of
maximum demand plus 5 paise per kWh.

(a) Find the annual bill and the overall costs per kWh is the load factor is 40%.

(b) What is the overall cost per kWh if (i) consumption was reduced by 25% with the same load
factor (ii) consumption remains the same as in (a) but the load factor is reduced to 30%?

Ans. (a) Rs 5504; 7.85p (b) (i) 7.85 p (ii) 8.80 p

Q9. A consumer takes a steady load of 1000 kW at a power factor of 0.707 lagging and pays Rs 80
per annum per kVA of maximum demand. Phase advancing plant costs Rs 128 per kVAr. Determine
the capacity of the phase advancing plant required for minimum overall annual expenditure. Interest
and depreciation total 10%. What will be the value of the new power factor of the supply? Deduce
and formula used.

Ans. 838 kVAr; 0.987 (lagging)

Q10     Two 50hp (metric) induction motors are each supplied on a tow part tariff at Rs 80 per kVA
of maximum demand plus 5 paise per kWh. The service needed is 3000 hours per annum at full load.
Motor A has efficiency 0.878 and p.f. 0.83 plus a capacitor costing Rs 75 per kVA to raise the p.f. to
0.91. Motor B with an efficiency 0.888 and p.f. 0.91 costs 1000 more than motor A. Assuming
interest and depreciation to be 12.5 % per annum for each motor and 8% for the capacitor, compare
the annual charges for two arrangements.

Ans. Net annual saving with motor B is Rs 36.80.
Q11      A factory takes a load of 200 kW at 0.85 p.f. lagging for 2500 hours per annum and buys
energy on a tariff of Rs 100 per kVA plus 5 paise per kWh consumed. If the power factor is improved
to 0.90 lagging by means of capacitors costing Rs 350 per kVA and having a power loss of 100 watts
per kVA calculate the annual charge for electrical energy (a) before and (b) after the installation of
capacitors and (c) the saving effected by their use. Allow 8% per annum for interest and depreciation
on the capacitors.

Ans. (a) Rs 48530 (b) Rs 48270 (c) Rs 260

Q12.    A generating station supplies the following loads:

15 MW, 12 MW, 8.5 MW, 6 MW and 0.45 MW. The annual load factor of the power station is 48%.
Calculate (i) the number of units supplied annually (ii) diversity factor and (iii) demand factor, if the
station has a maximum demand of 22 MW.

Ans. (i) 92.5 X 10e6 kWh (ii) 1.907 (iii) 52.5%

Q13. A power station has a maximum demand of 200 MW, a plant load factor of 0.6, a plant
capacity factor of 0.5 and a plant use factor of 0.8. Find (i) the daily energy consumed (ii) the reserve
capacity of the plant and (iii) maximum energy that can be produced daily.

Ans. (i) 2880 MWh (ii) 40 MW (iii) 5706 MWh

Q14. The maximum demand of a power supply system is 30 MW. The annual factors as follows:
Load factor = 60%; Capacity factor = 50%; Use factor = 75%.

Determine (i) the annual energy production (ii) reserve capacity and (iii) the hours during which the
plant is not in service per year.

Ans. (i) 157.68 X 10e6 kWh (ii) 6 MW (iii) 2920 hours.

Q15. The maximum demand of a consumer is 1 MW and the units consumed per annum are
500000 kWh. Calculate the reduction in cost if the power factor is raised from 0.5 to 0.8. The tariff is
Rs 900 per annum per kW demand plus Rs 1.50 per kWh plus Re 0.30 per kVAh reactive. Calculate
the flat rate tariff for a unity power factor load.

Ans. Rs 147310.00; Rs 3.30 per kWh

Q16. A consumer, whose connected load is 400 kVA, consumes 1 X 10e6 kWh per annum and the
maximum demand registered is 250 kVA. He is offered the following two alternative tariffs:

Tariff A: Rs 1000 per annum per kVA of connected load + first 150 kWh per KVA of connected load at
Rs 3.0/kWh, next 50000 kWh at Rs 2.00 per kWh and the rest at Re 1.0/kWh.

Tariff B: Rs 1200 per annum per kVA of maximum demand + first 150 kWh per kVA of maximum
demand at Rs 3.0 per kWh; next 50000 kWh at Rs 2.0/kWh and the rest at Re 1.0/kWh.

Which tariff is economical and what is the annual gain?

Ans. Tariff B is cheaper; Annual gain = Rs 14500000

Contenu connexe

Tendances

Protective relay
Protective relay Protective relay
Protective relay Uday Wankar
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1Md Irshad Ahmad
 
Generator Protection
Generator ProtectionGenerator Protection
Generator ProtectionPriten Vasa
 
Mathematical modelling of steam turbine
Mathematical modelling of steam turbineMathematical modelling of steam turbine
Mathematical modelling of steam turbinessusera970cc
 
Ppt on protection of power transformers
Ppt on protection of power transformersPpt on protection of power transformers
Ppt on protection of power transformerssiddharam kantoli
 
Bus duct fabrication
Bus duct fabricationBus duct fabrication
Bus duct fabricationSTUPIDPANDEY
 
Electrical Machines - II
Electrical Machines - IIElectrical Machines - II
Electrical Machines - IIkarthi1017
 
Alternator protection
Alternator protectionAlternator protection
Alternator protectionjawaharramaya
 
Line to Line & Double Line to Ground Fault On Power System
Line to Line & Double Line to Ground Fault On Power SystemLine to Line & Double Line to Ground Fault On Power System
Line to Line & Double Line to Ground Fault On Power SystemSmit Shah
 
Insulation coordination.
Insulation coordination.Insulation coordination.
Insulation coordination.Parth Patel
 
10 electrical installation-guide-2016
10 electrical installation-guide-201610 electrical installation-guide-2016
10 electrical installation-guide-2016JOSE NERI GARAMPIEL
 
Introduction to power system protection
Introduction to power system protectionIntroduction to power system protection
Introduction to power system protectionSaifUrrehman183
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSPartha Parida
 

Tendances (20)

Protective relay
Protective relay Protective relay
Protective relay
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1
 
Generator Protection
Generator ProtectionGenerator Protection
Generator Protection
 
Mathematical modelling of steam turbine
Mathematical modelling of steam turbineMathematical modelling of steam turbine
Mathematical modelling of steam turbine
 
Motor Protection
Motor ProtectionMotor Protection
Motor Protection
 
Ppt on protection of power transformers
Ppt on protection of power transformersPpt on protection of power transformers
Ppt on protection of power transformers
 
Protection of Transmission lines
Protection of Transmission linesProtection of Transmission lines
Protection of Transmission lines
 
Bus duct fabrication
Bus duct fabricationBus duct fabrication
Bus duct fabrication
 
Electrical Machines - II
Electrical Machines - IIElectrical Machines - II
Electrical Machines - II
 
Motor starter
Motor starterMotor starter
Motor starter
 
Alternator protection
Alternator protectionAlternator protection
Alternator protection
 
Line to Line & Double Line to Ground Fault On Power System
Line to Line & Double Line to Ground Fault On Power SystemLine to Line & Double Line to Ground Fault On Power System
Line to Line & Double Line to Ground Fault On Power System
 
Protection of alternator
Protection of alternatorProtection of alternator
Protection of alternator
 
Insulation coordination.
Insulation coordination.Insulation coordination.
Insulation coordination.
 
Switch yard & Protection
Switch yard & ProtectionSwitch yard & Protection
Switch yard & Protection
 
A.C Drives
A.C DrivesA.C Drives
A.C Drives
 
10 electrical installation-guide-2016
10 electrical installation-guide-201610 electrical installation-guide-2016
10 electrical installation-guide-2016
 
Introduction to power system protection
Introduction to power system protectionIntroduction to power system protection
Introduction to power system protection
 
Power factor correction
Power factor correctionPower factor correction
Power factor correction
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
 

En vedette

Unit1 And 2 Sample Solutions
Unit1 And 2 Sample SolutionsUnit1 And 2 Sample Solutions
Unit1 And 2 Sample SolutionsAbha Tripathi
 
Questions practice unit iv
Questions practice unit ivQuestions practice unit iv
Questions practice unit ivAbha Tripathi
 
Unit 2 samplesolutions
Unit 2 samplesolutionsUnit 2 samplesolutions
Unit 2 samplesolutionsAbha Tripathi
 
Unit 2 Questions_Nagrath kothari
Unit 2 Questions_Nagrath kothariUnit 2 Questions_Nagrath kothari
Unit 2 Questions_Nagrath kothariAbha Tripathi
 
Practice questions for unit ii
Practice questions for unit iiPractice questions for unit ii
Practice questions for unit iiAbha Tripathi
 
Step1 Single Line Diagram
Step1 Single Line DiagramStep1 Single Line Diagram
Step1 Single Line Diagramnanonon
 
TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...
TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...
TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...Mohammed TAMALI
 
Problemas resueltos cortocircuito trifasico
Problemas resueltos cortocircuito trifasicoProblemas resueltos cortocircuito trifasico
Problemas resueltos cortocircuito trifasicopaulelrapido
 
Project report on 33kv Substation and Automatic Power Factor Controller in ONGC
Project report on 33kv Substation and Automatic Power Factor Controller in ONGCProject report on 33kv Substation and Automatic Power Factor Controller in ONGC
Project report on 33kv Substation and Automatic Power Factor Controller in ONGCGirish Gupta
 
Unit 1, Power system Analysis
Unit 1, Power system AnalysisUnit 1, Power system Analysis
Unit 1, Power system AnalysisAbha Tripathi
 
Newton Raphson method for load flow analysis
Newton Raphson method for load flow analysisNewton Raphson method for load flow analysis
Newton Raphson method for load flow analysisdivyanshuprakashrock
 
Ee 1351 power system analysis
Ee 1351 power system analysisEe 1351 power system analysis
Ee 1351 power system analysisHari Kumar
 
File 1 power system fault analysis
File 1 power system fault analysisFile 1 power system fault analysis
File 1 power system fault analysiskirkusawi
 

En vedette (20)

Unit1 And 2 Sample Solutions
Unit1 And 2 Sample SolutionsUnit1 And 2 Sample Solutions
Unit1 And 2 Sample Solutions
 
Questions unit4
Questions unit4Questions unit4
Questions unit4
 
Questions practice unit iv
Questions practice unit ivQuestions practice unit iv
Questions practice unit iv
 
Unit v
Unit vUnit v
Unit v
 
Unit4questions
Unit4questionsUnit4questions
Unit4questions
 
Unit 2 samplesolutions
Unit 2 samplesolutionsUnit 2 samplesolutions
Unit 2 samplesolutions
 
Unit 2 Questions_Nagrath kothari
Unit 2 Questions_Nagrath kothariUnit 2 Questions_Nagrath kothari
Unit 2 Questions_Nagrath kothari
 
Practice questions for unit ii
Practice questions for unit iiPractice questions for unit ii
Practice questions for unit ii
 
Solutions -unit4
Solutions  -unit4Solutions  -unit4
Solutions -unit4
 
Practice questions
Practice questionsPractice questions
Practice questions
 
Unit1 8
Unit1 8Unit1 8
Unit1 8
 
Step1 Single Line Diagram
Step1 Single Line DiagramStep1 Single Line Diagram
Step1 Single Line Diagram
 
TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...
TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...
TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...
 
Problemas resueltos cortocircuito trifasico
Problemas resueltos cortocircuito trifasicoProblemas resueltos cortocircuito trifasico
Problemas resueltos cortocircuito trifasico
 
Project report on 33kv Substation and Automatic Power Factor Controller in ONGC
Project report on 33kv Substation and Automatic Power Factor Controller in ONGCProject report on 33kv Substation and Automatic Power Factor Controller in ONGC
Project report on 33kv Substation and Automatic Power Factor Controller in ONGC
 
Unit 1, Power system Analysis
Unit 1, Power system AnalysisUnit 1, Power system Analysis
Unit 1, Power system Analysis
 
Newton Raphson method for load flow analysis
Newton Raphson method for load flow analysisNewton Raphson method for load flow analysis
Newton Raphson method for load flow analysis
 
Ee 1351 power system analysis
Ee 1351 power system analysisEe 1351 power system analysis
Ee 1351 power system analysis
 
load flow 1
 load flow 1 load flow 1
load flow 1
 
File 1 power system fault analysis
File 1 power system fault analysisFile 1 power system fault analysis
File 1 power system fault analysis
 

Similaire à Unit1questions

Power generation and economics
Power generation and economicsPower generation and economics
Power generation and economicsSiraskarCom
 
Ee w07.1 w_ 2. electricity generation _ part 4 (missing money & capacity pay...
Ee  w07.1 w_ 2. electricity generation _ part 4 (missing money & capacity pay...Ee  w07.1 w_ 2. electricity generation _ part 4 (missing money & capacity pay...
Ee w07.1 w_ 2. electricity generation _ part 4 (missing money & capacity pay...Silvester Van Koten
 
How Power Factor corection works.pdf
How Power Factor corection works.pdfHow Power Factor corection works.pdf
How Power Factor corection works.pdfChristinaBoyd12
 
Pv tubewell economics potential pakistan
Pv tubewell economics potential pakistanPv tubewell economics potential pakistan
Pv tubewell economics potential pakistanakhtar ali
 
(General aspects of energy)
(General aspects of energy)(General aspects of energy)
(General aspects of energy)malathi051
 
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptxLecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptxFelcherLayugan
 
Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1NBoss
 
PV AND OTHER RENEWABLE ENERGY
 PV AND OTHER RENEWABLE ENERGY PV AND OTHER RENEWABLE ENERGY
PV AND OTHER RENEWABLE ENERGYH Janardan Prabhu
 
Tarrif and load curves
Tarrif and load curvesTarrif and load curves
Tarrif and load curvesGPERI
 
Load Forecasting Using LSTM Model
Load Forecasting Using LSTM ModelLoad Forecasting Using LSTM Model
Load Forecasting Using LSTM ModelIRJET Journal
 
Power system Stability, Equal area criteria
Power system Stability, Equal area criteriaPower system Stability, Equal area criteria
Power system Stability, Equal area criteriaAbha Tripathi
 
Power Factor.ppt
Power Factor.pptPower Factor.ppt
Power Factor.pptVidya Sagar
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)IJERD Editor
 

Similaire à Unit1questions (20)

Power generation and economics
Power generation and economicsPower generation and economics
Power generation and economics
 
Ch01-ESR-L02.pdf
Ch01-ESR-L02.pdfCh01-ESR-L02.pdf
Ch01-ESR-L02.pdf
 
Ee w07.1 w_ 2. electricity generation _ part 4 (missing money & capacity pay...
Ee  w07.1 w_ 2. electricity generation _ part 4 (missing money & capacity pay...Ee  w07.1 w_ 2. electricity generation _ part 4 (missing money & capacity pay...
Ee w07.1 w_ 2. electricity generation _ part 4 (missing money & capacity pay...
 
How Power Factor corection works.pdf
How Power Factor corection works.pdfHow Power Factor corection works.pdf
How Power Factor corection works.pdf
 
Pv tubewell economics potential pakistan
Pv tubewell economics potential pakistanPv tubewell economics potential pakistan
Pv tubewell economics potential pakistan
 
(General aspects of energy)
(General aspects of energy)(General aspects of energy)
(General aspects of energy)
 
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptxLecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
 
Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1
 
PROPOSAL
PROPOSALPROPOSAL
PROPOSAL
 
Introduction to ReGenX Generator Innovations & Commercialization Overview 201...
Introduction to ReGenX Generator Innovations & Commercialization Overview 201...Introduction to ReGenX Generator Innovations & Commercialization Overview 201...
Introduction to ReGenX Generator Innovations & Commercialization Overview 201...
 
PV AND OTHER RENEWABLE ENERGY
 PV AND OTHER RENEWABLE ENERGY PV AND OTHER RENEWABLE ENERGY
PV AND OTHER RENEWABLE ENERGY
 
Comparison study of lead-acid and lithium-ıon batteries for solar photovoltai...
Comparison study of lead-acid and lithium-ıon batteries for solar photovoltai...Comparison study of lead-acid and lithium-ıon batteries for solar photovoltai...
Comparison study of lead-acid and lithium-ıon batteries for solar photovoltai...
 
Psoc qp
Psoc qpPsoc qp
Psoc qp
 
Tarrif and load curves
Tarrif and load curvesTarrif and load curves
Tarrif and load curves
 
Wind turbine report
Wind turbine reportWind turbine report
Wind turbine report
 
Load Forecasting Using LSTM Model
Load Forecasting Using LSTM ModelLoad Forecasting Using LSTM Model
Load Forecasting Using LSTM Model
 
Power system Stability, Equal area criteria
Power system Stability, Equal area criteriaPower system Stability, Equal area criteria
Power system Stability, Equal area criteria
 
Power Factor.ppt
Power Factor.pptPower Factor.ppt
Power Factor.ppt
 
powerfactor.pdf
powerfactor.pdfpowerfactor.pdf
powerfactor.pdf
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
 

Plus de Abha Tripathi

Unit1 and 2 sample solutions
Unit1 and 2 sample solutionsUnit1 and 2 sample solutions
Unit1 and 2 sample solutionsAbha Tripathi
 
Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01Abha Tripathi
 
Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01Abha Tripathi
 
Symmetrical components
Symmetrical componentsSymmetrical components
Symmetrical componentsAbha Tripathi
 
Representation of power system components
Representation of power system componentsRepresentation of power system components
Representation of power system componentsAbha Tripathi
 
Gas and diesel Plant
Gas and diesel PlantGas and diesel Plant
Gas and diesel PlantAbha Tripathi
 
NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant, NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant, Abha Tripathi
 
Questions From 1st Unit Nagrath
Questions From 1st Unit NagrathQuestions From 1st Unit Nagrath
Questions From 1st Unit NagrathAbha Tripathi
 
Grading The Insulator Problem
Grading The Insulator ProblemGrading The Insulator Problem
Grading The Insulator ProblemAbha Tripathi
 

Plus de Abha Tripathi (18)

Questions unit3
Questions unit3Questions unit3
Questions unit3
 
Unit1 and 2 sample solutions
Unit1 and 2 sample solutionsUnit1 and 2 sample solutions
Unit1 and 2 sample solutions
 
Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01
 
Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01
 
Symmetrical components
Symmetrical componentsSymmetrical components
Symmetrical components
 
Representation of power system components
Representation of power system componentsRepresentation of power system components
Representation of power system components
 
Questions unit2 ch3
Questions unit2 ch3Questions unit2 ch3
Questions unit2 ch3
 
Renewable Sor
Renewable SorRenewable Sor
Renewable Sor
 
Gas and diesel Plant
Gas and diesel PlantGas and diesel Plant
Gas and diesel Plant
 
NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant, NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant,
 
Hydro E
Hydro EHydro E
Hydro E
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Soln unit5
Soln unit5Soln unit5
Soln unit5
 
Questions From 1st Unit Nagrath
Questions From 1st Unit NagrathQuestions From 1st Unit Nagrath
Questions From 1st Unit Nagrath
 
Unit 3 Part 1
Unit 3 Part 1Unit 3 Part 1
Unit 3 Part 1
 
Grading The Insulator Problem
Grading The Insulator ProblemGrading The Insulator Problem
Grading The Insulator Problem
 
Dc Distribution
Dc DistributionDc Distribution
Dc Distribution
 
Dc Distributed Load
Dc Distributed LoadDc Distributed Load
Dc Distributed Load
 

Dernier

UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfNirmal Dwivedi
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxEsquimalt MFRC
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024Elizabeth Walsh
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxDr. Sarita Anand
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseAnaAcapella
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...Poonam Aher Patil
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentationcamerronhm
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxJisc
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17Celine George
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsMebane Rash
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Association for Project Management
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.pptRamjanShidvankar
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - Englishneillewis46
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfPoh-Sun Goh
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the ClassroomPooky Knightsmith
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptxMaritesTamaniVerdade
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxAmanpreet Kaur
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibitjbellavia9
 

Dernier (20)

UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptx
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the Classroom
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 

Unit1questions

  • 1. CHAPTER TWO QUESTIONS WITH ANSWERS Q1. A substation supplies power by four feeders to its consumers. Feeder no 1 supplies six consumers whose individual demands are 70 kW, 90 kW, 20 kW, 50 kW, 10 kW and 20 kW, while maximum demand on the feeder is 200kW. Feeder no 2 supplies four consumers whose daily maximum demands are 60 kW, 40 kW, 70 kW and 30 kW while the maximum demand on feeder no 2 is 160 kW. Feeders no 3 and 4 have daily maximum demands of 150 kW and 200 kW respectively, while the maximum demand on the station is 600 kW. Determine the diversity factors for the consumers of feeder no 1 and feeder no 2 and for the four feeders. Ans: 1.3; 1.25 and 1.183 Q2. A generating station has the following daily loads: 0 to 6 hr 4000 kW 6 to 8 hr 3000kW 8 to 12 hr 8000kW 12 to 14 hr 2000kW 14 to 18 hr 7500kW 18 to 20 hr 3000kW 20 to 24 hr 4500kW Sketch load duration curve and determine the load factor and plant capacity factor assuming capacity of the plant is 11000 kW. Ans: 0.625, 0.4545 Q3. An industrial consumer having a maximum demand of 100 kW, maintains a load factor 60%. The tariff rates are Rs. 1500 per KVA of maximum demand per annum plus paise 30 per kWh of energy consumed. If the average pf is 0.8 lagging, calculate the total energy consumed per annum and annual bill. Q4. Compute the cost of electrical energy and average unit cost for consuming 450 kWh under block rate quoted as below: First 50 kWh at Rs. 3.80 per kWh Next 50 kWh at Rs. 3.20 per kWh Next 50 kWh at Rs. 2.80 per kWh
  • 2. Next 50 kWh at Rs. 2.40 per kWh Excess over 200 kWh at Rs. 2.10 per kWh. Q5. A synchronous motor having a power consumption of 50 kW is connected in parallel with a load of 200 kW having pf 0.8 lagging. The excitation of motor is adjusted until the combined pf becomes 0.9 lagging. Calculate the kVA input to the motor. Ans: 57.76 kVA Q6. It is desired to correct the power factor 0.95 by means of static condensers connected across each phase of a 3-phase, 400 V, 50 Hz motor installation having a maximum load of 50 kVA at pf of 0.75 lagging. What must be the capacity of each delta – connected capacitor? Ans: 244 uF Q7.A factory having a load of 5 MW at 0.8 lagging for 2000 hours per annum buys energy on tariff of Rs 500 per kVA plus Rs 2.5 per kWh consumed. If the power factor is improved to 0.95 lagging by means of capacitors costing Rs 1350 per kVA and having a power loss of 200 watts per kVA, calculate the annual charge for electrical energy (a) before and (b) after the installation of capacitors and (c) the saving effected by their use. Allow 8% per annum for interest and depreciation on the capacitors. Q8. A consumer has an annual consumption of 70080 kWh. The charge is Rs 100 per kW of maximum demand plus 5 paise per kWh. (a) Find the annual bill and the overall costs per kWh is the load factor is 40%. (b) What is the overall cost per kWh if (i) consumption was reduced by 25% with the same load factor (ii) consumption remains the same as in (a) but the load factor is reduced to 30%? Ans. (a) Rs 5504; 7.85p (b) (i) 7.85 p (ii) 8.80 p Q9. A consumer takes a steady load of 1000 kW at a power factor of 0.707 lagging and pays Rs 80 per annum per kVA of maximum demand. Phase advancing plant costs Rs 128 per kVAr. Determine the capacity of the phase advancing plant required for minimum overall annual expenditure. Interest and depreciation total 10%. What will be the value of the new power factor of the supply? Deduce and formula used. Ans. 838 kVAr; 0.987 (lagging) Q10 Two 50hp (metric) induction motors are each supplied on a tow part tariff at Rs 80 per kVA of maximum demand plus 5 paise per kWh. The service needed is 3000 hours per annum at full load. Motor A has efficiency 0.878 and p.f. 0.83 plus a capacitor costing Rs 75 per kVA to raise the p.f. to 0.91. Motor B with an efficiency 0.888 and p.f. 0.91 costs 1000 more than motor A. Assuming interest and depreciation to be 12.5 % per annum for each motor and 8% for the capacitor, compare the annual charges for two arrangements. Ans. Net annual saving with motor B is Rs 36.80.
  • 3. Q11 A factory takes a load of 200 kW at 0.85 p.f. lagging for 2500 hours per annum and buys energy on a tariff of Rs 100 per kVA plus 5 paise per kWh consumed. If the power factor is improved to 0.90 lagging by means of capacitors costing Rs 350 per kVA and having a power loss of 100 watts per kVA calculate the annual charge for electrical energy (a) before and (b) after the installation of capacitors and (c) the saving effected by their use. Allow 8% per annum for interest and depreciation on the capacitors. Ans. (a) Rs 48530 (b) Rs 48270 (c) Rs 260 Q12. A generating station supplies the following loads: 15 MW, 12 MW, 8.5 MW, 6 MW and 0.45 MW. The annual load factor of the power station is 48%. Calculate (i) the number of units supplied annually (ii) diversity factor and (iii) demand factor, if the station has a maximum demand of 22 MW. Ans. (i) 92.5 X 10e6 kWh (ii) 1.907 (iii) 52.5% Q13. A power station has a maximum demand of 200 MW, a plant load factor of 0.6, a plant capacity factor of 0.5 and a plant use factor of 0.8. Find (i) the daily energy consumed (ii) the reserve capacity of the plant and (iii) maximum energy that can be produced daily. Ans. (i) 2880 MWh (ii) 40 MW (iii) 5706 MWh Q14. The maximum demand of a power supply system is 30 MW. The annual factors as follows: Load factor = 60%; Capacity factor = 50%; Use factor = 75%. Determine (i) the annual energy production (ii) reserve capacity and (iii) the hours during which the plant is not in service per year. Ans. (i) 157.68 X 10e6 kWh (ii) 6 MW (iii) 2920 hours. Q15. The maximum demand of a consumer is 1 MW and the units consumed per annum are 500000 kWh. Calculate the reduction in cost if the power factor is raised from 0.5 to 0.8. The tariff is Rs 900 per annum per kW demand plus Rs 1.50 per kWh plus Re 0.30 per kVAh reactive. Calculate the flat rate tariff for a unity power factor load. Ans. Rs 147310.00; Rs 3.30 per kWh Q16. A consumer, whose connected load is 400 kVA, consumes 1 X 10e6 kWh per annum and the maximum demand registered is 250 kVA. He is offered the following two alternative tariffs: Tariff A: Rs 1000 per annum per kVA of connected load + first 150 kWh per KVA of connected load at Rs 3.0/kWh, next 50000 kWh at Rs 2.00 per kWh and the rest at Re 1.0/kWh. Tariff B: Rs 1200 per annum per kVA of maximum demand + first 150 kWh per kVA of maximum demand at Rs 3.0 per kWh; next 50000 kWh at Rs 2.0/kWh and the rest at Re 1.0/kWh. Which tariff is economical and what is the annual gain? Ans. Tariff B is cheaper; Annual gain = Rs 14500000